IR 05000255/2020003
ML20318A040 | |
Person / Time | |
---|---|
Site: | Palisades |
Issue date: | 11/13/2020 |
From: | Billy Dickson NRC/RGN-III/DRP/B2 |
To: | Corbin D Entergy Nuclear Operations |
References | |
IR 2020003 | |
Download: ML20318A040 (18) | |
Text
November 13, 2020
SUBJECT:
PALISADES NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000255/2020003
Dear Mr. Corbin:
On September 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Palisades Nuclear Plant. On October 28, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA/
Billy C. Dickson, Jr., Chief Branch 2 Division of Reactor Projects Docket No. 05000255 License No. DPR-20
Enclosure:
As stated
Inspection Report
Docket Number: 05000255 License Number: DPR-20 Report Number: 05000255/2020003 Enterprise Identifier: I-2020-003-0031 Licensee: Entergy Nuclear Operations, Inc.
Facility: Palisades Nuclear Plant Location: Covert, MI Inspection Dates: July 01, 2020 to September 30, 2020 Inspectors: J. Benjamin, Senior Reactor Inspector J. Bozga, Senior Reactor Inspector E. Fernandez, Reactor Inspector M. Holmberg, Senior Reactor Inspector P. Laflamme, Senior Resident Inspector J. Mancuso, Resident Inspector V. Myers, Senior Health Physicist C. St. Peters, Resident Inspector Approved By: Billy C. Dickson, Jr., Chief Branch 2 Division of Reactor Projects Enclosure
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Palisades Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
The plant began the inspection period at rated thermal power and remained at or near rated thermal power until August 5, 2020. On August 5, 2020, the plant began coast down until reaching approximately 88 percent power on August 30, 2020. On August 30, 2020, the plant was down powered and taken offline for a refueling outage. The plant remained offline for the remainder of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities, and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.
REACTOR SAFETY
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (3 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) 1-2 emergency diesel generator (EDG) lube oil and jacket water cooling water system on July 6, 2020
- (2) Station battery number 1 on August 6, 2020
- (3) Spent fuel pool (SFP) cooling system on September 15, 2020
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) South west penetration room on July 13, 2020
- (2) Cable spreading room on August 18, 2020
- (3) 1C 2.4kV switchgear room on August 24, 2020
- (4) Charging pump room on August 25, 2020
71111.06 - Flood Protection Measures
Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)
The inspectors evaluated internal flooding mitigation protections in the:
- (1) West engineering safeguards room on September 21, 2020
===71111.08P - Inservice Inspection Activities (PWR) PWR Inservice Inspection Activities Sample (IP Section 03.01) (1 Partial)
(1) (Partial)
The inspectors verified that the reactor coolant system boundary, steam generator tubes, reactor vessel internals, risk-significant piping system boundaries, and containment boundary are appropriately monitored for degradation and that repairs and replacements were appropriately fabricated, examined and accepted by reviewing the following activities from 08/31/2020 to 09/30/2020:
03.01.a - Nondestructive Examination and Welding Activities.
- Encoded Phased Array Ultrasonic Examination (PAUT) of SDC Safe End to Elbow Dissimilar Metal Weld. Component ID PCS-12-SDC-2H1-1
- Encoded Phased Array Ultrasonic Examination (PAUT) of SDC Safe End to Elbow Dissimilar Metal Weld. Component ID PCS-12-SDC-2H1-2
- Bare Metal Visual Exam (BMVT) of 1" Instrument Tap. Component ID PCS-042 Weld 6 "B Hot Leg"
- Bare Metal Visual Exam (BMVT) of 1" Instrument Tap. Component ID PCS-042 Weld 8 "B Hot Leg"
- Bare Metal Visual Exam (BMVT) of 1" Instrument Tap. Component ID PCS-042 Weld 10 "B Hot Leg" 03.01.b - Pressurized-Water Reactor Vessel Upper Head Penetration Examination Activities.
- Bare Metal Visuals (BMV) of 54 Penetrations on the Reactor Vessel Closure Head (RVCH)
- Half Nozzle Weld Repair of Penetrations 17 and 34, Work Order 00550825 03.01.c - Pressurized-Water Reactor Boric Acid Corrosion Control Activities.
- CR-PLP-2019-02918 Pressurizer Spray Valve from Loop 1A CV-1057
- CR-PLP-2019-04528 Flange downstream of MV-ES3418
- CR-PLP-2019-02059 Flange near HC4-H103 and Temporary Connection for SFP Cooling 03.01.d - Pressurized-Water Reactor Steam Generator Tube Examination Activities.
- Eddy current testing of 7,589 Tubes in steam generator (SG 1A) and 7753 Tubes in (SG 1B)
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01)
=
- (1) The inspectors observed and evaluated licensed operator performance in the Control Room during reactor shutdown on August 30, 2020
- (2) The inspectors observed and evaluated licensed operator performance in the Control Room during reduced inventory on September 4, 2020
Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)
- (1) The inspectors observed and evaluated PSLEG-LOR-20C-01 on August 11, 2020
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (2 Samples)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:
- (1) Chemical and volume control system on July 10, 2020
- (2) Service water system on September 22, 2020
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (4 Samples)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Elevated risk for planned maintenance on component cooling water system and battery charger #4 on July 27, 2020
- (2) Elevated risk for planned maintenance on high pressure safety injection and containment spray systems on July 28, 2020
- (3) Elevated risk for a severe weather warning impacting the 2400V 1C startup transformer breaker maintenance activities on August 10, 2020
- (4) Shutdown risk assessment during reduced inventory on September 8, 2020
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)
The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:
- (1) Elevated Lake Michigan water level evaluation on July 21, 2020
- (2) CV-0826 cotter pin misalignment evaluation on July 28, 2020
- (3) Spalling of the concrete near containment vertical tendon V-140 anchorage on August 21, 2020
- (4) Elevated inverter #4 temperatures evaluation on August 24, 2020
71111.19 - Post-Maintenance Testing
Post-Maintenance Test Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:
- (1) EDG 1-2 start test following PCV-1489 replacement on July 21, 2020
- (2) P-52 B component cooling water (CCW) baker testing on August 5, 2020
- (3) CV-0826 control valve testing on August 6, 2020
- (4) Core verification examination on September 25, 2020
- (5) Nuclear instrument source range testing on September 28, 2020
71111.20 - Refueling and Other Outage Activities
Refueling/Other Outage Sample (IP Section 03.01) (1 Partial)
(1) (Partial) The inspectors evaluated refueling outage 1R27 beginning August 30, 2020
71111.22 - Surveillance Testing
The inspectors evaluated the following surveillance tests:
Surveillance Tests (other) (IP Section 03.01)
- (1) QO-15B, P-52B component cooling water (CCW) pump test on July 30, 2020
- (2) RO-128-1, 1-1 EDG 24-hour load run test on August 8, 2020
- (3) Left train safety injection system test on August 18, 2020
- (4) RT-8C, engineering safeguards test on September 24, 2020
Inservice Testing (IP Section 03.01) (1 Sample)
- (1) QO-19B - high pressure safety injection (HPSI) pump and emergency safety system check valve operability test, on July 15,
RADIATION SAFETY
71124.01 - Radiological Hazard Assessment and Exposure Controls
Radiological Hazard Assessment (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated how the licensee identifies the magnitude and extent of radiation levels and the concentrations and quantities of radioactive materials and how the licensee assesses radiological hazards
Instructions to Workers (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated radiological protection-related instructions to plant workers
Contamination and Radioactive Material Control (IP Section 03.03) (2 Samples)
The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material:
- (1) The inspectors observed surveys of potentially contaminated material leaving the radiologically controlled are.
- (2) The inspectors observed workers exiting the radiologically controlled area
Radiological Hazards Control and Work Coverage (IP Section 03.04) (3 Samples)
The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities:
- (1) Reactor vessel disassembly under RWP 20200433
- (2) Scaffolding activities in containment under RWP 20200424
- (3) Steam generator primary side activities under RWP 20200454 High Radiation Area and Very High Radiation Area Controls (IP Section 03.05) (2 Samples)
The inspectors evaluated licensee controls of the following High Radiation Areas and Very High Radiation Areas:
- (1) Access to the reactor cavity, located inside containment
- (2) Area surrounding the regenerative heat exchanger, located inside containment Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 03.06) (1 Sample)
- (1) The inspectors evaluated radiation worker and radiation protection technician performance as it pertains to radiation protection requirements
71124.02 - Occupational ALARA Planning and Controls
Implementation of ALARA and Radiological Work Controls (IP Section 03.03) (2 Samples)
The inspectors evaluated the licensees communication of as low as is reasonably achievable ALARA and radiological work controls for the following work activities:
- (1) Reactor vessel disassembly under RWP 20200433
- (2) Steam generator primary side activities under RWP 20200454
Radiation Worker Performance (IP Section 03.04) (1 Sample)
The inspectors evaluated radiation worker and radiation protection technician performance during:
- (1) Reactor vessel disassembly under RWP
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
MS07: High Pressure Injection Systems (IP Section 02.06) ===
- (1) Unit 1 (July 1, 2018-June 30, 2020)
MS09: Residual Heat Removal Systems (IP Section 02.08) (1 Sample)
- (1) Unit 1 (July 1, 2018-June 30, 2020)
BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)
- (1) Unit 1 (July 1, 2018-June 30, 2020)
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On October 28, 2020, the inspectors presented the integrated inspection results to Mr. D. Corbin, Site Vice President, and other members of the licensee staff.
- On October 1, 2020, the inspectors presented the radiation protection inspection results to Mr. D. Corbin, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection Type Designation Description or Title Revision or
Procedure Date
71111.04 Corrective Action CR-PLP-2020- Protected Equipment for 1-2 Emergency Diesel Generator 07/06/2020
Documents 02120
CR-PLP-2020- Notification per MISO that Maintenance Activities Must be 07/06/2020
2126 Curtailed Due to Generation Availability Constraints
CR-PLP-2020- During Performance of MO-7A-1, FI-0890, Diesel Generator 07/08/2020
2149 1-1 Service Water Flow was Reading 710gpm
CR-PLP-2020- VC-10 Suction Pressure Cycling From 52 psig to 58 psig on 07/21/2020
298 PI-1676
CR-PLP-2020- P-7B Service Water Pump Basket Strainer 07/25/2020
2345
CR-PLP-2020- Corrosion Found During Rounds in Station Battery Number 2 07/26/2020
2354
CR-PLP-2020- Induction Disc of the GE 12IAC53A101A Relay 151-106 X- 08/10/2020
2542 Phase was Stuck to the Backstop of the Time Dial/Lever
Corrective Action CR-PLP-2020- NRC Identified the Floor Drain Cover on the South End of 07/06/2020
Documents 02129 the 1-2 Emergency Diesel Generator Ajar
Resulting from CR-PLP-2020- The NRC Identified that the 1-2 Emergency Diesel 07/06/2020
Inspection 02130 Generator Vents are Dirty and may Require Cleaning
CR-PLP-2020- NRC Identified a Potential Oil Leak on the North End of the 07/06/2020
2131 1-1 Emergency Diesel Generator
CR-PLP-2020- NRC Identified There is Vegetation Growing on the North 07/23/2020
2329 and North East Sides of EX-17, Station Transformer 17
CR-PLP-2020- NRC Identified Debris on the Floor of the 1-1 and 1-2 EDG 07/23/2020
2330 Rooms
Drawings M-221 Piping & Instrumentation Diagram, Spent Fuel Pool Cooling 61
System, Sheet 2
Miscellaneous DBD 2.07 Design Basis Document for Spent Fuel Pool Cooling System 5
Procedures AOP-26 Loss of Spent Fuel Pool Cooling 3
SOP-27 Fuel Pool System 72
71111.05 Corrective Action CR-PLP-2020- PI-5350A, Fire Protection System Header Pressure was 07/30/2020
Documents 02416 Trending Down
Fire Plans Pre-Fire Plan 13B Charging Pump Rooms / Elevation 590' 5
Inspection Type Designation Description or Title Revision or
Procedure Date
Pre-Fire Plan 2 Cable Spreading Room; Elevation 607' 5
Pre-Fire Plan 26 Southwest Cable Penetration Room; Elevation 590' & 607' 5
Pre-Fire Plan 4 1-C Switchgear Room and Manhole 1, 2, & 3/Elevation 590' 5
71111.06 Corrective Action CR-PLP-2020- Expansion Joint XJ-0421 Flood Barrier on HB-23-3" was 08/04/2020
Documents 02461 Identified as Having a Slit in the Joint Approximately Midway
Down the Southern Side of the Joint
Miscellaneous DBD 7.08 Design Basis Document Plant Protection Against Flooding 6
Procedures AOP-39 Internal Plant Flooding 1
71111.08P Corrective Action CR-PLP-2020- Ultrasonic Data Analysis of a Relevant Indication on 09/11/2020
Documents 03380 Penetration 34 on the Reactor Vessel Head
Resulting from CR-PLP-2020- Ultrasonic Data Analysis of a Relevant Indication on 09/13/2020
Inspection 03427 Penetration 17 on the Reactor Vessel Head
Procedures 54-ISI-400-023 NONDESTRUCTIVE EXAMINATION PROCEDURE 12/12/2018
Multi-Frequency Eddy Current Examination of SG Tubing
54-ISI-619-000 Automated Ultrasonic Examination of Open Tube RPV 07/30/2020
Closure Head Penetrations-Palisades Specific
CEP-NDE-0955 Visual Examination (VE) of Bare-Metal Surfaces 307
LMT-10-PAUT- Fully Encoded Phased Array Ultrasonic Examination of 3
007 Dissimilar Metal Piping Welds
SEP-BAC-PLP- Boric Acid Corrosion Control Program Engineering Nuclear 4
001 Programs Applicable Sites
71111.11Q Miscellaneous SES-405 LOR Simulator Exam Scenario 1
Procedures GOP-14 Reduced Inventory Checklist 53
GOP-8 Power Reduction and Plant Shutdown to Mode 2 or Mode 3 40
= 525°F
71111.12 Corrective Action CR-PLP-2018- CV-0869, CAC VHX-4 SW Inlet, Valve Actuator Moved in the 11/09/2018
Documents 05815 Closed or Open Direction, but Valve Itself did not Move
CR-PLP-2019- Baker Offline Motor Test Could not be Completed 12/16/2019
04925
CR-PLP-2020- Discharge Accumulator for P-55C Charging Pump the "As 08/05/2020
2475 Found" Pressure of the Tank Bladder was 1287 psig
CR-PLP-2020- Charging Pump "As Found" Pressure of the Tank Bladder 08/05/2020
2476 was 0.0 psig
CR-PLP-2020- Critical Service Water System (CSW) has Exceeded the 08/10/2020
Inspection Type Designation Description or Title Revision or
Procedure Date
2543 Near (a)(1) Threshold
CR-PLP-2020- Exceeded Maintenance Rule (MR) Performance Criteria 09/07/2020
03184 (PC) for Number of Functional Failures (#) in 24 Months for
the Main Steam System
Miscellaneous System Health Chemical & Volume Control System 2018
Report
System Health Chemical & Volume Control System 2019
Report
System Health CSW - Critical Service Water Q2-2019
Report
System Health CSW - Critical Service Water Q2-2020
Report
System Health CSW - Critical Service Water Q4-2018
Report
System Health CSW - Critical Service Water Q4-2019
Report
71111.13 Corrective Action CR-PLP-2020- Removed from Service to Clean BS-1318, P-7A Service 07/31/2020
Documents 02421 Water Pump Basket Strainer
CR-PLP-2020- Control Room Envelope 08/10/2020
2551
CR-PLP-2020- Entered AOP-38 "Acts of Nature" due to High Wind Warning 08/11/2020
2552 on August 10, 2020
CR-PLP-2020- Start Up Transformer 1-2 Electrical Maintenance Failed to 08/11/2020
2555 Finish the Work as Scheduled due to Acts of Nature
Procedures 4.11 Safety Function Determination Program 7
71111.15 Corrective Action CR-PLP-2020- Spalling of the Concrete Near Containment Vertical Tendon 06/24/2020
Documents 02009 V-140 Anchorage
CR-PLP-2020- The Official Monthly Lake Michigan Elevation for June, as 07/21/2020
2303 Measured by the Calumet Harbor, Illinois Buoy, has
Exceeded the Assumed Starting Elevation for the Design
Basis Seiche Event
CR-PLP-2020- Per CR-PLP-2020-02303 the Elevation of Lake Michigan in 07/22/2020
2316 the Area of the Plant has Exceeded the Assumed Design-
Basis Value for External Flooding Protection
Inspection Type Designation Description or Title Revision or
Procedure Date
CR-PLP-2020- Adjustment on HIC-0826, Instrument Air Regulator for CV- 07/27/2020
2365 0826
CR-PLP-2020- EK-EK-1171, Component CLG E-54B Hi-Lo Temp 07/28/2020
2366
CR-PLP-2020- Operator Noted EVI-27/D2, BTRY D02 DC Volt 07/29/2020
2389 Indicator/Undervolt RLY Reading 129 8V
CR-PLP-2020- Cooling Fan M201 in ED-09 was Discovered to be Operating 07/30/2020
2394 Approximately 18°F Warmer than the Other 2 Fans
CR-PLP-2020- Discovered in ED-09, Wire 821 on TC No. 3, Terminal J4-11 07/30/2020
2395 was Approximately 33°F Warmer than the Similar Wires
CR-PLP-2020- EK-1132, Service Water Pump Basket Strainer D/P Alarms 07/30/2020
2399 not Actuating at Proper D/P
CR-PLP-2020- RT-202B Precals for Channels 1 and 2 were Calibrated 07/30/2020
2405 Above Stated Ranges
CR-PLP-2020- Service Water Piping Inside Containment 09/02/2020
2941
CR-PLP-2020- Service Water Piping Inside Containment 09/02/2020
2943
Corrective Action CR-PLP-2020- Service Water P-7C was Removed from Service to Clean 08/01/2020
Documents 02432 BS-1320, P-7C Service Water Pump Basket Strainer
Resulting from CR-PLP-2020- Editorial Error at the Bottom of the Tabulation on FSAR 08/18/2020
Inspection 02617 Page 5.8-33
Engineering 86917 Continued Operation when Lake Michigan Design Basis 0
Changes Levels are Exceeded
289 Concrete Spalling Near V-140 Tendon Anchorage on 0
Containment Dome
87503 Supplement to EC 87289 on ACI Bearing Strength 0
87696 Supplement to EC 87289 and EC 87503 on Steel Plate 0
Applied Stresses
Engineering 87503 Supplement to EC 87289 on ACI Bearing Strength 0
Evaluations
Miscellaneous PLP-RPT-15- Palisades Nuclear Plant Flooding Hazard Re-Evaluation 1
00010 Report
Procedures QO-5, Valve Stroke Testing Data Sheet CV-0821, CV-0822, 08/29/2019
Inspection Type Designation Description or Title Revision or
Procedure Date
17 CV-0823, CV-0826
SOP-15 Palisades Nuclear Plant System Operating Procedure: 69
Service Water System
Work Orders 52922071 QO-5 -Vlv Test Proc (Inc Cont Isolation Vlvs) 05/26/2020
71111.19 Corrective Action CR-PLP-2020- Fan M-201 for ED-09 Inverter #4 was Replaced 07/31/2020
Documents 02423
CR-PLP-2020- Buildup of Dirt & Dust on the Bottom of M1, M2 &M201 Heat 07/31/2020
2424 Sinks
CR-PLP-2020- Service Water P-7B was Removed from Service to Clean 07/31/2020
2426 BS-1319, P-7B Service Water Pump Basket Strainer
CR-PLP-2020- SSC: CV-3057, Safety Injection Refueling Water Tank 09/02/2020
2911 (SIRWT) Isolation
Miscellaneous Control Room Logs 07/28/2020
Failure Modes NI-3, Wide Range Nuclear Instrument 09/13/2020
and Effects
Worksheet
Procedures EN-MA-125 Troubleshooting Control of Maintenance Activities 09/23/2020
EN-MA-134 Offline Motor Electrical Testing 07/27/2020
EN-RE-326 PWR Core Loading Verification 09/16/2020
EN-WM-105 Off-Line Baker Testing of Motor EMA-1208 for P-52B 07/27/2020
RFL-V-9 Core Verification 9
RI-99 Left Channel Nuclear Instrumentation Calibrations 18
SOP-22 Emergency Diesel Generator 80
Work Orders 00550833 NI-1/3A, Indication Failed - Replace Suspect 8D's "A8 & A9" 09/21/2020
2864755 EEQ Maint-Comp. Cooling. EMA-1208, P-52B Motor 07/27/2020
2872985 Core Mapping System Setup and Operation 09/16/2020
71111.20 Corrective Action CR-PLP-2020- CV-0701, SG E-50A FW Regulating Valve 08/30/2020
Documents 02793
CR-PLP-2020- Rod Deviation Alarms were Received 08/30/2020
2795
CR-PLP-2020- RV-2006, Letdown Heat Exch E-58 Inlet Safety Relief and 08/30/2020
2796 Primary Coolant System (PCS)
CR-PLP-2020- CV-2002 is not Opening with SV-2002B in AUTO 08/30/2020
2802
Inspection Type Designation Description or Title Revision or
Procedure Date
CR-PLP-2020- Boric Acid Leak was Identified on CRD-12 08/30/2020
2820
CR-PLP-2020- Boric Acid Leak was Identified on CRD-18 08/30/2020
2821
CR-PLP-2020- Air Hoses Were Ran Thru the Equipment Hatch Without Ops 09/01/2020
2894 Alignment and Hose Labeling per GOP-14
CR-PLP-2020- T-2, Condensate Storage Tank 09/05/2020
03094
CR-PLP-2020- Control Room Operators Entered AOP-36, Loss of 09/10/2020
262 Component Cooling
CR-PLP-2020- Breaker 25H9 (Generator Output Breaker) Failed to Close 09/18/2020
03620 from the Control Room
Corrective Action CR-PLP-2020- NRC Identified - During the Containment Walkdown a 08/31/2020
Documents 02838 Puddle of Oil was Found on the 590' Clean Waste Receiver
Resulting from Tank Room About Half Under the 607' Catwalk
Inspection
Procedures EM-04-08 Mode 3, Tave = 525°F Shutdown Margin Calculation 08/24/2020
EN-RE-302 PWR Reactivity Maneuver - Reactivity Plan Form 08/25/2020
GOP-14 Shutdown Cooling Operations 53
71111.22 Corrective Action CR-PLP-2020- PI-1475, Diesel Generator K-6A Fuel Oil Pressure was at 25 08/05/2020
Documents 02471 psig
CR-PLP-2020- RO-128-1, Diesel Generator 1-1 24 Hour Load Run, Table 08/05/2020
2472 for Acceptance Criteria
CR-PLP-2020- LLRT for Penetration MZ-42, Could not Establish <10sccm 08/31/2020
2834 on Step 5.2.13(h)2 and 3, Actual Reading was 30 sccm
CR-PLP-2020- Leakage from Containment Penetration #15 was 8400 sccm 09/04/2020
2996 and Exceeded the 5000 sccm Troubleshooting Guideline
CR-PLP-2020- CV-0847, SW Supply to Cont (MZ-12) 09/25/2020
03806
Procedures QO-1 Safety Injection System 70
QO-15 Inservice Test Procedure - Component Cooling Water 40
Pumps
QO-19B Inservice Test Procedure - HPSI Pumps and Emergency 44
Safety System Check Valve Operability Test
Inspection Type Designation Description or Title Revision or
Procedure Date
RT-8C Engineered Safeguards System - Left Channel 09/14/2020
Work Orders 52871419 RT-8C - Engineered Safeguards System - Left Channel 09/14/2020
2928850 QO-15B, Inservice Test Procedure - Component Cooling 07/27/2020
Pump P-52B
71124.01 Procedures EN-RP-101 Access Control for Radiologically Controlled Areas 15
EN-RP-106-01 Radiological Survey Guidlines 6
EN-RP-122 Alpha Monitoring 10
EN-RP-131 Air Sampling 17
Radiation Work 20200424 Scaffolding Activities in Containment 00
Permits (RWPs) 20200433 Refuel Project: Disassembly of the Reactor Head and 00
Associated Work Activities
200454 Steam Generator Primary Side Activities 00
71124.02 ALARA Plans 20200424 Scaffolding Activities in Containment 00
200433 Refuel Project: Disassembly of the Reactor Head and 00
Associated Work Activities
200454 Steam Generator Primary Side Activities 00
Procedures EN-RP-110 ALARA Program 14
71151 Miscellaneous NRC Performance Indicators 2Q2020 04/01/2020 -
06/30/2020
NRC Performance Indicators 1Q2020 01/01/2020 -
03/31/2020
NRC Performance Indicators 4Q2019 10/01/2019 -
2/31/2019
NRC Performance Indicators 3Q2019 07/01/2019 -
09/330/2019
NRC Performance Indicators 2Q2019 04/01/2019 -
06/30/2019
NRC Performance Indicators 4Q2018 10/01/2018 -
2/31/2018
NRC Performance Indicators 3Q2018 07/01/2018 -
09/30/2018
Procedures NRC Performance Indicators 1Q2019 01/01/2019 -
03/31/2019
71152 Corrective Action CR-PLP-2020- CV-0826 CCW HX E-54B SW Outlet Pinned Incorrectly 07/27/2020
Inspection Type Designation Description or Title Revision or
Procedure Date
Documents 02365
Procedures QO-5 Valve Test Procedure (Includes Containment Isolation 109
Valves)
SOP-15 Service Water System 70
16