MONTHYEARML24228A1952024-08-20020 August 2024 Restart Inspection Plan ML24058A4852024-02-28028 February 2024 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000255/20210062022-03-0202 March 2022 Annual Assessment Letter for Palisades Nuclear Plant, Unit 1, (Report 05000255/2021006) ML21327A2962021-11-23023 November 2021 Information Request for NRC Triennial Evaluations of Changes, Tests, and Experiments (50.59) Baseline Inspection; Inspection Report 05000255/2022010 ML21278A4442021-10-0505 October 2021 Notification of NRC Fire Protection Team Inspection Request for Information Inspection Report 05000255/2021010 ML21274A4172021-10-0505 October 2021 Request for Information for an NRC Triennial Heat Exchanger/Sink Performance Inspection and Request for Information Inspection Report 05000255/2021004 IR 05000255/20210052021-09-0101 September 2021 Updated Inspection Plan for Palisades Nuclear Plant (Report 05000255/2021005) IR 05000255/20200062021-03-0404 March 2021 Annual Assessment Letter for Palisades Nuclear Plant (Report 05000255/2020006) IR 05000255/20200052020-09-0101 September 2020 Updated Inspection Plan for Palisades Nuclear Plant (Report 05000255/2020005) ML20205L6282020-07-23023 July 2020 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000255/2020003 ML20133K0562020-05-14014 May 2020 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML20127H8712020-05-0606 May 2020 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Palisades Nuclear Plant IR 05000255/20190062020-03-0303 March 2020 Annual Assessment Letter Palisades Nuclear Plant (Report 05000255/2019006) IR 05000255/20190052019-08-28028 August 2019 Updated Inspection Plan for Palisades Nuclear Plant, Unit 1 (Report 05000255/2019005) ML19227A0652019-08-14014 August 2019 Inspection Plan for Palisades Nuclear Plant for Design Bases Assurance Inspection (Programs); Inspection Report 05000255/2019010 (DRS-N.FelizAdorno) IR 05000255/20180062019-03-0404 March 2019 Annual Assessment Letter for Palisades Nuclear Plant (Report 05000255/2018006) ML19056A1132019-02-25025 February 2019 Request for Information Design Bases Assurance Inspection (Program); NRC Inspection Report 05000255/2019010 (DRS-N. Feliz-Adorno) IR 05000255/20180052018-08-28028 August 2018 Updated Inspection Plan for Palisades (Report 05000255/2018005) IR 05000255/20170062018-03-0202 March 2018 Annual Assessment Letter for Palisades Nuclear Plant (Report 05000255/2017006) ML18047A7112018-02-16016 February 2018 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information (DRS-R.Baker) ML17304A4822017-10-31031 October 2017 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Palisades IR 05000255/20170052017-08-28028 August 2017 Updated Inspection Plan (Report 05000255/2017005) IR 05000255/20160062017-03-0101 March 2017 Annual Assessment Letter for Palisades Nuclear Plant (Report 05000255/2016006) IR 05000255/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Palisades Nuclear Plant (Report 05000255/2016005) ML16174A4132016-06-22022 June 2016 Information Request to Support Upcoming Temporary Instruction 191 Inspection at Palisades Nuclear Plant ML16125A5332016-05-0303 May 2016 Ltr. 05/03/16 Palisades Nuclear Plant - Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection (Mxg) IR 05000255/20150062016-03-0202 March 2016 Annual Assessment Letter for Palisades Nuclear Plant (Inspection Report 05000255/2015006) ML16057A1212016-02-25025 February 2016 Ltr. 02/25/16 Palisades Nuclear Plant - Information Request for and NRC Triennial Permanent Modifications and 10 CFR 50.59 (MOD/50.59) Baseline Inspection 05000255/2016007 ML16019A4602016-01-19019 January 2016 Information Request to Support Upcoming Problem Identification and Resolution Inspection at the Palisades Nuclear Plant IR 05000255/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Palisades Nuclear Plant (Report 05000255/2015005) ML15240A3442015-08-28028 August 2015 Ltr. 08/28/15 Palisades Nuclear Plant - Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information Inspection Report 05000255/2015004 (Axd) ML15211A5242015-07-30030 July 2015 Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000255/20154032015-06-18018 June 2015 Information Request for Temporary Instruction 2201/004 Inspection, Notification to Perform Inspecting of Implementation of Interim Cyber Security Milestones 1-7, 05000255/2015403 ML15124A9272015-05-0101 May 2015 Ltr. 05/01/15 Palisades Nuclear Plant - Notification of NRC Inspection and Request for Information (Msh) IR 05000255/20140012015-03-0404 March 2015 Annual Assessment Letter for Palisades Nuclear Plant (Report 05000255/2014001) ML15013A4812015-01-12012 January 2015 15 Palisades Fire Protection Request for Information ML14245A2982014-09-0202 September 2014 Mid-Cycle Assessment Letter for Palisades Nuclear Plant ML14063A2762014-03-0404 March 2014 Annual Assessment Letter for Palisades Nuclear Plant (Report 05000255/3013001) IR 05000255/20301302014-03-0404 March 2014 Annual Assessment Letter for Palisades Nuclear Plant (Report 05000255/3013001) ML13337A6552013-12-0303 December 2013 Ltr 12/3/13 Palisades Fire Protection Request for Information ML13246A2482013-09-0303 September 2013 2013 Palisades Nuclear Plant 2013 Mid-Cycle Letter Combined IR 05000255/20120012013-03-0404 March 2013 Annual Assessment Letter for Palisades Nuclear Plant (IR 05000255-12-001) ML12248A3182012-09-0404 September 2012 Mid-Cycle Assessment Letter for Palisades Nuclear Plant IR 05000255/20110072012-03-0505 March 2012 Annual Assessment Letter for Palisades Nuclear Plant (Report 05000255/2011007) IR 05000255/20110062011-09-0101 September 2011 Mid-Cycle Letter for Palisades Nuclear Plant, 05000255-11-006 ML1106206252011-03-0404 March 2011 EOC Annual Assessment Letter and Inspection/Security Plan ML1024402002010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan - Palisades Nuclear Power Plant ML1006102742010-03-0303 March 2010 EOC Annual Assessment Letter, Inspection/Activity Plan ML0924403762009-09-0101 September 2009 Palisades - Mid-Cycle Performance Review and Inspection Plan IR 05000255/20090012009-03-0404 March 2009 Annual Assessment Letter - Palisades Nuclear Plant (5000255/2009001) 2024-08-20
[Table view] Category:Letter
MONTHYEARML24312A2262024-11-0606 November 2024 Letter from C. Nelson, Michigan SHPO Regarding Palisades Nuclear Plant Architectural Survey ML24292A1572024-11-0505 November 2024 Ape Notification to Burt Lake Band Palisades ML24310A0142024-11-0505 November 2024 Ape Notification to Mackinac Bands of Chippewa Palisades ML24310A0132024-11-0505 November 2024 Ape Notification to Grand River Bands of Ottawa Indians Palisades ML24309A2032024-11-0404 November 2024 Ape Notification to Ottawa Tribe of Oklahoma Palisades ML24309A1972024-11-0404 November 2024 Ape Notification to Little Traverse Bay Bands of Odawa Indians Palisades ML24309A1982024-11-0404 November 2024 Ape Notification to Match E Be Nash She Wish Band of Pottawatomi Indians Palisades ML24309A1872024-11-0404 November 2024 Ape Notification to Grand Portage Band of Lake Superior Chippewa Palisades ML24309A2072024-11-0404 November 2024 Ape Notification to Quechan Tribe of the Fort Yuma Indian Reservation Palisades ML24309A1832024-11-0404 November 2024 Ape Notification to Bois Forte Band of the Minnesota Chippewa Tribe Palisades ML24309A2122024-11-0404 November 2024 Ape Notification to Sault Ste. Marie Tribe of Chippewa Indians Palisades ML24309A2042024-11-0404 November 2024 Ape Notification to Pokagon Band of Potawatomi Indians Palisades ML24292A0492024-11-0404 November 2024 Ape Notification to Bad River Band of the Lake Superior Tribe of Chippewa Indians Palisades ML24309A1932024-11-0404 November 2024 Ape Notification to Leech Lake Band of Ojibwe Palisades ML24309A2012024-11-0404 November 2024 Ape Notification to Mille Lacs Band of Ojibwe Palisades ML24309A1922024-11-0404 November 2024 Ape Notification to Lac Vieux Desert Band of Lk Superior Chippewa Indians Palisades ML24309A1892024-11-0404 November 2024 Ape Notification to Hannahville Indian Community Palisades ML24309A2002024-11-0404 November 2024 Ape Notification to Miami Tribe of Oklahoma Palisades ML24309A1952024-11-0404 November 2024 Ape Notification to Little River Band of Ottawa Indians Palisades ML24309A2112024-11-0404 November 2024 Ape Notification to Saint Croix Chippewa Indians of Wisconsin Palisades ML24309A1902024-11-0404 November 2024 Ape Notification to Lac Courte Oreilles Band of Lake Superior Chippewa Palisades ML24309A2022024-11-0404 November 2024 Ape Notification to Nottawaseppi Huron Band of the Potawatomi Palisades ML24309A1852024-11-0404 November 2024 Ape Notification to Citizen Potawatomi Nation Palisades ML24309A2142024-11-0404 November 2024 Ape Notification to White Earth Band of Minnesota Chippewa Tribe Palisades ML24309A2092024-11-0404 November 2024 Ape Notification to Red Lake Band of Chippewa Indians Palisades ML24309A1862024-11-0404 November 2024 Ape Notification to Forest County Potawatomi Community Palisades ML24309A1822024-11-0404 November 2024 Ape Notification to Bay Mills Indian Community Palisades ML24309A2052024-11-0404 November 2024 Ape Notification to Prairie Band Potawatomi Nation Palisades ML24309A2102024-11-0404 November 2024 Ape Notification to Saginaw Chippewa Indian Tribe of Michigan Palisades ML24309A2082024-11-0404 November 2024 Ape Notification to Red Cliff Band of Lake Superior Chippewa Indians Palisades ML24309A1992024-11-0404 November 2024 Ape Notification to Menominee Indian Tribe of Wisconsin Palisades ML24292A0072024-11-0404 November 2024 Ape Notification to Achp Palisades ML24309A1882024-11-0404 November 2024 Ape Notification to Grand Traverse Band of Ottawa and Chippewa Indians Palisades ML24309A1842024-11-0404 November 2024 Ape Notification to Chippewa Cree Indians of the Rocky Boys Reservation of Montana Palisades ML24309A1912024-11-0404 November 2024 Ape Notification to Lac Du Flambeau Band of Lake Superior Chippewa Indians Palisades ML24309A2132024-11-0404 November 2024 Ape Notification to Turtle Mountain Band of Chippewa Indians Palisades ML24309A2062024-11-0404 November 2024 Ape Notification to Prairie Island Indian Community Palisades PNP 2024-014, Request for USNRC to Rescind Approved Exemption Requests for 140.11(a)(4) and 50.54(w)(1), Reduction of Insurances2024-10-0909 October 2024 Request for USNRC to Rescind Approved Exemption Requests for 140.11(a)(4) and 50.54(w)(1), Reduction of Insurances PNP 2024-037, Response to Requests for Additional Information Regarding the Proposed Reauthorization of Power Operations Under Renewed Facility Operating License Number DPR-0202024-10-0404 October 2024 Response to Requests for Additional Information Regarding the Proposed Reauthorization of Power Operations Under Renewed Facility Operating License Number DPR-020 ML24267A2962024-10-0101 October 2024 Summary of Conference Call Regarding Steam Generator Tube Inspections ML24263A1712024-09-20020 September 2024 Environmental Request for Additional Information ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24219A4202024-09-12012 September 2024 Change in Estimated Hours and Review Schedule for Licensing Actions Submitted to Support Resumption of Power Operations (Epids L-2023-LLE-0025, L-2023-LLM-0005, L-2023-LLA-0174, L-2024-LLA-0013, L-2024-LLA-0060, L-2024-LLA-0071) IR 05000255/20244022024-09-0606 September 2024 Public: Palisades Nuclear Plant - Decommissioning Security Inspection Report 05000255/2024402 PNP 2024-029, Notice of Payroll Transition at Palisades Nuclear Plant2024-08-15015 August 2024 Notice of Payroll Transition at Palisades Nuclear Plant IR 05000255/20240022024-08-0909 August 2024 NRC Inspection Report No. 05000255/2024002 PNP 2024-030, Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 02024-08-0202 August 2024 Update Report for Holtec Decommissioning International Fleet Decommissioning Quality Assurance Program Rev. 3 and Palisades Transitioning Quality Assurance Plan, Rev 0 PNP 2024-032, Supplement to License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations2024-07-31031 July 2024 Supplement to License Amendment Request to Revise Selected Permanently Defueled Technical Specifications Administrative Controls to Support Resumption of Power Operations ML24206A0572024-07-25025 July 2024 PRM-50-125 - Letter to Alan Blind; Docketing of Petition for Rulemaking and Sufficiency Review Status (10 CFR Part 50) PNP 2024-033, Response to Request for Additional Information - License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations2024-07-24024 July 2024 Response to Request for Additional Information - License Amendment Request to Revise the Palisades Nuclear Plant Site Emergency Plan to Support Resumption of Power Operations 2024-09-06
[Table view] |
Text
UNITED STATES rch 4, 2009
SUBJECT:
ANNUAL ASSESSMENT LETTER - PALISADES NUCLEAR PLANT (5000255/2009001)
Dear Mr. Schwarz:
On February 10, 2009, the NRC staff completed its performance review of Palisades Nuclear Plant. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from January 1 through December 31, 2008. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information. A separate letter designated and marked as "Official Use Only - Security Information" will include the security cornerstone review and resultant inspection plan.
Overall, Palisades Nuclear Plant operated in a manner that preserved public health and safety and fully met all cornerstone objectives. Plant performance for the most recent quarter at Palisades was within the Regulatory Response column of the NRCs Action Matrix based on one inspection finding in the Occupational Radiation Safety cornerstone being classified as having low to moderate safety significance (White). This White finding, from the fourth quarter of 2008, involved failure to recognize and assess the impact of radiological hazards in the work place. Therefore, we plan to conduct a supplemental inspection (95001) in addition to reactor oversight process (ROP) baseline inspections at your facility. Please notify us of your readiness to conduct the supplemental inspection.
In our end-of-cycle assessment letter dated March 3, 2008, and mid-cycle assessment letter dated September 2, 2008, we advised you of a substantive cross-cutting issue in the area of Human Performance (HP) with a cross-cutting theme in the aspect of error prevention techniques (H.4(a)). You have instituted actions to improve performance in this area. Based on your performance, we have gained confidence in your use of error prevention techniques during this assessment period. The theme of error prevention techniques is considered closed. However, the NRC has identified a new substantive cross-cutting theme of documentation/procedures (H.2(c)) in the area of HP. During this assessment period, there were 17 findings documented with cross-cutting aspects in the HP area. Six of the findings shared a common cross-cutting aspect of H.2(c). In addition, these findings were from four different cornerstones. Therefore, a new substantive cross-cutting theme in the aspect of H.2(c) will be opened and the substantive cross-cutting issue will be open until the NRC gains confidence in your efforts and progress in addressing this aspect of human performance.
The enclosed inspection plan details the inspections, less those related to security, scheduled through June 30, 2010. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite.
Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the mid-cycle review.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact John (Jack) Giessner at 630-829-9619 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Cynthia D. Pederson, Director Division of Reactor Projects Docket No. 50-255;72-007 License No. DPR-20 DISTRIBUTION:
See next page
Letter to from C. Pederson dated March 4, 2009 SUBJECT: ANNUAL ASSESSMENT LETTER - PALISADES NUCLEAR PLANT (5000255/2009001)
cc w/encl: Senior Vice President Vice President Oversight Senior Manager, Nuclear Safety & Licensing Senior Vice President and COO Assistant General Counsel Manager, Licensing W. DiProfio W. Russell G. Randolph Supervisor, Covert Township Office of the Governor T. Strong, Chief, State Liaison Officer Michigan Department of Environmental Quality Michigan Office of the Attorney General Mayor of Bangor City Manager of Bangor Mayor of Hartford City Manager of Hartford Mayor of South Haven City Manager of South Haven Administrator, Allegan County Allegan County Sheriff Allegan County Emergency Management Coordinator County Coordinator Berrien County Sheriff Director, Berrien County Emergency Management Agency Chairman, Van Buren County Board Van Buren County Sheriff Director, Van Buren County Emergency Management Agency Mayor of Watervliet Mayor of Coloma G. Mortensen, INPO
Palisades Inspection / Activity Plan 03/01/2009 - 06/30/2010 Planned Dates No. of Staff Start End Inspection Activity Title on Site BI ENG - INSERVICE INSPECTION & TI-172 REVISION 1 1 3/23/2009 04/17/2009 IP 2515/172 Reactor Coolant System Dissimiliar Metal Butt Welds 3/23/2009 04/17/2009 IP 7111108P Inservice Inspection Activities - PWR BI RP - RADIATION PROTECTION BASELINE INSPECTION 2 3/30/2009 04/03/2009 IP 7112101 Access Control to Radiologically Significant Areas 3/30/2009 04/03/2009 IP 7112102 ALARA Planning and Controls FY 09 - PALISADES INIT PREP 05/09 3 5/04/2009 05/08/2009 W90208 OL - INITIAL EXAM - MAY/JUNE 2009 - PALI FY 09 - PALISADES INIT EXAM 05/09 3 5/25/2009 06/05/2009 W90208 OL - INITIAL EXAM - MAY/JUNE 2009 - PALI BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 6/15/2009 06/19/2009 IP 7112101 Access Control to Radiologically Significant Areas 6/15/2009 06/19/2009 IP 7112102 ALARA Planning and Controls BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 8/24/2009 08/28/2009 IP 7112103 Radiation Monitoring Instrumentation and Protective Equipment 8/24/2009 08/28/2009 IP 71151-BI01 Reactor Coolant System Activity 8/24/2009 08/28/2009 IP 71151-OR01 Occupational Exposure Control Effectiveness 8/24/2009 08/28/2009 IP 71151-PR01 RETS/ODCM Radiological Effluent BI EP - EP ROUTINE INSPECTION / PI VERIFICATION 1 0/19/2009 10/23/2009 IP 2515/175 Emergency Response Organization, Drill/Exercise Performance Indicator, Program Review 0/19/2009 10/23/2009 IP 7111402 Alert and Notification System Testing 0/19/2009 10/23/2009 IP 7111403 Emergency Response Organization Augmentation Testing 0/19/2009 10/23/2009 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies 0/19/2009 10/23/2009 IP 71151-EP01 Drill/Exercise Performance 0/19/2009 10/23/2009 IP 71151-EP02 ERO Drill Participation 0/19/2009 10/23/2009 IP 71151-EP03 Alert & Notification System BI ENG - ENGINEERING MODIFICATIONS / 50.59 INSP. 3 1/02/2009 11/20/2009 IP 7111117T Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 2/14/2009 12/18/2009 IP 2515/173 Review of the Implementation of the Industry Ground Water Protection Voluntary Initiative 2/14/2009 12/18/2009 IP 7112201 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems PI&R - BIENNIAL PROBLEM IDENTIFICATION AND RESO 4 1/11/2010 01/29/2010 IP 71152B Identification and Resolution of Problems BI OL - LIC. OPERATOR REQUAL. PROGRAM EVALUATION 2 2/08/2010 02/12/2010 IP 7111111B Licensed Operator Requalification Program
Palisades Inspection / Activity Plan 03/01/2009 - 06/30/2010 Planned Dates No. of Staff Start End Inspection Activity Title on Site BI EP - EP EXERCISE INSPECTION/PI VERIFICATION 4 03/01/2010 03/05/2010 IP 7111401 Exercise Evaluation 03/01/2010 03/05/2010 IP 71151-EP01 Drill/Exercise Performance 03/01/2010 03/05/2010 IP 71151-EP02 ERO Drill Participation 03/01/2010 03/05/2010 IP 71151-EP03 Alert & Notification System BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 03/08/2010 03/12/2010 IP 7112202 Radioactive Material Processing and Transportation BI ENG - TRIENNIAL FIRE PROTECTION INSPECTION 3 03/29/2010 04/16/2010 IP 7111105T Fire Protection [Triennial]
RI ENG - TRIENNIAL FIRE INS INFOR GATHERING TRIP 3 03/15/2010 03/19/2010 IP 7111105T Fire Protection [Triennial]
BI ENG - TRIENNIAL HEAT SINK INSPECTION 1 05/24/2010 05/28/2010 IP 7111107T Heat Sink Performance BI RP - RADIATION PROTECTION BASELINE INSPECTION 1 05/24/2010 05/28/2010 IP 7112203 Radiological Environmental Monitoring Program (REMP) And Radioactive Material Control Program However, the NRC has identified a new substantive cross-cutting theme of documentation/procedures (H.2(c)) in the area of HP. During this assessment period, there were 17 findings documented with cross-cutting aspects in the HP area. Six of the findings shared a common cross-cutting aspect of H.2(c). In addition, these findings were from four different cornerstones. Therefore, a new substantive cross-cutting theme in the aspect of H.2(c) will be opened and the substantive cross-cutting issue will be open until the NRC gains confidence in your efforts and progress in addressing this aspect of human performance.
The enclosed inspection plan details the inspections, less those related to security, scheduled through June 30, 2010. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite.
Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the mid-cycle review.
In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change this inspection plan, we will contact you to discuss the change as soon as possible. Please contact John (Jack) Giessner at 630-829-9619 with any questions you may have regarding this letter or the inspection plan.
Sincerely, Cynthia D. Pederson, Director Division of Reactor Projects Docket No. 50-255;72-007 License No. DPR-20 DISTRIBUTION:
See next page DOCUMENT NAME: G:\BRANCH TSS\ALL EOC\EOC CY 2008\EOC LETTERS\PALISADES 2008 EOC LETTER.DOC G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII NAME RLerch:mb:dtp JGiessner CPederson
- RML for DATE 02/27/09 02/27/09 02/26/09 OFFICIAL RECORD COPY