IR 05000255/2021010
| ML22041B099 | |
| Person / Time | |
|---|---|
| Site: | Palisades |
| Issue date: | 02/24/2022 |
| From: | Richard Skokowski Engineering Branch 3 |
| To: | Corbin D Entergy Nuclear Operations |
| References | |
| IR 2021010 | |
| Download: ML22041B099 (7) | |
Text
SUBJECT:
PALISADES NUCLEAR PLANT - TRIENNIAL FIRE PROTECTION INSPECTION REPORT 05000255/2021010
Dear Mr. Corbin:
On January 18, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Palisades Nuclear Plant and discussed the results of this inspection with Mr. D. Lucy, General Manager, Plant Operations and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Richard A. Skokowski, Chief Engineering Branch 3 Division of Reactor Safety Docket No. 05000255 License No. DPR-20
Enclosure:
As stated
Inspection Report
Docket Number:
05000255
License Number:
Report Number:
Enterprise Identifier:
I-2021-010-0058
Licensee:
Entergy Nuclear Operations, Inc.
Facility:
Palisades Nuclear Plant
Location:
Covert, MI
Inspection Dates:
November 29, 2021 to December 10, 2021
Inspectors:
J. Benjamin, Senior Reactor Inspector
A. Dahbur, Senior Reactor Inspector
J. Gilliam, Senior Reactor Inspector
Approved By:
Richard A. Skokowski, Chief
Engineering Branch 3
Division of Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a triennial fire protection inspection at Palisades Nuclear Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors completed a reduced inspection at Palisades Nuclear Plant which focused on a sample of programs, systems, and components the site will rely on after their decommissioning. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the coronavirus (COVID-19), inspectors were directed to begin telework. In addition, regional baseline inspections were evaluated to determine if all or a portion of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and on site. The inspections documented below met the objectives and requirements for completion of the IP.
REACTOR SAFETY
71111.21N.05 - Fire Protection Team Inspection (FPTI) Structures, Systems, and Components (SSCs) Credited for Fire Prevention, Detection, Suppression, or Post-Fire Safe Shutdown Review (IP Section 03.01)
The inspectors verified that components and/or systems will function as required to support the credited functions stated for each sample. Additional inspection considerations are located in the fire hazards analysis (FHA) or safe shutdown analysis (SSA).
- (1) Spent Fuel Pool Makeup and Cooling Capabilities
- (2) Aging Management Commitment for Fire Protection Sprinklers
Fire Protection Program Administrative Controls (IP Section 03.02) (1 Sample)
The inspectors verified that the selected control or process is implemented in accordance with the licensees current licensing basis. If applicable, ensure that the licensees FPP contains adequate procedures to implement the selected administrative control. Verify that the selected administrative control meets the requirements of all committed industry standards.
- (1) Combustible Control Program
Fire Protection Program Changes/Modifications (IP Section 03.03) (1 Sample)
The inspectors verified the following:
a.
Changes to the approved FPP do not constitute an adverse effect on the ability to safely shutdown.
b.
The adequacy of the design modification, if applicable.
c.
Assumptions and performance capability stated in the SSA have not been degraded through changes or modifications.
d.
The FPP documents, such as the Updated Final Safety Analysis Report, fire protection report, FHA, and SSA were updated consistent with the FPP or design change.
e.
Post-fire SSD operating procedures, such as abnormal operating procedures, affected by the modification were updated.
- (1) Fire Protection Program Change to DBD 7.10 "Design Basis Document for NFPA 805 Fire Protection Program," Section 3.6.2 "Standpipe and Hose Station"
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On January 18, 2022, the inspectors presented the triennial fire protection inspection results to Mr. D. Lucy, General Manager, Plant Operations and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
CR-PLP-2004-
0464
EA-FPS-2001-01 Objectives Not Met w/ Hose Reels 19 &
with Track Alley Sprinkler
08/04/2004
CR-PLP-2004-
0486
EA-FPS-2001-01 Objectives Not Meet with Hose Reels 19
and 20 with Track Alley Sprinklers
08/04/2004
CR-PLP-2019-
230
Create a WR to Perform a Visual Inspection and
Functional Test of Door-1001
10/22/2019
Corrective Action
Documents
LR-LAR-2009-
244 CA 25
Replace or Test Sprinkler Heads
09/15/2009
CR-PLP-2021-
03060
Changes Did Not Have FP Impact Review
2/02/2021
CR-PLP-2021-
03126
PLP-RPT-12-00053 and DBD-7.10 Have Incorrect Nozzle
Manufacturer and Model
2/10/2021
Corrective Action
Documents
Resulting from
Inspection
CR-PLP-2022-
00075
Revise EA-FPS-2001-01 to Reflect the Installed 75 psi
Automatic Nozzles at Hose Reel 19 and 20
01/12/2022
NET-28086-000-
Criticality Safety Analysis for the Palisades Spent Fuel
Pool with Region 2 Empty Cells Credit
Engineering
Evaluations
PAD 20-0047
FPSP-SO-2 Inspection and Testing of Palisades Plant Fire
Doors
Fire Plans
FPF
Pre Fire Plans Manual
DBD 7.10
Design Basis Document for NFPA 805 Fire Protection
Program," Section 3.6.2 "Standpipe and Hose Station
Miscellaneous
FAQ 07-0040
Non-Power Operations Clarifications
Control of Hot Work and Ignition Sources
Control of Hot Work and Ignition Sources
Control of Combustibles
FPIP-4
Fire Protection Systems and Fire Protection Equipment
FPSP-AO-3
Fire Hose Reel/Rack Station Valve Check
Procedures
SOP-27
Fuel Pool System
71111.21N.05
Self-
Assessments
LO-PLPLO-2020-
00073
Pre-NRC Triennial Fire Protection Inspection Focused
Self-Assessment
06/08/2021