MONTHYEARML24302A2622024-11-0101 November 2024 Letter to CA SHPO Regarding DCPP Dseis ML24302A1922024-11-0101 November 2024 Ltr to G. Frausto Coastal Band of Chumash Indians Re DCPP Dseis ML24302A1952024-11-0101 November 2024 Ltr to M. Olivas Tucker Ytt Re DCPP Dseis ML24302A1912024-11-0101 November 2024 Ltr to C. Mcdarment Tule River Tribe Re DCPP Dseis ML24302A1942024-11-0101 November 2024 Ltr to K. Kahn Santa Ynez Band of Chumash Indians Re DCPP Dseis ML24302A1962024-11-0101 November 2024 Ltr to SLO County Chumash Indians Re DCPP Dseis ML24302A1932024-11-0101 November 2024 Letter to G. Pierce Salinan Tribe of Monterey, SLO Re DCPP Dseis ML24302A1972024-11-0101 November 2024 Letter to V. Sage Walker Northern Chumash Tribal Council Re DCPP Dseis ML24302A2612024-11-0101 November 2024 Letter to Achp Re DCPP Dseis ML24275A0622024-10-30030 October 2024 NRC to NMFS Request Initiate Formal Endangered Species Act Consultation and Abbreviated Essential Fish Habitat for Proposed License Renewal of DCP Plant Units 1, 2 IR 05000275/20240032024-10-30030 October 2024 Integrated Inspection Report 05000275/2024003 and 05000323/2024003 and Independent Spent Fuel Storage Installation Report 07200026/2024001 ML24269A0122024-10-29029 October 2024 OEDO-24-00083 2.206 Petition Diablo Canyon Seismic CDF - Response to Petitioner Letter ML24284A3122024-10-28028 October 2024 Ltr to P Ting, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants ML24284A3112024-10-28028 October 2024 Ltr to a Peck, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants IR 05000275/20240132024-10-28028 October 2024 – License Renewal Report 05000275/2024013 and 05000323/2024013 DCL-24-103, Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 22024-10-24024 October 2024 Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 2 ML24261B9492024-10-24024 October 2024 Issuance of Amendment Nos. 246 and 248 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) IR 05000275/20244042024-10-23023 October 2024 Security Baseline Inspection Report 05000275/2024404 and 05000323/2024404 ML24277A0292024-10-18018 October 2024 NRC to Fws Req. for Concurrence W. Endangered Species Act Determinations for Diablo Canyon Power Plant Units 1,2, ISFSI Proposed License Renewals in San Luis Obispo Co., CA DCL-24-092, Supplement and Annual Update License Renewal Application, Amendment 12024-10-14014 October 2024 Supplement and Annual Update License Renewal Application, Amendment 1 DCL-24-098, Material Status Report for the Period Ending August 31, 20242024-10-0909 October 2024 Material Status Report for the Period Ending August 31, 2024 DCL-24-091, Response to Request for Additional Information by the Office of Nuclear Reactor Regulation2024-10-0303 October 2024 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation IR 05000275/20253012024-10-0303 October 2024 Notification of NRC Initial Operator Licensing Examination 05000275/2025301; 05000323/2025301 ML24240A0222024-09-20020 September 2024 Letter to A. Peck Environmental Impact Statement Scoping Summary Report for Diablo Canyon Nuclear Power Plant Units 1 and 2 ML24260A1222024-09-14014 September 2024 14 Sept 2024 Ltr - California Coastal Commission to Pg&E, Incomplete Consistency Certification for Requested Nuclear Regulatory Commission License Renewal for Diablo Canyon Power Plant DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) ML24262A2462024-09-11011 September 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Petitioner Response to Acknowledgement Letter - DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - IR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 DCL-24-079, DC-2024-07 Post Exam Comments Analysis2024-08-0202 August 2024 DC-2024-07 Post Exam Comments Analysis DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL ML24155A2182024-06-18018 June 2024 OEDO-23-00350-NRR - (LTR-23-0228-1) - Closure Letter - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24129A1762024-06-14014 June 2024 National Historic Preservation Act Section 106 Consultation – Results of Identification and Evaluation (Docket Number: 72-026) ML24200A2052024-06-0707 June 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project for Diablo Canyon License Renewal ML24099A2192024-05-29029 May 2024 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24117A0132024-05-20020 May 2024 Letter to Paula Gerfen-Diablo Canyon Units 1 and 2-Regulatory Audit Regarding Severe Accident Mitigation Alternatives for the License Renewal Application 2024-09-09
[Table view] |
Text
Ms. Paula Gerfen Senior Vice President, Generation and Chief Nuclear Officer Pacific Gas and Electric Company Diablo Canyon Nuclear Power Plant P.O. Box 56 Mail Code 104/6 Avila Beach, CA 93424
SUBJECT:
DIABLO CANYON NUCLEAR POWER PLANT, UNITS 1 AND 2 -
DETERMINATION OF ACCEPTABILITY AND SUFFICIENCY FOR DOCKETING AND NOTICE OF OPPORTUNITY TO REQUEST A HEARING REGARDING PACIFIC GAS AND ELECTRIC COMPANYS APPLICATION FOR LICENSE RENEWAL
Dear Ms. Gerfen:
By letter dated November 7, 2023 (Agencywide Documents Access and Management System Accession No. ML23311A154), Pacific Gas and Electric Company submitted an application for the renewal of Facility Operating License Nos. DPR-80 and DPR-82 for Diablo Canyon Nuclear Power Plant (DCPP), Units 1 and 2 to the U.S. Nuclear Regulatory Commission (NRC). By letter dated November 14, 2023 (ML23293A105), and Federal Register Notice dated November 20, 2023 (88 FR 80780), the NRC noticed the receipt and availability of this application.
The NRC staff has determined that the application contains sufficient information for the agency to formally docket the application and begin its safety and environmental reviews. Docketing the application does not preclude the NRC from requesting additional information as the reviews proceed, and it does not indicate whether the NRC will renew the licenses.
The NRC staffs acceptance review of an application is intended to identify whether the application is reasonably complete and conforms to the timing and information requirements in applicable regulations. The NRC staff reviewed the DCPP license renewal application following the guidance in NUREG-1800, Revision 2, Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants, and NUREG-1555, Supplement 1, Revision 1, Standard Review Plans for Environmental Reviews for Nuclear Power Plants, to determine if the application is sufficient and acceptable for docketing in accordance with Title 10 of the Code of Federal Regulations (10 CFR) Sections 2.101, Filing of application, 51.45, Environmental report, 51.53(c), Operating license renewal stage, 54.19, Contents of applicationgeneral information, 54.21, Contents of applicationtechnical information, 54.22, Contents of applicationtechnical specifications, and 54.23, Contents of applicationenvironmental information. The NRC staff also conducted four pre-submittal meetings regarding the DCPP license renewal application, as documented in letters dated January 6, 2023 (ML23004A149),
June 1, 2023 (ML23143A226), June 23, 2023 (ML23172A196), and September 26, 2023 (ML23265A190). December 19, 2023 Based on the results of the NRC staffs sufficiency review, the staff has concluded that the DCPP license renewal application is acceptable for docketing. Given the lesser scope and depth of the acceptance review as compared to a detailed technical review, the NRC staffs determination does not preclude requests for additional information or topic-specific audits.
During the NRC staffs detailed technical review, there may be instances identified in which issues that impact the staffs ability to complete the detailed technical review are identified. You will be notified by separate correspondence if any further information is needed to support the NRC staffs detailed technical review.
The NRC staff is in the process of formulating its projected review schedule and resource estimates for the DCPP license renewal application to complete the reviews required by 10 CFR Parts 51, Environmental Protection Regulations for Domestic Licensing and Related Regulatory Functions, and 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants. The NRC staff will provide you with its projected review schedule and resource estimates by separate correspondence.
Enclosed is a copy of the notice related to the DCPP license renewal application that is being sent to the Office of the Federal Register for publication. This notice announces the acceptance for docketing of and the opportunity to request a hearing and to petition for leave to intervene on the application. The NRCs regulations require a minimum of 60 days to request a hearing and petition for leave to intervene. Here, in consideration of the holiday season, the NRC staff is extending the time period for requesting a hearing and petitioning for leave to intervene to 75 days from the date of the publication of the notice in the Federal Register.
If you have any questions on this matter, please contact Mr. Brian Harris by email at Brian.Harris2@nrc.gov or Ms. Kimberly Conway by email at Kimberly.Conway@nrc.gov.
Sincerely, Brian K, Harris, Senior Project Manager License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-275 and 50-323
Enclosure:
Copy of Federal Register Notice cc w/encl: Listserv Signed by Harris, Brian on 12/19/23
Pkg: ML23341A002 Letter: ML23341A004 FRN: ML23341A003 NRR-106 OFFICE NRR/DNRL/NLRP/PM NRR/ DNRL/NLIB/LA NRR/DNRL/NLRP/BC NMSS/REFS/EPMB1/BC NAME BHarris SGreen LGibson SKoenick DATE 12/05/23 12/07/23 12/07/23 12/11/23 OFFICE NRR/DNRL/D OGC NRR/DNRL/NLRP/PM NAME BSmith: SLee for JWachutka BHarris DATE 12/11/23 12/14/23