IR 05000275/2016002

From kanterella
Jump to navigation Jump to search
NRC Inspection Report 05000275/2016002 and 05000323/2016002
ML16215A511
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 08/02/2016
From: Jeremy Groom
NRC/RGN-IV/DRP/RPB-A
To: Halpin E
Pacific Gas & Electric Co
Jeremy Groom
References
IR 2016002
Download: ML16215A511 (47)


Text

UNITED STATES ust 2, 2016

SUBJECT:

DIABLO CANYON POWER PLANT - NRC INSPECTION REPORT 05000275/2016002 AND 05000323/2016002

Dear Mr. Halpin:

On June 30, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Diablo Canyon Power Plant, Units 1 and 2. On July 13, 2016, the NRC inspectors discussed the results of this inspection with Mr. J. Welsch and other members of your staff.

Inspectors documented the results of this inspection in the enclosed inspection report.

NRC inspectors documented one finding of very low safety significance (Green) in this report.

This finding involved a violation of NRC requirements. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the NRC Enforcement Policy.

If you contest the violation or significance of the NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC resident inspector at the Diablo Canyon Power Plant.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC resident inspector at the Diablo Canyon Power Plant.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Jeremy R. Groom, Chief Project Branch A Division of Reactor Projects Docket Nos. 50-275 and 50-323 License Nos. DPR-80 and DPR-82 Enclosure:

Inspection Report 05000275/2016002 and 05000323/2016002 w/ Attachments:

1.) Supplemental Information 2.) RFI for Inservice Inspection 3.) RFI for Occupational Radiation Safety Inspection cc w/ enclosure: Electronic Distribution

SUMMARY

IR 05000275/2016002, 05000323/2016002; 04/01/2016 - 06/30/2016; Diablo Canyon Power

Plant; Problem Identification and Resolution.

The inspection activities described in this report were performed between April 1 and June 30, 2016, by the resident inspectors at Diablo Canyon Power Plant and inspectors from the NRCs Region IV office. One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. The significance of inspection findings is indicated by their color (Green, White, Yellow, or Red), which is determined using Inspection Manual Chapter 0609, Significance Determination Process. Their cross-cutting aspects are determined using Inspection Manual Chapter 0310, Aspects within the Cross-Cutting Areas. Violations of NRC requirements are dispositioned in accordance with the NRC Enforcement Policy. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process.

Cornerstone: Barrier Integrity

Green.

The inspectors reviewed a self-revealed, non-cited violation of Technical Specification (TS) 5.4.1.a, Procedures, for the licensees failure to place a spent fuel assembly in its correct location in the spent fuel pool (SFP) in accordance with Procedure OP B-8H, Spent Fuel Pool Work Instructions. Specifically, the fuel handling crew moved spent fuel assembly TT69 to location E-37 rather than its intended location E-27. In response to this error, reactor engineering performed a technical specification verification in order to ensure that fuel assembly TT69 could remain in Cell E-37. The licensee suspended further fuel movements pending corrective action and remediation of the operators. The licensee entered this into the corrective action program as Notifications 50846834 and 50847067.

The licensees failure to place a spent fuel assembly in its correct location in the SFP was a performance deficiency. The performance deficiency is more than minor, and therefore a finding, because it is associated with the configuration control attribute of the Barrier Integrity Cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers (fuel cladding, reactor coolant system, and containment) protect the public from radionuclide releases caused by accidents or events. Using Inspection Manual Chapter 0609, Attachment 04, Initial Characterization of Findings, and Appendix A, Exhibit 3, Barrier Integrity Screening Questions, the inspectors determined that the finding was of very low safety significance (Green) because: (1) the finding did not adversely affect decay heat removal capabilities from the spent fuel pool causing the pool temperature to exceed the maximum analyzed temperature limit specified in the site-specific licensing basis, (2) the finding did not result from fuel handling errors, dropped fuel assembly, dropped storage cask, or crane operations over the SFP that caused mechanical damage to fuel clad and a detectible release of radionuclides, (3) the finding did not result in a loss of spent fuel pool water inventory decreasing below the minimum analyzed level limit specified in the site-specific licensing basis, and (4) the finding did not affect the SFP neutron absorber, fuel bundle misplacement (i.e., fuel loading pattern error) or soluble Boron concentration. This finding had a cross-cutting aspect in the area of human performance associated with avoiding complacency. Specifically, individuals failed to recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes and individuals failed to implement appropriate error reduction tools (Section 4OA2). [H.12]

PLANT STATUS

Units 1 and 2 began the inspection period at full power.

On April 22, 2016, Unit 1, reduced power to 88 percent power for planned main turbine testing and returned to full power that same day.

On May 1, 2016, Unit 2, was shut down for a planned refueling outage. On June 2, 2016, Unit 2 returned to operation and began a controlled power ascension; it returned to full power on June 8, 2016.

Units 1 and 2 operated at or near full power for the remainder of this inspection period.

REPORT DETAILS

REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity

1R01 Adverse Weather Protection

Readiness for Impending Adverse Weather Conditions

a. Inspection Scope

On April 25, 2016, the inspectors completed an inspection of the stations readiness for impending adverse weather conditions. The inspectors reviewed plant design features, the licensees procedures to respond to high winds, and the licensees implementation of these procedures. The inspectors evaluated operator staffing and accessibility of controls and indications for those systems required to control the plant.

These activities constituted one sample of readiness for impending adverse weather conditions, as defined in Inspection Procedure 71111.01.

b. Findings

No findings were identified.

1R04 Equipment Alignment

Partial Walk-Down

a. Inspection Scope

The inspectors performed partial system walk-downs of the following risk-significant systems:

  • April 25, 2016, Unit 2, safety injection pump 2-1
  • May 17, 2016, Unit 2, auxiliary seawater pumps 2-1 and 2-2
  • June 3, 2016, Unit 2, component cooling water system

The inspectors reviewed the licensees procedures and system design information to determine the correct lineup for the systems. They visually verified that critical portions of the systems were correctly aligned for the existing plant configuration.

These activities constituted four partial system walk-down samples as defined in Inspection Procedure 71111.04.

b. Findings

No findings were identified.

1R05 Fire Protection

.1 Quarterly Inspection

a. Inspection Scope

The inspectors evaluated the licensees fire protection program for operational status and material condition. The inspectors focused their inspection on five plant areas important to safety:

  • April 11, 2016, Unit 1 and 2, 480V Switchgear Rooms and Hot Shutdown Panel; Fire Areas 5-A/B-1, 5-A/B-2, 5-A/B-3, and 5-A/B-4
  • May 13, 2016, Unit 1 and 2, , auxiliary building elevation 128 foot; Fire Areas 7A and 7B
  • May 16, 2016, Unit 1 and 2, intake structure; Fire Areas 30-A-1 through 30-A-5,
  • May 19, 2016, Unit 1 and 2, 12 kV switchgear room and cable spreading rooms; Fire Areas 10 and 20
  • June 3, 2016, Unit 2, turbine building 85 foot elevation; Fire Area TB-7 For each area, the inspectors evaluated the fire plan against defined hazards and defense-in-depth features in the licensees fire protection program. The inspectors evaluated control of transient combustibles and ignition sources, fire detection and suppression systems, manual firefighting equipment and capability, passive fire protection features, and compensatory measures for degraded conditions.

These activities constituted five quarterly inspection samples, as defined in Inspection Procedure 71111.05.

b. Findings

No findings were identified.

.2 Annual Inspection

a. Inspection Scope

On April 13, 2016, the inspectors completed their annual evaluation of the licensees fire brigade performance. This evaluation included observation of an announced fire drill associated with a simulated fire in the Unit 1 turbine generator.

During this drill, the inspectors evaluated the capability of the fire brigade members, the leadership ability of the brigade leader, the brigades use of turnout gear and fire-fighting equipment, and the effectiveness of the fire brigades team operation. The inspectors also reviewed whether the licensees fire brigade met NRC requirements for training, dedicated size and membership, and equipment.

These activities constituted one annual inspection sample, as defined in Inspection Procedure 71111.05.

b. Findings

No findings were identified.

1R08 Inservice Inspection Activities

The activities described in subsections 1 through 4 below constitute completion of one inservice inspection sample, as defined in Inspection Procedure 71111.08.

.1 Non-destructive Examination Activities and Welding Activities

a. Inspection Scope

The inspectors directly observed the following nondestructive examinations:

SYSTEM WELD IDENTIFICATION EXAMINATION TYPE Residual Heat Removal Hot Leg Recirculation Before Ultrasonic V-8702 Weld No. WIB-245 Residual Heat Removal Hot Leg Recirculation Before Ultrasonic V-8702 Weld No. WIB-246 Reactor Vessel Radial Support Keys Visual (VT-3)

Steam Generator Steam Generator 2-1 Top Ultrasonic Head/Shell Weld Pressurizer WIB-359OL (Safety C) Ultrasonic Phased Array The inspectors reviewed records for the following nondestructive examinations:

SYSTEM WELD IDENTIFICATION EXAMINATION TYPE Safety Injection Accumulator 2-2, Nozzle C-1A Liquid Penetrant

SYSTEM WELD IDENTIFICATION EXAMINATION TYPE Safety Injection Accumulator 2-2, Nozzle C-1A Ultrasonic (Refueling Outages 2R10, 2R12,

2R14 , 2R16, 2R18 and 2R19)

Residual Heat Removal Valve RHR-2-1028 Weld Liquid Penetrant No. FW-3 Residual Heat Removal Hot Leg Recirculation Before Ultrasonic V-8702 Weld No. WIB-245 (PSI and Second 10-year ISI)

Residual Heat Removal Hot Leg Recirculation Before Radiograph V-8702 Weld No. WIB-245 (Construction)

During the review and observation of each examination, the inspectors observed whether activities were performed in accordance with the ASME Code requirements and applicable procedures. The inspectors reviewed two indications that were previously examined and observed whether the licensee evaluated and accepted the indications in accordance with the ASME Code and/or an NRC approved alternative. The inspectors also reviewed the qualifications of all nondestructive examination technicians performing the inspections to determine whether they were current.

The inspectors performed a focused review of a flaw found on weld WIB-245 noted in the table above, and documented in Notification 50852155. The flaw was identified during a scheduled ultrasonic examination in the residual heat removal system on a pipe-to-elbow weld. The licensee sized the flaw and found it to be unacceptable per ASME Code,Section XI, Table IWB 3514-2, Allowable Planar Flaws. Subsequently, the licensee completed an evaluation of the flaw using the criteria in IWB-3640, Evaluation Procedure and Acceptance Criteria for Flaws in Austenitic and Ferritic Piping, and Section XI, Appendix C, Evaluation of Flaws in Piping. At the time of the inspection, the inspectors verified that the flaw analysis was acceptable per ASME Code requirements. Specifically, the inspectors verified that the analysis took into consideration the most limiting degradation mechanism and that the crack growth analysis bounded those conditions.

The inspectors directly observed a portion of the following welding activities:

SYSTEM WELD IDENTIFICATION WELDING TYPE Residual Heat Removal Valve RHR-2-1028 Gas Tungsten Arc Weld No. FW-3 Welding The inspectors reviewed records for the following welding activities:

SYSTEM WELD IDENTIFICATION WELDING TYPE Safety Injection Accumulator 2-2 Nozzle C-1A Gas Tungsten Arc Weld No. 1 and 2 Welding

The inspectors reviewed whether the welding procedure specifications and the welders had been properly qualified in accordance with ASME Code Section IX requirements.

The inspectors also determined whether that essential variables were identified, recorded in the procedure qualification record, and formed the bases for qualification of the welding procedure specifications.

b. Findings

No findings were identified.

.2 Vessel Upper Head Penetration Inspection Activities

a. Inspection Scope

No inspection of the reactor vessel upper head penetration was performed.

b. Findings

No findings were identified.

.3 Boric Acid Corrosion Control Inspection Activities

a. Inspection Scope

The inspectors reviewed the licensees implementation of its boric acid corrosion control program for monitoring degradation of those systems that could be adversely affected by boric acid corrosion. The inspectors reviewed the documentation associated with the licensees boric acid corrosion control walk-down as specified in Procedure ER1.ID2, Boric Acid Corrosion Control Program, Revision 7. The inspectors reviewed whether the visual inspections emphasized locations where boric acid leaks could cause degradation of safety-significant components, and whether engineering evaluation used corrosion rates applicable to the affected components and properly assessed the effects of corrosion-induced wastage on structural or pressure boundary integrity. The inspectors observed whether corrective actions taken were consistent with the ASME Code and 10 CFR 50, Appendix B, requirements.

b. Findings

No findings were identified.

.4 Steam Generator Tube Inspection Activities

a. Inspection Scope

(Secondary Side Inspections)

Steam Generator eddy current examinations were not performed. The inspectors reviewed secondary side inspection results and verified the licensee did not have to take corrective actions in response to the examination results.

b. Findings

No findings were identified.

.5 Identification and Resolution of Problems

a. Inspection Scope

The inspectors reviewed six condition reports which dealt with inservice inspection activities and found the corrective actions for inservice inspection issues were appropriate. From this review, the inspectors concluded that the licensee has an appropriate threshold for entering inservice inspection issues into the corrective action program and has procedures that direct a root cause evaluation when necessary. The licensee also has an effective program for applying industry inservice inspection operating experience. Specific documents reviewed during this inspection are listed in the attachment.

b. Findings

No findings were identified.

1R11 Licensed Operator Requalification Program and Licensed Operator Performance

.1 Review of Licensed Operator Requalification

a. Inspection Scope

On June 21, 2016, the inspectors observed an evaluated simulator scenario performed by an operating crew. The inspectors assessed the performance of the operators and the evaluators critique of their performance. The inspectors also assessed the modeling and performance of the simulator during the simulator training scenario.

These activities constituted completion of one quarterly licensed operator requalification program sample, as defined in Inspection Procedure 71111.11.

b. Findings

No findings were identified.

.2 Review of Licensed Operator Performance

a. Inspection Scope

The inspectors observed the performance of on-shift licensed operators in the plants main control room. At the time of the observations, the plant was in a period of heightened activity. The inspectors observed the operators performance of the following activities:

  • April 4-5, 2016, Unit 1, air side AC seal oil pump replacement and adjustment of seal oil regulating valves, associated with the main turbine hydrogen seal oil system, due to the high risk of a turbine trip, including the pre-job brief

In addition, the inspectors assessed the operators adherence to plant procedures, including the conduct of operations procedure and other operations department policies.

These activities constituted completion of one quarterly licensed operator performance samples, as defined in Inspection Procedure 71111.11.

b. Findings

No findings were identified.

1R12 Maintenance Effectiveness

a. Inspection Scope

The inspectors reviewed two instances of degraded performance or condition of safety-related structures, systems, and components (SSCs):

  • June 29, 2016, 480 V ac switchgear room ventilation system performance criteria review, Notification 50684617 The inspectors reviewed the extent of condition of possible common cause SSC failures and evaluated the adequacy of the licensees corrective actions. The inspectors reviewed the licensees work practices to evaluate whether these may have played a role in the degradation of the SSCs. The inspectors assessed the licensees characterization of the degradation in accordance with 10 CFR 50.65 (the Maintenance Rule), and verified that the licensee was appropriately tracking degraded performance and conditions in accordance with the Maintenance Rule.

These activities constituted completion of two maintenance effectiveness samples, as defined in Inspection Procedure 71111.12.

b. Findings

No findings were identified.

1R13 Maintenance Risk Assessments and Emergent Work Control

a. Inspection Scope

The inspectors reviewed four risk assessments performed by the licensee prior to changes in plant configuration and the risk management actions taken by the licensee in response to elevated risk:

  • May 1, 2016, elevated risk during Unit 2, 4160 volt bus G auto-transfer testing, Surveillance Test Procedure STP M-13G
  • May 3, 2016, elevated risk during Unit 2, performance of integrated plant testing, Surveillance Test Procedure STP M-15
  • June 6, 2016, elevated risk during Unit 2, ATWS [Anticipated Transient Without Scram] mitigation actuation system inoperability, Notification 50856997
  • June 9, 2016, elevated risk during Unit 1, 480 volt switchgear cooling fans online maintenance, Notification 50818501 The inspectors verified that these risk assessments were performed timely and in accordance with the requirements of 10 CFR 50.65 (the Maintenance Rule) and plant procedures. The inspectors reviewed the accuracy and completeness of the licensees risk assessments and verified that the licensee implemented appropriate risk management actions based on the result of the assessments.

The inspectors verified that the licensee appropriately developed and followed a work plan for these activities. The inspectors verified that the licensee took precautions to minimize the impact of the work activities on unaffected SSCs.

These activities constituted completion of four maintenance risk assessments and emergent work control inspection samples, as defined in Inspection Procedure 71111.13.

b. Findings

No findings were identified.

1R15 Operability Determinations and Functionality Assessments

a. Inspection Scope

The inspectors reviewed three operability determinations that the licensee performed for degraded or nonconforming SSCs:

  • June 27, 2016, operability evaluation of degraded condition identified during inspections of reactor vessel baffle former bolting as reported in event reports and industry experience, Notification 50848011 The inspectors reviewed the timeliness and technical adequacy of the licensees evaluations. Where the licensee determined the degraded SSC to be operable, the inspectors verified that the licensees compensatory measures were appropriate to provide reasonable assurance of operability. The inspectors verified that the licensee had considered the effect of other degraded conditions on the operability of the degraded SSC.

These activities constituted completion of three operability and functionality review samples, as defined in Inspection Procedure 71111.15.

b. Findings

No findings were identified.

1R18 Plant Modifications

a. Inspection Scope

On May 27, 2016, the inspectors reviewed a Unit 2, temporary plant modification that installed, temporary temperature monitoring thermocouples around residual heat removal piping per TMOD 60090550.

The inspectors verified that the licensee had installed this temporary modification in accordance with technically adequate design documents. The inspectors verified that this modification did not adversely impact the operability or availability of affected SSCs.

The inspectors reviewed design documentation and plant procedures affected by the modification to verify the licensee maintained configuration control.

These activities constituted completion of one sample of temporary modifications, as defined in Inspection Procedure 71111.18.

b. Findings

No findings were identified.

1R19 Post-Maintenance Testing

a. Inspection Scope

The inspectors reviewed four post-maintenance testing activities that affected risk-significant SSCs:

  • May 2, 2016, Unit 2, component cooling water pump 2-2 functional testing of relay 2 FS267 following replacement, Maintenance Procedure MP E-60.2HG12
  • May 31, 2016, Unit 2, post maintenance testing following replacement of rod control fuses, Work Order 64104543 The inspectors reviewed licensing- and design-basis documents for the SSCs and the maintenance and post-maintenance test procedures. The inspectors observed the performance of the post-maintenance tests to verify that the licensee performed the tests in accordance with approved procedures, satisfied the established acceptance criteria, and restored the operability of the affected SSCs.

These activities constituted completion of four post-maintenance testing inspection samples, as defined in Inspection Procedure 71111.19.

b. Findings

No findings were identified.

1R20 Refueling and Other Outage Activities

a. Inspection Scope

During the stations refueling outage that concluded on June 2, 2016, the inspectors evaluated the licensees outage activities. The inspectors verified that the licensee considered risk in developing and implementing the outage plan, appropriately managed personnel fatigue, and developed mitigation strategies for losses of key safety functions.

This verification included the following:

  • Review of the licensees outage plan prior to the outage
  • Review and verification of the licensees fatigue management activities
  • Monitoring of shut-down and cool-down activities
  • Verification that the licensee maintained defense-in-depth during outage activities
  • Observation and review of reduced-inventory and mid-loop activities
  • Monitoring of heat-up and startup activities These activities constituted completion of one refueling outage sample, as defined in Inspection Procedure 71111.20.

b. Findings

No findings were identified.

1R22 Surveillance Testing

a. Inspection Scope

The inspectors observed six risk-significant surveillance tests and reviewed test results to verify that these tests adequately demonstrated that the SSCs were capable of performing their safety functions:

In-service tests:

  • April 8, 2016, Unit 1, safety injection pump 1-1 surveillance test, per Procedure STP P-SIP-11 Containment isolation valve surveillance tests:
  • May 8, 2016, Unit 1, penetration 82 containment isolation valve leak test, per Procedure STP V-682B
  • May 19, 2016, Unit 2, penetration 30 containment isolation valve leak test, per Procedure STP V-630B Reactor coolant system leak detection tests:

Other surveillance tests:

  • April 22, 2016, Unit 1, main turbine stop, governor and intercept valve test, per Procedure STP M-21C
  • May 30-31, 2016, Unit 2, digital rod position indication functional test, per Procedure STP R-1C The inspectors verified that these tests met technical specification requirements, that the licensee performed the tests in accordance with their procedures, and that the results of the test satisfied appropriate acceptance criteria. The inspectors verified that the licensee restored the operability of the affected SSCs following testing.

These activities constituted completion of six surveillance testing inspection samples, as defined in Inspection Procedure 71111.22.

b. Findings

No findings were identified.

RADIATION SAFETY

Cornerstones: Public Radiation Safety and Occupational Radiation Safety

2RS1 Radiological Hazard Assessment and Exposure Controls

a. Inspection Scope

The inspectors evaluated the licensees performance in assessing the radiological hazards in the workplace associated with licensed activities. The inspectors assessed the licensees implementation of appropriate radiation monitoring and exposure control measures for both individual and collective exposures. During the inspection, the inspectors interviewed licensee personnel, walked down various areas in the plant, performed independent radiation dose rate measurements, and observed postings and physical controls. The inspectors reviewed licensee performance in the following areas:

  • Radiological hazard assessment, including a review of the plants radiological source terms and associated radiological hazards. The inspectors also reviewed the licensees radiological survey program to determine whether radiological hazards were properly identified for routine and non-routine activities and assessed for changes in plant operations.
  • Instructions to workers including radiation work permit requirements and restrictions, actions for electronic dosimeter alarms, changing radiological conditions, and radioactive material container labeling.
  • Contamination and radioactive material control, including release of potentially contaminated material from the radiologically controlled area, radiological survey performance, radiation instrument sensitivities, material control and release criteria, procedural guidance, and control and accountability of sealed radioactive sources.
  • Radiological hazards control and work coverage. During walk-downs of the facility and job performance observations, the inspectors evaluated ambient radiological conditions, radiological postings, adequacy of radiological controls, radiation protection job coverage, and contamination controls. The inspectors also evaluated dosimetry selection and placement as well as the use of dosimetry in areas with significant dose rate gradients. The inspectors examined the licensees controls for items stored in the spent fuel pool and evaluated airborne radioactivity controls and monitoring.
  • Radiation worker performance and radiation protection technician proficiency with respect to radiation protection work requirements. The inspectors determined if workers were aware of significant radiological conditions in their workplace, radiation work permit controls/limits in place, and electronic dosimeter dose and dose rate set points. The inspectors observed radiation protection technician job performance, including the performance of radiation surveys.
  • Problem identification and resolution for radiological hazard assessment and exposure controls. The inspectors reviewed audits, self-assessments, and corrective action program documents to verify problems were being identified and properly addressed for resolution.

These activities constituted completion of the seven required samples of radiological hazard assessment and exposure control program, as defined in Inspection Procedure 71124.01.

b. Findings

No findings were identified.

2RS2 Occupational ALARA Planning and Controls

a. Inspection Scope

The inspectors assessed licensee performance with respect to maintaining individual and collective radiation exposures as low as is reasonably achievable (ALARA). The inspectors performed this portion of the attachment during the refueling outage, in order to directly observe the licensees ALARA process activities including planning, implementation of radiological work controls, execution of work activities, and ALARA review of work-in-progress. During the inspection the inspectors interviewed licensee personnel, reviewed licensee documents, and evaluated licensee performance in the following areas:

  • Implementation of ALARA and radiological work controls, including a review of the planned radiological administrative, operational, and engineering controls, compared to results achieved in the field.
  • Radiation worker performance, including radiation protection technician performance during work activities performed in radiation areas, airborne radioactivity areas, or high radiation areas.
  • Problem identification and resolution for ALARA and radiological work controls.

The inspectors reviewed audits, self-assessments, and corrective action program documents to verify problems were being identified and properly addressed for resolution.

These activities constituted completion of two of the five required samples of occupational ALARA planning and controls program, as defined in Inspection Procedure 71124.02.

b. Findings

No findings were identified.

OTHER ACTIVITIES

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Security

4OA1 Performance Indicator Verification

.1 Safety System Functional Failures (MS05)

a. Inspection Scope

For the period of April 1, 2015 through March 31, 2016, the inspectors reviewed licensee event reports (LERs), maintenance rule evaluations, and other records that could indicate whether safety system functional failures had occurred. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 7, and NUREG-1022, Event Reporting Guidelines: 10 CFR 50.72 and 50.73, Revision 3, to determine the accuracy of the data reported.

These activities constituted verification of the safety system functional failures performance indicator Units 1 and 2, as defined in Inspection Procedure 71151.

b. Findings

No findings were identified.

.2 Mitigating Systems Performance Index: Emergency AC Power Systems (MS06)

a. Inspection Scope

The inspectors reviewed the licensees mitigating system performance index data for the period of April 1, 2015 through March 31, 2016, to verify the accuracy and completeness of the reported data. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 7, to determine the accuracy of the reported data.

These activities constituted verification of the mitigating system performance index for emergency ac power systems for Units 1 and 2, as defined in Inspection Procedure 71151.

b. Findings

No findings were identified.

.3 Mitigating Systems Performance Index: High Pressure Injection Systems (MS07)

a. Inspection Scope

The inspectors reviewed the licensees mitigating system performance index data for the period of April 1, 2015 through March 31, 2016, to verify the accuracy and completeness of the reported data. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 7, to determine the accuracy of the reported data.

These activities constituted verification of the mitigating system performance index for high pressure injection systems for Units 1 and 2, as defined in Inspection Procedure 71151.

b. Findings

No findings were identified.

.4 Occupational Exposure Control Effectiveness (OR01)

a. Inspection Scope

The inspectors verified that there were no unplanned exposures or losses of radiological control over locked high radiation areas and very high radiation areas during the period of October 1, 2015, to March 31, 2016. The inspectors reviewed a sample of radiologically controlled area exit transactions showing exposures greater than 100 mrem. The inspectors used definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 7, to determine the accuracy of the reported data.

These activities constituted verification of the occupational exposure control effectiveness performance indicator as defined in Inspection Procedure 71151.

b. Findings

No findings were identified.

.5 Radiological Effluent Technical Specifications (RETS)/Offsite Dose Calculation Manual

(ODCM) Radiological Effluent Occurrences (PR01)

a. Inspection Scope

The inspectors reviewed corrective action program records for liquid or gaseous effluent releases that occurred between October 1, 2015, and March 31, 2016, and were reported to the NRC to verify the performance indicator data. The inspectors used

definitions and guidance contained in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 7, to determine the accuracy of the reported data.

These activities constituted verification of the radiological effluent technical specifications (RETS)/offsite dose calculation manual (ODCM) radiological effluent occurrences performance indicator as defined in Inspection Procedure 71151.

b. Findings

No findings were identified.

4OA2 Problem Identification and Resolution

.1 Routine Review

a. Inspection Scope

Throughout the inspection period, the inspectors performed daily reviews of items entered into the licensees corrective action program and periodically attended the licensees condition report screening meetings. The inspectors verified that licensee personnel were identifying problems at an appropriate threshold and entering these problems into the corrective action program for resolution. The inspectors verified that the licensee developed and implemented corrective actions commensurate with the significance of the problems identified. The inspectors also reviewed the licensees problem identification and resolution activities during the performance of the other inspection activities documented in this report.

b. Findings

No findings were identified.

.2 Semiannual Trend Review

a. Inspection Scope

The inspectors reviewed the licensees corrective action program, performance indicators, system health reports, and other documentation to identify trends that might indicate the existence of a more significant safety issue. The inspectors reviewed the corrective action program emergent issue process to assess the licensee integrated response to events impacting equipment performance and requiring enhanced station support.

These activities constituted completion of one semiannual trend review sample, as defined in Inspection Procedure 71152.

b. Observations and Assessments The emerging issue and event investigation process supplements the corrective action program and is controlled by quality-related procedures. The process is used to identify and resolve emergent problems to ensure rigorous and timely responses to conditions that require integrated and enhance station support beyond normal operations. Since January 2016, there have been over fifty emergent issues documented. The inspectors

reviewed several emerging issue summaries to determine if proper work control processes were followed and appropriate corrective actions were taken.

The inspector reviewed the following emerging issue final summaries:

  • May 12, 2016, component cooling water 2-2 damaged wire, Notification 50848143
  • May 16, 2016, RHR-2-8700B broken stem mounted position switch, Notification 50852180
  • May 17, 2016, ultrasonic testing (UT) indication on weld WIB-245, Notification 50852155
  • June 3, 2016, Unit 2, main generator hydrogen leakage, Notification 50856272 The inspectors observed that licensee use of the procedure was well documented including a detailed problem statement, extent of condition, bridging strategies, and documentation of the decision-making processes. The inspectors determined the use of the emergent issues process was well coordinated and implemented in accordance to procedure guidance.

c. Findings

No findings were identified.

.3 Annual Follow-up of Selected Issues

a. Inspection Scope

The inspectors selected the following issue for an in-depth follow-up:

  • On April 20, 2016, Notifications 50846834 and 50847067 documenting a misplaced fuel assembly in the spent fuel pool.

The inspectors assessed the licensees problem identification threshold, cause analyses, extent of condition reviews and compensatory actions. The inspectors verified that the licensee appropriately prioritized the planned corrective actions and that these actions were adequate to correct the condition.

These activities constituted completion of one annual follow-up sample as defined in Inspection Procedure 71152.

b. Findings

Introduction.

The inspectors reviewed a Green, self-revealed, non-cited violation of Technical Specification (TS) 5.4.1.a, Procedures, for the licensees failure to place a spent fuel assembly in its correct location in the spent fuel pool (SFP) in accordance with Procedure OP B-8H, Spent Fuel Pool Work Instructions. Specifically, the fuel handling crew moved spent fuel assembly TT69 to location E-37 rather than to its intended location E-27.

Description.

On April 20, 2016, as part of the preparations for the 2016 Unit 2 refueling outage (2R19), the licensee performed fuel movements per procedure OP B-8H, Spent Fuel Pool Work Instructions. Procedure OP B-8H directs fuel movements per the tracking sheets developed in procedure PEP R-8H, Spent Fuel Pool Fuel Assembly Movement Planning, Attachment 9.1, SFP Fuel or Insert Movement Authorization and Instructions. Step 57 of Attachment 9.1 was to move fuel assembly TT69 from Initial location Z-26 to Final location E-27. The fuel handlers inadvertently moved this fuel assembly to location E-37. The fuel handlers continued moving fuel until Step 63 of 9.1, when they discovered their mistake. This step required operators to move fuel assembly TT57 to location E-37. When the fuel handlers attempted to place fuel assembly TT57 in its Final location, they discovered that there was already an assembly located in cell E-37. Upon discovery of the error, the fuel handlers stopped fuel handling operations, returned fuel assembly TT57 to its Initial location and notified site management.

Subsequent review determined that, as part of the process for moving fuel in the SFP, operators use a white board to track the planned fuel moves. Procedure OP B-8H, Step 4.3.11, allows the use of a white board as an external visual aid: Ensure an external visual aid is available to allow the fuel handlers a quick reference to SFP location (e.g. a white board or electronic display). The Final location used in Step 56 of the move plan was Y-37. As operators prepared to move assembly TT69, the SRO did not fully erase the Y-37. Instead, the operator changed the Y to E and mistakenly left the 37. The fuel handlers failed to recognize the discrepancy between the white board and the procedure, and continued with moving fuel assembly TT69 to the incorrect Final location.

In response to this error, reactor engineering performed a technical specification verification in order to ensure that fuel assembly TT69 could remain in Cell E-37. The licensee suspended further fuel movements pending corrective action and remediation of the operators involved in the error. The licensee entered this issue into the corrective action program as Notifications 50846834 and 50847067 in order to determine the cause of this error.

Analysis.

The licensees failure to place a spent fuel assembly in its correct location in the SFP was a performance deficiency. The performance deficiency is more than minor, and therefore a finding, because it is associated with the configuration control attribute of the Barrier Integrity Cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers (fuel cladding, reactor coolant system, and containment) protect the public from radionuclide releases caused by accidents or events. Using Inspection Manual Chapter 0609, Attachment 04, Initial Characterization of Findings, and Appendix A, Exhibit 3, Barrier Integrity Screening Questions, the inspectors determined that the finding was of very low safety significance (Green) because:

(1) the finding did not adversely affect decay heat removal capabilities from the spent fuel pool causing the pool temperature to exceed the maximum analyzed temperature limit specified in the site-specific licensing basis,
(2) the finding did not result from fuel handling errors, dropped fuel assembly, dropped storage cask, or crane operations over the SFP that caused mechanical damage to fuel clad AND a detectible release of radionuclides,
(3) the finding did not result in a loss of spent fuel pool water inventory decreasing below the minimum analyzed level limit specified in the site-specific licensing basis, and
(4) the finding did not affect the SFP neutron absorber, fuel bundle misplacement (i.e., fuel loading pattern error) or soluble Boron

concentration. This finding had a cross-cutting aspect in the area of human performance associated with avoid complacency. Specifically, individuals failed to recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes, and individuals failed to implement appropriate error reduction tools [H.12].

Enforcement.

Technical Specification 5.4.1(a), Procedures, requires, in part, that written procedures shall be established, implemented and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Appendix A, February 1978, Quality Assurance Program Requirements. Regulatory Guide 1.33, Appendix A, Section 2.k, Preparation for Refueling and Refueling Equipment Operation, requires specific procedures for preparation for refueling and refueling equipment operation. The licensee established procedure OP B-8H, Spent Fuel Pool Work Instructions, Revision 45A, for preparation for refueling and refueling equipment operation to meet the Regulatory Guide 1.33 requirement. Step 6.2.9 of OP B-8H requires operators to, move assembly to final location AND obtain peer check.

Contrary to the above, on April 20, 2016, the licensee failed to move an assembly to its final location and obtain a peer check. Specifically, the licensee failed to move fuel assembly TT69 to location E-27 as required. This violation is being treated as a non-cited violation, consistent with Section 2.3.2.a of the Enforcement Policy, because it was of very low safety significance (Green) and was entered into the licensees corrective action program as Notifications 50846834 and 50847067.

NCV 05000323/2016002-01, Misplaced Spent Fuel Assembly in the Spent Fuel Pool

4OA3 Follow-up of Events and Notices of Enforcement Discretion

(Closed) LER 05000275/1-2015-001-00 and -01: Both Trains of Residual Heat Removal Inoperable Due to Circumferential Crack on a Socket Weld On December 31, 2014, the licensee identified a through-wall leak associated with a socket weld for the Unit 1, residual heat removal system relief valve inside containment.

The event was reportable in accordance to 10 CFR 50.73(a)(2)(v)(B), any event or condition that could have prevented the fulfillment of the safety function of structures or systems, that are needed to; remove residual heat and mitigate the consequences of an accident. The licensee determined the root cause of the cracked socket weld was due to cyclic stress as a result of resonant vibration. Corrective actions included replacing two socket welds, modifying pipe supports, and correcting the condition causing the resonant vibrations.

This issue was reviewed by the NRC, and, as documented in NRC Inspection Report 05000275/2015004, 05000323/2015004 (ML16035A481), the inspectors identified one non-cited violation, NCV 05000275/2015004-02, Failure to Identify a Cause and Implement Actions to Prevent Recurrence of a Significant Condition Adverse to Quality.

All corrective actions and required responses have been completed.

No additional deficiencies were identified during the review of the licensee event report.

This licensee event report is closed.

These activities constituted completion of one event follow-up sample, as defined in Inspection Procedure 71153.

4OA6 Meetings, Including Exit

Exit Meeting Summary

On May 13, 2016, the inspectors presented the radiation safety inspection results to Mr. E.

Halpin, Senior Vice President, Generation and Chief Nuclear Officer, and other members of the licensee staff. The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.

On May 23, 2016, the inspectors presented the inspection results to Mr. J. Welsch, Site Vice President, and other members of the licensee staff. The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.

On July 13, 2016, the resident inspectors presented the inspection results to Mr. J. Welsch, Site Vice President, and other members of the licensee staff. The licensee acknowledged the issues presented. The licensee confirmed that any proprietary information reviewed by the inspectors had been returned or destroyed.

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

T. Baldwin, Director, Nuclear Site Services
E. Brackeen, System Engineer
D. Evans, Director, Security & Emergency Services
M. Franenheim, Manager, Performance Improvement
R. Gagne, Foreman, Radiation Protection
P. Gerfen, Senior Director Plant Manager
M. Ginn, Manager, Emergency Planning
D. Gonzalez, Supervisor, Nuclear Engineering
E. Halpin, Sr. Vice President, Chief Nuclear Officer Generation
H. Hamzehee, Manager, Regulatory Services
M. Hayes, General Foreman, Radiation Protection
A. Heffner, NRC Interface, Regulatory Services
J. Hill, Nuclear Lead ISI, NDE Specialist
J. Hinds, Director, Quality Verification
L. Hopson, Director Maintenance Services
T. Irving, Manager, Radiation Protection
K. Johnston, Director of Operations
J. Loya, Manager, Quality Verification
J. MacIntyre, Director of Equipment Reliability
M. McCoy, NRC Interface, Regulatory Services
C. Miller, Radioactive Waste Engineer, Radiation Protection
J. Morris, Senior Advising Engineer
C. Murry, Director Nuclear Work Management
J. Nimick, Senior Director Nuclear Services
P. Nugent, Director, Quality Verification
A. Peck, Director, Nuclear Engineering
L. Pulley, Manager, Nuclear Projects
R. Rogers, General Foreman, Radiation Protection
M. Sarantos, Foreman, Radiation Protection
L. Sewell, Principle Health Physicist, Radiation Protection
A. Warwick, Supervisor, Emergency Planning
J. Welsch, Site Vice President

LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED

Opened and Closed

Misplaced Spent Fuel Assembly in the Spent Fuel Pool

05000323/2016002-01 NCV

(Section 4OA2.3)

Closed

Both Trains of Residual Heat Removal Inoperable Due to

05000275/1-2015-001-01 LER

Circumferential Crack on a Socket Weld (Section 4OA3)

Attachment 1

Section 1R01: Adverse Weather Protection

Procedure

Number Title Revision

CP M-16 Severe Weather 9

Notifications

50847527 50847529

Section 1R04: Equipment Alignment

Procedures

Number Title Revision

OP J-6B:I-A Unit 2; Diesel Generator 2-1 - Alignment Checklist 0

MA1.ID9 Compressed Gas Cylinder Control 5

OP B-3A:II Safety Injection System Alignment Verification for Plant 23B

Startup

OP K-10A12 Sealed Component Checklist for Safety Injection Pump 2-1 3

OP E-5:I-A Auxiliary Saltwater - Alignment Verification 1

DCM S-14 Component Cooling Water System 28

Notifications

50846801 50847096 50847135 50847138 50831942

50850323

Work Order 64076822

Drawings

Number Description Revision

108010 Residual Heat Removal System 30

57724 Equipment Location Plan @ Elev. 85-0 Auxiliary & 31

Containment Buildings

57725 Equipment Location Plan @ Elev. 91-0 & 100-0 Aux., 33

Containment & Fuel Handling Bldgs.

107714 Component Cooling Water System 65

441311 Component Cooling Water Pumps 28

Section 1R05: Fire Protection

Procedures

Number Title Revision

OM8.ID2 Fire Systems Impairment 19

TQ1.DC12 Fire Brigade and Emergency Response Training 14

Appendix 9.5H Inspection and Testing Requirements and Program 21

FSAR Update Administration

Notifications

50708845 50797482 50704617 50804445 50804409

50852808

Work Orders

68041060 68040600

Drawings

Number Description Revision

111906 Unit 1&2, Auxiliary Building Elev. 115 foot 8

111906 Fire Protection Auxiliary Building 128 foot Elevation 3

4002030 Type Penetration and Door AREA H-Auxiliary Building 4

TB-3 Turbine Building Elevation 85 Unit 1 6

TB-4 Turbine Building Elevation 76 3

TB-5 Turbine Building EV. 85 & 76 Unit 1 4

TB-14 Turbine Building Elevation 85 Unit 2 8

TB-16 Turbine Building EV. 85 & 76 Unit 2 5

111906 sheet 9 Unit 1-140 foot Elev. Pre-fire Plans TB10/TB11 6

PA-1 Intake Structure Unit 1&2 5

PA-2 Intake Structure Unit 1&2 2

111906-32 Intake Structure 18 5

111906, Sheet 11 Turbine Building Elevation 85 Unit 2 8

106718, Sheet 9 Operating Valve ID - Fire Protection 166

106718, Sheet 7 Operating Valve ID - Fire Protection 180

Section 1R08: Inservice Inspection Activities

Procedures

Number Title Revision / Date

NDE PT-1 Visible Dye Liquid Penetrant Examination Procedure 5

ISI X-1 Visual Examination of the Reactor Vessel Interior 7

ISI X-3 Core Plate and Core Support Structure Examination 1

for Foreign Objects

PCR-93-086 Diablo Canyon Unit 2 Accumulator Nozzle April 16, 1993

Replacement Analysis and Technical Support

M000004 Accumulator Nozzle Replacement 2 and 3

OM8.ID1 Fire Loss Prevention 26

WDI-STD-088 Underwater Remote Visual Examination of Reactor 13

Vessel Internals

DCL-93-266 Accumulator Nozzle Cracking Due to Intergranular November 24, 1993

Stress Corrosion

ISI ADD Additional, Supplemental and Successive Inspections 6

SUCCESS

NDE UT ACC Ultrasonic Examination of Accumulator Tank Nozzle 0

NOZ and Similar Fittings

NDE UT-WOL- Manual Phased Array Ultrasonic Examination of Weld 1

PA1 Overlaid Similar and Dissimilar Metal Welds

OM7.ID12 Operability Determination 34

OM7.ID1 Problem Identification and Resolution 48A

Steam Generator Degradation Assessment Refueling 0

Outage 2R19

Notifications

50849012 50662092 50836915 50824452 50848555

50848522

Work Orders

60089765 64072507 68039802 64077050 64002431

R0266133 R0222784

Drawings

Number Title Revision

108009 Safety Injection System 55

26421 Safety Injection System Accumulator Tank 2-2 5

663216 Accumulator Tanks 2-1 & 2-2 Details of Nozzles 7

Section 1R11: Licensed Operator Requalification Program and Licensed Operator

Performance

Procedures

Number Title Revision

OP J-4B:II Hydrogen Seal Oil - Shutdown and Drain 17

OP1.DC10 Conduct of Operations 45

OP1.DC10 Conduct of Operations 46

OP B-1A:VII CVCS - Makeup Control System Operation 57

OP L-4 Normal Operation at Power 89A

STP M-21C Main Turbine Valve Testing 46

Notifications

50821148 50847167

Drawing

Number Title Revision

106722-4 Seal Oil System One Line Diagram 22

Section 1R12: Maintenance Effectiveness

Procedure

Number Title Revision

AD7.ID11 Fluid Leak Management Program 4

Notifications

50679028 50684617 50691277

Miscellaneous

Number Description Date

M-Rule S-43/E-43 Maintenance Rule Goal/Status Record March 19, 2015

Section 1R13: Maintenance Risk Assessments and Emergent Work Control

Procedures

Number Title Revision

STP M-13G 4 kV Bus G Non-SI Auto-Transfer Test 51

STP I-33A Reactor Trip and ESF Response Time Testing 35

AD7.ID14 Assessment of Integrated Risk 7

AD8.ID1 Outage Planning and Management 24A

STP M-15 Integrated Test of Engineered Safeguards and Diesel 66

Generators

AD7.DC6 On-Line Maintenance Risk Management 23

AD7.ID14 Assessment of Integrated Risk 7

AD8.DC55 Outage Safety Scheduling 38

Notifications

50838301 50341974 50818501 50818131 50856997

Work Orders

64004855 64102294

Miscellaneous

Number Title Date

Unit 1 Operators logs, Night Shift November 7, 2015

Unit 1 Operators logs, Day Shift November 8, 2015

PRA07-04 AMSAC Allowed Outage Time Extension September 12, 2007

Section 1R15: Operability Determinations and Functionality Assessments

Procedures

Number Title Revision

STP I-19-L61 Containment Structure Sump 1-2 Level Channel LT-61 11

Calibration

STP I-19-L61 Containment Structure Sump 2-2 Level Channel LT-61 11

Calibration

OM4.ID3 Operational Experience Program 27

PEP V-7B Test of ECCS Valve Interlocks 9

Notifications

50843404 50845141 50845746 50848966 50850712

50850715 50850717 50851485 50851561 50848011

50465474

Section 1R18: Plant Modifications

Procedures

Number Title Revision

CF4.ID7 Temporary Alterations 29

CF4.ID3 Modification Implementation 29

Notifications

50852155 50854126 50429891 50854511

Maintenance Orders

60090550 60090551

Section 1R19: Post-Maintenance Testing

Procedures

NUMBER TITLE Revision

MP E-60.2HG12 Circuit Function Test - 4 kV Cubicle HG12 (CCWP22)` 5

STP M-12B Battery Charger Performance Test 17

STP V-3P6A Exercising Valves LCV-111 AFW pump Discharge 26

STP R-1B Rod Drop Measurement 37

STP V-630 Penetration 30 containment isolation valve leak testing 25

Notifications

50848143 50708845 50835185 50854003 50849539

Work Orders

64098910 64098978 64150035 64112280 64104543

64163441 64071257

Section 1R20: Refueling and Other Outage Activities

Procedures

Number Title Revision

OP A-2:II Reactor Vessel - Draining the RCS to the Vessel Flange - 48

With Fuel in Vessel

OP L-4 Normal Operation at Power 73A

OP L-5 Plant Cooldown From Minimum Load to Cold Shutdown 84

OP A-2:II RCS Draining to Half Loop operations with Fuel in the 51

Vessel

O A-2:IX Vacuum Refill of the RCS 28

Notifications

50848106 50851420 50852155 50851640 50852155

Clearances/Tagouts

Number Description Revision / Date

2C19 R-64-001 480V Transformer Clearance 1

2C19 R-23-003 Cable Spreading Room Clearance 3

2C19 R-12-003B Containment Spray Header Supply May 18, 2016

Other Document

Number Title Revision

2R19 Outage Safety Plan 0

Section 1R22: Surveillance Testing

Procedures

Number Title Revision

STP I-19-L61 Containment Structure Sump 1-1 Channel LT-61 Calibration 11

STP M-21C Main Turbine Valve Testing 46

STP P-SIP-11 Routine Surveillance Test of Safety Injection Pump 1-1 24

STP V-682B Penetration 82B and 82C Containment Isolation Valve Leak 13

Testing

STP R-1C Digital Rod Position Functional Testing 21

STP R-1B Rod Drop Measurement 37

Notifications

50848966 50847182 50561599 50561646 50547286

50032499 50844530 50850358 50855643 50855659

50856133 50849539

Work Orders

64147458 64101598 64101609

Drawings

Number Description Revision

106709 Operating Valve ID - Safety Injection System 69

2009 Sheet 5 Safety Injection System Piping Diagram 76

Section 2RS1: Radiological Hazard Assessment and Exposure Controls

Procedures

Number Title Revision

RCP D-220 Control of Access to High, Locked High, and Very High 49

Radiation Areas

RCP D-240 Radiological Posting 23

RCP D-310 RCA Access Control 26

RCP D-500 Routine and Job Coverage Surveys 42

RCP D-620 Radioactive Source Control Program 11, 12

RP1 Radiation Protection 7

RP1.DC6 Radiation Protection Code of Conduct 2A

RP1.ID10 Embryo/Fetus Protection Program 8

RP1.ID16 Radiation Worker Expectations 7A

RP1.ID6 Personnel Dose Limits and Monitoring Requirements 14

Notifications

50813035 50814660 50815794 50816107 50820370

50820879 50842634 50842635 50848062

Audits and Self-Assessments

Number Title Date

2930028 2016 Radiation Protection Audit Report February 16, 2016

153060061 Quality Verification: Personal Electronic Dosimeter Alerts November 5, 2015

50839149 Quick Hit Self-Assessment Report: April 11, 2016

2016 2R19 NRC Inspection 71151-OR1

2660002 Quality Verification: Radiological Survey Documentation September 15, 2015

50839147 Quick Hit Self-Assessment Report: April 12, 2016

NRC Pre-Inspection on Radiological Hazard Assessment

and Exposure Controls

50839230 Quick Hit Self-Assessment Report: April 8, 2015

Pre-Inspection of NRC Performance Indicator PR01

RETS/ODCM Occurrences

Radiation Work Permits

Number Title Revision

15-1014B 1R19 Lower Reactor Cavity Decontamination 0

15-1021 1R19 CETNA Maintenance 0

15-1030 1R19 NI and Excore Annulus Work 1

15-1042 1R19 Primary Steam Generator Nozzle Dam Work 0

15-1082 1R19 Entry into Cavity for Rx Head Set and 0

Inspection

16-2002 2R19 Scaffolding in Containment 0

16-2006 2R19 Decontamination Activities in Containment 0

16-2015 2R19 Minor Work in Posted HRA/LHRA/VHRA in 0

Containment

16-2020 2R19 Reactor Disassembly 1

16-2023 2R19 Fuel Movement and Underwater Work in 0

Containment

16-2027 2R19 Reactor Reassembly 1

16-2032 2R19 Seal Table and MIDS Work 0

16-2037 2R19 RCDT, Rx Cavity Sump, & Under Vessel Work 0

16-2065 2R19 High Dose Valves 0

Radiation Surveys

Number Title Date

47947 HCV-111 Flange Adapter Install May 1, 2016

44308 CVCS-1-9 Valve Replacement (Cutout and Weld) October 14, 2015

44365 RHR-1-8727A Valve Removal and Replacement October 14, 2015

47474 U-2 140 SFP Transfer Canal April 11, 2016

48364 TSC Calibration Facility May 7, 2016

Miscellaneous Documents

Title Date

Source Inventory (969 sources) April 13, 2016

NSTS Annual Inventory Reconciliation Report January 11, 2016

JL Shepherd Maintenance Logs 2014-2015

Unit 1 Spent Fuel Pool Map February 17, 2016

Unit 2 Spent Fuel Pool Map April 6, 2016

Section 2RS2: Occupational ALARA Planning and Controls

Procedures

Number Title Revision

RCP D-200 Writing RWPs and ALARA Processes 54

RCP D-202 RWP Work Instructions 12

RP1.ID1 ALARA Program 9

RP1.ID9 Radiation Work Permits 13

RP1.ID15 Radiological Risk Assessment 4

Notifications

50663602 50669239 50808462 50811370 50811698

50813275 50813719 50815003 50815627 50824304

50833148 50833156 50848791 50848792

Audits and Self-Assessments

Number Title Date

2930028 2016 Radiation Protection Program Audit Report February 8, 2016

153500021 Quality Verification: Station ALARA Ownership February 10, 2016

Radiation Work Permits

Number Title Revision

15-1044 1R19 Primary Steam Generator Eddy Current Testing 0

and Tube Work

15-1065 1R19 High Dose Valves 0

16-0035B Radiography inside the PA, Outside in the RCA 0

16-2050 2R19 RCP Pump Maintenance 0

16-2085 2R19 Core Barrel Movement 0

Temporary Shielding Requests

Number Title Date

16-202 RHR Lines 508,509, 927 April 30, 2016

16-219 U-2 CTMT 115 RCP 2-3 Line 255 & RRs (Mode 5) May 1, 2016

16-228 Unit 2 CTMT 115 LCV 459-460 Actuator Work May 2, 2016

16-271 Handrail Shielding for Core Barrel Work May 10, 2016

Miscellaneous Documents

Title Date

Outage 2R19 ALARA Review Committee Meeting Notes May 11, 2016

2R19 Outage ALARA Report May 9-13, 2016

Section 4OA1: Performance Indicator Verification

Miscellaneous

Number Title Date

1-TS-16-0042 Technical Specification Tracking Containment Spray February 1, 2016

Pump 1-2 outage sheet

CD-Entry 4.0 Unit 1 & 2, Consolidated Data Entry 4.0 MSPI Derivation March 31, 2016

Report High Pressure Injection System

Notifications

50809622 50807757 50807756

Section 4OA2: Problem Identification and Resolution

Procedures

Number Title Revision

OM7.ID7 Emerging Issue and Event Investigations 18

Notifications

50848143 50852066 50852345 50852180

PAPERWORK REDUCTION ACT STATEMENT

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control

Number 31500011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget control

number.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its

enclosure will be available electronically for public inspection in the NRC Public Document

Room or from the Publicly Available Records (PARS) component of NRCs document

system (ADAMS). ADAMS is accessible from the NRC web site at http://www.nrc.gov/reading-

rm/adams.html (the Public Electronic Reading Room).

Information Request

March 17, 2016

Notification of Inspection and Request for Information

Diablo Canyon Nuclear Power Plant, Unit 2

NRC Inspection Report 05000323/2016002

INSERVICE INSPECTION DOCUMENT REQUEST

Inspection Dates: May 9-20, 2016

Inspector: Isaac Anchondo

A. Information Requested for the In-Office Preparation Week

The following information should be sent to the Region IV office in hard copy or electronic

format (ims.certrec.com preferred), in care of Isaac Anchondo, by April 25, 2016, to facilitate

the selection of specific items that will be reviewed during the onsite inspection week. The

inspector will select specific items from the information requested below and then request

from your staff additional documents needed during the onsite inspection week (Section B of

this enclosure). We ask that the specific items selected from the lists be available and ready

for review on the first day of inspection. Please provide requested documentation

electronically if possible. If requested documents are large and only hard copy formats are

available, please inform the inspector(s), and provide subject documentation during the first

day of the onsite inspection.

If you have any questions regarding this information request, please call the inspector as

soon as possible.

On May 9, 2016, reactor inspectors from the Nuclear Regulatory Commissions (NRC)

Region IV office will perform the baseline inservice inspection at Diablo Canyon Nuclear

Power Plant, Unit 2, using NRC Inspection Procedure 71111.08, "Inservice Inspection

Activities. Experience has shown that this inspection is a resource intensive inspection

both for the NRC inspectors and your staff. The date of this inspection may change

dependent on the outage schedule you provide. In order to minimize the impact to your

onsite resources and to ensure a productive inspection, we have enclosed a request for

Attachment 2

documents needed for this inspection. These documents have been divided into two

groups. The first group (Section A of the enclosure) identified information to be provided

prior to the inspection to ensure that the inspectors are adequately prepared. The second

group (Section B of the enclosure) identifies the information the inspectors will need upon

arrival at the site. It is important that all of these documents are up to date and complete in

order to minimize the number of additional documents requested during the preparation

and/or the onsite portions of the inspection.

We have discussed the schedule for these inspection activities with your staff and

understand that our regulatory contact for this inspection will be Mr. Mike McCoy of your

licensing organization. The tentative inspection schedule is as follows:

Preparation week: April 25, 2016

Onsite weeks: May 9-20, 2016

Our inspection dates are subject to change based on your updated schedule of outage

activities. If there are any questions about this inspection or the material requested,

please contact the lead inspector Isaac Anchondo at (817) 200-1152 or e-mail

Isaac.Anchondo@nrc.gov.

A.1 ISI/Welding Programs and Schedule Information

1. A detailed schedule (including preliminary dates) of:

1.1. Nondestructive examinations planned for ASME Code Class Components

performed as part of your ASME Section XI, risk informed (if applicable), and

augmented inservice inspection programs during the upcoming outage.

Please include the ASME Examination Category (i.e., B-A) and Item Number

(i.e., B1.10) of each component within the format that this information will be

provided.

1.2. Examinations planned for Alloy 82/182/600 components that are not included in

the Section XI scope (If applicable)

1.3. Examinations planned as part of your boric acid corrosion control program

(Mode 3 walkdowns, bolted connection walkdowns, etc.)

1.4. Welding activities that are scheduled to be completed during the upcoming

outage (ASME Class 1, 2, or 3 structures, systems, or components)

2. A copy of ASME Section XI Code Relief Requests and associated NRC safety

evaluations applicable to the examinations identified above.

2.1. A list of ASME Code Cases currently being used to include the system and/or

component the Code Case is being applied to.

3. A list of nondestructive examination reports which have identified recordable or

rejectable indications on any ASME Code Class components since the beginning of

the last refueling outage. This should include the previousSection XI pressure

test(s) conducted during start up and any evaluations associated with the results of

the pressure tests.

4. A list including a brief description (e.g., system, code class, weld category,

nondestructive examination performed) associated with the repair/replacement

activities of any ASME Code Class component since the beginning of the last outage

and/or planned this refueling outage.

5. If reactor vessel weld examinations required by the ASME Code are scheduled to

occur during the upcoming outage, provide a detailed description of the welds to be

examined and the extent of the planned examination. Please also provide reference

numbers for applicable procedures that will be used to conduct these examinations.

6. Copy of any 10 CFR Part 21 reports applicable to structures, systems, or

components within the scope of Section XI of the ASME Code that have been

identified since the beginning of the last refueling outage.

7. A list of any temporary noncode repairs in service (e.g., pinhole leaks).

8. Please provide copies of the most recent self-assessments for the inservice

inspection, welding, and Alloy 600 programs.

9. Copy of the procedures for welding techniques and NDE that will be used during the

outage.

A.2 Boric Acid Corrosion Control Program

1. Copy of the procedures that govern the scope, equipment, and implementation of the

inspections required to identify boric acid leakage and the procedures for boric acid

leakage/corrosion evaluation.

2. Please provide a list of leaks (including code class of the components) that have

been identified since the last refueling outage and associated corrective action

documentation. If during the last cycle, the unit was shutdown, please provide

documentation of containment walkdown inspections performed as part of the boric

acid corrosion control program.

A.3 Steam Generator Tube Inspections

1. A detailed schedule of:

  • Steam generator secondary side inspection activities for the upcoming outage

2. Copy of SG history documentation given to vendors performing secondary side

examinations of the SGs during the upcoming outage (If applicable)

3. Copy of previous outage SG tube operational assessment

4. Identify and quantify any SG tube leakage experienced during the previous operating

cycle. Also provide documentation identifying which SG was leaking and corrective

actions completed and planned for this condition.

5. Provide past history of the condition and issues pertaining to the secondary side of

the steam generators (including items such as loose parts, fouling, top of tube sheet

condition, crud removal amounts, etc.).

A.4 Additional Information Related to All Inservice Inspection Activities

1. A list with a brief description of inservice inspection and boric acid corrosion control

program-related issues (e.g., CRs) entered into your corrective action program since

the beginning of the last refueling outage. For example, a list based upon data base

searches using key words related to piping such as: inservice inspection, ASME

Code,Section XI, NDE, cracks, wear, thinning, leakage, rust, corrosion, boric acid, or

errors in piping examinations.

2. Provide training (e.g., Scaffolding, Fall Protection, FME, Confined Space) if they are

required for the activities described in A.1 through A.3.

3. Please provide names and phone numbers for the following program leads:

Inservice inspection (examination, planning)

Containment exams

Reactor pressure vessel head examinations

Snubbers and supports

Repair and replacement program

Licensing

Site welding engineer

Boric acid corrosion control program

Steam generator inspection activities (site lead and vendor contact)

B. Information to be Provided On-site to the Inspector(s) at the Entrance Meeting

(May 9, 2016):

B.1 Inservice Inspection/Welding Programs and Schedule Information

1. Updated schedules for inservice inspection/nondestructive examination activities,

including planned welding activities, and schedule showing contingency repair

plans, if available

2. For ASME Code Class welds selected by the inspector from the lists provided from

Section A of this enclosure, please provide copies of the following documentation

for each subject weld:

  • Weld data sheet (traveler)
  • Weld configuration and system location
  • Applicable Code Edition and Addenda for weldment
  • Applicable Code Edition and Addenda for welding procedures
  • Applicable welding procedures used to fabricate the welds
  • Copies of procedure qualification records (PQRs) supporting the weld

procedures from B.1.b.v

  • Copies of welders performance qualification records (WPQ)
  • Copies of the nonconformance reports for the selected welds

(If applicable)

  • Radiographs of the selected welds and access to equipment to allow

viewing radiographs (if radiographic testing was performed)

  • Copies of the preservice examination records for the selected welds

qualifications records for reviewing.

3. For the inservice inspection-related corrective action issues selected by the

inspectors from Section A of this enclosure, provide a copy of the corrective actions

and supporting documentation.

4. For the nondestructive examination reports with relevant conditions on ASME Code

Class components selected by the inspectors from Section A above, provide a copy

of the examination records, examiner qualification records, and associated

corrective action documents.

5. A copy of (or ready access to) most current revision of the inservice inspection

program manual and plan for the current interval

6. For the nondestructive examinations selected by the inspectors from Section A of

this enclosure, provide a copy of the nondestructive examination procedures used

to perform the examinations (including calibration and flaw characterization/sizing

procedures). For ultrasonic examination procedures qualified in accordance with

ASME Code,Section XI, Appendix VIII, provide documentation supporting the

procedure qualification (e.g., the EPRI performance demonstration qualification

summary sheets). Also, include qualification documentation of the specific

equipment to be used (e.g., ultrasonic unit, cables, and transducers including serial

numbers) and nondestructive examination personnel qualification records.

B.2 Boric Acid Corrosion Control Program

1. Please provide boric acid walk down inspection results, an updated list of boric acid

leaks identified so far this outage, associated corrective action documentation, and

overall status of planned boric acid inspections.

2. Please provide any engineering evaluations completed for boric acid leaks identified

since the end of the last refueling outage. Please include a status of corrective actions

to repair and/or clean these boric acid leaks. Please identify specifically which known

leaks, if any, have remained in service or will remain in service as active leaks.

B.3 Steam Generator Tube Inspections

1. Copy of the guidance to be followed in order to perform FOSAR inspections

2. Copy of the guidance to be followed if a loose part or foreign material is identified in

the steam generators during FOSAR inspections

3. List of corrective action documents generated by the vendor and/or site with respect

to steam generator inspection activities

B.4 Codes and Standards

1. Ready access to (i.e., copies provided to the inspector(s) for use during the inspection

at the onsite inspection location, or room number and location where available):

  • Applicable Editions of the ASME Code (Sections V, IX, and XI) for the inservice

inspection program and the repair/replacement program.

2. Copy of NDE procedures (i.e., UT, MT, PT examinations) to be used on ASME Code

required examinations during this outage.

3. Boric Acid Corrosion Guidebook Revision 1 - EPRI Technical Report 1000975.

The following items are requested for the

Occupational Radiation Safety Inspection

at Diablo Canyon

May 9 - 13, 2016

Integrated Report 2016002

Inspection areas are listed in the attachments below.

Please provide the requested information on or before April 19, 2016.

Please submit this information using the same lettering system as below. For example, all

contacts and phone numbers for Inspection Procedure 71124.01 should be in a file/folder titled

1- A, applicable organization charts in file/folder 1- B, etc.

If information is placed on ims.certrec.com, please ensure the inspection exit date entered is at

least 30 days later than the onsite inspection dates, so the inspectors will have access to the

information while writing the report.

In addition to the corrective action document lists provided for each inspection procedure listed

below, please provide updated lists of corrective action documents at the entrance meeting.

The dates for these lists should range from the end dates of the original lists to the day of the

entrance meeting.

If more than one inspection procedure is to be conducted and the information requests appear

to be redundant, there is no need to provide duplicate copies. Enter a note explaining in which

file the information can be found.

If you have any questions or comments, please contact John ODonnell at (817) 200-1441 or

John.ODonnell@nrc.gov.

PAPERWORK REDUCTION ACT STATEMENT

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget,

control number 3150-0011.

Attachment 3

1. Radiological Hazard Assessment and Exposure Controls (71124.01) and

Performance Indicator Verification (71151)

Date of Last Inspection: October 12, 2015

A. List of contacts and telephone numbers for the Radiation Protection Organization Staff

and Technicians

B. Applicable organization charts

C. Audits, self-assessments, and LERs written since date of last inspection, related to this

inspection area

D. Procedure indexes for the radiation protection procedures

E. Please provide specific procedures related to the following areas noted below.

Additional Specific Procedures may be requested by number after the inspector reviews

the procedure indexes.

1. Radiation Protection Program Description

2. Radiation Protection Conduct of Operations

3. Personnel Dosimetry Program

4. Posting of Radiological Areas

5. High Radiation Area Controls

6. RCA Access Controls and Radworker Instructions

7. Conduct of Radiological Surveys

8. Radioactive Source Inventory and Control

9. Declared Pregnant Worker Program

F. List of corrective action documents (including corporate and subtiered systems) since

date of last inspection

a. Initiated by the radiation protection organization

b. Assigned to the radiation protection organization

NOTE: The lists should indicate the significance level of each issue and the search

criteria used. Please provide in document formats which are searchable so that the

inspector can perform word searches.

If not covered above, a summary of corrective action documents since date of last

inspection involving unmonitored releases, unplanned releases, or releases in which any

dose limit or administrative dose limit was exceeded (for Public Radiation Safety

Performance Indicator verification in accordance with IP 71151)

G. List of radiologically significant work activities scheduled to be conducted during the

inspection period (If the inspection is scheduled during an outage, please also include a

list of work activities greater than 1 rem, scheduled during the outage with the dose

estimate for the work activity.)

H. List of active radiation work permits

I. Radioactive source inventory list

a. All radioactive sources that are required to be leak tested

b. All radioactive sources that meet the 10 CFR Part 20, Appendix E, Category 2 and

above threshold. Please indicate the radioisotope, initial and current activity (w/assay

date), and storage location for each applicable source.

J. The last two leak test results for the radioactive sources inventoried and required to be

leak tested. If applicable, specifically provide a list of all radioactive source(s) that have

failed its leak test within the last two years

K. A current listing of any non-fuel items stored within your pools, and if available, their

appropriate dose rates (Contact / @ 30cm)

L. Computer printout of radiological controlled area entries greater than 100 mrem since

the previous inspection to the current inspection entrance date. The printout should

include the date of entry, some form of worker identification, the radiation work permit

used by the worker, dose accrued by the worker, and the electronic dosimeter dose

alarm setpoint used during the entry (for Occupational Radiation Safety Performance

Indicator verification in accordance with IP 71151).

2. Occupational ALARA Planning and Controls (71124.02)

Date of Last Inspection: July 27, 2015

A. List of contacts and telephone numbers for ALARA program personnel

B. Applicable organization charts

C. Copies of audits, self-assessments, and LERs, written since date of last inspection,

focusing on ALARA

D. Procedure index for ALARA Program

E. Please provide specific procedures related to the following areas noted below.

Additional Specific Procedures may be requested by number after the inspector reviews

the procedure indexes.

1. ALARA Program

2. ALARA Committee

3. Radiation Work Permit Preparation

F. A summary list of corrective action documents (including corporate and subtiered

systems) written since date of last inspection, related to the ALARA program. In addition

to ALARA, the summary should also address Radiation Work Permit violations,

Electronic Dosimeter Alarms, and RWP Dose Estimates

NOTE: The lists should indicate the significance level of each issue and the search

criteria used. Please provide in document formats which are searchable so that the

inspector can perform word searches.

G. List of work activities greater than 1 rem, since date of last inspection

Include original dose estimate and actual dose.

H. Site dose totals and 3-year rolling averages for the past 3 years (based on dose of

record)

I. Outline of source term reduction strategy

J. If available, provide a copy of the ALARA outage report for the most recently completed

outages for each unit

K. Please provide your most recent Annual ALARA Report.

A3-3