MONTHYEARML24311A1232024-11-14014 November 2024 – Report for the Aging Management Audit Regarding the License Renewal Application Review IR 05000275/20240102024-11-0707 November 2024 Biennial Problem Identification and Resolution Inspection Report 05000275/2024010 and 05000323/2024010 IR 05000275/20244022024-11-0707 November 2024 Security Baseline Inspection Report 05000275/2024402 and 05000323/2024402 IR 07200026/20244012024-11-0606 November 2024 Independent Spent Fuel Storage Installation Security Inspection Report 07200026/2024401 DCL-24-095, CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 20232024-11-0606 November 2024 CFR 50.46 Annual Report of Emergency Core Cooling System Evaluation Model Changes for Peak Cladding Temperature for 2023 ML24302A1912024-11-0101 November 2024 Ltr to C. Mcdarment Tule River Tribe Re DCPP Dseis ML24302A1942024-11-0101 November 2024 Ltr to K. Kahn Santa Ynez Band of Chumash Indians Re DCPP Dseis ML24302A2612024-11-0101 November 2024 Letter to Achp Re DCPP Dseis ML24302A1972024-11-0101 November 2024 Letter to V. Sage Walker Northern Chumash Tribal Council Re DCPP Dseis ML24302A1962024-11-0101 November 2024 Ltr to SLO County Chumash Indians Re DCPP Dseis ML24302A1932024-11-0101 November 2024 Letter to G. Pierce Salinan Tribe of Monterey, SLO Re DCPP Dseis ML24302A2622024-11-0101 November 2024 Letter to CA SHPO Regarding DCPP Dseis ML24302A1922024-11-0101 November 2024 Ltr to G. Frausto Coastal Band of Chumash Indians Re DCPP Dseis ML24302A1952024-11-0101 November 2024 Ltr to M. Olivas Tucker Ytt Re DCPP Dseis ML24276A1482024-10-30030 October 2024 NRC to Fws Request for Concurrence with Endangered Species Act Determinations for Diablo Canyon Power Plant, Units 1, 2, ISFSI Proposed License Renewals in San Luis Obispo Co, CA IR 05000275/20240032024-10-30030 October 2024 Integrated Inspection Report 05000275/2024003 and 05000323/2024003 and Independent Spent Fuel Storage Installation Report 07200026/2024001 ML24275A0622024-10-30030 October 2024 NRC to NMFS Request Initiate Formal Endangered Species Act Consultation and Abbreviated Essential Fish Habitat for Proposed License Renewal of DCP Plant Units 1, 2 ML24269A0122024-10-29029 October 2024 OEDO-24-00083 2.206 Petition Diablo Canyon Seismic CDF - Response to Petitioner Letter ML24284A3112024-10-28028 October 2024 Ltr to a Peck, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants ML24284A3122024-10-28028 October 2024 Ltr to P Ting, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants IR 05000275/20240132024-10-28028 October 2024 – License Renewal Report 05000275/2024013 and 05000323/2024013 ML24261B9492024-10-24024 October 2024 Issuance of Amendment Nos. 246 and 248 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) DCL-24-103, Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 22024-10-24024 October 2024 Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 2 IR 05000275/20244042024-10-23023 October 2024 Security Baseline Inspection Report 05000275/2024404 and 05000323/2024404 ML24277A0292024-10-18018 October 2024 NRC to Fws Req. for Concurrence W. Endangered Species Act Determinations for Diablo Canyon Power Plant Units 1,2, ISFSI Proposed License Renewals in San Luis Obispo Co., CA DCL-24-092, Supplement and Annual Update License Renewal Application, Amendment 12024-10-14014 October 2024 Supplement and Annual Update License Renewal Application, Amendment 1 DCL-24-098, Material Status Report for the Period Ending August 31, 20242024-10-0909 October 2024 Material Status Report for the Period Ending August 31, 2024 DCL-24-091, Response to Request for Additional Information by the Office of Nuclear Reactor Regulation2024-10-0303 October 2024 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation IR 05000275/20253012024-10-0303 October 2024 Notification of NRC Initial Operator Licensing Examination 05000275/2025301; 05000323/2025301 ML24240A0222024-09-20020 September 2024 Letter to A. Peck Environmental Impact Statement Scoping Summary Report for Diablo Canyon Nuclear Power Plant Units 1 and 2 ML24260A1222024-09-14014 September 2024 14 Sept 2024 Ltr - California Coastal Commission to Pg&E, Incomplete Consistency Certification for Requested Nuclear Regulatory Commission License Renewal for Diablo Canyon Power Plant DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) ML24262A2462024-09-11011 September 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Petitioner Response to Acknowledgement Letter - DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - IR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 DCL-24-079, DC-2024-07 Post Exam Comments Analysis2024-08-0202 August 2024 DC-2024-07 Post Exam Comments Analysis IR 05000275/20240122024-07-31031 July 2024 License Renewal Report 05000275/2024012 and 05000323/2024012 DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 2024-09-09
[Table view] |
Text
Violet Sage Walker, Chairwoman Northern Chumash Tribal Council P.O. Box 6533 Los Osos, CA 93412
SUBJECT:
CONSULTATION UNDER SECTION 106 OF THE NATIONAL HISTORIC PRESERVATION ACT REGARDING THE DIABLO CANYON INDEPENDENT SPENT FUEL STORAGE INSTALLATION (ISFSI) LICENSE RENEWAL REQUEST (DOCKET NUMBER: 72-26)
Dear Chairwoman Violet Sage Walker:
The U.S. Nuclear Regulatory Commission (NRC) staff has received, by letter dated March 9, 2022, an application from Pacific Gas and Electric (PG&E) to renew Special Nuclear Material License (SNM)-2511 for the Diablo Canyon Independent Spent Fuel Storage Installation (ISFSI). In 2004, the NRC issued PG&E a 20-year license to receive, possess, store, and transfer Diablo Canyon Power Plant spent fuel to the Diablo Canyon ISFSI. The current license expires on March 22, 2024. If this renewal is approved, PG&E would be authorized to continue interim storage of spent fuel at the Diablo Canyon ISFSI for a 40-year period, beginning on March 23, 2024. The Diablo Canyon ISFSI is located on the California coast in San Luis Obispo County, California, roughly equidistant from San Francisco and Los Angeles (site layout enclosed).
The NRC staff is preparing an environmental assessment (EA) associated with its considerations of this request in accordance with the NRC regulation in Title 10 of the Code of Federal Regulations Part 51 that implements the National Environmental Policy Act of 1969, as amended (NEPA). Consistent with 36 CFR 800.8(c), Use of the NEPA process for section 106 purposes, the NRC staff has chosen to use the process and documentation required for the preparation of an EA to comply with Section 106 in lieu of the procedures set forth in 36 CFR 800.3 through 800.6. The EA will include an analysis of potential impacts to historic and cultural resources. The request does not include new construction at the existing Diablo Canyon ISFSI.
Because you have expressed interested in engaging with the NRC about the Diablo Canyon site in the past, the NRC staff is requesting any information you may have regarding historic or cultural resources that may be affected by the proposed ISFSI license renewal, such as specific sites that have traditional religious or cultural significance to your Tribe.
On Nov 7th, 2023, PG&E submitted an application to renew the two Diablo Canyon Power Plant Licenses DPR-80 and DPR-82 (ML23311A154). This proposed action for the Diablo Canyon ISFSI License SNM-2511 is separate from the proposed renewal of the two Diablo Canyon Power Plant Licenses DPR-80 and DPR-82. The NRC staff will be conducting a separate Section 106 consultation for the proposed license renewal of the power plants and will reach out to you in a separate letter regarding that action.
November 27, 2023
V. Sage Walker 2
The Diablo Canyon ISFSI license renewal application is publicly available in the NRC Public Document Room located at One White Flint North, 11555 Rockville Pike, Rockville, Maryland 20852, or from the NRCs Agencywide Documents Access and Management System [ADAMS].
The ADAMS Public Electronic Reading Room is accessible at: http://www.nrc.gov/reading-rm/adams.html. The application is found at ML22068A189.
Please submit any information you may have regarding this environmental review within 30 days of receipt of this letter to the U.S. Nuclear Regulatory Commission, ATTN: Michelle Rome, Chief, 11555 Rockville Pike, Mail Stop T-4B16, Rockville, Maryland 20852.
If you have any questions, please contact Jean Trefethen via email at jean.trefethen@nrc.gov or via phone at 301-415-0867. Thank you for your assistance.
Sincerely, John M. Moses, Deputy Director Division of Rulemaking, Environmental and Financial Support Office of Nuclear Material Safety and Safeguards Docket No.: 72-26
Enclosures:
1.
Diablo Canyon ISFSI Site Layout (from PG&E 2022 Diablo Canyon ISFSI LRA)-
2.
Diablo Canyon ISFSI Controlled Area Boundary (from PG&E 2022 Diablo Canyon ISFSI LRA)
Signed by Moses, John on 11/27/23
ML23307A006
- concurrence via email OFFICE NMSS/REFS NMSS/REFS NMSS/REFS/
DD NMSS/REFS
/OGC NMSS/RE FS/DD NAME IJohnston AWalker-Smith MRome AGendelma n