IR 05000255/2021003

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000255/2021003
ML21305A943
Person / Time
Site: Palisades Entergy icon.png
Issue date: 11/03/2021
From: Billy Dickson
NRC/RGN-III/DRP/B2
To: Corbin D
Entergy Nuclear Operations
References
IR 2021003
Download: ML21305A943 (21)


Text

SUBJECT:

PALISADES NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000255/2021003

Dear Mr. Corbin:

On September 30, 2021, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Palisades Nuclear Plant. On October 21, 2021, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding did not involve a violation of NRC requirements.

If you disagree with a finding not associated with a regulatory requirement in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Palisades Nuclear Plant.

November 3, 2021 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Billy C. Dickson, Jr., Chief Branch 2 Division of Reactor Projects Docket No. 05000255 License No. DPR-20

Enclosure:

As stated

Inspection Report

Docket Number:

05000255

License Number:

DPR-20

Report Number:

05000255/2021003

Enterprise Identifier:

I-2021-003-0102

Licensee:

Entergy Nuclear Operations, Inc.

Facility:

Palisades Nuclear Plant

Location:

Covert, MI

Inspection Dates:

July 01, 2021 to September 30, 2021

Inspectors:

G. Hansen, Senior Emergency Preparedness Inspector

P. Laflamme, Senior Resident Inspector

C. St. Peters, Resident Inspector

Approved By:

Billy C. Dickson, Jr., Chief

Branch 2

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Palisades Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Properly Classify Steam Dump Control Relay Caused Atmospheric Dump Valves to be Rendered Inoperable Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green FIN 05000255/2021003-01 Open/Closed None (NPP)71153 A finding of green significance was self-revealed on June 16, 2021, for the licensee's failure to properly classify the steam dump control relay (SDCR). Specifically, the licensee did not classify the SDCR in 2005 in accordance with fleet procedure FP-E-SE-02 "Component Classification," and as a result, the SDCR exceeded the vendor recommended service life without an evaluation. This led to the SDCR's failure, which rendered the atmospheric dump valves (ADVs) inoperable.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000255/2021-001-00 LER 2021-001-00 for Palisades Nuclear Plant,

Atmospheric Steam Dump Valves Inoperable Due to Relay Failure 71153 Closed

PLANT STATUS

The plant began the inspection period at rated thermal power. On July 28, 2021, the plant was down powered to 23 percent for condensate pump maintenance. The plant was returned to full power on July 31, 2021. On August 10, 2021, the plant was down powered to 88 percent for heater drain pump discharge header maintenance. The plant was returned to full power on August 11, 2021 and remained at or near full power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident and regional inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week, increasing the amount of time on-site as local COVID-19 conditions permitted.

As part of their on-site activities, resident inspectors conducted plant status activities as described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP

===71152, Problem Identification and Resolution, observed risk significant activities; and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01)===

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Right train component cooling water on July 26, 2021 (2)1-1 Emergency Diesel Generator (EDG) starting air system on September 7, 2021
(3) Service water screen system on September 23, 2021

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the left train containment spray system on August 23, 2021.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Area 4: 1C 2.4kV switchgear room on July 14, 2021
(2) Fire Area 16: Component cooling pump room, elevation 590' on July 20, 2021
(3) Fire Area 13B: Charging pump room on July 27, 2021
(4) Fire Area 12: 12 Battery Room; elevation 607' on September 21, 2021

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated PLSEG-OPS-21C-02 Multi-Department Event and PLSEG-LOR-21C-07 Secondary Malfunctions on August 12, 2021.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Chemical volume and control system on September 23, 2021

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Fire protection system on July 1, 2021

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Emergent work activities associated with water intrusion into 2B, condensate pump, motor thrust bearing, and subsequent power reduction for repair on July 28, 2021
(2) Emergent work activities associated with P-10A, heater drain pump discharge header inspection, and subsequent power reduction for repair on August 10, 2021
(3) Emergent work activities associated with the 1-2 EDG #7L cylinder sleeve replacement on August 17, 2021

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Safety injection (SI) suction piping flange evaluation on July 21, 2021
(2) Pressurizer vapor phase sample line evaluation on July 27, 2021
(3) EDG 1-1 governor evaluation on August 2, 2021
(4) Volume control system evaluation on September 3, 2021
(5) CV-0826 valve performance evaluation on September 13, 2021

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) Charging pump P-55A packing and O-ring replacement and testing on July 19, 2021
(2) Hydrogen monitoring system maintenance and testing on July 26, 2021 (3)2B condensate pump oil cooler replacement and testing on July 29, 2021 (4)1-2 EDG cylinder 7L sleeve replacement and testing on August 23, 2021
(5) P-10A heater drain pump maintenance and testing on August 11, 2021 (6)1-1 EDG Governor replacement and testing on August 30, 2021

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) QO-16 P-54B; Containment Spray Pump Test on August 4, 2021
(2) QO-21B; P-8B Steam Driven AFW Pump Test on August 10, 2021
(3) QO-5; Service Water Valve Stroke Test on August 24, 2021
(4) QO-20B; P-67B Inservice Inspection Low Pressure Safety Injection Test, on September 7, 2021

Inservice Testing (IP Section 03.01) (1 Sample)

(1) QO-19A; P-66A High Pressure Safety Injection (HPSI) Surveillance, on July 7, 2021

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the following maintenance and testing of the alert and notification system:

Annual siren inspection and maintenance records for the period from August 2019 to August 2021

Monthly alert notification system (siren) tests for the period from August 2019 to August 2021

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the Emergency Preparedness Organization

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.01) (1 Sample)

The inspectors evaluated:

(1) An emergency preparedness (EP) drill on September 22,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS07: High Pressure Injection Systems (IP Section 02.06)===

(1) July 1, 2020 through June 30, 2021

MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)

(1) July 1, 2020 through June 30, 2021

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1) July 1, 2020 through June 30, 2021

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) July 01, 2020 through June 30, 2021 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) July 01, 2020 through June 30, 2021 EP03: Alert and Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
(1) July 01, 2020 through June 30, 2021

71152 - Problem Identification and Resolution

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Safety injection and refueling water tank roof inspection evaluation on September 27, 2021

71153 - Follow-up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000255/2021-001-00, Atmospheric Steam Dump Valves Inoperable Due to Relay Failure (ADAMS Accession No. ML21226A001). The inspection conclusions associated with this LER are documented in the Inspection Results Section of this report.

INSPECTION RESULTS

Observation: SIRW Tank Roof Inspection Evaluation 71152 The inspectors reviewed the associated causal evaluation, failure mode analysis, culpability model, performance analysis, and corrective actions associated with the SIRW tank roof inspections, water collection, and subsequent chemistry samples performed on June 17, 2021. The inspectors selected this issue to review because the initial chemistry results did not match the expected results. Specifically, one of the initial isotopes identified during the filtration sample analysis was CO-58, a short-lived isotope not expected to be found on the SIRW roof. The inspectors noted that the licensee immediately performed an additional review and subsequent analysis to validate the initial results. In response, the licensee investigated the original test methodology and discovered that a chemistry technician used a contaminated filtration apparatus typically used for primary coolant analysis during the sample preparation to analyze the original sample resulting in contaminating the sample with CO-58. In their review, the inspectors inspected the SIRW tank roof area and interviewed chemistry personnel. The inspectors collaborated with a regional inspector with a background in chemistry who reviewed the spectrum chemistry analysis and associated white paper. A review of the spectrum analysis from the water sample obtained on the SIRW tank roof and samples utilizing the same filtration rig, like the one used for the analysis of the roof water indicated that the water found on the SIRW tank roof did not originate from the SIRW tank. For corrective actions, the licensee generated several condition reports. These condition reports, including efforts to enhance field presence by supervisors, managers, and quality assurance personal, along with a read and sign document specifying that filtration of non-routine samples is not permitted per EN-CY-110, Chemistry Gamma Spectroscopy System Operation.

Failure to Properly Classify Steam Dump Control Relay Caused Atmospheric Dump Valves to be Rendered Inoperable Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green FIN 05000255/2021003-01 Open/Closed None (NPP)71153 A finding of green significance was self-revealed on June 16, 2021, for the licensee's failure to properly classify the steam dump control relay (SDCR). Specifically, the licensee did not classify the SDCR in 2005 in accordance with fleet procedure FP-E-SE-02 "Component Classification," and as a result, the SDCR exceeded the vendor recommended service life without an evaluation. This led to the SDCR's failure, which rendered the atmospheric dump valves (ADVs) inoperable.

Description:

In 2005, the licensee performed a classification verification of all systems, structures, and components (SSCs) using external resources. During this effort, the SDCR, a non-safety related relay, was not properly classified in accordance with fleet procedure FP-E-SE-02, "Component Classification" Rev. 0, Section 5.1.5, "Determine Duty Cycle and Service Condition" step 2, which says "Duty Cycle - There are two primary choices for Duty Cycle:

high or low. The selected duty cycle will be applied to each component and the result recorded in the spreadsheet/ database. The primary question is: Does the component operate continuously or cycle repeatedly? It is considered 'high' if 'yes'. The SDCR was classified as critical, low duty cycle, mid service condition (CLM) instead of critical, high duty cycle, mid service condition (CHM). The SDCR duty cycle should have been "HIGH" due to the normally energized state of the relay. A high duty cycle classification of the relay would have resulted in a replacement PM interval of 18 years. During the same time frame of 2005, the site documented in condition report CR-PLP-2005-00222 that the SDCR relay was subject to the same failure mode documented in NRC Bulletin No. 84-02 but was never replaced with a new relay. This was due to the model number being confused with a non-HFA relay. CR-PLP-2005-00222 recommended replacing the SDCR relay with a newer Century Series coil design relay and directed adding the replacement to the scope of CR-PLP-2004-02235-CA-4. There were no changes made to the evaluation scope of CR-PLP-2004-02235-CA-4, and the relay was never replaced. In 2018, a fleet-wide effort to review all critical components was performed by Rolls Royce, and the SDCR was included in the review, but no changes to the classification were suggested.

On June 16, 2021, with the reactor at full power, the SDCR failed, causing the four ADVs to be rendered inoperable (as reported in LER 05000255/2021-001-00, Atmospheric Steam Dump Valves Inoperable Due to Relay Failure (ADAMS Accession No. ML21226A001)). The Control Room staff smelled an acrid odor and, upon investigating, found the SDCR showing signs of overheating. Control logic power was lost, which resulted in the site entering a 24-hour shutdown action statement (LCO 3.7.4) for the loss of steam dump control function, and plant risk changed from green to orange. Due to the SDCR overheating, the relay short circuited and caused an overcurrent in the IM13 circuit and fuse FUZ/IM13-1 opening. This resulted in a loss of power to the IM13 scheme. The loss of power disabled the automatic fast-open function of the ADVs and disabled manual operation of ADVs from HIC-0780A (C-01 panel in the Control Room) and from HIC-0780B and HIC-0781B (C-33 panel in the engineered safeguards panel room). An 8-hour non-emergency 10 CFR 50.72(b)(3)(v)(D)report was made to the NRC due to "an event or condition that at the time of discovery could have prevented the fulfillment of the safety function of structures or systems that are needed to mitigate the consequences of an accident."

The site sent the failed relay to United Controls International (UCI) for analysis, and it was confirmed to have failed due to overheating. The licensee performed an apparent cause analysis (ACA). The licensee assessed in the ACA that the direct cause of the SDCR relay was an internal failure of the electrical coil. The failure to correctly classify the SDCR during the preventative maintenance optimization (PMO) effort in 2005 and the failure to address the known relay coil problem for the SDCR in the corrective action program (CAP) in 2005 were also identified as causal factors. The ACA also noted there was evidence that in 1988, the site canceled a project to replace non-safety related HFA relays, such as the SDCR. The licensee reviewed the extent of condition (EOC) to identify if any other HFA relays were potentially impacted in the same manner and criteria, as described previously. One relay was identified, and the site created a work order (WO) to include replacement of the relay, 63X/HIC-0780 (Main Steam Dump Quick Open Relay), per the work order process.

The inspectors responded to the site when the site risk changed from green to orange. The inspectors evaluated the licensee's understanding of the situation, plan to replace the SDCR, and associated compensatory actions. The inspectors determined the licensee failed to properly classify the SDCR duty cycle on more than one occasion.

Corrective Actions: The licensee wrote condition report CR-PLP-2021-1591. An apparent cause analysis was performed which included an EOC to ensure that all HFA relays with outdated coil designs were identified. The site replaced the relay.

Corrective Action References: CR-PLP-2021-1591

Performance Assessment:

Performance Deficiency: The licensee failed to properly classify the SDCR in accordance with FP-E-A-02. Specifically, the licensee failed to follow Section 5.1.5, "Determine Duty Cycle and Service Condition" step 2, which says "Duty Cycle - There are two primary choices for Duty Cycle: high or low. The selected duty cycle will be applied to each component and the result recorded in the spreadsheet/ database. The primary question is: Does the component operate continuously or cycle repeatedly? It is considered 'high' if 'yes'. This led to the SDCR exceeding the vendor recommended service life without an evaluation, subsequent failure, and resultant ADV inoperability.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, the licensee failed to properly classify the SDCR duty cycle. This resulted in the SDCR failing from overheating, causing the ADVs to be rendered inoperable.

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors screened the finding against the Mitigating Systems screening questions in Exhibit 2 and answered "NO" to every question. This resulted in the finding screening to green.

Cross-Cutting Aspect: Not Present Performance. No cross-cutting aspect was assigned to this finding because the inspectors determined the finding did not reflect present licensee performance.

Enforcement:

The inspectors did not identify a violation of regulatory requirements associated with this finding.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On October 21, 2021, the inspectors presented the integrated inspection results to Mr. D. Corbin, Vice President, Operations, and other members of the licensee staff.

On September 2, 2021, the inspectors presented the Emergency Preparedness inspection results to Mr. D. Corbin, Vice President, Operations, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-PLP-2021-

01756

Emergency Diesel Generator (EDG) System Was Not

Walked Down During the 2nd Quarter of 2021 in Accordance

With EN-DC-178

07/01/2021

Corrective Action

Documents

CR-PLP-2021-

01782

Air Leak Coming From a Through Wall Wear Spot on

Copper Tubing That is Between MV-CA198A, Instrument Air

Isolation and MV-CA198, MSIV CV-0501 and CV-0510 NS

Header Vent

07/05/2021

DBD 1.01

Design Basis Document for Component Cooling Water

DBD 1.02

Design Basis Document for Service Water System

Miscellaneous

DBD 2.03

Design Basis Document for Containment Spray

DBD 5.02

Design Basis Document for Emergency Generator and

Generator Protective Systems

SOP-15

Service Water System

SOP-16

Component Cooling Water System

SOP-22

Emergency Diesel Generator

71111.04

Procedures

SOP-3

Engineered Safeguards

109

Fire Area 12

Battery Room, Elevation 607'

Fire Area 13B

Charging Pump Rooms, Elevation 590'

71111.05

Fire Plans

Fire Area 4

1C 2.4kV Switchgear Room, Elevation 590'

PLSEG-LOR-

21C-07

Secondary Malfunctions

71111.11Q

Miscellaneous

PLSEG-OPS-

21C-02

Multi-Department Event

CR-PLP-2018-

2540

Charging Pumps P-55A, P-55B, P-55C Trip Unexpectedly

05/25/2018

CR-PLP-2021-

01962

P-55A Charging Pump, Speed and Flow Stability Are

Different From Before the Speed Reducer Was Replaced

07/26/2021

CR-PLP-2021-

2110

The Condensate System (CDS-CDS) is Near Maintenance

Rule (a)(1) Status

08/06/2021

71111.12

Corrective Action

Documents

CR-PLP-2021-

2165

The Main Feedwater System Has Exceeded its Maintenance

Rule Performance Criteria of <2 Functional Failures in the

Previous 24 Months

08/12/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-PLP-2021-

209

The Maintenance Rule Evaluation Associated With MV-

FW155 R-1A Turbine Driver

08/18/2021

CR-PLP-2021-

2456

Quarterly System Walkdown for CVC/CBA "Chemical and

Volume Control/Concentrated Boric Acid"

09/21/2021

PLP-RPT-12-

00026

EGAD-EP-10 Palisades Maintenance Rule Scoping

Document

Miscellaneous

PLP-RPT-12-

00026 EGAD-EP-

Palisades Maintenance Rule Scoping Document

CR-PLP-2021-

01984

Condensate Pump P-2B Thrust Bearing Temp

07/28/2021

CR-PLP-2021-

01992

Temperature Element for CRD-18 Control Rod Drive

Mechanism - Rx Head Loc'n Rose From Approximately

154 Degrees F to Approximately 164 Degrees F

07/28/2021

CR-PLP-2021-

2012

Condensate Pump, P-2B Change in Vibration Frequency for

the Upper Motor Bearing

07/29/2021

CR-PLP-2021-

2120

Steam Leak at the Base of P-10A Heater Drain Pump

08/09/2021

CR-PLP-2021-

2123

Discovered Small Leak on Cap of MV-HED160, Heater Drain

Pump P-10B Discharge Drain

08/09/2021

CR-PLP-2021-

2181

The Jacket Water Supply Header for K-6B, Emergency

Diesel Generator 1-2

08/16/2021

CR-PLP-2021-

2193

Phoenix Qualitative Fire Risk Safe Shutdown Path Definition

08/17/2021

CR-PLP-2021-

2198

Jacket Water Outlet Elbow Brace is Cracked in Two Spots

08/18/2021

Corrective Action

Documents

CR-PLP-2021-

2199

After Removal of Cylinder Liner an Indication Was Found On

the Block Where the Liner Sits

08/18/2021

AOP-7

Rapid Power Reduction

71111.13

Procedures

GOP-5

Power Escalation in Mode 1

07/29/2021

CR-PLP-2021-

01702

A Water Bubble Between the SIRW Roof Membrane

06/25/2021

71111.15

Corrective Action

Documents

CR-PLP-2021-

01783

Emergency Diesel Generator 1-1

07/06/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-PLP-2021-

01921

K-6B (Emergency Diesel Generator 1-2) Start On Both Air

Start Motors Slower Than Average

07/21/2021

CR-PLP-2021-

01975

Boric Acid Build-Up Was Present on the Swagelok Fitting

Located Between CV-1901 (Pressurizer T-72 Vapor Phase

SX-1045) and MV-PC1045D (Vapor Phase SX-1045

CV-1901 Inlet)

07/27/2021

CR-PLP-2021-

2129

The PCS Unidentified Leak Rate Appears to Have Taken a

Step Change Higher After the Downpower 07/29/2021

08/09/2021

CR-PLP-2021-

223

Diesel Generator 1-2 Local Regulator Switch, Generator

Voltage Did Not Raise As Expected

08/20/2021

CR-PLP-2021-

251

CV-0826 (CCW HX E-54B SW Outlet) Was Timed Stroked

Open Unsat During QO-5 Valve Test Procedure

08/24/2021

CR-PLP-2021-

2333

Entered Action Level 3 Per Admin 4.19, PCS Leak Rate

Monitoring Program, For PCS Unidentified Leak Rate

Greater Than Baseline Mean by Three Standard Deviations

09/03/2021

CR-PLP-2021-

2449

The Muffin Fan On the Rear of PY-0102B, "B" Thermal

Margin Monitor, Is In Distress

09/21/2021

Drawings

M-219, Sheet 1B

Process Sampling System

90753

Operability Basis Input for EDG 1-1 (Emergency Diesel

Generator) EGA Droop Potentiometer Maximum Acceptance

Range

EC-90325

Operability Basis Input for EDG 1-1 (Emergency Diesel

Generator) Hunting

Engineering

Changes

EC-90958

Operability Input for CR-PLP-2021-02251 for Stroke Time of

CV-0826

08/24/2021

EA-C-PAL-99-

209B-01

Generation of Flow Rate Acceptance Criteria for Technical

Specification Test RO-216

EN-OP-104

5, Operability Evaluation Basis Form

Proc. 4.19

PCS Leakage Decision Flowchart

Procedures

SEP-PLP-IST-

101

Inservice Testing of Plant Valves

564567-01

K-6A Governor Tuning (Elect)

08/02/2021

Work Orders

564567-04

Replace Diesel Generator EGA Control Box

08/02/2021

71111.19

Corrective Action

CR-PLP-2021-

P-55A, 'A' Charging Pump

07/02/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

01768

CR-PLP-2021-

01772

P-55A 'A' Charging Pump Placed in Service in Parallel With

P-55C

07/03/2021

CR-PLP-2021-

01869

Inspections On M-55A (P-55A Charging Pump Fluid Drive)

07/15/2021

CR-PLP-2021-

01911

EC-162 Containment Hydrogen Monitoring Panel (Right)

07/21/2021

CR-PLP-2021-

01913

PM of Breaker 52-2423, (P-2402 Hydrogen Sample Pump),

Per WO 52898258-02

07/21/2021

CR-PLP-2021-

2000

Upper Oil Cooler Was Removed From P-2B Condensate

Pump Motor

07/29/2021

CR-PLP-2021-

2180

Small Crack On Cylinder 7L

08/16/2021

Documents

CR-PLP-2021-

2183

EDG 1-2 Monthly Test, Starting Air Pressure for Train A

08/16/2021

CVC-M-1

P-55A Charging Pump Frequent Maintenance

SPS-E-11

480 Volt Breaker Inspection and Repair

WI-SPS-E-02

Insulation Resistance Testing of Electrical Equipment

Procedures

WI-SPS-E-02

Megger Test Form

07/29/2021

00565778-01

EMA-2205, Condensate Pump Motor Replace Upper

Cooler - E-908B

07/29/2021

00565778-11

P-2B EMA-2205

07/29/2021

2898258-01

PM-Breaker 52-2423 (P-2402)

05/24/2021

2956357-01

P-55A, 'A' Charging Pump Maintenance

05/03/2021

Work Orders

564567-03

K-8A; RE-131 Load Reject Surveillance (I&C)

08/03/2021

CR-PLP-2-21-

2137

As Found Speed Was 3588 RPM (Band 3540-3580) as Left

Speed is 3562 RPM

08/09/2021

CR-PLP-2021-

2114

Sixth Consecutive Day Above the Baseline Mean

08/07/2021

CR-PLP-2021-

2117

A Confirmatory Leakrate Was Required Per Admin 4.19,

PCS Leakrate Monitor Program

08/08/2021

CR-PLP-2021-

2130

Secured P-8B Per QO-21 Direction

08/09/2021

71111.22

Corrective Action

Documents

CR-PLP-2021-

P-7C Service Water Pump Test, the Vibration Data Taken

09/20/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2437

Was Higher Than Expected

CR-PLP-2021-

2441

1-2 Diesel Generator "B" Air Start Motor Started the Engine

Outside of Acceptable Start Time

09/20/2021

QO-19A

Inservice Test Procedure - HPSI Pumps and ESS Check

Valve Operability Test

QO-20

Inservice Test Procedure - Low Pressure Safety Injection

Pumps

Procedures

QO-21

Inservice Test Procedure - Auxiliary Feedwater Pumps

08/19/2021

CR-PLP-2019-

04657

PWS Siren 40 Non-Functional

11/21/2019

CR-PLP-2020-

00843

Siren Preventative Maintenance Identified Cracked Power

Pole for Siren 040

03/16/2020

CR-PLP-2020-

01388

Siren 057 AC Power Failure

04/30/2020

Corrective Action

Documents

CR-PLP-2021-

01827

Siren 8 Audio Current Failure

07/10/2021

Federal Emergency Management Agency Palisades Nuclear

Plant Public ANS Approval Letter

2/20/2012

Federal Emergency Management Agency Letter; Provisions

for Backup Alert and Notification (ANS) for the Palisades

Nuclear Power Plant Emergency Planning Zone (EPZ)

2/10/2012

Palisade Nuclear Plant Public Warning System Replacement

Project Design Report

10/01/2002

Documentation of Public Warning System Monthly Tests

08/01/2019-

06/30/2021

Alert Notification System Maintenance Records

07/01/2019-

06/30/2019

20 Emergency Preparedness Public Information Mailer

08/19/2020

Miscellaneous

Emergency Preparedness Brochure (Internet Website

Document)

09/01/2021

71114.02

Procedures

PAL PWS

Palisades Nuclear Plant Public Warning System Operating

Procedure

71114.03

Corrective Action

Documents

CR-PLP-2020-

04067

ERO Shift Did Not Complete Work Task Corrective Action

10/08/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-PLP-2021-

00963

Outdated Documents in Allegan County Offsite Liaison ERO

Position Binder

04/08/2021

Palisades Nuclear Station On-Shift Staffing Analysis Final

Report

Emergency Response Organization Off-Hours,

Unannounced, Augmentation Response Test Records

08/01/2019-

06/30/2021

Emergency Response Organization Training Records

(12 samples)

08/31/2021

Miscellaneous

Current Emergency Response Organization Team Staffing

08/06/2021

EI-2.2

Emergency Staff Augmentation

Procedures

EN-EP 310

Emergency Response Organization Notification System

CR-PLP-2019-

03742

Emergency Kit 9 Inventory Issues

09/17/2019

CR-PLP-2019-

04155

Q3 2019 Vulnerability Management Assessment Discovered

EP Only CDAs Were Not Receiving Microsoft Operating

System Upgrades and Security Patches

10/16/2019

CR-PLP-2020-

252

Inform Program Would Not Connect to the Server

01/27/2020

CR-PLP-2020-

00596

Inform Program Deficiencies Related to Technical Data

Form Inputs

2/24/2020

CR-PLP-2020-

00957

Dedicated NRC Phone Lines Not Working in Control Room

03/25/2020

CR-PLP-2020-

01802

EAL Initiating Condition (IC) Use During 8 Year Cycle

06/04/2020

CR-PLP-2021-

00567

TSC Inventory - Incorrect Procedure Revisions

03/03/2021

CR-PLP-2021-

01135

EP Fleet Assessment Team - Negative Observation for

ERO Drill Participation Performance Indicator

04/26/2021

Corrective Action

Documents

CR-PLP-2021-

01469

New South Haven Hospital - Coordination of Management

Change and Radiological Emergency Response

06/28/2021

Monthly Emergency Communications Test Records

08/01/2019-

06/30/2021

71114.05

Miscellaneous

Emergency Response Facilities Emergency Kits Quarterly

Inventory Records

08/01/2019-

06/30/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Emergency Response Facilities Monthly Communications

Test Records

08/01/2019-

06/30/2021

Emergency Preparedness Exercise and Drill Evaluation

Reports

08/01/2019-

08/31/2021

Emergency Preparedness Letters of Agreement (LOAs) With

Off-Site Response and Support Organizations

08/01/2019-

08/31/2021

KLD TR-1161

Palisades Power Plant 2020 Population Update Analysis

09/16/2020

LO-PLPLO-2021-

0039

Pre-NRC Emergency Planning Program Inspection

Assessment

05/19/2021

QA-7-2020-PLP-1

Quality Assurance Audit Report - Emergency Preparedness

05/11/2020

QA-7-2021-PLP-1

Quality Assurance Audit Report - Emergency Preparedness

05/11/2021

EAL Basis

Emergency Action Level Technical Bases

SEP

Palisades Nuclear Plant Site Emergency Plan

SEP Supplement

EAL Wall Charts

Procedures

SEP, Supplement

Evacuation Time Estimates

Corrective Action

Documents

CR-PLP-2020-

00564

TSC Security Coordinator Laptop Missing During Emergency

Planning Drill

2/20/2020

NRC Performance Indicator High Pressure Injection

(HPSI) (MS-07)

07/02/2020 -

06/30/2021

NRC Performance Indicators Mitigating Systems

Performance Indicator Residual Heat Removal (RHR)

(MS-09)

07/02/2020 -

06/30/2021

71151

Miscellaneous

NRC Performance Indicators Barrier Integrity Reactor

Coolant System (BI-02)

07/02/2020 -

06/30/2021

CR-PLP-2021-

01702

A Water Bubble Between the SIRW Roof Membrane

06/25/2021

CR-PLP-2021-

01735

Walkdown of the T-58 SIRW Tank Roof

07/01/2021

71152

Corrective Action

Documents

CR-PLP-2021-

01749

Cross Contaminated Sample

07/08/2021

71153

Corrective Action

Documents

CR-PLP-2004-

235

Significant Event Notification 248

03/24/2004

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-PLP-2005-

222

Steam Dump Control Relay Type HFA Not Updated

01/11/2005

CR-PLP-2021-

01592

SDCR Relay (Steam Dump Control Relay) Showed Signs of

Over-Heating

06/16/2021

FP-E-SE-02

Component Classification

Procedures

FP-PE-PM-01

Preventative Maintenance Program

0