IR 05000255/2002007

From kanterella
Jump to navigation Jump to search
IR 05000255-02-007, on 07/01/2002 - 09/28/2002, Nuclear Management Company, LLC, Palisades Nuclear Generating Plant. Flood Protection
ML022950507
Person / Time
Site: Palisades Entergy icon.png
Issue date: 10/22/2002
From: Anton Vegel
NRC/RGN-III/DRP/RPB6
To: Cooper D
Nuclear Management Co
References
IR-02-007
Download: ML022950507 (49)


Text

ber 22, 2002

SUBJECT:

PALISADES NUCLEAR GENERATING PLANT USNRC INSPECTION REPORT 50-255/02-07(DRP)

Dear Mr. Cooper:

On September 28, 2002, the USNRC completed an inspection at your Palisades Nuclear Generating Plant. The enclosed report documents the inspection findings which were discussed on October 3, 2002, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

Based on the results of this inspection, we identified two issues of very low safety significance (Green) that were determined to involve violations of NRC requirements. However, because of the very low safety significance and because the issues were entered into your corrective action program, the USNRC is treating these issues as Non-Cited Violations in accordance with Section VI.A.1 of the USNRC s Enforcement Policy.

If you deny these Non-Cited Violations, you should provide a response with a basis for your denial, within 30 days of the date of this inspection report, to the U. S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with a copy to the Regional Administrator, U. S. Nuclear Regulatory Commission - Region III, 801 Warrenville Road, Lisle, IL 60532-4351; the Director, Office of Enforcement, U. S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector Office at the Palisades facility.

The USNRC has increased security requirements at the Palisades plant in response to the terrorist attacks on September 11, 2001. Although the USNRC is not aware of any specific threat against nuclear facilities, the USNRC issued an Order and several threat advisories to commercial power reactors to strengthen licensees' capabilities and readiness to respond to a potential attack. The USNRC continues to monitor overall security controls and will issue temporary instructions in the near future to verify by inspection the licensees compliance with the Order and current security regulations. In accordance with 10 CFR 2.790 of the USNRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the USNRC Public Document Room or from the Publicly Available Records (PARS) component of USNRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Anton Vegel, Chief Branch 6 Division of Reactor Projects Docket No. 50-255 License No. DPR-20

Enclosure:

Inspection Report 50-255/02-07(DRP)

REGION III==

Docket No: 50-255 License No: DPR-20 Report No: 50-255/02-07(DRP)

Licensee: Nuclear Management Company, LLC Facility: Palisades Nuclear Generating Plant Location: 27780 Blue Star Memorial Highway Covert, MI 49043-9530 Dates: July 1 through September 28, 2002 Inspectors: J. Lennartz, Senior Resident Inspector R. Krsek, Resident Inspector T. Madeda, Physical Security Inspector D. Nelson, Radiation Specialist Observers: M. Castanedo, Nuclear Safety Intern J. Maynen, Physical Security Inspector Approved by: Anton Vegel, Chief Branch 6 Division of Reactor Projects

SUMMARY OF FINDINGS

IR 05000255/02-07, Nuclear Management Company, LLC, on 07/01/2002 - 09/28/2002,

Palisades Nuclear Generating Plant. Flood Protection.

This report covers a 3-month period of baseline resident inspection and announced baseline inspections in radiation safety and physical protection. The inspection was conducted by the resident inspectors, a regional radiation protection specialist inspector and a physical security inspector. Two Green Findings with associated Non-Cited Violations were identified during the inspection. The significance of most findings is indicated by their color (Green, White, Yellow,

Red) using Inspection Manual Chapter 0609, Significance Determination Process, (SDP).

Findings for which the SDP does not apply may be Green or be assigned a severity level after USNRC management review. The USNRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG 1649, Reactor Oversight Process,

Revision 3, dated July 2000.

A. Inspection Findings

Cornerstone: Mitigating Systems

Green.

The inspectors identified a Green Finding that is being treated as a Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions,

Procedures, and Drawings, for the failure to ensure activities affecting quality were prescribed by documented procedures of a type appropriate to the circumstances. Specifically, the activities affecting quality dealt with the inspection and maintenance of the safety-related expansion joints utilized as flood and high energy line break barriers between the component cooling water and west engineered safeguards rooms.

This issue was more than minor because if left uncorrected the safety-related expansion joints could degrade further, undetected, which could result in an inadequate flood and high energy line break barrier between the component cooling water and the west engineered safeguards rooms. The finding was determined to be a licensee performance deficiency of very low safety significance (Green) by the significance determination process because the finding: (1) was not a design or qualification deficiency; (2) did not represent an actual loss of safety function of a system; (3) did not represent an actual loss of a safety function of a single train for greater than Technical Specification outage time; (4) did not represent an actual loss of a safety function of one or more Non-Technical Specification trains of equipment; and (5) did not screen as potentially risk significant due to a seismic, flooding, or severe weather initiating event. (Section 1R06.1)

Green.

The inspectors identified a Green finding that is being treated as a Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Actions, for the failure to promptly identify and correct conditions adverse to quality regarding Flood Door-196A which protected the safety-related equipment in the component cooling water room from a flood in the turbine building.

This issue was more than minor because the licensee failed to take adequate corrective actions for a previously identified issue involving the degradation of Flood Door 196A which could potentially cause a flood in the turbine building to spread to the component cooling water room. The finding was determined to be a licensee performance deficiency of very low safety significance (Green) by the significance determination process because the finding: (1) was not a design or qualification deficiency; (2) did not represent an actual loss of safety function of a system; (3) did not represent an actual loss of a safety function of a single train for greater than Technical Specification outage time; (4) did not represent an actual loss of a safety function of one or more Non-Technical Specification trains of equipment; and (5) did not screen as potentially risk significant due to a seismic, flooding, or severe weather initiating event. (Section 1R06.2)

B. Licensee Identified Findings Violations of very low safety significance, which were identified by the licensee have been reviewed by the inspectors. Corrective actions taken or planned by the licensee have been entered into the licensees corrective action program. These violations and corrective action tracking numbers are listed in Section 4OA7 of this report.

REPORT DETAILS

A list of documents reviewed within each inspection area is included at the end of the report.

Summary of Plant Status

The plant was at full power for the majority of the inspection period with the following exceptions:

C On August 26, 2002, operations personnel identified a problem with the seal cooler for the non-safety related Heater Drain Pump P-10B. Plant power was reduced to approximately 88 percent and the pump was removed from service for repairs. Also, licensee personnel had been monitoring a previously identified oil leak on Primary Coolant Pump P-50D and on August 27, 2002, engineering personnel recommended, based on industry operating experience, that oil be added immediately to the lower oil reservoir because of a slight rise in the motors lower bearing temperature. Therefore plant power was reduced to approximately 50 percent to address this emergent issue.

Reactor power was raised to approximately 88 percent on August 28, 2002, following the oil addition to Primary Coolant Pump P-50D. On August 30, 2002, reactor power was raised to full power following the completion of repairs to the seal oil cooler for the non-safety related Heater Drain Pump P-10B.

C On September 21, 2002, operations personnel identified a ground on the non-safety related 2400 volt electrical Bus 1-E which was subsequently traced to Heater Drain Pump P-10B. Reactor power was reduced to approximately 88 percent and non-safety related Heater Drain Pump P-10B was removed from service to repair the ground.

Following the repairs, reactor power was raised to full power on September 21, 2002.

C On September 28, 2002, reactor power was reduced to approximately 25 percent to conduct a planned oil addition to the Reactor Coolant Pump P-50D and the plant was returned to full power on September 29, 2002, following the oil addition.

REACTOR SAFETY

Cornerstones: Initiating Event, Mitigating Systems, Barrier Integrity, Emergency Preparedness

1R04 Equipment Alignment

.1 Quarterly Equipment Alignment Walkdowns

a. Inspection Scope

The inspectors performed partial walkdowns of accessible equipment for the High Pressure Air System, the Component Cooling Water System and the Containment Spray System. The train of high pressure air in the west safeguards room which contained High Pressure Air Compressor C-6B was walked down while the redundant High Pressure Air Compressor C-6A in the east safeguards room was out of service for maintenance during the week of July 15, 2002. The train of component cooling water which contained Pumps 52A and P-52C was walked down while the redundant Component Cooling Water Pump P-52B was out of service for planned motor replacement during the week of July 28, 2002. Containment Spray Pump P-54A was walked down during the week of August 18, 2002.

For the systems walked down, the inspectors verified that accessible equipment and components were appropriately aligned and that no discrepancies existed which would impact the systems safety function. Portions of the system alignment inspection included discussions and system walkdowns with operations and engineering personnel.

The inspectors also reviewed condition reports related to equipment alignment issues to verify that the problems were appropriately characterized and to verify that identified corrective actions were reasonable.

b. Findings

No findings of significance were identified.

.2 Semiannual Equipment Alignment Walkdowns

a. Inspection Scope

The inspectors walked down the Auxiliary Feedwater System during the week of August 11, 2002. The inspectors utilized system operating procedures and Auxiliary Feedwater System checklists to verify that accessible system components were correctly aligned. The inspectors also reviewed active maintenance work requests, active design and engineering issues, including known operator workarounds and temporary modifications, to verify that the equipments safety function was not adversely impacted.

b. Findings

No findings of significance were identified.

1R05 Fire Protection Area Walkdowns

a. Inspection Scope

The inspectors toured the following areas in which a fire could affect safety-related equipment:

  • East Engineered Safeguards Room (Fire Area 10);
  • 1D Switchgear Room (Fire Area 3);
  • Spent Fuel Pool Cooling Room (Fire Area 17); and
  • Safety Injection Refueling Water Tank (Fire Area 32).

The inspectors assessed the material condition of the passive fire protection features and verified that transient combustibles and ignition sources were appropriately controlled. The inspectors reviewed documentation for randomly selected completed surveillances to verify that the fire suppression system, smoke detection system, and manual fire fighting equipment as contained in the these areas were available.

The inspectors also verified that the fire protection equipment that was installed and available in the fire areas corresponded with the equipment which was referenced in the applicable portions of the Final Safety Analysis Report, Section 9.6, Fire Protection.

Finally, the inspectors verified that required compensatory actions were being implemented for designated fire areas.

The inspectors also reviewed condition reports related to fire protection activities to verify that the problems were appropriately characterized and to verify that identified corrective actions were reasonable.

b. Findings

No findings of significance were identified.

1R06 Flood Protection

.1 Deficiencies Identified with Expansion Joints Utilized as Flood and High Energy Line

Break Barriers Between the Component Cooling Water and West Engineered Safeguards Rooms

a. Inspection Scope

The inspectors performed the internal flood protection features inspection in the west engineered safeguards and component cooling water rooms which contain risk significant structures, systems and components.

The inspectors conducted walkdowns and design reviews, including reviews of preventive maintenance activities for the following attributes associated with these rooms:

C Sealing of equipment below the floodline, such as electrical conduits; C Holes or unsealed penetrations in floors and walls between flood areas; C Adequacy of watertight doors between flood areas; C Common drain system and sumps, including floor drain piping and check valves where credited for isolation of flood areas within plant buildings; C Sources of potential internal flooding that are not analyzed or not adequately maintained, for example failure of flexible piping expansion joints, roof leaks, and failure of service water lines; and C Condition and availability of temporary or removable flood barriers.

The inspectors also assessed condition reports related to identified flood protection issues to verify that the problems were appropriately characterized.

b. Findings

Introduction The inspectors identified a Green Finding that is being treated as a Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the failure to ensure activities affecting quality, specifically the inspection and maintenance of the safety-related expansion joints utilized as flood and high energy line break barriers, were prescribed by documented procedures of a type appropriate to the circumstances and accomplished in accordance with those procedures.

Description The inspectors reviewed Procedure MSM-M-16, Inspection of Watertight Barriers, and preventive maintenance activities associated with the safety-related expansion joints in the component cooling water and west engineered safeguards rooms that had been completed. The expansion joints served as a flood barrier separating the component cooling water room from the west engineered safeguards room located one level below.

The component cooling water room was susceptible to internal floods from a postulated failure of the main feed or service water lines or from a high energy line break of the main steam lines located in the room.

The inspectors walked down the components, and reviewed design basis information concerning the purpose and design requirements for the expansion joints. The inspectors also reviewed vendor manual information concerning recommended inspections and service life requirements and discussed these with cognizant engineering and maintenance personnel.

The inspectors identified numerous adverse issues associated with activities related to the safety-related expansion joints which included:

(1) the adequacy of prescribed and recently completed inspections;
(2) the adequacy of the current inspection program;
(3) the adequacy of the frequency of inspection; and
(4) the knowledge and skill level of personnel assigned to perform the inspections. Consequently, the inspectors concluded that the inspection and maintenance of the safety-related expansion joints had been inadequate. Some specific issues included the following:

C Inspection procedures and work instructions did not prescribe specific actions to ensure that the expansion joints were clean and free of debris which could hinder the ability to perform an adequate external visual inspection. Follow-up inspections determined the majority of expansion joints had not been cleaned in several years; C Inspection procedures and work instructions did not ensure total inspection of the expansion joints and did not prescribe any techniques to ensure complete inspection of the expansion joints; C Inspection of the internal portion of the expansion joints was not included or considered as part of the inspection process, even though degradation could occur internally. In the 30-year service of these expansion joints, the internals had not been inspected; C No basis existed for the current frequency of inspection which appeared contrary to vendor recommendations; and C Inspection procedures did not contain appropriate quantitative or qualitative acceptance criteria for determining that activities were accomplished satisfactorily.

The inspectors also identified that Expansion Joints XJ-423 and XJ-425 had not been previously inspected as part of the licensees program and that Expansion Joint XJ-432 was not inspected by licensee personnel in 1998 when the inspection was last performed because insulation covered the expansion joint. In response to these deficiencies, licensee personnel subsequently performed inspections on Expansion Joints XJ-432, XJ-423 and XJ-425 and all three failed the inspection acceptance criteria.

Further analysis by the licensee determined that while the expansion joints were degraded, the joints could still perform their intended function.

The inspectors determined that the failure to ensure that inspections and maintenance of expansion joints utilized as flood and high energy line break barriers were prescribed by and being accomplished in accordance with documented procedures of a type appropriate to the circumstances was a licensee performance deficiency warranting a significance evaluation.

Analysis The inspectors concluded that the finding was greater than minor in accordance with IMC 0612, Power Reactor Inspection Reports, Appendix B, Issue Disposition Screening, issued on April 29, 2002, because the finding would become a more significant concern if left uncorrected. Specifically, continued inadequate inspections and maintenance of the safety-related expansion joints could result in additional undetected degradation. Consequently, the mitigating systems objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences could be affected. Specifically, additional degradation of the safety-related expansion joints could potentially result in an internal flood or high energy line break in the component cooling water room to propagate to and adversely affect the safety-related mitigating equipment in the west engineered safeguards room.

The inspectors evaluated the finding using Manual Chapter 0609, Significance Determination Process, Appendix A, Significance Determination of Reactor Inspection Findings for At-Power Situations, Phase 1 screening, and determined that the finding:

C was not a design or qualification deficiency; C did not represent an actual loss of safety function of a system; C did not represent an actual loss of a safety function of a single train for greater than Technical Specification outage time; C did not represent an actual loss of a safety function of one or more Non-Technical Specification trains of equipment; and C did not screen as potentially risk significant due to a seismic, flooding, or severe weather initiating event.

Therefore, the finding was determined to be of very low safety significance (Green).

Enforcement 10 CFR 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, requires, in part, that activities affecting quality be prescribed by documented procedures of a type appropriate to the circumstances and be accomplished in accordance with those procedures. Contrary to this, licensee personnel failed to ensure that activities affecting quality, specifically the inspection and maintenance of the safety-related expansion joints utilized as flood and high energy line break barriers separating the component cooling water and west engineered safeguards rooms, were prescribed by and accomplished in accordance with documented procedures of a type appropriate to the circumstances. This violation is associated with an NRC identified finding that is characterized by the significance determination process as having very low risk significance (Green) and is being treated as a Non-Cited Violation of 10 CFR 50 Appendix B, Criterion XVI, consistent with Section VI.A.1 of the NRC Enforcement Policy. (NCV 50-255/02-07-01)

This finding and associated Non-Cited Violation is in the licensees corrective action program as Condition Reports CAP031186, Expansion Joint XJ-423 (Bellows Expansion Joint for HB-23-16") Failed Visual Inspection, CAP031187,Expansion Joint XJ-425 (Bellows Expansion Joint for HC-4-8") Failed Visual Inspection, and, CAP031188, Expansion Joint XJ-432 (Bellows Expansion Joint for HB-23-24") Failed Visual Inspection. The licensee determined that the issues raised by the inspectors constituted a significant condition adverse to quality. Consequently, the licensee assigned the highest significance level to the condition report, Level A, and formed a root cause evaluation team to determine the root and contributing causes for the finding raised by the inspectors.

.2 Failure to Implement Adequate Corrective Action for Previously Identified Flood Barrier

Deficiencies

a. Inspection Scope

The inspectors walked down the component cooling water room to verify the adequacy of watertight doors between flood areas. The inspectors also assessed previous corrective action documents, maintenance work control documents and recent inspections associated with Flood Door-196A which separated the component cooling water room from the turbine building.

b. Findings

Introduction The inspectors identified a Green Finding that is being treated as a Non-Cited Violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Actions, for the failure to promptly identify and correct conditions adverse to quality regarding Flood Door-196A which protects the safety-related equipment in the component cooling water room from a flood in the turbine building.

Description In January 2001, the inspectors performed a flood protection inspection and identified a degraded condition associated with the watertight seals for Door-196A which separated the turbine building flood zone from the component cooling water room flood zone. At that time, licensee personnel entered this issue into the corrective action program as Condition Report CPAL0100142, Some Flood Barriers Not Included in Procedure for Inspection of Watertight Barriers. The January 2001 inspection sample was documented in NRC Inspection Report 50-255/01-02(DRP) Section 1R06.

During walkdowns of the component cooling water room in September 2002, the inspectors identified that watertight seals for Flood Door-196A were in a condition worse than previously noted in January 2001, in that, physical gaps existed around the perimeter of the door and the watertight seal.

The inspectors subsequently reviewed the apparent cause evaluation and corrective actions for CPAL0100142. The corrective actions included adding Flood Door-196A to the inspection procedure for watertight barriers but the condition report evaluation did not identify any corrective actions to fix the degraded condition of the watertight seal. In December 2001, licensee personnel implemented the revised inspection procedure and identified the same deficient conditions for Flood Door 196A that the inspectors identified in January 2001.

Condition Report CPAL0104118, Watertight Door 196A Failure, Turbine Building/Component Cooling Water Room 590 Jailhouse Door, was generated and entered into the corrective action program after Flood Door-196A failed to meet the acceptance criteria during the December 2001 inspection. Subsequently, Work Order 24114391 was implemented in July 2002 as a corrective action to replace the watertight seals. However, the inspectors concluded that the corrective actions were inadequate in that Flood Door 196A was left in a degraded condition worse than previously identified in January 2001. Specifically, physical gaps, which did not previously exist, were identified between the door and the new watertight seal.

The inspectors determined that the failure to promptly identify and correct conditions adverse to quality regarding Flood Door-196A was a licensee performance deficiency warranting a significance evaluation.

Analysis The inspectors concluded that the finding was greater than minor in accordance with IMC 0612, Power Reactor Inspection Reports, Appendix B, Issue Disposition Screening, issued on April 29, 2002, because the finding:

(1) involved the protection against external factors (flood protection) and human performance attributes of the mitigating systems cornerstone;
(2) affected the mitigating systems objective of ensuring the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences because a flood in the turbine building could potentially spread to the component cooling water room; and
(3) the licensee failed to take adequate corrective actions for a previously identified minor violation. The inspectors also determined that this finding affected the cross-cutting issue of problem identification and resolution.

The inspectors evaluated the finding using Manual Chapter 0609, Significance Determination Process, Appendix A, Significance Determination of Reactor Inspection Findings for At-Power Situations, Phase 1 screening, and determined that the finding:

C was not a design or qualification deficiency; C did not represent an actual loss of safety function of a system; C did not represent an actual loss of a safety function of a single train for greater than Technical Specification outage time; C did not represent an actual loss of a safety function of one or more Non-Technical Specification trains of equipment; and C did not screen as potentially risk significant due to a seismic, flooding, or severe weather initiating event.

Therefore, the finding was determined to be of very low safety significance (Green).

10 CFR 50, Appendix B, Criterion XVI, Corrective Actions, requires in part that conditions adverse to quality be promptly identified and corrected. Contrary to this, licensee personnel failed to promptly correct the condition adverse to quality documented in Condition Reports CPAL0100142 and CPAL0104118 initiated in January 2001 and December 2001, respectively, as evidenced by the degraded water tight seal for Flood Door 196A. This violation is associated with an NRC identified finding that is characterized by the significance determination process as having very low risk significance (Green) and is being treated as a Non-Cited Violation of 10 CFR 50 Appendix B, Criterion XVI, consistent with Section VI.A.1 of the NRC Enforcement Policy. (NCV 50-255/02-07-02)

This finding and associated Non-Cited Violation is in the licensees corrective action program as Condition Report CAP031146, Gaps Identified in Flood Door 196A to Component Cooling Water Room.

1R11 Licensed Operator Requalification

.1 Quarterly Resident Inspector Licensed Operator Performance Observations

a. Inspection Scope

The inspectors observed licensed operator performance during an evaluated simulator scenario on September 25, 2002. The inspectors assessed the licensed operators ability to respond, in accordance with applicable emergency operating procedures, to a Loss Of Coolant Accident concurrent with a loss of safety-related 2400 Volt Electrical Bus 1C and three stuck rods. The inspectors also observed the post-scenario critique to assess the licensee evaluators ability to identify deficient operator performance.

b. Findings

No findings of significance were identified.

1R12 Maintenance Effectiveness

a. Inspection Scope

The inspectors reviewed the licensees maintenance effectiveness for the Emergency Diesel Generator Heating Ventilation and Air Conditioning System which was designated as having high safety significance.

The inspectors reviewed work order histories and selected condition reports written against the system over the last 4 years to verify that licensee personnel completed maintenance and addressed system problems appropriately. Completed work orders were reviewed to determine if there was an adverse trend in system performance that could be attributed to inappropriate work practices and to determine if there were any common cause issues that had not been addressed.

The inspectors reviewed selected condition reports and associated maintenance rule evaluations to verify that the identified system problems were appropriately characterized and were dispositioned in accordance with the licensees maintenance rule program. The inspectors also verified that designated corrective actions were reasonable and had been implemented as scheduled.

b. Findings

No findings of significance were identified.

1R13 Maintenance Risk Assessments and Emergent Work Evaluation

a. Inspection Scope

The inspectors reviewed, Operators Risk Reports, Shift Supervisor logs, and maintenance activity schedules to verify that equipment necessary to minimize plant risk was operable or available as required. The inspectors also conducted plant tours to verify that equipment necessary to minimize risk was available for use during the following planned and emergent maintenance activities:

C Planned maintenance on Component Cooling Water Pump P-52B concurrent with emergent maintenance on Emergency Diesel Generator 1-2; C Planned maintenance on Fuel Oil Transfer Pump P-18A and Containment Spray Pump P-54B; C Planned maintenance on the Switchyard Front, F, Bus C Planned maintenance and surveillance activities on Emergency Diesel Generator 1-1; and C Planned maintenance on High Pressure Safety Injection Pump P-66A and High Pressure Air Compressor C-6A, concurrent with emergent troubleshooting activities due to a ground on non safety-related 2400 Volt Electrical Bus 1E.

The inspectors discussed plant configuration control for the maintenance activities with operations, maintenance and work control center staff to verify that work activities were appropriately controlled.

In addition, the inspectors reviewed select condition reports to verify that problems regarding maintenance risk assessments and control of emergent work activities were appropriately characterized and entered into the licensees corrective action program.

b. Findings

No findings of significance were identified.

1R14 Personnel Performance Related to Non-Routine Plant Evolutions and Events

a. Inspection Scope

The inspectors observed and assessed performance by radiation protection personnel, maintenance personnel and operations personnel during the following non-routine evolutions which occurred during the inspection period:

C Spent resin sluice from Tank T-100 to a high integrity container on July 16, 2002; C Containment entries to add oil to Primary Coolant Pump P-50D on August 28, and September 28, 2002, while the plant was at 50 percent and 25 percent power respectively; C Troubleshooting activities for an electrical ground on non-safety related 2400 Volt Electrical Bus 1E on September 19, 2002. Plant operators reduced reactor power to 88 percent to repair the affected equipment after significant troubleshooting on electrical equipment identified the location of the electrical ground.

The inspectors reviewed radiation work permits and radiation planning that was in place to keep personnel radiation dose during the oil additions to the primary coolant pump and the spent resin sluice as-low-as-reasonably-achievable. The inspectors also reviewed radiation dose records after the evolutions to verify that the radiation planning efforts were effective.

The inspectors reviewed the applicable Off-Normal Procedures, System Operating Procedures, General Operating Procedures, Administrative Procedures and Technical Specifications for these events to verify that procedural guidance was appropriately followed. Further, the inspectors reviewed the control room logs and the resultant condition reports which were initiated to verify that these issues were entered into the corrective action program with the appropriate characterization and significance.

b. Findings

No findings of significance were identified.

1R15 Operability Evaluations

a. Inspection Scope

The inspectors reviewed the operability assessments as documented in the associated condition reports for the following risk significant components:

  • Expansion Joints Utilized for Flood and High Energy Line Break Protection between the Component Cooling Water and West Engineered Safeguards Rooms.

The inspectors interviewed the cognizant engineers and reviewed the supporting documents to assess the adequacy of the operability assessments for the current plant Mode. The inspectors also reviewed the applicable sections of the Technical Specifications, Final Safety Analysis Report, and Design Basis Documents to verify that the operability assessments were technically adequate and that the components remained available, such that no unrecognized increase in plant risk had occurred.

Further, the inspectors reviewed condition reports to verify that identified problems associated with the operability evaluations were appropriately characterized and entered into the licensees corrective action program.

b. Findings

No findings of significance were identified.

1R19 Post Maintenance Testing

a. Inspection Scope

The inspectors observed portions of post maintenance testing and reviewed documented testing activities following scheduled maintenance to determine whether the tests were performed as written. The inspectors also verified that applicable testing prerequisites were met prior to the start of the tests and that the effect of testing on plant conditions was adequately addressed by control room operators. The inspectors reviewed the following post maintenance test activities:

  • Component Cooling Water Pump P-52B;
  • Fuel Oil Transfer Pump P-18A;
  • High Pressure Air Compressor C-6B;
  • Safeguards Transformer EX-07; and
  • Thermal Margin Monitor Channel C.

The inspectors reviewed post maintenance testing criteria to verify that the test criteria was appropriate with respect to the scope of work performed and that the acceptance criteria were clear.

In addition, the inspectors reviewed the completed tests and procedures to verify that the tests adequately verified system operability. Documented test data was reviewed to verify that the data was complete and that the equipment met the procedure acceptance criteria, which demonstrated that the equipment was able to perform the intended safety functions.

Further, the inspectors reviewed condition reports regarding post maintenance testing activities to verify that identified problems were appropriately characterized.

b. Findings

No findings of significance were identified.

1R22 Surveillance Testing

a. Inspection Scope

The inspectors observed portions of the following surveillance testing activities conducted on risk-significant plant equipment to verify that testing was conducted in accordance with prescribed procedures:

  • Station Batteries ED-01 and ED-02;
  • Fire Protection Pumps P-9A, P-9B and P-41; and
  • Safety Injection and Refueling Water Tank Level Instrumentation.

The inspectors reviewed the documented test data for the Technical Specification Surveillance Test procedures and the associated basis documents to verify that testing acceptance criteria were satisfied.

In addition, the inspectors reviewed applicable portions of Technical Specifications, the Final Safety Analysis Report and Design Basis Documents to verify that the surveillance tests adequately demonstrated that system components could perform designated safety functions.

Further, the inspectors reviewed condition reports regarding surveillance testing activities to verify that identified problems were appropriately characterized.

b. Findings

No findings of significance were identified.

1R23 Temporary Plant Modifications

a. Inspection Scope

The inspectors reviewed the temporary modification package and associated 10 CFR 50.59 evaluations for the following temporary modifications:

  • TM 1999-032, Reactor Head Temperature Monitoring;

In addition, the inspectors reviewed condition reports to verify that identified problems regarding temporary modifications were appropriately characterized.

b. Findings

No findings of significance were identified.

1E06 Emergency Plan Drill Evaluation (71114.06)

a. Inspection Scope

The inspectors observed a licensed operator simulator training session on September 25, 2002, in which the Shift Supervisor was required to implement the Emergency Plan in response to the simulated plant conditions during the scenario. The inspectors verified that the Shift Supervisor declared the emergency condition and completed the required notifications to State and Local Police authorities, and the NRC in an accurate and timely manner in accordance with the licensees emergency plan.

b. Findings

No findings of significance were identified.

RADIATION SAFETY

Cornerstone: Occupational Radiation Safety

2OS1 Access Control to Radiologically Significant Areas (71121.01)

.1 Plant Walkdowns and Radiological Controls

a. Inspection Scope

The inspectors reviewed the radiological conditions of work areas within radiation areas and high radiation areas in the radiologically restricted area to verify the adequacy of radiological boundaries and postings. This included walkdowns of high and locked high radiation area boundaries in the Auxiliary Building and the Spent Fuel Pool. The inspectors performed independent measurements of area radiation levels and reviewed associated licensee controls to determine if the controls (i.e., surveys, postings, and barricades) were adequate to meet the requirements of 10 CFR Part 20 and the licensees Technical Specifications.

The inspectors reviewed the licensees records to determine if highly activated or contaminated materials (non-fuel) were stored in the spent fuel pool. Since no highly activated or contaminated materials were currently stored in the spent fuel pool, the inspectors reviewed the licensees procedures to evaluate the effectiveness of the physical and programmatic controls for storage of highly activated or contaminated materials in the spent fuel pool.

b. Findings

No findings of significance were identified.

.2 Job in Progress Reviews

a. Inspection Scope

The inspectors reviewed all radiological job requirements including radiation work permit requirements and work procedure requirements for maintenance activities on the T-100 Spent Resin Storage Tank. The inspectors attended the pre-job briefing for the maintenance activities to determine if the radiological conditions in the work area were adequately communicated to the workers. Following the briefing, the inspectors observed activities at the work site to verify the adequacy of radiological controls including required surveys, radiation protection job coverage, and contamination controls.

b. Findings

No findings of significance were identified.

.3 Radiation Worker Performance

a. Inspection Scope

The inspectors observed radiation worker practices during maintenance activities on the T-100 Spent Resin Storage Tank to determine if the workers were aware of the significant radiological conditions in their workplace and the radiation work permit controls/limits in place. The inspectors also evaluated whether the workers performance reflected the level of radiological hazards present.

The inspectors reviewed condition reports and action requests to determine if there had been radiological incidents that resulted from radiation worker errors. The inspectors reviewed each to determine if there had been an observable pattern traceable to a similar cause for the errors and whether or not the corrective action program had addressed those causes.

b. Findings

No findings of significance were identified.

.4 Radiation Protection Technician Proficiency

a. Inspection Scope

The inspectors observed radiation protection technician (RPT) performance during maintenance activities on the T-100 Spent Resin Storage Tank to determine if the RPTs enforced radiation protection work requirements at the work site. The inspectors also determined if the RPTs were aware of the significant radiological conditions in their workplace, and the radiation work permit controls/limits, and that their performance was consistent with their training and qualifications with respect to the radiological hazards and work activities.

The inspectors reviewed action requests that documented incidents that resulted from RPT errors. The inspectors reviewed each to determine if there was an observable pattern traceable to a similar cause for the incidents and whether the corrective action program addressed those causes.

b. Findings

No findings of significance were identified.

2OS2 As-Low-As-Is-Reasonably-Achievable (ALARA) Planning and Controls (71121.02)

.1 Radiological Work/ALARA Planning

a. Inspection Scope

The inspectors reviewed post job ALARA reports for reinstalling seismic restraints on Control Rod Drive Upper Housings and for reinstalling 45 Control Rod Drive Upper Housings during the 2001 Spring Refueling and Inspection Outage (REFOUT01). The inspectors evaluated the accuracy of exposure estimates in the ALARA plans for those activities, compared the actual exposure results versus the initial exposure estimates, the estimated and actual dose rates as well as the estimated and actual man-hours expended. The inspectors reviewed the exposure history for each activity as well as the post job ALARA reports to determine if management had monitored the exposure status of each activity, to determine if in-progress ALARA job reviews were needed and performed, to determine if additional engineering/dose controls had been established, and to determine if required corrective documents had been generated.

b. Findings

No findings of significance were identified.

.2 Verification of Exposure Estimate Goals and Exposure Tracking System

a. Inspection Scope

The inspectors reviewed the post job ALARA reports for reinstalling seismic restraints on Control Rod Drive Upper Housings and for reinstalling 45 Control Rod Drive Upper Housings during the 2001 Spring Refueling and Inspection Outage (REFOUT01) to evaluate the methodology and assumptions used by the licensee for each activities exposure estimates and exposure goals. Actual job exposure data was compared with estimates to verify that the licensee had projected and, thus, controlled radiological exposure. The inspectors also reviewed the licensees exposure tracking system to verify that the level of exposure tracking detail, exposure report timeliness, and exposure report distribution were sufficient to support control of collective exposures for each activity.

b. Findings

No findings of significance were identified.

.3 Source-Term Reduction and Control

a. Inspection Scope

The inspectors evaluated the licensees source-term reduction program in order to verify that the licensee had an effective program in place, and was knowledgeable of plant source term and techniques for its reduction. Areas of review included:

C The installation of permanent shielding in Auxiliary Building; C The hot spot reduction program; C The installation of additional steam generator platforms; and C Elimination of the Radwaste Evaporators.

The inspectors also reviewed the results of source-term reduction initiatives implemented prior to REFOUT01 to determine if the program had been successful in reducing system wide source-term.

b. Findings

No findings of significance were identified.

.4 Identification and Resolution of Problems

a. Inspection Scope

The inspectors reviewed a Chemical and Radiological Services focused self-assessment of the ALARA Program to evaluate the effectiveness of the self-assessment process to identify, characterize, and prioritize problems. The inspectors also reviewed corrective action documentation (condition reports and action requests) to verify that access control and ALARA related issues were adequately addressed.

b. Findings

No findings of significance were identified.

SAFEGUARDS

Cornerstone: Physical Protection (PP)

3PPI Access Authorization (AA) Program (Behavior Observation Only) (71130-01)

a. Inspection Scope

The regional security inspector interviewed five supervisors and five non-supervisors (both licensee and contractor employees) to determine their knowledge and practice of implementing licensee behavior observation program responsibilities. Selected procedures pertaining to the implementation of the Behavior Observation Program and associated training activities were also reviewed. Also, the licensees most recent fitness-for-duty semi-annual test results were reviewed. In addition, the inspector reviewed a sample of assessments, audits, and security logged events that pertained to the licensees behavior observation program. The inspector also interviewed selective licensee and security contractor managers to evaluate their knowledge and use of the licensees corrective action system.

b. Findings

No findings of significance were identified.

3PP2 Access Control (Identification, Authorization and Search of Personnel, Packages, and Vehicles) (71130.02)

a. Inspection Scope

The regional security inspector reviewed the licensees protected area access control testing and maintenance programs and related procedures. The inspector observed licensee testing of all in-service access control equipment located at the licensees protected area portal to determine if testing and maintenance practices were effective and performance based. On at least two occasions, during peak ingress periods, the inspector observed in-processing search of personnel, packages, and vehicles at the licensees protected area portal to determine if those practices were conducted in an effective manner and were in accordance with regulatory requirements. Interviews with randomly selected security personnel were conducted and records were reviewed to verify that security staffing levels were consistently and appropriately implemented. The inspector also reviewed the licensees process and practice for limiting access to only authorized personnel to the protected area and vital equipment through a selected sample of personnel access authorization lists and actual protected and vital area entries.

The inspector reviewed the licensees program to control hard-keys, and computer input of security-related personnel data.

The regional security inspector reviewed a random sample of licensee assessments, audits, maintenance records, and security logged events for identification and resolution of problems. In addition, the inspector interviewed several licensee and contract security managers to evaluate their knowledge and use of the licensees corrective action program.

b. Findings

No findings of significance were identified.

3PP3 Response to Contingency Events (71130.03)

The Office of Homeland Security (OHS) developed a Homeland Security Advisory System (HSAS) to disseminate information regarding the risk of terrorist attacks. The HSAS implements five color-coded threat conditions with a description of corresponding actions at each level. NRC Regulatory Information Summary (RIS) 2002-12a, dated August 19, 2002, NRC Threat Advisory and Protective Measures System, discusses the HSAS and provides additional information on protective measures to licensees.

a. Inspection Scope

On September 10, 2002, the NRC issued a Safeguards Advisory to reactor licensees to implement the protective measures described in RIS 2002-12a in response to the Federal government declaration of threat level Orange. Subsequently, on September 24, 2002, the OHS downgraded the national security threat condition to Yellow and a corresponding reduction in the risk of a terrorist threat.

The inspector interviewed licensee personnel and security staff, observed the conduct of security operations, and assessed licensee implementation of the threat level Orange protective measures. Inspection results were communicated to the region and headquarters security staff for further evaluation.

b. Findings

No findings of significance were identified.

OTHER ACTIVITIES (OA)

4OA1 Performance Indicator Verification

.1 Safety System Unavailability Performance Indicators

a. Inspection Scope

The inspectors verified that the performance indicator data submitted by the licensee was accurate and complete regarding the unavailability of the Auxiliary Feedwater System and the Residual Heat Removal System.

The inspectors reviewed control room logs, licensee monthly operating reports, licensees Incident Analysis System logs, completed Technical Specification Surveillance Tests, and the licensees maintenance work order database for components taken out of service in the auxiliary feedwater and residual heat removal systems, to verify that the licensee had accurately reported the systems unavailability time for July 2001 through July 2002.

In addition, the inspectors discussed the data with the licensee staff responsible for gathering and reporting the information related to the performance indicators.

b. Findings

No findings of significance were identified.

.2 Physical Protection Performance Indicators

a. Inspection Scope

The regional security inspector reviewed the data for the Physical Protection Performance Indicators pertaining to Fitness-For-Duty/Personnel Reliability, Personnel Screening Program, and Protected Area Security Equipment Performance. Specifically, a sample of plant reports related to security events, security shift activity logs, fitness-for-duty reports, and other applicable security records were reviewed for the period between January 2002 and July 2002. In addition, appropriate licensee security management personnel were interviewed regarding their interpretation and application regarding the data submitted for the physical protection performance indicators.

b. Findings

No findings of significance were identified.

.3 Radiation Safety and Reactor Coolant System Activity Performance Indicators

d. Inspection Scope

The inspectors verified the licensees assessment of its performance indicators for the previous four calendar quarters for the occupational and public radiation safety cornerstones as well as the reactor coolant system (RCS) specific activity. No reportable elements were identified by the licensee for the 3rd and 4th quarters of 2001 or 1st and 2nd quarters of 2002. The inspectors compared the licensees data with the previous four quarters condition reports, public dose records, and RCS specific activity records to verify that there were no occurrences during those quarters concerning the occupational and public radiation safety cornerstones and the RCS specific activity.

4OA2 Identification and Resolution of Problems

a. Inspection Scope

The inspectors reviewed apparent and root cause evaluations associated with the following Condition Reports:

  • CPAL0101862, Incorrect Wire Lifted in SPS-E-12 Resulted in Current Transformer Circuit Being Open Circuited.
  • CPAL0201832, Service Water System Filter F-1005 Plugged Up with Sand.

The inspectors verified that the following attributes were adequately addressed in the licensees evaluations and associated corrective actions:

  • Consideration of extent of condition, generic implications, common cause and previous occurrences;
  • Classification and prioritization of the resolution of the problem, commensurate with safety significance;
  • Identification of the root and contributing causes of the problem;
  • Identification of corrective actions which were appropriately focused to correct the problem;
  • Completion of completed corrective actions in a timely manner commensurate with the safety significance of the issue; and
  • Implementation of longer term corrective actions appear appropriate and adequate compensatory actions were in place to minimize a problem until the permanent action was completed.

The inspectors also discussed the corrective actions and associated evaluations with applicable site personnel including the condition report evaluators and system engineers.

b. Findings

No findings of significance were identified.

4OA4 Cross-Cutting Findings

.1 A finding described in Section 1R06.2 of this report had, as its primary cause, a problem

identification and resolution deficiency, in that, the licensee failed to promptly correct a condition adverse to quality associated with flood barriers between the turbine building and component cooling room previously identified by the inspectors in January 2001.

4OA6 Meetings

.1 Exit Meeting

The inspectors presented the inspection results to Mr. D. Cooper and other members of licensee management on October 3, 2002. Licensee personnel acknowledged the findings presented. The inspectors asked licensee personnel whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.

.2 Interim Exit Meetings

Interim exit meetings were conducted for:

C Safeguards inspection with Mr. R. Remus, Assistant Plant Manager, on August 15, 2002 C As-Low-As-Is-Reasonably-Achievable Planning and Controls, and Access Control to Radiologically Significant Areas with Mr. R. Remus, Assistant Plant Manager on August 22, 2002

4OA7 Licensee Identified Violations

The following violations of very low significance were identified by licensee personnel and are violations of NRC requirements which meets the criteria for Section VI of the NRC Enforcement Manual, NUREG-1600, for being dispositioned as Non-Cited Violations.

Cornerstone: Mitigating Systems

Conditions adverse to quality are required by 10 CFR 50, Appendix B, Criterion XVI, Corrective Action, to be promptly identified and corrected. As described in Condition Reports, CPAL0202723, Oil Leakage From Differential Pressure Switch DPS-1487/

Housekeeping Issue - Emergency Diesel Generator 1-2, and CPAL0202862, Conduit on 1-2 Diesel Generator Found Full of Oil, licensee personnel failed to promptly identify and correct a condition adverse to quality.

On July 25, 2002, as a corrective action for CPAL0202723, Work Order 24212928 was completed which replaced the differential pressure switch that was leaking oil.

Maintenance personnel, while completing Work Order 24212928, had documented that the differential pressure switch was full of oil, that oil was running down the conduit, that the oil would continue to leak out of the conduit until the conduit was replaced or cleaned out and that the only oil noted during the post maintenance test was the oil that was coming out of the conduit. A work request was written to replace or clean the conduit at an undetermined later date. However, no further actions were taken to evaluate extent of condition and no condition report was generated to enter the issues documented in the work package into the licensees corrective action program.

On July 31, 2002, operations personnel identified oil leaking from the conduit and approximately two to three gallons of oil was drained from the conduit during troubleshooting. Operations personnel subsequently generated Condition Report CPAL0202862 and declared Emergency Diesel Generator 1-2 inoperable because of poor material condition with the potential to adversely affect required attendant instrumentation.

Consequently, this resulted in entry into an unplanned technical specification action statement for the inoperable emergency diesel generator and emergent work on safety-related plant equipment. The condition adverse to quality, oil in the conduit, that adversely affected emergency diesel generator operability could have been addressed during the scheduled maintenance on July 25, 2002, had licensee personnel addressed the problems that were documented in the work package within the corrective action program.

KEY POINTS OF CONTACT Licensee T. Brown, Manager, Chemical and Radiological Services D. Cooper, Site Vice President D. Crabtree, Systems Engineering Manager P. Harden, Director, Engineering G. W. Hettel, Manager, Maintenance and Construction L. Lahti, Licensing Manager D. G. Malone, Supervisor, Regulatory Assurance D. J. Malone, General Plant Manager G. Packard, Operations Manager R. Remus, Assistant Plant Manager J. Waddell, NMC/Acting Security Manager NRC J. Eads, Project Manager, NRR D. Hood, Project Manager, NRR D. Passehl, Acting Branch Chief, RIII S. Reynolds, Deputy Division Director, Division of Reactor Projects, RIII A. Vegel, Branch Chief, RIII LIST OF ITEMS OPENED AND CLOSED Opened 50-255/02-07-01 NCV Green. 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the failure to ensure the inspection and maintenance of the safety-related expansion joints utilized as flood and high energy line break barriers were prescribed by and accomplished in accordance with documented procedures of a type appropriate to the circumstances.

50-255/02-07-02 NCV Green. 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Actions, for the failure to promptly identify and correct conditions adverse to quality regarding Flood Door-196A which protects the safety-related equipment in the component cooling water room from a flood in the turbine building.

Closed 50-255/02-07-01 NCV Green. 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the failure to ensure the inspection and maintenance of the safety-related expansion joints utilized as flood and high energy line break barriers were prescribed by and accomplished in accordance with documented procedures of a type appropriate to the circumstances.

50-255/02-07-02 NCV Green. 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Actions, for the failure to promptly identify and correct conditions adverse to quality regarding Flood Door-196A which protects the safety-related equipment in the component cooling water room from a flood in the turbine building.

LIST OF

DOCUMENTS REVIEWED

1R04 Equipment Alignment

Plant Procedures

MO-29 Technical Specification Surveillance Procedure Revision 33 and 9

and Basis Document - Engineered Safety System

Alignment

SOP-12 Feedwater System Revision 41

Checklist CL 12.5 Auxiliary Feedwater System Supply (Except K-8 Revision 41

SOP-12 Steam Supply)

14

Checklist CL 12.5 Except K-8 Steam Supply Checklist Revision 41

SOP-12

15

T-345 Completed Special Test T-345 - AFW Pumps Revision 2

P-8A/B Firemain Backup Line Flush, completed

May 13, 1994

AP-4.00 Operations Organization, Responsibilities, and Revision 23

Conduct

SOP-20 High Pressure Control Air System Revision 19

Checklist CL 3.1 Engineered Safeguards System Checklist Revision 47

SOP-3

10

Checklist CL 16 Component Cooling System Checklist Revision 22

SOP-16

AP-4.02 Control of Equipment Revision 18

SWSO-4, Fire Protection System - Molluscide Treatment for Revision 5

Zebra Mussels

Miscellaneous Documents

DBD 1.03 Design Basis Document - Auxiliary Feedwater Revision 5

Control Room Deficiency, Operator Work-Around August 15, 2002

and Operator Challenges Reports

WO24211178 Accurate Temperature Indication/Detection of

Tanks T-2 and T-81 is suspect

EAR-1999-0174 Review and Revise CIS Design Information in

Sections 5.8, 6.7, Table 5.8-4 and Figure 6-6 of

FSAR

M-207, Sheet 11 Piping and Instrument Diagram - Feedwater and Revision 1

Condensate System

M-207, Sheet 2 Piping and Instrument Diagram - Auxiliary Revision 31

Feedwater System

M-205, Sheet 2 Piping and Instrument Diagram - Main Steam and Revision 62

Auxiliary Turbine Systems

M-220, Sheet 1 Piping and Instrument Diagram - Makeup Revision

Domestic Water and Chemical Injection Systems

M-204, Sheet 1A Piping and Instrument Diagram - Safety Injection Revision 27

Containment Spray and Shutdown Cooling

System

M-204, Sheet 1 Piping and Instrument Diagram - Safety Injection Revision 73

Containment Spray and Shutdown Cooling

System

M-204, Sheet 1B Piping and Instrument Diagram - Safety Injection Revision 31

Containment Spray and Shutdown Cooling

System

M-203, Sheet 2 Piping and Instrument Diagram - Safety Injection Revision 27

Containment Spray and Shutdown Cooling

System

M-209, Sheet 2 Piping and Instrument Diagram - Component Revision 30

Cooling System

Condition Reports Reviewed to Assess Problem Identification Characterization

CPAL0002701 Steam Leaking Past Auxiliary Feedwater Pump

Normal Steam Supply Valve CV-0522B Disc/Seat

CAP031154 Corrective Action from CPAL0000625 Not

Properly Implemented

CAP031074 Emergency Feed Supply Line to Auxiliary

Feedwater Pumps Subjected to Sand

Accumulation

CAP031446 Broken U-Bolt Identified on Common Drain to

Steam Generator Code Safeties

Condition Reports Reviewed to Assess Cause Evaluations

CPAL970478 Runout of Fire Pumps and or Tank-2

Overpressure Concerns During Auxiliary

Feedwater System Crosstie

CPAL0000625 Auxiliary Feedwater Pump P-8A Outboard Motor

Bearing Contained Metal Shavings

CPAL0002607 Contaminant Found in Bottom of Auxiliary

Feedwater Pump P-8A Inboard and Outboard

Pump Bearing Oilers

1R05 Fire Protection

Plant Procedures

FP-MS-1 Fire Protection Check Sheet - Monthly Inspection Revision 2

and Testing of Fire Doors for Fire Areas 17, 24,

FPSP-RM-5 Palisades Plant Fire Damper Data Sheet - Fire

Area 3

FPSP-SI-1 Data Sheet for Alarm Bells and Ionization Smoke Revision 2

Detectors for Fire Areas 3,10, 17, 26

FPSP-RP-11 Fire Barrier Penetration Seal/Conduit Seal Revision 4

Inspection Form for Fire Areas 3, 17, 10, 24, 26

FPSP-MO-1 Fire Suppression Water System Valve Alignment Revision 3

- Verification Checkoff Sheet for MV-FP147

FPSP-QO-2 Fire Protection Sprinkler System Water Flow Revision 1

Switch Alarm Check Sheet for Fire Areas 3, 26

FPSP-SO-2 Safety-Related Fire Door Data Sheet for Fire Revision 0

Area 24, 26

FPSP-AO-2 Fire Suppression Water System Fire Valve Revision 3

Operation Data Sheet

FPSP-RO-9 Sprinkler Head Locations, Fire Areas 3, 26 Revision 0

ONP-12 Off-Normal Procedure - Acts of Nature Revision 17

AP-4.02 Administrative Procedure - Control of Equipment Revision 18

ONP-25.1 Off-Normal Procedure - Fire Which Threatens Revision 11

Safety-Related Equipment

PFM-E-1 Emergency Post-Fire Repair For Appendix R Revision 4

Equipment

ONP25.2 Off-Normal Procedure - Alternate Safe Shutdown Revision 17

Procedure

Miscellaneous Documents

EA-PSSA-00-001 Palisades Plant Post Fire Safe Shutdown Revision 1

Summary Report, for Fire Areas 10, 3, 5, 24, 26,

17, and 32

Palisades Plant Analysis for Fire Areas 10, 3, 5, 24, 26, 17, and Revision 4

Fire Hazards 32

Analysis

BTP ASB 9.5-1 U.S. NRC Branch Technical Position 9.5-1 - Revision 1

Guidelines for Fire Protection for Nuclear Power

Plants

Consumer Power Company - List of Changes Revision 2

and Response to Appendix A to Branch August 24, 1996

Technical Position APCSB 9.5-1 and Regulatory

Guides 1.78 and 1.101

FSAR 9.6 Final Safety Analysis Report, Section 9.6 - Fire Revision 23

Protection

U.S. NRC Fire Protection Safety Evaluation September 1, 1978

Report by the Office of Nuclear Reactor

Regulation, U.S. Nuclear Regulatory Commission

in the Matter of Consumers Power Company

Palisades Plant

EA-FPP-95-056 Engineering Analysis - Evaluation of the Effects Revision 0

of a Fire Occurring in the SIRW Tank Area (Fire

Area 32) on Associated Fire Barriers

EA-FPP-95-041 Engineering Analysis - Analysis of Combustible Revision 1

Loading for Fire Area 32, SIRW Tank and CCW

Roof Area

X-NECO/FP009 Preventative Maintenance Activity, Inventory of

Appendix R Emergency Parts

Condition Reports Reviewed to Assess Problem Identification Characterization

CPAL0202678 Nitrogen Bottles For N2 Station #6 Secured with

Rubber Tie Down Strap

CPAL0202717 FSAR Table 9-10 Incorrectly Indicates the

Number of Water Flow Switches Associated With

the 1-D Switchgear Room 223 Automatic Fire

Suppression System

CPAL0202542 Fire Door 71 From Bus 1C to Diesel Generator 1-

Room Found Partially Open

CPAL0202646 Deficiencies Note During NRC Walkdown of West

Safeguards

CAP031435 Drawing Inaccuracies on P&ID M-216, Sheet 7

for Fire Area 32

CAP031260 Inadequate Installation of Connector on Appendix

R Spare Cables

Condition Reports Reviewed to Assess Corrective Actions

CPAL0102818 Apparent Trend of the Hotbutton Fire Protection

CPAL0200253 Apparent Decline in Engine Speed For Diesel

Engine K-5 / Fire Pump P-9B

1R06 Flood Protection

Periodic and Predetermined Activity (Preventative Maintenance)

MSM-071 Preventive Maintenance for the Inspection of

Watertight Barriers

24714345 Work Order - Completion of MSM-071 1998 June 1998

Inspections

24614409 Work Order - Completion of MSM-071 1997 July 1998

Inspections

24512369 Work Order - Completion of MSM-071 1996 March 1996

Inspections

24111281 Work Order - Annual Inspection of Watertight December 2001

Barriers

MSM-091 5-year Preventive Maintenance for the

Inspection of Watertight Barriers

Miscellaneous Documents

DBD-7.08 Design Basis Document, Plant Protection Revision 3

Against Flooding

Staff Evaluation Report of Individual Plant April 22, 1999

Examination of External Events Submittal on

Palisades Nuclear Plant

MSM-M-16 Permanent Maintenance Procedure, Revisions 9, 8, 7

Inspection of Watertight Barriers

M0384 0010 Vendor Manual - Garlock Inc. Installation and

Maintenance Instructions for Expansion Joints

Bechtel Original Civil/Structural High Energy May 27, 1975

Line Break (HELB) Outside Containment

Design Calculations

5935-M-139 Requisition Number for Engineered December1969

Safeguards Pump Room Pipe Penetration

Seals and Expansion Joints

24812207 Work Order - Inspect Expansion Joint XJ- October 1999

0430 per MSM-M-16

24812204 Work Order - Inspect Expansion Joint XJ- October 1999

0431 per MSM-M-16

289549 Work Request - Remove Insulation from XJ-

2 and inspect expansion joint

C-100 Construction Print - Standard Concrete Details Revision 5

C-88 Construction Print - Architectural Details Revision 1

C-48 Construction Print - Architectural Auxiliary and Revision 19

Reactor Buildings

Condition Reports Reviewed to Assess Problem Identification Characterization

CAP031146 Gaps Identified in Flood Door 196A to

Component Cooling Water Room

CAP031150 June 1998 Expansion Joint Inspection Results

Not Effectively Documented/Reviewed

CAP031164 Flood Doors Dogging Requirements

CAP031186 Expansion Joint XJ-423 (Bellows Expansion

Joint for HB-23-16") Failed Visual Inspection)

CAP031187 Expansion Joint XJ-425 (Bellows Expansion

Joint for HC-4-8") Failed Visual Inspection)

CAP031188 Expansion Joint XJ-432 (Bellows Expansion

Joint for HB-23-24") Failed Visual Inspection)

CAP031355 Non-Engineering Documentation to Support

Operability Determinations

Condition Reports Reviewed to Assess Corrective Actions

CPAL0202352 Inspection Discrepancy Results for Expansion

Joint XJ-0432 in MSM-M-16 Performed in

June 1998

CPAL0100142 Some Flood Barriers Not Included in

Procedure for Inspection of Watertight

Barriers

CPAL0104137 Potential Adverse Trend: Material Condition of

Watertight Doors

1R11 Licensed Operator Requalification

SPE-Y Simulator Performance Exam - LOCA with Revision 1

loss of Bus 1C and Stuck Rods

Documented results for simulator performance September 25, 2002

evaluation, Shift 3

1R12 Maintenance Effectiveness

Miscellaneous Documents

Emergency Diesel Generator Room Fans

Maintenance Rule Scoping Document and

Related Maintenance Rule Performance

Indicators

Online Work Review Report - Work Orders for

work weeks 2242 and 2244

EAR 98-0050 Engineering Assistance Request - V-24 Fan

Motor Conduit Repairs

Work Orders

24513530 V-24A, K-6A Diesel Generator Room Vent Fan

24513529 V-24B, K-6A Diesel Generator Room Vent Fan

24513531 V-24C, K-6A Diesel Generator Room Vent Fan

24013808 PM-Breaker / Starter 52-2425 V-24C

24013711 PM-Breaker / Starter 52-2435 V-24D

24112399 1-2 EDG Air Dampers D-28, D-29 and D-22 PM

24112713 V-24B Gravity Damper

Condition Reports Reviewed to Assess Corrective Actions

CPAL9800118 V-24D Motor Conduit Flange Bolts

Broken/Missing

CAPL9800124 Breaker 52-2545 (V-24B) Found in Tripped

Condition

CPAL9800321 V-24B Cycling Frequently In Auto

CPAL0200504 Work Orders for Diesel Generator Room

Ventilation Backdraft Damper Replacement

Needs TM to Maintain EDG Operability

CPAL0103706 D/G Room Vent Fan Would Not Start In Hand

CPAL0001121 Diesel Generator Room Ventilation Temperature

Setpoints in Question

CPAL9801398 Breaker 52-2435 (V-24B) Connector Loose

Condition Reports Reviewed to Assess Problem Identification Characterization

CAP031029 Equipment Control During Maintenance - Diesel

Generator Cooling Fans

CAP031031 Incomplete MOD Package EAR-98-0050 -

Corrective Action Incomplete

1R13 Maintenance Risk Assessments and Emergent Work Evaluation

Plant Procedures

Admin. 4.02 Administrative Procedure 4.02 - Control of Revision 18

Equipment

Miscellaneous Documents

Operators Risk Reports, Shift Supervisor Log

Entries, and Daily Work Schedules for July 29,

2002, through August 1, 2002, during emergent

maintenance on Emergency Diesel Generator 1-2

concurrent with a planned outage on Component

Cooling Water Pump P-52B

Operators Risk Reports, Shift Supervisor Log

Entries, and Daily Work Schedules for August

20th through 22nd, 2002, During Planned

Maintenance Activities on Fuel Oil Transfer Pump

P-18A

Operators Risk Reports, Shift Supervisor Log

Entries, and Daily Work Schedules for September

6th during planned maintenance activities in the

switchyard and on Emergency Diesel Generator

1-1

Operators Risk Reports, Shift Supervisor Log

Entries, and Daily Work Schedules for September

11-13, 2002, during a planned outage on the

switchyard Front Bus and safeguards

transformer

Operators Risk Reports, Shift Supervisor Log

Entries, and Daily Work Schedules for September

17th through 20th, 2002, During Planned

Maintenance Activities on High Pressure Safety

Injection Pump P-66A and High Pressure Air

Compressor C-6A, in addition to emergent

maintenance on Electrical Bus 1-E

Condition Reports Reviewed to Assess Problem Identification Characterization

CAP031305 Degraded Motor Condition Found While

Performing Preventive Maintenance on

Compressor C-6A Motor

CAP031313 Spurious Alarm EK-3519, Diesel Fire Pump P-41

Engine Trouble

1R14 Non-Routine Plant Evolutions and Events

Plant Procedures

SOP-18B Radioactive Waste System - Solid Revision 18

WI-RSD-R-008 Spent Resin Transfers To Resin Liners In Track Revision 7

Alley

SOP-2B Chemical and Volume Control System Revision 14

Purification and Chemical Injection

Miscellaneous Documents

Spent Resin Transfer pre-job checklist July 15, 2002

P020524 Radiation Work Permit - Sluice T-100 resin to a Revision 0

HIC in a shipping cask in Track Alley

A-CMT-97-068 Action item record - Reply to Notice of Violation, September 8, 1997

inadequate procedure for the operation of the

solid radwaste system

Radiation dose summary for T-100 resin sluice

P020518 Radiation Work Permit - Perform Surveys and Revision 1

Add Oil to Primary Coolant Pump P-50D

Radiological Survey Sheet - B Steam Generator August 26, 2002

Platform (618' / 624')

Radiation dose summaries for oil additions to

PCP P-50D

Condition Reports Reviewed to Assess Problem Identification Characterization

CPAL0202715 Enough Clean Radwaste Filters Not Available for

T-100 Spent Resin Storage Tank Sluice

CPAL0202712 Valve Stem Sheared on MV-DMW737, Primary

Makeup Water to T-100, During T-100 Spent

Resin Storage Tank Sluice

CPAL0202688 Spent Resin Tank T-100 Sluice Results in

Elevated Dose Rates In Various Radwaste

Systems

CPAL0202641 F-57A, Primary Drain Tank Filter Became

Clogged While Draining Water From T-100

Radwaste Spent Resin Storage Tank

CAP031331 Unexpected Alarms due to Bus 1E Ground

CAP031363 Breaker 152-306 Failed to Close from the Control

Room When Restored from Bus 1E

Troubleshooting

CAP031367 Bus 1E Ground Identified on X-Phase Bolted

Connection of Heater Drain Pump P-10B

CAP031281 Primary Coolant Pump P-50D Lower Oil

Reservoir Change

CAP031282 Fuel Oil Found in Diesel Fire Pump P-41 Lube Oil

Sump

1R15 Operability Evaluations

CPAL0003231 DPS-1487 (K-6B Lube Oil Differential Pressure

Switch) Found Leaking During Calibration

WO24212928 Work Order - K-6B Lube Oil Filter Differential

Pressure, DPS-1487

CPAL0202723 Condition Report Evaluation - Oil Leakage From

Differential Pressure Switch DPS-1487 /

Housekeeping Issue - Emergency Diesel

Generator 1-2

CPAL0202862 Condition Report Evaluation - Conduit on 1-2

Diesel Generator Found Full of Oil

CAP031009 Multiple Check Valves Incorrectly Modeled in

System Hydraulic Analyses

CAP031074 Emergency Feed Supply Line to Auxiliary

Feedwater Pumps Subjected to Sand

Accumulation

CAP031150 June 1998 Expansion Joint Inspection Results

Not Effectively Documented/Reviewed

CAP031164 Flood Doors Dogging Requirements

CAP031186 Expansion Joint XJ-423 (Bellows Expansion Joint

for HB-23-16") Failed Visual Inspection)

CAP031187 Expansion Joint XJ-425 (Bellows Expansion Joint

for HC-4-8") Failed Visual Inspection)

CAP031188 Expansion Joint XJ-432 (Bellows Expansion Joint

for HB-23-24") Failed Visual Inspection)

Miscellaneous Documents

SWSO-4, Fire Protection System - Molluscide Treatment for Revision 5

Zebra Mussels

EA-A-PAL-94-095 Engineering Analysis - Auxiliary Feedwater Revision 0

Pumps Net Positive Suction Head

EA-C-PAL-95- Engineering Analyses - Incorporation of a Higher Revision 2

0053B-01 Auxiliary Feedwater Pump Low Suction Pressure

Trip Setpoint from the Tank-2/-81 Inventory

Calculations Using the RETRAN Program

Condition Reports Reviewed To Assess Problem Identification Characterization

CAP026576 Diesel Past Operability Not Documented Under

CPAL0202862

1R19 Post Maintenance Testing

Plant Procedures

QO-15 Inservice Test Procedure - Component Cooling Revision 16

Water Pumps and associated basis document

EM-09-04, Pump Test Hydraulic Circuits Revision 19

EM-09-04, Table 2, Allowable Ranges of Test Quantities Revision 19

SOP-22 System Operating Procedure - Emergency Diesel Revision 32

Generators

Work Orders

24113333 Replacement of I/I-1010C; Replace TMM

Channel C Delta T Power Deviation Isolator

with a New Replacement

212973 K-6B Lube Oil Filter Differential Pressure Switch

210985 Component Cooling Water Pump P-52B Motor

210890 Pump P-18A Pump Coupling Inspection,

Lubrication and Preventive Maintenance

24111602 Repair EX-07, Safeguards Transformer 1-1,

Disconnect MOD-24F1

24114065 Repair EX-07, Safeguards Transformer 1-1,

Minor Hot Spots on Bolted Connections

211241 Compressor C-6B, Routine PM Breaker 52-771

24114433 Compressor C-6B, Drill Slots in Compressor Box

to Allow Proper Sheave

210840 Compressor C-6B Aftercooler/Air Dryer/Valve

Preventive Maintenance

24112484 Compressor C-6B Breaker 52-771 Cycled When

Unit Reached High Pressure Shutdown

Miscellaneous Documents

SHO-1

EAR-200-0403 Engineering Assistance Request -

Replacement/Redesign of Thermal Margin

Monitor Isolators

VT-2 Examiner Certification Records July 31, 2002

M0034 0075 Vendor Manual - Falk Corporation Installation

and Maintenance Instructions for Steel Flex

Couplings Type T10

Condition Reports Reviewed to Assess Problem Identification Characterization

CAP026573 Post Maintenance Testing For 1-2 Diesel

Generator Not Fully Documented

CPAL0202881 Threaded Connection for MV-CC189 (P-52B

Discharge Drain) Found Loose During RTS for P-

2B

CPAL0202867 Gaskets Found on P-52B Rotating Element Not

on Design Document

CPAL0202868 P-52B Rotating Element Assembled Incorrectly

CAP030858 Data Rounding and Editorial Changes Associated

With TSSP QO-15

1R22 Surveillance Testing

Completed Technical Specification Surveillance Tests

QO-14 Technical Specification Surveillance Procedure - Revision 18

Inservice Test - Service Water Pumps, completed

July 1, 2002 for Service Water Pump P-7B

QO-14 Technical Specification Surveillance Procedure Revision 12

Basis Document - Inservice Test - Service Water

Pumps

QE-35 Technical Specification Surveillance Test - ED-01 Revision 5

and ED-02 Battery Checks - Quarterly,

Completed July 23, 2002

QE-35 Technical Specification Surveillance Test Basis Revision 3

ED-01 and ED-02 Battery Checks - Quarterly,

Completed July 23, 2002

RO-52 Fire Suppression Water System Functional Test Revision 20

and Fire Pump Capacity Test - Completed

September 13, 2002

RO-52 Fire Suppression Water System Functional Test Revision 20

and Fire Pump Capacity Test - Completed

October 26, 2001 for Fire Pump P-9B

RO-52 Fire Suppression Water System Functional Test Revision 20

and Fire Pump Capacity Test - Completed

November 29, 2001 for Fire Pump P-41

RO-52 Fire Suppression Water System Functional Test Revision 19

and Fire Pump Capacity Test - Completed July

20, 2001

RI-38 Technical Specification Surveillance and Special Revision 12

Test - Safety Injection Refueling Water Tank

Level Instrument Calibration - Completed

September 23, 2002

RPS-I-7 Anticipated Transient Without Scram (ATWS) Revision 3

Calibration / Functional Testing

Miscellaneous Documents

Certificates of Calibration for the following pieces various test dates

Measuring and Testing Equipment : 006907,

003569, and 008303

RO-52 Fire Suppression Water System Functional Test Revision 9

and Fire Pump Capacity Test Basis Document

RI-38 Technical Specification Surveillance and Special Revision 7

Test Basis Document - Safety Injection Refueling

Water Tank Level Instrument Calibration

DBD-2.05 Design Basis Document - Reactor Protective Revision 3

System Safety Injection Signal Anticipated

Transient Without Scram

Condition Reports Reviewed to Assess Problem Identification Characterization

CAP031279 Issues Associated With Execution of RO-52 Fire

Pump Capacity Test

CAP031316 Relief Valve Setting Procedural Discrepancies

Noted in Test RO-52 Rev. 20

CAP031328 Potential Technical Specification Surveillance

Procedure RO-52 Frequency Reduction

Opportunity

CAP031329 Technical Specification Procedure RO-52

Inadequacies

1R23 Temporary Plant Modifications

Plant Procedures

AP-9.31 Temporary Modification Control Revision 19

Temporary Modification Packages

TM-2000-006 Isolate Auxiliary Feedwater Pump Turbine Steam

Supply from Pressure Control Valve CV-0522A

TM-99-032 Reactor Head Temperature Research Project

Condition Reports Reviewed To Assess Problem Identification Characterization

CAP031113 Temporary Modification TM 2000-06 Tag #5 Not

Hanging in the Plant

1E06 Emergency Plan Drill Evaluation

Plant Procedures

EI-3 Communications and Notifications Revision 19

EI-1 Emergency Classification and Actions Revision 40

2OS1 Access Control to Radiologically Significant Areas

Dose Reduction Action Plan August 19, 2002

RWP 2002-0517 T-100 Spent Resin Storage Tank Revision 1

Maintenance

RWP 2002-0517 RWP Scope Addition Form, T-100 Spent Revision 0

Resin Storage Tank Maintenance

AP Procedure No. 7.03 Radiation Work Permit Revision 15

2OS2 As-Low-As-Is-Reasonably-Achievable (ALARA) Planning and Controls

RWP 2001-1035 ALARA Post-Job Review, Reinstall September 17, 2002

Seismic Restraints on the Control Rod

Drive Upper Housings

RWP 2001-1034 ALARA Post-Job Review, Reinstall Control September 19, 2002

Rod Drive Upper Housings

Refueling Outage 2001 ALARA Report Revision 1

Dose Reduction Action Plan August 19, 2002

Palisades Nuclear Plant Self-Assessment

Report, Hot Spot Program 11.28.01 -

2.12/01

AP Procedure No. 7.17 Hot Spot Program Revision 2

AP Procedure No. 7.02 ALARA Program Revision 11

3PPI Physical Protection - Access Authorization (AA) Program

NGA01FO001H NMC Plant Access Training May 31, 2002

FP-S-AA-001 Access Authorization Revision 4

Program - CBOP

FFD-01 FFD Requirements and Revision 13

Responsibilities

AA/FFD - Condition Reports January - August 2002

(13)

2-002-8-043 FFD/AA - Nuclear Oversight July 9, 2002

Observation Report

Westinghouse Access January 18, 202

Programs Fitness-For-Duty

Program

Condition Reports - Security January - July 2002

Related

3PP2 Physical Protection - Access Control

SIP-18 Security Systems and August 17, 2001

Equipment Testing

SIP-4 Personnel Access April 29, 2002

SIP-5 Search Procedures and August 3, 2001

Property Removal

Requirements

SIP-7 Photo Badging July 27, 2001

SIP-16 Locks, Keys, and Photo July 21, 2000

Badge Control

Palisades Safeguards Event January - July 2002

Log

Condition Reports - Security January - July 2002

Related

PAP-10.24 NMC Access Authorization

Program

Vehicle Search Detection January - July 2002

Drill - 23

Access Search Detection Drill January - July 2002

- 28

4OA1 Performance Indicator Verification - Physical Protection

3.09 Data Collection, Review and Revision 5, April 11, 2002

Reporting for NRC

Performance Indicator

Program - Physical Protection

Program

Performance Indicator Log - January - July 2002

Physical Protection

Safeguards Event Logs January - July 2002

Performance Indicator Verification - Safety System Unavailability

AFW Unavailability Data Reported To NRC from

3rd Quarter 2000 thru 2nd Quarter 2002

Control Room Log Entry Reports 3rd Quarter

2000, and 1st and 2nd Quarter 2002

RHR Unavailability Data Reported To NRC from

2rd Quarter 2001 thru 2nd Quarter 2002

RHR System Engineers Compilation of

Unavailability Data from 2rd Quarter 2001 thru 2nd

Quarter 2002

NEI 99-02 Regulatory Assessment Performance Indicator Revisions 0, 1 and 2

Guideline

Plant Procedures

RO-127 Auxiliary Feedwater System 18 Month Test

QO-21 Inservice Test Procedure - Auxiliary Feedwater

Pumps

Work Orders

24014930 P-8A Perform Alignment of Pump P-8A to Motor

EMA-1104

24914012 P-8B Packing Failed, Replace Outboard Packing

and Shaft O-Ring

24014258 P-8C, Pump Coupling Inspection/Lube PM

Condition Reports Reviewed To Assess Corrective Actions

CPAL0202435 Adverse Trend In INPO Indicator for Auxiliary

Feedwater

Condition Reports Reviewed To Assess Appropriate Characterization

CAP031443 Errors Identified in the Maintenance Rule

Performance Indicator for Containment Spray

Pump P-54C

CAP031475 NRC Performance Indicator Data for RHR

System

Performance Indicator Verification - Radiation Safety and RCS Activity

NRC Occupational Exposure Control April 13, 2001,

Effectiveness Reports (Action Request July 10, 2001,

Reviews) July 15, 2001,

September 28, 2001,

October 31, 2001,

December 4, 2001,

December 31, 2001,

January 22, 2002,

February 1, 2002,

February 28, 2002,

March 28, 2002,

April 30, 2002,

May 30, 2002,

July 1, 2002

Palisades 2001 Annual Radioactive March 2002

Effluent Release and Waste Disposal

Report

1st and 2nd Quarter Offsite Dose Reports August 2002

CPAL0200359 Failure of Workers ED to Record Dose in January 24. 2002

High Radiation Area

CPAL0200441 Door Handle to VCT Door, a Locked High January 31, 2002

Radiation Area Was Loose

CPAL0201659 Unintentional and Nonmalevalent Exit April 26, 2002

From Vital Area

CPAL0201685 Individual Received Entry Level Dose April 29, 2002

Alarm

CPAL0201972 Telemetric Dosimeter Did Not Function May 19, 2002

Properly

CPAL0202506 Electronic Dosimeter Entry Dose Limit July 2, 2002

Alarm (EDL) Set Point Exceeded

4OA2 Identification and Resolution of Problems

Condition Reports Reviewed to Assess Corrective Actions

CPAL0101862 Incorrect Wire Lifted in SPS-E-12 Resulted in

Current Transformer Circuit Being Open Circuited

CPAL0201832 Service Water System Filter F-1005 Plugged Up

with Sand and associated corrective action

documents

Miscellaneous Documents

EOP - 1.0 Emergency Operating Procedure - Standard Revision 12

Post Trip Actions

EOP - 9.0, MVAE- Functional Recovery Procedure - Maintenance of Revision 14

AC-1 Vital AC Power -Offsite Power

EOP - 9.0, MVAE- Functional Recovery Procedure - Maintenance of Revision 14

AC-2 Vital AC Power -Diesel Generators

ONP - 6.1 Off Normal Procedure - Loss of Service Water Revision 10

46