IR 05000255/2020002

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000255/2020002 and Exercise of Enforcement Discretion
ML20224A204
Person / Time
Site: Palisades 
Issue date: 08/11/2020
From: April Nguyen
NRC/RGN-III
To: Corbin D
Entergy Nuclear Operations
References
EA-17-115 IR 2020002
Download: ML20224A204 (19)


Text

August 11, 2020

SUBJECT:

PALISADES NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000255/2020002 AND EXERCISE OF ENFORCEMENT DISCRETION

Dear Mr. Corbin:

On June 30, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Palisades Nuclear Plant. On July 23, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

April M. Nguyen, Acting Chief Branch 2 Division of Reactor Projects

Docket No. 05000255 License No. DPR-20

Enclosure:

As stated

Inspection Report

Docket Number:

05000255

License Number:

DPR-20

Report Number:

05000255/2020002

Enterprise Identifier: I-2020-002-0033

Licensee:

Entergy Nuclear Operations, Inc.

Facility:

Palisades Nuclear Plant

Location:

Covert, MI

Inspection Dates:

April 1, 2020 to June 30, 2020

Inspectors:

J. Benjamin, Senior Reactor Inspector

P. Laflamme, Senior Resident Inspector

J. Mancuso, Resident Inspector

V. Myers, Senior Health Physicist

C. St. Peters, Resident Inspector

Approved By:

April M. Nguyen, Acting Chief

Branch 2

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Palisades Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status EDG EA-17-115 Enforcement Action EA-17-115: Enforcement Discretion for Tornado Missile Protection Non-Conforming Conditions 71111.15 Discussed

PLANT STATUS

The plant began the inspection period at rated thermal power and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html.

Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time the resident inspectors performed periodic site visits each week and during that time conducted plant status activities as described in IMC 2515, Appendix D; observed risk significant activities, and completed on-site portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on-site. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated summer readiness of offsite and alternating current (AC) power systems on June 3, 2020

External Flooding Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated flood protection barriers, mitigation plans, procedures, and equipment are consistent with the licensees design requirements and risk analysis assumptions for coping with external flooding on June 9, 2020

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Emergency diesel generator (EDG) 1-1 on April 23, 2020
(2) Right train high pressure safety injection (HPSI) system on June 3, 2020
(3) Left train low pressure safety injection (LPSI) system on June 15, 2020

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations while performing a complete walkdown of the right train auxiliary feedwater (AFW) system during the week of May 18, 2020

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Area 24: AFW pump room, elevation 571' on April 10, 2020
(2) Fire Areas 5 & 7: 1-1 diesel generator and fuel oil day tank rooms, elevation 590' on April 24, 2020
(3) Fire Area 33: Technical Support Center, elevation 625' on May 7, 2020
(4) Fire Area 1: Control Room, elevation 625' on June 29, 2020

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated PLSEG-LOR-20B-04 on June 19, 2020

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Thermal margin monitoring system on April 20, 2020
(2) Primary coolant system on May 29, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Risk management activities and emergent work for P1-A, main feedwater pump (MFP), recirculation valve steam leak on April 23, 2020
(2) Emergent troubleshooting and work management activities associated with letdown system pressure control on April 29, 2020
(3) Elevated risk for planned shutdown cooling system testing on June 10, 2020

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Review of identified tornado missile protection nonconformance during the week of April 6, 2020
(2) Thermal margin monitor channel A operability evaluation on May 5, 2020
(3) Quench tank pressure rise evaluation on June 25, 2020
(4) Pressurizer heater breaker friction block evaluation on June 26, 2020

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Temporary modification to CV-944A manual side packing on April 17, 2020

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the following post maintenance test activities to verify system operability and functionality:

(1) Control Room ventilation system testing following planned maintenance activities on April 27, 2020
(2) Letdown stop valve orifice testing following planned maintenance activities on May 7, 2020
(3) CV-0711, P-1A MFP recirculation valve testing following body to bonnet steam leak repairs on May 14, 2020

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1)1-2 EDG monthly surveillance test on April 21, 2020

(2) Reactor protection matrix logic quarterly surveillance test on June 3, 2020

Inservice Testing (IP Section 03.01) (1 Sample)

(1) QO-42, shutdown cooling valves test on June 10, 2020

FLEX Testing (IP Section 03.02) (1 Sample)

(1) FLEX Standby PM: P-1003, One Year Operational Test on April 14,

RADIATION SAFETY

71124.03 - In-Plant Airborne Radioactivity Control and Mitigation

Use of Respiratory Protection Devices (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated the licensees use of respiratory protection devices

Self-Contained Breathing Apparatus for Emergency Use (IP Section 03.04) (1 Sample)

(1) The inspectors evaluated the licensees use and maintenance of self-contained breathing apparatuses

71124.04 - Occupational Dose Assessment

Source Term Characterization (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated licensee performance as it pertains to radioactive source term characterization

External Dosimetry (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated licensee performance as it pertains to external dosimetry that is used to assign occupational dose

Special Dosimetric Situations (IP Section 03.04) (2 Samples)

The inspectors evaluated the following special dosimetric situations:

(1) Dose assessment for a declared pregnant worker in 2019
(2) Effective dose equivalent assessment for individual performing reactor head work in

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02)

=

(1) Unit 1 (April 1, 2019-March 31, 2020)

MS05: Safety System Functional Failures (SSFFs) Sample (IP Section 02.04) (1 Sample)

(1) Unit 1 (April 1, 2019-March 31, 2020)

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends with a focus on human performance issues that might be indicative of a more significant safety issue during the period from January 1, 2020 to June 30, 2020

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Letdown relief valve lift and subsequent isolation adverse condition analysis, as documented in CR-PLP-2020-00611, during the week of May 18, 2020

71153 - Follow-up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) Licensee Event Reports 05000255/2017-001-00/01, "Inadequate Protection from Tornado Missiles Identified Due to Nonconforming Conditions" retraction

This LER was submitted and subsequently retracted LERs 05000255/2017-001-00(01) by licensee correspondence titled "Cancellation of Licensee Event Reports 2017-001-00 and 2017-001-01, "Inadequate Protection from Tornado Missiles Identified Due to Nonconforming Design Conditions", dated March 31, 2020, ADAMS Accession No. ML20091J599. The inspectors reviewed the LER and completed an inspection sample listed under 71111.15, Operability Determination, of this report.

INSPECTION RESULTS

EDG (Discussed)

Enforcement Action EA-17-115: Enforcement Discretion for Tornado Missile Protection Non-Conforming Conditions EDG 71111.15

Description:

On June 10, 2015, the NRC issued Regulatory Issue Summary 2015-06, Tornado Missile Protection, focusing on the requirements regarding tornado-generated missile protection and required compliance with the facility-specific licensing basis. The Regulatory Issue Summary also provided examples of noncompliances that had been identified through different mechanisms and referenced Enforcement Guidance Memorandum (EGM) 15-002, which was also issued on June 10, 2015. Revision 1 of EGM 15-002 was issued on February 7, 2017. The EGM revision provided guidance to allow the NRC staff to exercise enforcement discretion when an operating power plant licensee did not comply with the current licensing basis for tornado-generated missile protection. Specifically, the discretion applied to structures, systems, and components (SSCs) declared inoperable resulting in TS Limiting Conditions for Operation (LCOs) that would require a reactor shutdown or mode change if the licensee could not meet the required actions within the TS completion time. The discretion allowed the licensee to re-establish operability through compensatory measures and established criteria for continued operation of the facility as longer-term corrective actions were implemented.

On March 29, 2017, the licensee initiated condition reports (CRs) CR-PLP-2017-01248, CR-PLP-2017-01249, CR-PLP-2017-01250, CR-PLP-2017-01251, CR-PLP-2017-01252, and CR-PLP-2017-01253, identifying multiple nonconforming conditions of their site-specific licensing basis. Specifically, the licensee identified multiple non-conforming conditions related to inadequate tornado-generated missile protection. The licensee declared multiple SSCs inoperable, promptly implemented interim compensatory measures, and subsequently exited the TS LCO action statements based upon NRC EGM 15-002 guidelines. The NRC documented additional information in Integrated Inspection Report 05000255/2018001.

On January 20, 2020, the licensee completed a tornado missile nonconformance review to document the licensing basis for Palisades tornado missile protection features, specifically regarding the non-conforming issues identified as a result of NRC Regulatory Issue Summary 2015-06. The licensees review concluded that the previously identified non-conforming issues were, in fact, conforming to the current licensing basis. As such, the licensee concluded that corrective actions were not required to restore compliance.

The inspectors reviewed the licensees nonconformance review documented in Engineering Change (EC) 85113, condition reports initiated by the licensee, historic NRC correspondence, aspects of the original conditional operating license and final operating license, the original FSAR, the UFSAR, related safety evaluation report correspondence, the incorporation of the Systematic Evaluation Program into the current licensing basis and other documents provided in the documents reviewed section of this report. Consistent with the licensees review documented in EC 85113, the inspectors did not identify any non-conforming conditions, findings or violations. As a result, no corrective actions are required and EA-17-115 is considered closed.

Observation: Semi-Annual Trend Review 71152 The inspectors review was focused on human performance issues, but also considered the results of daily inspector CAP item screening and licensee trending efforts. The inspectors review nominally considered the 6-month period of January 2020 through June 2020, although some examples expanded beyond those dates when warranted by the scope of the trend.

The inspectors reviewed condition reports, trend reports, and human performance evaluations to address performance oversight at the site. During the inspection period, the NRC inspectors noted a few challenges where low-level human performance errors occurred in multiple departments, including Operations, Maintenance, Security, and Training.

Examples included the operation of a breaker failure relay during maintenance activities which resulted in an unexpected trip of the switchyard 345 kV rear bus, not all required sections of Simulator Exercise Guide (SEG) being covered during the Licensed Operator initial simulator training, a level-3 tagging error, a missed window to block MSIV closure, and an unplanned water transfer to SIRWT. Although the above examples did not challenge safety function or equipment reliability, these issues illustrated a decline in the use of human performance tools, which could potentially impact nuclear safety.

The licensee appropriately entered these issues into the CAP and completed timely evaluations addressing each challenge listed above. Corrective actions included training, site-wide communications reinforcing standards and expectations, and a re-emphasis on the following human performance tools: pre-job briefs; procedure use and adherence; and verification and validation activities. The inspectors determined that the corrective actions taken to date appeared to be effective at addressing the identified gaps and plan to continue to evaluate these actions during routine observations and inspections.

Observation: Letdown Relief Valve Lift Adverse Condition Analysis Review 71152 The inspectors reviewed the events, circumstances, and causal evaluation associated with the letdown relief valve, RV-2006, lift that occurred on February 25, and again on March 4, 2020. Their efforts included assessing the licensee's Failure Mode Analysis (FMA),troubleshooting, trending, and aggregate review activities. Additionally, the inspectors reviewed primary coolant system leakage trends, equipment condition assessments for the letdown system, monthly containment tour results, and quench tank level monitoring. The inspectors also interviewed operators, maintenance workers, and engineering personnel to complete their assessment efforts. In their review, the inspectors noted that the direct cause of relief valve lift was attributed to a localized pressure transient in the letdown system resulting from the intermediate letdown pressure controller timing sensitivity coupled with gas void collapse at the relief valve seat. For corrective actions, the licensee replaced RV-2006 and re-tuned the intermediate letdown pressure controller, which resulted in stabilizing system pressure. Therefore, since the licensee sufficiently determined the direct cause of relief valve lift and successfully completed corrective actions, the inspectors concluded the licensee actions taken were timely and effective commensurate with safety significance.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On July 23, 2020, the inspectors presented the integrated inspection results to Mr. D. Corbin, Site Vice President, and other members of the licensee staff.
  • On May 13, 2020, the inspectors presented the radiation protection inspection results to Mr. D. Corbin, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Corrective Action

Documents

CR-PLP-2020-

01398

Boot Seals on South Wall (Containment) of Room 121 A

(Dog House)

05/01/2020

CR-PLP-2020-

01864

Lake Michigan Level has Potentially Exceeded the Design

Basis Elevation of 583.2 ft MSL

06/10/2020

Engineering

Changes

EC 0000029653

Revise Flooding Analysis to Reflect Changes in Plant

Configuration

Revision 0

Miscellaneous

Engineering

Information

Record 51-

26987-000

Palisades Nuclear Plant Flooding Hazard Re-Evaluation

Report

05/09/2015

PNP 2015-018

Required - Response 2 for Near-Term Task Force

Recommendation 2.1: Flooding - Hazard Re-Evaluation

Report

03/11/2015

71111.04

Corrective Action

Documents

CR-PLP-2020-

295

During Walkdown of EDG 1-1 Noted that Flexible Piping for

Crankcase Exhaust Motors was Degrading

04/23/2020

CR-PLP-2020-

01381

While Performing Maintenance in the Aux Feed Pump

Room, I&C Technicians Noticed Water Running Down the

Wall

04/30/2020

CR-PLP-2020-

01418

1-1 Diesel Generator Found that the Number 7L Petcock

was Spinning Freely When he Attempted to Open it

05/04/2020

CR-PLP-2020-

01806

Received EK-1319, Safety Injection Tank T-82B Hi-Lo Level

Unexpectedly

06/05/2020

CR-PLP-2020-

01861

MO-3045, Safety Injection Tank T-82B Outlet Isolation Valve

06/10/2020

CR-PLP-2020-

01883

PT-0510, Turbine Bypass Valve Controller Pressure for

CV-0511 Turbine Bypass Valve

06/11/2020

CR-PLP-2020-

01884

P-8D Diesel Driven Aux Feedwater Pump

06/11/2020

CR-PLP-2020-

01911

Nitrogen Station 5 Bottle Station has a Leak Somewhere

Causing Lowering Station Pressure

06/15/2020

CR-PLP-2020-

01915

PI-3027 HP Air to CV-3027 Actuator is Reading 192 psig,

eSOMS Limit is 190 psig

06/15/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-PLP-2020-

01916

Observed Water Leaking from Overhead Drain Header Line

06/15/2020

Corrective Action

Documents

Resulting from

Inspection

CR-PLP-2020-

01969

NRC Inspector Noted a Discrepancy Between In-Plant

Labeling and a Table in SOP-3 Attachment 18.

06/22/2020

Procedures

SOP-3,

18

Engineered Safeguard Administrative Control Verification

Revision 106

71111.05

Corrective Action

Documents

CR-PLP-2020-

01406

Fire Protection Check Sheet Annual Inspection Sticker was

Past Due

05/03/2020

CR-PLP-2020-

01869

P-8D, Diesel Driven Aux Feedwater Pump

06/10/2020

Fire Plans

Pre-Fire Plan 1

Control Room Elev 625'

Revision 5

71111.11Q Procedures

PSLEG-LOR-

20B-04

TG Synch Scenario

Revision 2

71111.12

Corrective Action

Documents

CR-PLP-2019-

0152

Received Alarm EK-0748, Reactor Water Low Level

Indication LIA-0105 Alarm

01/11/2019

CR-PLP-2020-

00032

CA-03 Maintenance Rule (a)(1) Evaluation Component

Failure Performance Criteria Exceeded on PCS/PZR

Instrumentation

01/28/2020

CR-PLP-2020-

01148

Water and Oil Mixture on the Floor of SFP Heat Exchanger

Room

04/11/2020

CR-PLP-2020-

01155

P-67A(LPSI Pump) has Boron Precipitate on Studs/Nuts at

Motor/Pump Interface

04/13/2020

CR-PLP-2020-

01176

CV-2056 Failure to Align to Clean Waste Receiver Tank

04/15/2020

CR-PLP-2020-

227

'A' Charging Pump Speed Elevated from Previous

Indications During CVCS Double Charging and Letdown

04/18/2020

CR-PLP-2020-

01320

Thermal Margin Monitor (TMM) PY-0102C Repeat

Functional Failure

04/27/2020

CR-PLP-2020-

01400

Time Displayed on the Three Recently Replaced LCD

Thermal Margin Monitor Screens (B/C/D) is One Hour Later

than Actual Time

05/02/2020

71111.12

Corrective Action

Documents

CR-PLP-2020-

01937

Chemical & Volume Control System (CVC-CVC) has

Exceeded its Maintenance Rule Reliability Performance

Criteria

06/17/2020

Miscellaneous

PZR System Health Report 2Q2018

04/01/2018 -

06/30/2019

PZR System Health Report 4Q2018

10/01/2018 -

2/31/2018

PZR System Health Report 2Q2019

04/01/2019 -

06/30/2019

PZR System Health Report 4Q2019

10/01/2019 -

2/31/2019

PCS System Health Report 2Q2019

04/01/2019 -

06/30/2019

PCS System Health Report 2Q2018

04/01/2018 -

06/30/2018

PCS System Health Report 4Q2018

10/01/2018 -

2/31/2018

PCS System Health Report 4Q2019

04/01/2019 -

06/30/2019

WT-WTPLP-

2017-00011

CA-81 Proposed New Maintenance Rule Functional Failure

Performance Criteria for Primary Coolant System

Instruments

08/11/2017

71111.13

Corrective Action

Documents

CR-PLP-2020-

264

Steam Leak Identified on CV-0711 Feed Pump P-1A

Recirculation

04/22/2020

CR-PLP-2020-

01522

Integrated Risk for RI-95B, Aux Feedwater Flow FT-0749

Instrument Loop Calibration was Reclassified on the Day of

Execution

05/12/2020

Drawings

M-202

Chemical & Volume Control System Piping & Instrument

Diagram

Revision 62

M-207

Feedwater & Condensate System Piping & Instrument

Diagram

Revision 53

Miscellaneous

Adverse

Condition and

Monitoring Plan

for WO 543553

CV-0711, Feed Pump P-1A Recirculation, Steam Leak

04/22/2020

71111.15

Corrective Action

CR-PLP-2017-

Service Water System Tornado Missile Nonconformance

03/29/2017

Documents

248

Issue

CR-PLP-2017-

249

Fuel Oil System Tornado Missile Nonconformance Issue

03/29/2017

CR-PLP-2017-

250

Emergency Diesel Generator Tornado Missile

Nonconformance Issue

03/29/2017

CR-PLP-2017-

251

Control Room Ventilation System Tornado Missile

Nonconformance Issue

03/29/2017

CR-PLP-2017-

252

Steam Driven Auxiliary Feedwater Pump Tornado Missile

Nonconformance Issue

03/29/2017

CR-PLP-2017-

252

Component Cooling Water System Tornado Missile

Nonconformance Issue

03/29/2017

CR-PLP-2018-

00556

Additional Component Cooling Water System Tornado

Missile Vulnerability

01/31/2018

CR-PLP-2020-

00740

Thermal Margin Monitor (TMM) Screen is Showing Double

Numbers on Top of Each Other

03/04/2020

CR-PLP-2020-

242

Operability of the Class EC-2 Piping

04/20/2020

CR-PLP-2020-

2077

Small Packing Leak from CV-1656

06/29/2020

Engineering

Changes

EC 0000085113

Tornado Missile Nonconformance Review

01/29/2020

Miscellaneous

NUREG-0820

Integrated Plant Safety Assessment Systematic Evaluation

Program Palisades Plant

10/01/1982

NUREG-0820

Supplement 1

Integrated Plant Safety Assessment Systematic Evaluation

Program Palisades Plant

11/01/1983

NUREG-1424

Safety Evaluation Report Related to the full-term Operating

License for Palisades Nuclear Plant

11/01/1990

Operability

Evaluations

CR-PLP-2020-

01988

Pressurizer Heater Friction Block Operability Evaluation

06/23/2020

Procedures

QI-25

Thermal Margin Monitor Constant Checks

03/05/2020

Work Orders

00531075

PY-0102D; Replace Components and Reset Error Code 75,

QI-25

10/10/2019

00540421-01

PY-0102A; Replace Video Card and Other Components as

Needed

03/16/2020

71111.18

Corrective Action

Documents

CR-PLP-2020-

01118

Received Alarm EK-0545 Preferred AC Bus No. 2

Unexpectedly

04/08/2020

Operability

Evaluations

EN-LI-113

Licensing Basis Document Change Process

Revision 19

Procedures

EN-LI-100

Process Applicability Determination

Revision 29

Work Orders

00541712

CV-0944A Install Packing Follower Temp Block

04/06/2020

71111.19

Corrective Action

Documents

CR-PLP-2020-

248

Y-Phase Pole on Breaker 52-2624 (Condensing Unit VC-10

for Air Handling Unit V-96) Failed Instantaneous Overcurrent

Testing

04/21/2020

CR-PLP-2020-

275

During Inspection of PO-1712 (Modulating Damper D-21

Positioner), Electricians Observed that the Locking Nuts and

Feedback Arm were Loose on the Shaft

04/22/2020

Engineering

Changes

EC 86710

Temporary Leak Repair of the Pressure-Seal Body-to-

Bonnet Joint on Main Feedwater Pump (P-1A) Recirculation

Valve CV-0711

04/28/2020

Miscellaneous

Field Change

Request 86817

Installation Adjustments for EC-86710 Temporary Leak

Repair of the Pressure-Seal Body-to-Bonnet Joint on Main

Feedwater Pump (P-1A) Recirculation Valve CV-0711

Revision 0

Procedures

MO-33

Control Room Ventilation Emergency Operation

04/22/2020

Work Orders

0052856686

2-2624 (VC-10) OPS PMT

04/21/2020

00534222-03

3Y-8; New HGA Relay for VC-10 PMT

04/21/2020

00543553-01

CV-0711 - P-1A Recirc Valve

04/28/2020

00543843-02

CV-2004, OPS PMT

05/06/2020

71111.22

Corrective Action

Documents

CR-PLP-2020-

247

Cylinder Exhaust Temperature for 9R Cylinder was Found

Low Out of Specification

04/21/2020

CR-PLP-2020-

280

Relay for High Pressure Safety Injection (HPSI) P-66A

Protection was Found to Have its High Dropout, Dropout

Low

04/22/2020

CR-PLP-2020-

01970

SPI Control Rod Position Indication

06/22/2020

Procedures

MO-7A-2

Emergency Diesel Generator 1-2

04/21/2020

QI-3

Reactor Protection Matrix Logic Tests

Revision 7

QO-42

Inservice Testing of Shutdown Cooling Control Valves

Revision 24

QO-42

11

Mode 1, 2, or 3 (Greater than 325°F) Valve Exercising

Stroke Time Data Sheet

06/10/2020

Work Orders

0052910968-01

MO-7A-2 Emergency Diesel Generator 1-2 (K6B)

04/06/2020

0052925885-01

QO-42 IST Shutdown Cooling Valves

06/10/2020

71124.03

Corrective Action

CR-PLP-2019-

PortaCount Suspicious Fit Factor Warning Received

03/19/2019

Documents

01160

Miscellaneous

FPF-GET-RPT

2

MSA Powered Air Purifying Respirator Practical

Revision 29

MED FPEX-MED-

PHYRSP

Respirator Medical Evaluation Records for Various

Individuals

Various

Dates

N/A

Posi3 USB Test Results for Scott Air-Paks 0867 and 1681

09/04/2019

N/A

Posi3 USB Test Results for Scott Air-Pak 1685

09/05/2019

PL-TRN19-2924

SCBA Practical and Fit Test

2/13/2019

PL-TRN20-0563

SCBA Practical and Fit Test

04/07/2020

PL-TRN20-0570

SCBA Practical and Fit Test

04/07/2020

PLLP-FBT-

SCOTTSCBA75

Training for Scott Air-Pak Self Contained Breathing

Apparatus

Revision 06

WI-RSD-T-008

SCBA Inspection Log

03/13/2020

Procedures

EN-RP-502

Inspection and Maintenance of Respiratory Protection

Equipment

Revision 10

EN-RP-505

PortaCount Respirator Fit Testing

Revision 07

Radiation Work

Permits (RWPs)

20190310

Forced Outage Containment Decontamination Activities

Revision 00

20190318

Pressurizer Spray Valve CV-1057 Maintenance

Revision 02

Work Orders

2906597

B5B SCBA Breathing Air Systems

2/20/2020

2907638

Respiratory Protection Equipment Inspection

04/09/2020

71124.04

Corrective Action

Documents

CR-PLP-2019-

00857

Dose Rate Alarm During Charging Pump Work

2/27/2019

Corrective Action

Documents

Resulting from

Inspection

CR-HQN-2020-

01009

EN-RP-206 Potential Causes for Dosimetry Discrepancies

High-E Code Value Low

05/11/2020

CR-PLP-2020-

01517

Dosimetry Discrepancies and Ag-110m

05/12/2020

Miscellaneous

EN-RP-203,

9.3

Dosimetry Investigation Report for Various Individuals

2/27/2020

PLP-RPT-19-009

Update to TID 2015-008 rev 5, Palisades Dosimetry

Background Performance

Revision 0

Procedures

EN-RP-210

Area Monitoring Program

Revision 1

Work Orders

2814864

TLD Monitoring Program

04/01/2019

71151

Corrective Action

Documents

CR-PLP-2020-

01041

The Monthly Performance Indicator (PI) for Critical Scope

Survival and Schedule Completion Changed from Green to

Red for the Month of March 2020

04/01/2020

Miscellaneous

4Q2019 NRC Performance Indicators

10/01/2019 -

2/31/2019

3Q2019 NRC Performance Indicators

07/01/2019 -

09/30/2019

2Q2019 NRC Performance Indicators

04/01/2019 -

06/30/2019

1Q2020 NRC Indicator Safety System Functional Failures

01/01/2020 -

03/31/2020

4Q2019 NRC Indicator Safety System Functional Failures

10/01/2019 -

2/31/2019

3Q2019 NRC Indicator Safety System Functional Failures

07/01/2019 -

09/31/2019

2Q2019 NRC Indicator Safety System Functional Failures

04/01/2019 -

06/30/2019

1Q2020 NRC Performance Indicators

01/01/2020 -

03/31/2020

71152

Corrective Action

Documents

CR-PLP-2019-

03474

Inadvertent Water Transfer from SFP to SIRWT

09/05/2019

CR-PLP-2020-

00611

RV-2006 Lifted Unexpectedly During Plant Evolution

04/14/2020

CR-PLP-2020-

00696

Palisades Oversight of Switchyard Activities

03/02/2020

CR-PLP-2020-

284

Received Alarm EK-0704, Letdown Heat Exch Tube Inlet Hi-

Lo Press Unexpectedly

04/22/2020

CR-PLP-2020-

01314

Received EK-0704, Letdown Heat Exch Tube Hi-Lo Press

Momentarily While Lowering Charging Letdown per SOP-2A

04/26/2020

CR-PLP-2020-

01818

The PPC Shows a Declining Tave Trend on the "8 Hour"

and "Day" Trend Time Frames

06/06/2020

CR-PLP-2020-

01938

Quench Tk Level and Pressure Along with a Rise in

Temperature on RV-2006 Intermediate Letdown Relief Valve

06/17/2020

CR-PLP-2020-

01950

On 06/04/2020 Quench Tank Pressure Started Rising at a

Rate of Approximately 1.2 psig/day

06/17/2020

Miscellaneous

DPRM/APRM Report

2/2020

DPRM/APRM Report

11/2019

71152

Procedures

EN-LI-102

Corrective Action Program

Revision 40

EN-LI-118

Casual Analysis Process

Revision 31

Work Orders

0052910968-01

MO-7A-2 Emergency Diesel Generator 1-2 (K-6B)

04/06/2020