IR 05000255/2019004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000255/2019004 and 07200007/2019001
ML20028D909
Person / Time
Site: Palisades  
Issue date: 01/28/2020
From: Billy Dickson
NRC/RGN-III/DRP/B2
To: Corbin D
Entergy Nuclear Operations
References
IR 2019001, IR 2019004
Download: ML20028D909 (27)


Text

January 28, 2020

SUBJECT:

PALISADES NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000255/2019004 AND 07200007/2019001

Dear Mr. Corbin:

On December 31, 2019, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Palisades Nuclear Plant. On January 15, 2020, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Billy C. Dickson, Jr, Chief Branch 2 Division of Reactor Projects

Docket No. 05000255; 07200007 License No. DPR-20

Enclosure:

As stated

Inspection Report

Docket Number:

05000255; 07200007

License Number:

DPR-20

Report Number:

05000255/2019004; 07200007

Enterprise Identifier: I-2019-004-0054; I-2019-001-0115

Licensee:

Entergy Nuclear Operations, Inc.

Facility:

Palisades Nuclear Plant

Location:

Covert, Michigan

Inspection Dates:

October 01, 2019 to December 31, 2019

Inspectors:

J. Cassidy, Senior Health Physicist

J. Dalzell, Health Physicist

R. Edwards, Senior Health Physicist

E. Fernandez, Reactor Inspector

G. Hansen, Sr. Emergency Preparedness Inspector

P. Laflamme, Senior Resident Inspector

V. Myers, Senior Health Physicist

J. Winslow, Resident Inspector

Approved By:

Billy C. Dickson, Jr, Chief

Branch 2

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Palisades Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000255/2018-003-01 LER 2018-003-01 for Palisades Nuclear Plant,

Indications Identified in Reactor Pressure Vessel Head Nozzle Penetrations 71153 Closed

PLANT STATUS

The plant began the inspection period at rated thermal power, and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed plant status activities described in IMC 2515, Appendix D, Plant Status, and conducted routine reviews using IP 71152, Problem Identification and Resolution. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures for the following systems during the week of November 11, 2019:

Auxiliary Feedwater (AFW) and Service Water

Impending Severe Weather Sample (IP Section 03.03) (1 Sample)

(1) The inspectors evaluated readiness for impending adverse weather conditions for a high wind warning on November 27, 2019

71111.04Q - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Right Train Component Cooling Water (CCW) during maintenance and testing of P-52A on October 9, 2019
(2) Left and Right Train Emergency Diesel Generators (EDGs) during P-7A Service Water Pump replacement on October 24 and 25, 2019
(3) P-8 Motor Driven AFW system during P-8C AFW scheduled maintenance on October 30, 2019

71111.05A - Fire Protection (Annual)

Annual Inspection (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated fire brigade performance during a drill on November 8, 2019

71111.05Q - Fire Protection

Quarterly Inspection (IP Section 03.01) (3 Samples)

The inspectors evaluated fire protection program implementation in the following selected areas:

(1) Fire Area 23; Turbine Building - South Area on October 24, 2019
(2) Fire Area 9; Screen House/Intake Structure during P-7A replacement on October 25, 2019
(3) Fire Area 10; East Engineered Safeguards Room on November 29, 2019

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 02.02a.) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) 1D Switchgear Room, Cable Spreading Room, and Battery Rooms on December 30 and 31, 2019

71111.07A - Heat Sink Performance

Annual Review (IP Section 02.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) 1-2 EDG Jacket Water Heat Exchanger on December 23, 2019

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification biennial written examinations and annual operating tests administered from February 18 through March 22, 2019.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated Licensed Operator Requalification Training PLSEG-LOR-19E-01 on November 25, 2019

71111.12 - Maintenance Effectiveness

Routine Maintenance Effectiveness Inspection (IP Section 02.01) (2 Samples)

The inspectors evaluated the effectiveness of routine maintenance activities associated with the following equipment and/or safety significant functions:

(1) Power supplies associated with the AFW actuation system during the week of December 16, 2019
(2) Reactor Protection System during the week of December 16, 2019

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated the risk assessments for the following planned and emergent work activities:

(1) Emergent troubleshooting and repairs following Source Range Neutron Flux Instrument Channel 1/3 Power Supply failure during the week of October 1, 2019
(2) Elevated risk during scheduled 7A Service Water Pump replacement and testing during the week of October 21, 2019
(3) Emergent troubleshooting and repairs following trip of VC-10 Control Room Heating, Ventilation, and Air Conditioning (HVAC) Condensing Unit and unplanned Limiting Condition for Operations (LCO) during the week of November 4, 2019

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 02.02) (4 Samples)

The inspectors evaluated the following operability determinations and functionality assessments:

(1) Evaluation of NI-1/3A Failure during the week of October 7, 2019 (2)1-1 EDG Turbocharger Operability as documented in CR-PLP-2019-004060 on October 17, 2019
(3) Evaluation of acceptability for carbon steel nuts on P-7A Service Water Pump as documented in CR-PLP-2019-04275 on October 24, 2019.
(4) Evaluation of loose shim packs on discharge head to floor connection of P-7A Service Water Pump as documented in CR-PLP-2019-04832 on December 9, 2019

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Engineering Change (EC) 83228, Removal of Service Water Pump Lateral Restraints on November 22, 2019

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the following post maintenance tests:

(1) RI-99 after replacement of Source Range Neutron Flux Power Supply on October 2, 2019
(2) MO-7A1 following A1 starting air pressure controller (PCV-1479) on October 7, 2019
(3) QO-19 after P-66B motor testing on October 16, 2019
(4) QO-14 after P-7A motor replacement on October 24, 2019

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) QO-21C; P-8C AFW System Test on October 30, 2019
(2) QO-16B; P-54B Containment Spray Test on November 5, 2019
(3) RT-71M; Class 2 Inservice Test for Safety Injection and Refueling Water Tank on November 20, 2019

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspector completed the evaluation of submitted Emergency Action Level and Emergency Plan changes on November 25, 2019. This evaluation does not constitute NRC approval.

RADIATION SAFETY

71124.01 - Radiological Hazard Assessment and Exposure Controls

Radiological Hazard Assessment (IP Section 02.01) (1 Sample)

The inspectors evaluated radiological hazards assessments and controls.

(1) The inspectors reviewed the following:

Radiological Surveys

  • 649' Spent Fuel Pool Area
  • East Safeguards Area
  • 590' Primary System Drain Tank Pump Room

Risk Significant Radiological Work Activities

  • Dry Fuel Storage Campaign - Loading Cask
  • Offline Electrical Motor Testing
  • PLP-AS-100819-0689
  • PLP-AS-101119-0707
  • PLP-AS-101119-0708

Instructions to Workers (IP Section 02.02) (1 Sample)

The inspectors evaluated instructions to workers including radiation work permits used to access high radiation areas.

(1) The inspectors reviewed the following:

Radiation Work Packages

===20190107 - Decontamination and Housekeeping Activities in Locked High Radiation/High Radiation Areas/High Contamination Areas

  • 20190240 - Dry Fuel Storage Campaign - Preparation, Loading, and Demobilization

Electronic Alarming Dosimeter Alarms

  • Error 70111 11/25/2018 04:55

Labeling of Containers

  • Hose Storage Box 649' Spent Fuel Pool
  • Areva Camera Equipment 649' Spent Fuel Pool
  • Crane Control Tool Box 649' Spent Fuel Pool
  • Contaminated Drum 625' Track Alley
  • High Efficiency Particulate Air Vacuum Cleaners 625' Storage Area

Contamination and Radioactive Material Control (IP Section 02.03)===

The inspectors evaluated licensee processes for monitoring and controlling contamination and radioactive material.

(1) The inspectors verified the following sealed sources are accounted for and are intact:
  • CE-9848
  • 87-CS-S-18

Radiological Hazards Control and Work Coverage (IP Section 02.04) (1 Sample)

The inspectors evaluated in-plant radiological conditions during facility walkdowns and observation of radiological work activities.

(1) The inspectors also reviewed the following radiological work package for areas with airborne radioactivity:
  • No work packages were available for review during this inspection.

High Radiation Area and Very High Radiation Area Controls (IP Section 02.05) (1 Sample)

(1) The inspectors evaluated risk-significant high radiation area and very high radiation area controls.

Radiation Worker Performance and Radiation Protection Technician Proficiency (IP Section 02.06) (1 Sample)

(1) The inspectors evaluated radiation worker performance and radiation protection technician proficiency.

71124.02 - Occupational ALARA Planning and Controls

Radiological Work Planning (IP Section 02.01) (1 Sample)

The inspectors evaluated the licensees radiological work planning.

(1) The inspectors reviewed the following activities:
  • 2018-0434; Reassembly of the Reactor Head and Associated Work Activities
  • 2018-0444; Removal/Installation of Control Rod Drive Seal Housing Packages and Removal/Installation of Drive Motors
  • 2018-0450; Under Head Repair

Verification of Dose Estimates and Exposure Tracking Systems (IP Section 02.02) (1 Sample)

The inspectors evaluated dose estimates and exposure tracking.

(1) The inspectors reviewed the following as low as reasonably achievable planning documents:
  • 2018-0434; Reassembly of the Reactor Head and Associated Work Activities
  • 2018-0444; Removal/Installation of Control Rod Drive Seal Housing Packages and Removal/Installation of Drive Motors
  • 2018-0450; Under Head Repair

71124.05 - Radiation Monitoring Instrumentation

Calibration and Testing Program (IP Section 02.02) (1 Sample)

The inspectors evaluated the calibration and testing program implementation.

(1) The inspectors evaluated the calibration program for the containment high range radiation monitors. These activities supplement those in inspection report

===05000255/2019002 and constitute a complete sample.

71124.08 - Radioactive Solid Waste Processing and Radioactive Material Handling, Storage,

and Transportation

Radioactive Material Storage (IP Section 02.01)

The inspectors evaluated radioactive material storage.

(1) The inspectors toured the following areas:
  • East Radioactive Waste Building
  • South Storage Building
  • Refueling Outage Materials Pole Barn

The inspectors performed a container check (e.g., swelling, leakage and deformation)on the following containers:

  • 4 Boxes outside East Radioactive Waste Building
  • 3 Boxes inside East Radioactive Waste Building
  • 2 Boxes Inside South Storage Building
  • 3 Boxes Inside Refueling Outage Materials Pole Barn
  • 1 High Integrity Container Outside the Steam Generator Blowdown Resin Vessels

Radioactive Waste System Walkdown (IP Section 02.02)===

The inspectors evaluated the following radioactive waste processing systems [and processes] during plant walkdowns:

(1) Liquid or Solid Radioactive Waste Processing Systems
  • Advanced Liquid Processing System
  • M-18 Sludge and Waste Oil Collection

Radioactive Waste Resin and/or Sludge Discharges Processes

  • Advanced Liquid Processing System

Waste Characterization and Classification (IP Section 02.03) (1 Sample)

The inspectors evaluated the radioactive waste characterization and classification for the following waste streams:

(1)

  • Dry Active Waste
  • Advanced Liquid Processing System Resins
  • Tank 100 Resins

Shipment Preparation (IP Section 02.04) (1 Sample)

The inspectors evaluated the following radioactive material shipment preparation processes:

(1) The inspectors evaluated training and qualification records for selected individuals due to limited observation of the radioactive material shipment preparation process.

Shipping Records (IP Section 02.05) (1 Sample)

The inspectors evaluated the following non-excepted package shipment records:

(1)

  • 2017-RW-017
  • 2018-RW-004
  • 2018-RW-007
  • 2018-RW-011

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) Unit 1 (October 1, 2018 - September 30, 2019)

MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)

(1) Unit 1 (October 1, 2018 - September 30, 2019)

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in critical component failures that might be indicative of a more significant safety issue.

Annual Follow-up of Selected Issues (IP Section 02.03) (1 Sample)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Human performance issues associated with the failure to block the main steam isolation valve (MSIV) closure interlock within the required band on July 28, 2019, as documented in CR-PLP-2019-02920 and the unplanned transfer of water to the safety injection and refueling water tank (SIRWT) on September 4, 2019, as documented in CR-PLP-2019-03474.

71153 - Followup of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000255/2018-003-01, Indications Identified in Reactor Pressure Vessel Head Nozzle Penetrations (ADAMS accession: ML19210D347)

The inspectors reviewed the updated LER submittal. The previous LER submittal was reviewed in Inspection Report 05000255/2019002 Sections 71111.08 and

===71153. The inspectors concluded that no additional violations of NRC requirements occurred.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

60855.1 - Operation of an Independent Spent Fuel Storage Installation at Operating Plants

Operation of an Independent Spent Fuel Storage Installation at Operating Plants===

(1) The inspectors evaluated the licensees independent spent fuel storage installation cask loading activities on September 30th through October 4th. Specifically, the inspectors observed the following activities;
  • Installation of the transfer cask (HI-TRAC) lid
  • Alternate cooling operations
  • Canister processing including bulk water removal (blowdown) and forced helium dehydration
  • Vent and drain port cover welding and non-destructive weld evaluations
  • Radiological field surveys

The inspectors performed walkdowns of the East and North ISFSI pads, including independent radiation surveys, and walkdowns of the ISFSI haul path and vertical cask transporter (VCT).

The inspectors evaluated the following:

  • Spent fuel selection for the three casks for this loading campaign
  • Selected corrective action program action requests
  • Selected 72.48 screenings and evaluations

INSPECTION RESULTS

Assessment 71152 The inspectors reviewed evaluations associated with two human performance errors documented in the corrective action program (CAP), including completed and planned corrective actions and effectiveness reviews. On July 28, 2019, during plant cooldown from Mode 3 to Mode 5, the licensee failed to block the main steam isolation valve (MSIV) closure interlock within the required band per procedure. No valve actuations occurred as a result of the failure to block the interlock because previous operator actions closed both MSIVs. The licensee's investigation of the issue revealed that Operations personnel were aware of the procedure step, but prioritized a required step to block the safety injection signal (SIS) prior to blocking the MSIV closure interlock because they believed there was enough time to block SIS then block the MSIV closure interlock. Following completion of blocking the SIS, the operators identified that steam generator pressures were below the required band for blocking the MSIV closure interlock. The operators verified system logic and blocked the MSIV closure interlock.

On September 4, 2019, the licensee identified that a valve was not closed as required per procedure SOP-27, "Fuel Pool System" during a change in system configuration. This resulted in the unplanned transfer of water from the spent fuel pool to the safety injection and refueling water tank (SIRWT). The operators verified all valve positions associated with the evolution and identified that MV-SFP127, spent fuel pool (SFP) demineralizer T-50 outlet to SIRWT, was partially open when it should have been closed. The operators then closed MV-SFP127 to establish the appropriate system configuration. The inspectors reviewed the licensee's final adverse condition analysis, and discussed the results of the analysis with the licensee.

Additional corrective actions from the evaluations included communicating lessons learned from these events with all operating crews. The inspectors determined that the corrective actions were appropriate and timely based on the safety significance of the issues.

Minor Violation 71152 Minor Violation: The inspectors reviewed CR-PLP-2019-03474 associated with the unplanned transfer of water to the SIRWT. The licensee identified that standard operating procedure SOP-27, "Fuel Pool System," was not implemented as written. Specifically, on September 4, 2019, operators did not implement step 7.3.4(e)(2), which states to "close and lock MV-SFP127," as written. This resulted in the inadvertent transfer of water from the spent fuel pool to the SIRWT. Standard operating procedure SOP-27 provides instructions for operation of the spent fuel pool system as discussed in Regulatory Guide 1.33, Revision 2, Appendix A, Section 3.h. The inspectors identified this as a minor violation of Technical Specification (TS) 5.4.1.a. Licensee staff documented this issue in their CAP as CR-PLP-2019-03474.

Screening: The inspectors determined the performance deficiency was minor. Consistent with the guidance in IMC 0612, "Power Reactor Inspection Reports," Appendix B, "Issue Screening," the inspectors determined that the performance deficiency was not a finding of more than minor significance based on answering 'No' to all of the more-than-minor screening questions. The inspectors also reviewed the examples of minor issues in IMC 0612, Appendix E, "Examples of Minor Issues," and determined that this issue was most closely related to Example 4.b in that that this was a procedural error that had no safety consequences.

Enforcement:

This failure to comply with TS 5.4.1.a constitutes a minor violation that is not subject to enforcement action in accordance with the NRCs Enforcement Policy.

Minor Violation 71152 Minor Violation: The inspectors reviewed CR-PLP-2019-02920 associated with the failure to block the MSIV closure interlock in the required band. The licensee identified that general operating procedure GOP-9, "Mode 3 > 525F to Mode 4 or Mode 5," was not implemented as written. Specifically, on July 28, 2019, operators did not implement step 3.7, which states "When 3 of 4 associated Steam Generator pressure sigmas indicate between 510 and 550 psia and the indicator is between alarm flags, then depress the associated pushbutton to bypass MSIV closure: HS/LPE-50A, bypass of MSIV closure pushbutton; and HS/LPE-50B, bypass of MSIV closure pushbutton," as written when they did not depress HS/LPE-50A and HS/LPE-50B when 3 of 4 associated Steam Generator pressure sigmas indicated between 510 and 550 psia. General operating procedure GOP-9 provides instructions for general plant operating procedures from hot standby to cold shutdown as discussed in Regulatory Guide 1.33, Revision 2, Appendix A, Section 2.j. The inspectors identified this as a minor violation of TS 5.4.1.a. This issue was documented in the licensee's CAP as CR-PLP-2019-02920.

Screening: The inspectors determined the performance deficiency was minor. Consistent with the guidance in Inspection Manual Chapter (IMC) 0612, "Power Reactor Inspection Reports," Appendix B, "Issue Screening," the inspectors determined that the performance deficiency was not a finding of more than minor significance based on answering 'No' to all of the more-than-minor screening questions. The inspectors also reviewed the examples of minor issues in IMC 0612, Appendix E, "Examples of Minor Issues," and determined that this issue was most closely related to Example 4.b in that that this was a procedural error that had no safety consequences.

Enforcement:

This failure to comply with TS 5.4.1.a constitutes a minor violation that is not subject to enforcement action in accordance with the NRCs Enforcement Policy.

Observation: Semi-Annual Trend Review 71152 The inspectors review focused on critical component failures/ degradation and subsequent challenges to online and equipment reliability, but also considered the results of daily inspector CAP item screening and licensee trending efforts. The inspectors review nominally considered the 6-month period of July 2019 through December 2019, although some examples expanded beyond those dates when warranted by the scope of the trend.

The inspectors reviewed condition reports, trend reports, maintenance rule evaluations, and causal evaluations addressing human performance and equipment reliability at the site.

During the inspection period, the NRC inspectors noted a few challenges to equipment reliability. Specifically, the inspectors observed and reviewed activities associated with thermal margin monitor (TMM) channel C and D screen failures and subsequent inoperabilities, a failed source range power supply to NI Channels 1 & 3 and resultant inoperability, the loss of V-49A, CRDM cooling fan (1 of 2) resulting in slightly higher CRDM seal temperatures, multiple momentary losses of group 2 pressurizer backup heaters, and CRDM #14 & #23 seal degradation coupled with the digital electro-hydraulic system power supply failure and resultant maintenance outage.

For the latter two instances, the inspectors noted that the licensee identified, monitored, and then repaired both equipment issues during a planned maintenance outage July 27-31, 2019.

Regarding the multiple TMM screen failures and subsequent screen replacement, the inspectors noted that the licensee identified their lack of sufficient long-term planning to ensure TMM reliability as a contributing cause. For corrective action, the licensee plans to install new LCD replacement screens of higher quality. The licensee concluded that this will also address the reliability concerns. Although these issues illustrated a challenge to online and equipment reliability, the inspectors did not identify an adverse trend during this assessment period.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 15, 2020, the inspectors presented the integrated inspection results to Mr. D. Corbin, Vice President, Operations, and other members of the licensee staff.
  • On October 4, 2019, the inspectors presented the Radiation Protection Program inspection results to Mr. D. Corbin, Vice President, Operations, and other members of the licensee staff.
  • On October 21, 2019, the inspectors presented the Independent Spent Fuel Storage Installation inspection results to Mr. D. Lucy, Acting Site Vice President and other members of the licensee staff.
  • On November 15, 2019, the inspectors presented the Radiation Protection Program inspection results to Mr. D. Corbin, Vice President, Operations, and other members of the licensee staff.
  • On November 25, 2019, the inspectors presented the Emergency Action Level and Emergency Plan Changes inspection results to Mr. D. Malone and other members of the licensee staff.
  • On December 17, 2019, the inspectors presented the Licensed Operator Requalification program annual examination results review inspection results to Mr. F. Korfias, Operations Exams Superintendent and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

60855.1

ALARA Plans

EN-RP-105

Radiological Work Permits

Corrective Action

Documents

Review of Selected Corrective Action Reports Since

January 2017

CR-PLP-2016-

05475

HI-STORM FW Combustible Controls

11/16/2016

Engineering

Changes

EC-71123

Perform Modification to Change the East Trolley Limit Switch

on L-3 per CR 2016-4562

Miscellaneous

Certificate of Compliance No. 1032, Amendment No. 1

Final Safety Analysis Report on the HI-STORM FW MPC

Storage System

Selected 10 CFR 72.48 and 50.59 ISFSI Related Screenings

and Evaluations Since January 2017

Response to Palisades NRC Inspection Question on

HI-TRAC Lift Bracket Bolt Inspection per HSP-366

10/02/2019

Certificates of Conformance for Purchase Order 107236

08/12/2015

DOC-103-007R2

Leased HI-TRAC VW for Use at Palisades (Entergy)

Documentation Package

09/26/2019

DOC-104-107-

016R1

Leased MPC-37 Lift Bracket for HI-STORM FW

Documentation Package

06/25/2019

DOC-104-209-

018R1

Leased MPC-37 Lift Cleat Documentation Package

06/25/2019

DOC-104-702-

23R1

Leased HI-TRAC VW Lift Yoke to Palisades Documentation

Package

06/25/2019

DOC-104-731-

019R1

Leased MPC Lid Lift Adapter and MPC Lid Lift Rigging

Documentation Package

06/25/2019

DOC-2251-

004R1

Lower Fuel Shims for Palisades Nuclear Plant

Documentation Package

08/09/2019

DTF-3005-015B

Palisades Training Records

09/24/2019

EN-DC-223

MPC Loading Plan for MPC 123, 124 and 125

Revision 4

PROC No.

FSHO-17A

MPC-37 Fuel Verification

10/01/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Report No. PLP

21032

Palisades 10 CFR 72.212 Evaluation Report

09/09/2019

NDE Reports

Report No.

915741-123-01

Report of Visual Non-Destructive Examination

10/04/2010

WO 52844949-01

Annual Crane Liquid Penetrant Examination

08/08/2019

Procedures

AT-36

ISFSI Pad Monitoring Program

AT-9

Examination of Ventilated Concrete Cask Assembly Exterior

GQP - 9.2

High Temperature Liquid Penetrant Examination and

Acceptance Standards for Welds, Base Materials and

Cladding (50° - 350°F)

GQP - 9.6

Visual Examination of Welds

Procedure No.

FHS-M-41B

HI-STORM FW Dry Fuel Loading Operations - MPC Loading

Procedure No.

FHS-M-41C

HI-STORM FW Dry Fuel Loading Operations - MPC Sealing

and Drying

Procedure No.

FHS-M041D

HI-STORM FW Dry Fuel Loading Operations - MPC Transfer

to HI-STORM

Radiation

Surveys

Periodic Radiological Surveys Performed Since

January 2017

Self-Assessments

2019 Readiness Assessment

09/05/2019

QA-20-2018-PLP-

Audit Report: Independent Spent Fuel Storage Installation

07/08/2019

Work Orders

HSP-169

HI-STORM Offloading and Preparation for Site Fabrication

Completion

WO 00517524-04

Limits on Crane are Not Working Properly - Investigate

07/25/2019

WO 52832037

AT-9 Dry Fuel Storage Cask Exterior Inspection

06/04/2019

WO 52832038

AT-36 ISFSI Pad Monitoring Program

07/25/2019

71111.01

Corrective Action

Documents

Resulting from

Inspection

CR-PLP-2019-

04653

NRC Identified Gaps in Insulation

11/21/2019

CR-PLP-2019-

04723

NRC Resident Identified a Cable/Extension Cord Hanging

Over the Edge of the Roof on the North Side of the Turbine

Building

11/27/2019

CR-PLP-2019-

04807

Unsecure Items Identified by the NRC

2/06/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

Certificate of Analysis for T-10A

07/29/2019

Site Certification Letter for Winter Readiness

2019/2020

2019-2020 Winter Weather Contingency Plan

Procedures

AOP-38

Acts of Nature

EN-CY-122

Diesel Fuel Oil Program

EN-FAP-EP-010

7.14, Severe Weather Missile Hazard Reduction

Guidance

SOP-15

Service Water System

SOP-23

Plant Heating System

Work Orders

WO 52848891

Perform Cold Weather Checksheets

10/23/2019

71111.04Q Corrective Action

Documents

CR-PLP-2019-

01047

A Small Puddle of Fuel Oil was Noticed on the Floor Below

MV-FO705, P-18A/B Discharge to FO Day Tank T-40

03/13/2019

CR-PLP-2019-

2813

HP Air Compressor in West Safeguards was Found to Have

a Minor Leak

07/19/2019

CR-PLP-2019-

04084

MV-CC942, Component Cooling Water (CCW) P-52B

Discharge, has Evidence of Past Leakage on the East Side

of the Upper Flange

10/10/2019

CR-PLP-2019-

04344

Observed Roof Leak of ~60-80 Drops per Minute on West

Side of 625' Elevation of Turbine Deck

10/30/2019

CR-PLP-2019-

04369

CK-FW743, Auxiliary Feedwater Pump P-8B has a Body to

Bonnet Leak of 5 Drops per Minute

10/31/2019

Corrective Action

Documents

Resulting from

Inspection

CR-PLP-2019-

04101

NRC Identified a Large Amount of Carbon Build Up on the

Southwest Portion of the Turbocharger

10/11/2019

Drawings

M-214, Sheet 1

Piping & Instrument Diagram, Lube Oil, Fuel Oil, & Diesel

Generator Systems

Miscellaneous

DBD-1.03

Design Basis Document for Auxiliary Feedwater System

Procedures

SOP-12,

14

Auxiliary Feedwater System Checklist

SOP-22

Emergency Diesel Generators

71111.05A

Procedures

EN-TQ-125

PLDRL-FBT-FIREDRILL (19-018)

11/08/2019

EN-TQ-125,

Fire Drill Report

11/15/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.05Q Fire Plans

Pre Fire Plan

Area 10

East Engineered Safeguards Room/ Elevation 570'

Pre Fire Plan

Area 23

Turbine Building - South / Elevation 590'

Pre Fire Plan

Area 9

Screen House / Intake Structure / Elevation 590'

Procedures

EN-DC-161

Control of Combustibles

71111.06

Calculations

EA-C-PAL-95-

26-01

Internal Flooding Evaluation for Plant Areas Outside

Contaiment

3a

Corrective Action

Documents

CR-PLP-2019-

04899

PMID 50083994-02 May Not be Effective

2/13/2019

CR-PLP-2019-

04945

Two of Three Drains in Cable Spreading are Plugged

2/17/2019

71111.07A

Corrective Action

Documents

CR-PLP-2019-

01138

Eddy Current Testing of the E-31B "EDG 1-2 Lube Oil

Cooler"

03/19/2019

Procedures

EPS-M-14A

Diesel Generator Every Cycle Maintenance

03/18/2019

SEP-HX-PLP-001 Supplemental HX Visual Inspection Checklist - Jacket Water

Cooler

03/18/2019

Work Orders

2771367-01

K-6B 1-2 D/G 24 Month PM

03/18/2019

71111.11A

Miscellaneous

Palisades Annual Licensed Operator Requalification

Summary Results for 2019

3/29/2019

71111.11Q Corrective Action

Documents

CR-PLP-2019-

224

The CRT Screen for PY-0102A 'A' Channel Thermal Margin

Monitor is Growing Dim

10/21/2019

CR-PLP-2019-

04476

During Training, Instructor Identified that the InForm

Program was Configured to the "Palisades" Jurisdiction

11/07/2019

71111.12

Corrective Action

Documents

CR-PLP-2018-

05433

EC-187D, AFAS Sensor Channel Cabinet, has No 12 Volt

DC Power

11/02/2018

CR-PLP-2019-

213

Received EK-0137, Auxilary Feedwater AFAS-FOGG

Subsystem Trip

03/23/2019

CR-PLP-2019-

222

P/S-0712 from CR-PLP-2018-05433 was Not Sent to the

Vendor for Failure Analysis

03/25/2019

CR-PLP-2019-

03549

Maintenance Rule (a)(1) Action Plan, Thermal Margin

Monitor (TMM) Displays

2/04/2019

CR-PLP-2019-

PY-0102C: Thermal Margin Monitor Channel 'C' Display has

09/14/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

03687

Dimmed in is now Unreadable

CR-PLP-2019-

04016

Two Maintenance Rule Repeat Functional Failures

Associated with the Thermal Margin Monitors (TMM)

10/07/2019

CR-PLP-2019-

04540

Documented Failures of TMM Circuit Cards

11/14/2019

CR-PLP-2019-

04603

NI-07 Power Range Instrumentation

11/19/2019

CR-PLP-2019-

04739

PY-0102C: Thermal Margin Monitor Channel 'C' Display is

Very Dim

2/02/2019

CR-PLP-2019-

04747

PY-1020D, Thermal Margin Monitor Channel 'D', Varies

more than the Other Channels

2/03/2019

Miscellaneous

System Health

Report

Engineered Safety Features Actuation System

Q2 2019

System Health

Report

Reactor System Protection

Q2 2019

Procedures

EN-DC-205

Maintenance Rule Monitoring

EN-DC-206

Maintenance Rule (a)(1) Process

Work Orders

WO 512169

P/S-0712, Replace AFAS (SCD) Power Supply

2/01/2018

WO 521490

AFAS Trip Alarm Due to P/S-0706 De-Energizing

03/25/2019

WO 521968

P/S-0704, Replace AFAS Power Supply

10/08/2019

WO 521972

P/S-0708, Replace AFAS Power Supply

06/11/2019

71111.13

Corrective Action

Documents

CR-PLP-2019-

03973

NI 1/3A Wide Range Power Display was Found Reading

Approximately 10% Power

10/03/2019

CR-PLP-2019-

04406

VC-10, Control Room HVAC Refrig Condensing Unit Trouble

Light on Panel C-11A

11/02/2019

CR-PLP-2019-

04417

Received Alarm EK-0547, 125V DC Bus Ground

Unexpectedly

11/04/2019

CR-PLP-2019-

04420

VC-10 (Control Room HVAC Refrigeration Condensing Unit)

Bearing was Damaged

11/04/2019

CR-PLP-2019-

04421

VC-10 (Control Room H-VAC Compressor) Under Work Order #533966 has Non-Conforming Parts

11/04/2019

CR-PLP-2019-

04430

Main Exhaust Fan V6A Tripped on Overcurrent

11/04/2019

Procedures

EN-MA-157

Maintenance Configuration Control

10/02/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

RI-99

Left Channel Nuclear Instrumentation Calibrations

10/22/2019

SOP-35

Neutron Monitoring System

Work Orders

WO 531972

NI-1/3A Failed Low

10/1/2019

71111.15

Corrective Action

Documents

CR-PLP-2019-

03911

NI-1/3A, Source & Wide Range Neutron Monitor Ch 1/3,

Appeared to Fail Low

09/30/2019

CR-PLP-2019-

03973

NI-1/3A Wide Range Power Display was Found Reading

Approximately 10% Power

10/03/2019

CR-PLP-2019-

275

Carbon Steel Nuts had been Installed on the Stainless Steel

Studs Between the Pump and the First Column

10/24/2019

CR-PLP-2019-

04832

P-7A Service Water Pump Shim Packs are Loose on

Discharge Head to Floor Connection

2/09/2019

Drawings

E-61, Sheet 2A

Schematic Diagram Source & Wide Range #1/3 Nuclear

Instrumentation

VEN-MI-RA,

Sheet 857

Neutron Flux Monitoring System Source & Wide Range

Channels

Engineering

Changes

EC 27090

Palisades EDG Turbo Support Cracking Report by MPR

Associates

EC 37737

Approval of Spare Service Water Pump Bowl from Hydroaire

and Other Associated Components Not Previously Approved

by Other ECs

EC 84410

Operability Basis Input for Left Train Source/Wide Range

Nuclear Instrumentation, NI-1/3A

EC 84509

Operability Basis Input for EDG 1-1 (Emergency Diesel

Generator) Turbo Mount Cracks

EC 84714

Acceptability for Carbon Steel Nuts between P-7A Pump and

the First Column

EC 85226

Loose Shim on P-7A

Work Orders

WO 506696

P-7A; Replace/Rebuild

10/23/2019

WO 52874649-1

K-6A Turbocharger Support Inspection

10/09/2019

71111.18

Calculations

A13499-C-001

Evaluation of Service Water Pumps P-7A, 7B & 7C to

determine Feasibility of Removing the Lateral Bracket

Support at Elevation 583'

Corrective Action

Documents

CR-PLP-2019-

287

During performance of QO-14A Inservice Test PRocedure-

Service Water Pumps (WO-520027), Motor Outboard

10/25/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Bearing vibration M1Z was measured in the "Alert Range"

CR-PLP-2019-

04705

P-7A, Service Water Pump Outboard Motor Radial M1Z was

recorded in "Alert Range" during QO-14A

11/26/2018

Engineering

Changes

EC 83228

Optional Removal of SW Pump Restraints Below

Floor/Above Water

71111.19

Corrective Action

Documents

CR-PLP-2019-

03990

Adjust A10-R30 in NI-1/3A to Adjust for Present Reactor

Power

10/04/2019

Procedures

QO-14

Inservice Test Procedure - Service Water Pumps

QO-19

Inservice Test Procedure - HPSI Pumps and ESS Check

Valve Operability Test

Work Orders

WO 506696

P-7A; Replace/Rebuild

10/23/2019

WO 520027

QO-14A - P-7A, IST Service Water Pump

10/25/2019

WO 52819026

EEQ - EMA-1113 HPSI Pump P-66B Motor

10/16/2019

WO 52889284

QO-19B - High Pressure Safety Injection Pump & ESS

Check Valve Operation

10/16/2019

WO 531972-05

NI-1/3 Failed Low - Replace Drawer, (RTS)

10/14/2019

71111.22

Corrective Action

Documents

CR-PLP-2019-

04359

Overvoltage Protection for P/S 0737A Work Instructions are

not Adequate for the Task

10/30/2019

CR-PLP-2019-

04367

The PMID has not been Updated to Credit the Installation of

a New Calibrated Gauge as Due 1/22/2020

10/30/2019

CR-PLP-2019-

04428

Temporary Installed Gauges Interfered with the Operation of

DPI-0319B Bypass Valve (IB) Which Caused Delays During

the Test to Adjust the Installed Gauges

11/04/2019

Drawings

M-204

Piping & Instrument Diagram Safety Injection Containment

Spray

VEN-M-107,

Sheet 4

SIRW Tank to Charging Pumps, Stress Isometric 03323

VEN-M107,

Sheet 2278

Stress Isometric Safety Injection, Containment Spray &

Shutdown Cooling System

Operability

Evaluations

QO-21

Inservice Test Procedure - Auxiliary Feedwater Pumps

Procedures

CEP-NDE-0902

VT-2 Examination Checklist for SIRW Tank

11/20/2019

QO-16

Inservice Test Procedure - Containment Spray Pumps

11/04/2019

QO-21

Inservice Test Procedure - Auxiliary Feedwater Pumps

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

RT-71M

Class 2 System Inservice Test for Safety Injection and

Refueling Water Tank

11/20/2019

SOP-12

System Operating Procedure: Feedwater System

10/2/2019

SOP-4

Containment Spray System

Work Orders

WO 52895070

QO-16B-P-54B, I&C Install Test Gauges

11/04/2019

71114.04

Miscellaneous

CFR50.54(Q) Training Documentation Record -

McKinney

03/15/2018

CFR50.54(Q) Training Documentation Record - Howard

11/15/2017

CFR50.54(Q) Training Documentation - Exemption

Approval Form - D. Malone

2/24/2012

CFR 50.54(Q)(3) Screening - Site Emergency Plan

Revision 31

09/18/18

CFR 50.54(Q)(3) Evaluation - Site Emergency Plan

Revision 31

09/18/18

SEP

Site Emergency Plan

Procedures

EN-EP-305

Emergency Planning 10CFR50.54(q) Review Program

SEP

Site Emergency Plan

71124.01

Corrective Action

Documents

CR-PLP-2018-

03839

Gate to T-69 Found Open

0/8/22/20018

CR-PLP-2019-

04491

Increased Dose Rates in Primary System Drain Tank Room

11/09/2019

Procedures

EN-RP-106

Radiological Survey Documentation

EN-RP-121

Radioactive Material Control

EN-RP-131

Air Sampling

EN-RP-143

Source Control

Radiation

Surveys

PLP-1910-00005

590 Primary System Drain Tank Room

10/01/2019

PLP-1910-00074

649 Spent Fuel Pool Area

10/09/2019

PLP-1910-00100

649 Spent Fuel Pool Area

10/12/2019

PLP-1910-00104

East Engineered Safeguards

10/13/2019

PLP-1910-00216

East Engineered Safeguards

10/30/2019

PLP-2011-00028

590 Primary System Drain Tank Room

11/09/2019

PLP-2011-00033

590 Primary System Drain Tank Room

11/11/2019

PLP-2011-00034

590 Primary System Drain Tank Room

11/11/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Radiation Work

Permits (RWPs)

20190107

Decontamination and Housekeeping Activities in Locked

High Radiation/High Radiation Areas/High Contamination

Areas

20190209

Activities Requiring Access to LHRAs

20190240

Dry Fuel Storage Campaign - Loading (MPC-37-05) (MPC-

37-06) (MPC-37-07) and Prep/Demob Activities

Self-Assessments LO-PLPLO-2019-

00011

2019 Radiological Hazard Assessment and Exposure

Controls Self-Assessment

09/18/2019

Work Orders

2738305 01

Perform Annual Rad Source Inventory

2/08/2018

2802850 01

Perform Annual Rad Source Inventory

2/14/2019

2823888 01

Offline Motor Electrical Testing

09/16/2019

71124.02

ALARA Plans

ALARA Plan for RWP 2018-0444

10/17/2018

ALARA Plan for RWP 2018-0454

10/16/2018

ALARA Plan for RWP 2018-0450

11/20/2018

ALARA Plan for RWP 2018-0450

11/23/2018

ALARA Plan for RWP 2018-0434

10/16/2018

Miscellaneous

Post Job ALARA Review for RWP 2018-0434

03/08/2019

40% Job In Progress Review for RWP 2018-0454

11/06/2018

Post Job ALARA Review for RWP 2018-0454

2/06/2019

80% Job In Progress Review for RWP 2018-0444

2/18/2018

40% Job In Progress Review for RWP 2018-0444

11/06/2018

Post Job ALARA Review for RWP 2018-0444

2/07/2019

Post Job ALARA Review for RWP 2018-0450

2/28/2019

40% Job In Progress Review for RWP 2018-0450

2/01/2018

80% Job In Progress Review for RWP 2018-0450

2/13/2018

40% Job In Progress Review for RWP 2018-0434

2/18/2018

80% Job In Progress Review for RWP 2018-0434

2/19/2018

Procedures

EN-RP-105

Radiological Work Permits

Radiation Work

Permits (RWPs)

2018-0434

Refuel Project: Reassembly of the Reactor Head and

Associated Work Activities

2018-0444

Reactor Head Inspection: Removal/Installation of Control

Rod Drive Seal Housing Packages and Removal/Installation

of Control Rod Drive Mechanism Drive Motors.

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2018-0450

1R26 Emergent Reactor Head Nozzle Repair and Support

Activities

2018-0454

Steam Generator Primary Side Activities

71124.05

Work Orders

2770033

RI-86G-2 High Range Containment Monitor Calibration

01/17/2019

2777256

RI-86G-1 - High Range Containment Monitor Calibration -

Source Test

11/04/2018

71124.08

Corrective Action

Documents

CR-PLP-2018-

297

Radiation Monitor is East Rad Waste Removed from Service

Due to Spurious Auto-Dialer Alarms in the Control Room

01/18/2018

CR-PLP-2018-

215

Troubleshoot and Repair Nuisance Auto-Dialer Alarms at

East Rad Waste

03/15/2018

CR-PLP-2018-

04820

Auto-Dialer Alarm Function Found Unplugged from

Radiation Monitor in East Radwaste Building

10/17/2018

CR-PLP-2019-

247

Prioritize Repair of the Auto-Dial Control Room Alarm

Function for the East Rad Waste Radiation Monitor

01/24/2019

Miscellaneous

Memo To From

JLSmith

Palisades Plant - Shippers Qualifications 2018 REvision

05/30/2018

Procedures

DM-OP-046-

161046

Operation of the Energy Solutions ALPS System at

Palisades Nuclear Power Station

EN-RW-102

Radioactive Waste Shipping

EN-RW-104

Scaling Facators

EN-RW-106

Integrated Transportation Security Plan

Self-Assessments LO-PLPLO-2019-

00010

Pre-NRC Inspection Radioactive Solid Waste Processing

and Radioactive Material Handling, Storage and

Transportation Self-Assessment

07/10/2019

Shipping Records 2017-RW-017

8-120-B Metal Cask with Poly HIC Liner Containing T-100

Resins

10/30/2017

2018-RW-004

3-60B-1 Metal Cask with 3-60 Steel Liner containing

Irradiated Hardware

03/06/2019

2018-RW-007

14-170-32 Metal Cask containing High Rad Metal Waste in

Liner

09/13/2018

2018-RW-011

(2) 20' Sea Lands containing Dry Active Waste & Metal

Waste for Processing

11/07/2018

Work Orders

00486643

East Radwaste Auto-Dialer Bringing in Nuisance Alarms

10/17/2017

71151

Corrective Action

CR-PLP-2019-

Diesel Generator 1-1 Service Water Flow was Reading

10/07/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

04023

Elevated at 710 gpm

Miscellaneous

MSPI Derivation

Documents

MSPI Derivation Documents for October 1, 2018 through

September 30, 2019

10/01/2018 -

09/30/2019

71152

Corrective Action

Documents

CR-PLP-2019-

2920

Operating Crew Missed the Window to Block MSIV Closure

07/28/2019

CR-PLP-2019-

229

Three-Year Trend of Power Supply Failures

08/15/2019

CR-PLP-2019-

03474

Unplanned Transfer of Water to SIRWT

09/04/2019

CR-PLP-2019-

04024

Emergency Diesel Generator 1-1 Test, TI-1481, K-6A Jacket

Water Temperature Indicator was Reading 140 Degrees

Fahrenheit

10/07/2019

CR-PLP-2019-

292

CRDM Cooling Fan Tripped

10/25/2019

CR-PLP-2019-

04583

Aggregate Performance Issue (AP) Associated with Rework

Performance Rated

11/18/2019

CR-PLP-2019-

04674

Large Amounts of Boric Acid under P-54C, Containment

Spray Pump

11/23/2019

CR-PLP-2019-

04824

CRDM Cooling Fan V-49A Failure

2/07/2019

CR-PLP-2019-

04935

Create a Contigency Work Order with Four Tasks to Replace

any Thermo Margin Monitor CRT Display Screens

2/17/2019

CR-PLP-2019-

05001

NIOS Identified: Problem Identified During Review of

CR-PLP-2019-03474

2/19/2019

Miscellaneous

APRM Report

Palisades Performance Improvement

08/2019

Procedures

Admin 4.02

Control of Equipment

EN-HU-102

Human Performance Traps and Tools

GOP-9

Mode 3 > 525F to Mode 4 or Mode 5

SOP-27

Fuel Pool System

71153

Miscellaneous

05000255

Indications Identified in Reactor Pressure Vessel Head

Nozzle Penetrations

01