MONTHYEARIR 05000275/20192012019-06-0303 June 2019 @, NRC Inspection Report 05000275/2019201 and 05000323/2019201 ML17103A6392017-04-13013 April 2017 Notification of Evaluations of Changes, Tests, and Experiments Inspection (05000275/2017002 and 05000323/2017002) and Request for Information IR 05000275/20160102017-02-28028 February 2017 NRC Denial of Pacific Gas and Electric Company Appeal of Diablo Canyon Power Plant - Final Significance Determination of a White Finding; NRC Inspection Report 05000275/2016010 and 05000323/2016010 IR 05000275/20162012016-10-26026 October 2016 NRC Security Inspection Report 05000275/2016201 and 05000323/2016201 (Cover Letter Only) IR 05000275/20164052016-07-15015 July 2016 Cover Letter for NRC Security Inspection Report 05000275/2016405 and 05000323/2016405 ML16196A3942016-07-14014 July 2016 Notification of NRC Triennial Fire Protection Baseline Inspection 05000275/2016008 and 05000323/2016008 and Request for Information IR 05000275/20154022016-03-0202 March 2016 Non-Public Security Inspection Plan for Diablo Canyon Nuclear Power Plant, Units 1 and 2 (NRC Physical Security Inspection Report Numbers 05000275/2015402 and 05000323/2015402) ML15268A1482015-09-30030 September 2015 Review of Steam Generator Tube Inspection Report for Cycle 18 (2R18) Refueling Outage in Fall 2014 IR 05000275/20105012011-01-10010 January 2011 IR 05000275-10-501, 05000323-10-501, on 12/31/2010, Diablo Canyon Power, Unit 1 & 2 - NRC Annual Emergency Preparedness IR 05000275/20085012009-03-13013 March 2009 IR 05000275-08-501, and IR 05000323-08-501, on 11/31/2008, for Diablo Canyon Power Plant Units 1 and 2 - Emergency Preparedness Annual Inspection Report ML0822005022008-08-0707 August 2008 NRC Inspection Report 05000275/2008002 and 05000323/2008002, Response to Disputed Non-cited Violation ML0820505092008-07-23023 July 2008 Notification of Inspection (NRC Inspection Report 05000275-08-004 05000323-08-004) and Request for Information IR 05000275/20075012008-02-21021 February 2008 IR 05000275-07-501, and IR 05000323-07-501, on 12/31/2007, for Diablo Canyon, Units 1 and 2, Emergency Preparedness Annual ML0712801192007-05-14014 May 2007 Ltr. to John S. Keenan Diablo Canyon Power Plant - NRC Material Control and Accounting Program Inspection ML0623303072006-08-21021 August 2006 Errata for Diablo Canyon Power Plant - NRC Problem Identification and Resolution Inspection Report 05000275/2006012 and 05000323/2006012 IR 05000275/20010112002-05-0101 May 2002 IR 05000275/2001-011, IR 05000323/2001-011, 12/30/01 to 04/06/02, Pacific Gas and Electric. Co., Diablo Canyon Nuclear Power Plant Units 1 and 2. Equipment Alignments: Personnel Perf. Rel to Nonroutine Plant Evals. and Events IR 05000275/20020072002-04-0808 April 2002 IR 05000275/2002-007, IR 05000323/2002-007, on 2/22/02 - 3/1/02; Pacific Gas and Electric Co.; Diablo Canyon Nuclear Power Plant Units 1 and 2. Special Team Insp Rpt. Problem Identification & Resolution, Event Response, Operability Eval, Mo 2019-06-03
[Table view] Category:Letter
MONTHYEARML24302A2622024-11-0101 November 2024 Letter to CA SHPO Regarding DCPP Dseis ML24302A1922024-11-0101 November 2024 Ltr to G. Frausto Coastal Band of Chumash Indians Re DCPP Dseis ML24302A1952024-11-0101 November 2024 Ltr to M. Olivas Tucker Ytt Re DCPP Dseis ML24302A1912024-11-0101 November 2024 Ltr to C. Mcdarment Tule River Tribe Re DCPP Dseis ML24302A1942024-11-0101 November 2024 Ltr to K. Kahn Santa Ynez Band of Chumash Indians Re DCPP Dseis ML24302A1962024-11-0101 November 2024 Ltr to SLO County Chumash Indians Re DCPP Dseis ML24302A1932024-11-0101 November 2024 Letter to G. Pierce Salinan Tribe of Monterey, SLO Re DCPP Dseis ML24302A1972024-11-0101 November 2024 Letter to V. Sage Walker Northern Chumash Tribal Council Re DCPP Dseis ML24302A2612024-11-0101 November 2024 Letter to Achp Re DCPP Dseis ML24275A0622024-10-30030 October 2024 NRC to NMFS Request Initiate Formal Endangered Species Act Consultation and Abbreviated Essential Fish Habitat for Proposed License Renewal of DCP Plant Units 1, 2 IR 05000275/20240032024-10-30030 October 2024 Integrated Inspection Report 05000275/2024003 and 05000323/2024003 and Independent Spent Fuel Storage Installation Report 07200026/2024001 ML24269A0122024-10-29029 October 2024 OEDO-24-00083 2.206 Petition Diablo Canyon Seismic CDF - Response to Petitioner Letter ML24284A3122024-10-28028 October 2024 Ltr to P Ting, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants ML24284A3112024-10-28028 October 2024 Ltr to a Peck, Diablo Canyon Nuclear Power Plant Units 1 and 2 Notice of Avail of Draft Supplement 62 to the GEIS for Lic Renew of Nuclear Plants IR 05000275/20240132024-10-28028 October 2024 – License Renewal Report 05000275/2024013 and 05000323/2024013 DCL-24-103, Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 22024-10-24024 October 2024 Pg&Es Voluntary Submittal of Information Related to 10 CFR 2.206 Petition Regarding Seismic Core Damage Frequency for DCPP, Units 1 and 2 ML24261B9492024-10-24024 October 2024 Issuance of Amendment Nos. 246 and 248 Revision to Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) IR 05000275/20244042024-10-23023 October 2024 Security Baseline Inspection Report 05000275/2024404 and 05000323/2024404 ML24277A0292024-10-18018 October 2024 NRC to Fws Req. for Concurrence W. Endangered Species Act Determinations for Diablo Canyon Power Plant Units 1,2, ISFSI Proposed License Renewals in San Luis Obispo Co., CA DCL-24-092, Supplement and Annual Update License Renewal Application, Amendment 12024-10-14014 October 2024 Supplement and Annual Update License Renewal Application, Amendment 1 DCL-24-098, Material Status Report for the Period Ending August 31, 20242024-10-0909 October 2024 Material Status Report for the Period Ending August 31, 2024 DCL-24-091, Response to Request for Additional Information by the Office of Nuclear Reactor Regulation2024-10-0303 October 2024 Response to Request for Additional Information by the Office of Nuclear Reactor Regulation IR 05000275/20253012024-10-0303 October 2024 Notification of NRC Initial Operator Licensing Examination 05000275/2025301; 05000323/2025301 ML24240A0222024-09-20020 September 2024 Letter to A. Peck Environmental Impact Statement Scoping Summary Report for Diablo Canyon Nuclear Power Plant Units 1 and 2 ML24260A1222024-09-14014 September 2024 14 Sept 2024 Ltr - California Coastal Commission to Pg&E, Incomplete Consistency Certification for Requested Nuclear Regulatory Commission License Renewal for Diablo Canyon Power Plant DCL-24-087, License Renewal - Historic and Cultural Resources Reference Documents (Redacted)2024-09-12012 September 2024 License Renewal - Historic and Cultural Resources Reference Documents (Redacted) ML24262A2462024-09-11011 September 2024 10 CFR 2.206 - Diablo Canyon Units 1 and 2 Seismic - Petitioner Response to Acknowledgement Letter - DCL-24-083, CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated2024-09-0909 September 2024 CFR Part 21 Notification: Commercially Dedicated Snubber Valve Not Properly Heat Treated DCL-24-078, Pre-Notice of Disbursement from Decommissioning Trust2024-09-0303 September 2024 Pre-Notice of Disbursement from Decommissioning Trust DCL-24-082, Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment2024-08-28028 August 2024 Decommissioning Draft Biological Assessment and Draft Essential Fish Habitat Assessment ML24205A0662024-08-27027 August 2024 OEDO-24-00083 - 10 CFR 2.206 - Ack Letter - Diablo Canyon Units 1 and 2 Seismic Core Damage Frequency - IR 05000275/20240052024-08-22022 August 2024 Updated Inspection Plan for Diablo Canyon Power Plant, Units 1 and 2 (Report 05000275/2024005 and 05000323/2024005) DCL-24-077, Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident2024-08-15015 August 2024 Responses to NRC Requests for Additional Information on Diablo Canyon Power License Renewal Application Severe Accident DCL-24-075, Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React2024-08-0808 August 2024 Response to Request for Additional Information for License Amendment Request 23-02, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power React IR 05000275/20240022024-08-0606 August 2024 Integrated Inspection Report 05000275/2024002 and 05000323/2024002 DCL-24-079, DC-2024-07 Post Exam Comments Analysis2024-08-0202 August 2024 DC-2024-07 Post Exam Comments Analysis DCL-24-070, License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies2024-07-31031 July 2024 License Amendment Request 24-03 Revision to Technical Specification 5.5.16 for Permanent Extension of Type a and Type C Leak Rate Test Frequencies DCL-24-071, Core Operating Limits Report for Unit 2 Cycle 252024-07-22022 July 2024 Core Operating Limits Report for Unit 2 Cycle 25 DCL-2024-523, Submittal of Report on Discharge Self-Monitoring2024-07-18018 July 2024 Submittal of Report on Discharge Self-Monitoring ML24187A1352024-07-16016 July 2024 Letter to Paula Gerfen - Diablo Canyon Units 1 and 2 - Summary of June 2024 Audit Related to the License Renewal Application Severe Accident Mitigation Alternatives Review IR 05000275/20240142024-07-11011 July 2024 Age-Related Degradation Inspection Report 05000275/2024014 and 05000323/2024014 IR 05000275/20244012024-07-0808 July 2024 Security Baseline Inspection Report 05000275/2024401 and 05000323/2024401 (Full Report) IR 05000323/20240112024-07-0303 July 2024 License Renewal Phase Report 05000323/2024011 DCL-2024-527, Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant2024-07-0101 July 2024 Sea Turtle Stranding Report (Loggerhead Sea Turtle) Diablo Canyon Power Plant DCL-24-066, Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL2024-06-27027 June 2024 Request to Extend the Nrg Approval of Alternative for Use of Full Structural Weld Overlay, REP-RHR-SWOL ML24155A2182024-06-18018 June 2024 OEDO-23-00350-NRR - (LTR-23-0228-1) - Closure Letter - 10 CFR 2.206 Petition from Mothers for Peace and Friends of the Earth Regarding Diablo Canyon ML24129A1762024-06-14014 June 2024 National Historic Preservation Act Section 106 Consultation – Results of Identification and Evaluation (Docket Number: 72-026) ML24200A2052024-06-0707 June 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project for Diablo Canyon License Renewal ML24099A2192024-05-29029 May 2024 Issuance of Amendment Nos. 245 and 247 Revision to TSs to Adopt TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML24117A0132024-05-20020 May 2024 Letter to Paula Gerfen-Diablo Canyon Units 1 and 2-Regulatory Audit Regarding Severe Accident Mitigation Alternatives for the License Renewal Application 2024-09-09
[Table view] |
Text
ber 26, 2016
SUBJECT:
DIABLO CANYON POWER PLANT, UNITS 1 AND 2 - NRC SECURITY INSPECTION REPORT 05000275/2016201 AND 05000323/2016201
Dear Mr. Halpin:
On September 16, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed a security inspection at your Diablo Canyon Power Plant, Units 1 and 2. On September 27, 2016, the NRC inspectors discussed results of this inspection with Mr. Jan Nimick, Senior Director, Nuclear Services, and other members of your staff. The results of this inspection are documented in the enclosed inspection report.
NRC inspectors documented one finding of very low security significance (Green) in this report.
This finding involved a violation of NRC requirements. The NRC is treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2.a of the Enforcement Policy.
If you contest this violation or the significance of this NCV, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Nuclear Security and Incident Response; the Director, Office of Enforcement; and the NRC resident inspector at the Diablo Canyon Power Plant, Units 1 and 2.
One cross-cutting aspect was assigned a finding in the area of Human Performance, Questioning Attitude. Specifically, because the licensee failed to stop when faced with uncertain conditions. Risks are evaluated and managed before preceeding [H.11].
If you disagree with a cross-cutting aspect assignment or a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Nuclear Security, and Incident Response; and the NRC resident inspector at the Diablo Canyon Power Plant, Units 1 and 2. This letter will be available for public inspection at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Request for Withholding.
The enclosed report contains Safeguards Information as defined by 10 CFR 73.21, Protection of Safeguards Information: Performance Requirements, and its disclosure to unauthorized individuals is prohibited by Section 147 of the Atomic Energy Act of 1954, as amended.
Therefore, the material enclosed report will not be made publicly available. If you choose to provide a response that contains Safeguards Information, please provide the level of protection described in 10 CFR 73.21. Otherwise, if you choose to provide a response that contains Security-Related Information, please mark your entire response Security-Related Information - Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390(b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.
Sincerely,
/RA J. Willis acting for/
Robert C. Johnson, Chief Security Performance Evaluation Branch Division of Security Operations Office of Nuclear Security and Incident Response Docket Nos.: 05000275, 05000323 License Nos.: DPR-80, DPR-82 Nonpublic Enclosure: Inspection Report 05000275/2016201 and 05000323/2016201 w/Attachments: Supplemental Information cc w/ enclosure: Douglas Evans, Site Security Manager cc w/o enclosure: James M. Welsch, Vice President, Nuclear Generation ML16279A410 Entire Report: Non-Sensitive Publicly Available Keyword:
SUNSI Review Complete Sensitive Non-Publicly Available MD 3.4 Non-Public A.3 By:
Cover Letter Only: Non-Sensitive Publicly Available Keyword:
SUNSI Review Complete Sensitive Non-Publicly Available SUNSI Review Complete By:
OFFICE NSIR/DSO/SPEB NSIR/DSO/SPEB NSIR/DSO/SPEB RIV NSIR/DSO/SPEB NAME A. Woyansky J. Clark J. Berry M. Haire R.C. Johnson SIGNATURE (J. Willis for)
DATE 9/27/16 10/13/16 10/03/16 10/18/16 10/24/16