IR 05000255/2020004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000255/2020004
ML21043A019
Person / Time
Site: Palisades 
Issue date: 02/11/2021
From: Billy Dickson
NRC/RGN-III/DRP/B2
To: Corbin D
Entergy Nuclear Operations
References
IR 2020004
Download: ML21043A019 (25)


Text

February 11, 2021

SUBJECT:

PALISADES NUCLEAR PLANT - INTEGRATED INSPECTION REPORT 05000255/2020004

Dear Mr. Corbin:

On December 31, 2020, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Palisades Nuclear Plant. On January 21, 2021, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; the Director, Office of Enforcement; and the NRC Resident Inspector at Palisades.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region III; and the NRC Resident Inspector at Palisades. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Billy C. Dickson, Jr., Chief Branch 2 Division of Reactor Projects

Docket No. 05000255 License No. DPR-20

Enclosure:

As stated

Inspection Report

Docket Number:

05000255

License Number:

DPR-20

Report Number:

05000255/2020004

Enterprise Identifier: I-2020-004-0030

Licensee:

Entergy Nuclear Operations, Inc.

Facility:

Palisades Nuclear Plant

Location:

Covert, MI

Inspection Dates:

October 01, 2020 to December 31, 2020

Inspectors:

E. Fernandez, Reactor Inspector

G. Hansen, Senior Emergency Preparedness Inspector

P. Laflamme, Senior Resident Inspector

V. Myers, Senior Health Physicist

C. St. Peters, Resident Inspector

Approved By:

Billy C. Dickson, Jr., Chief

Branch 2

Division of Reactor Projects

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Palisades, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Follow Procedure Results in an Arc to Ground and Entry into Abnormal Operating Procedure (AOP) 36 "Loss of Component Cooling Water (CCW)" Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events Green NCV 05000255/2020004-01 Open/Closed

[H.11] -

Challenge the Unknown 71152 A self-revealed Green finding and associated non-cited violation (NCV) of Technical Specification 5.4.1a occurred on September 9, 2020, when the licensee failed to follow plant procedure EN-MA-101, "Conduct of Maintenance." Specifically, the licensee's failure to correctly implement step 5.3.2c of procedure EN-MA-101 resulted in the supervisor getting involved in the hands-on work. This resulted in an arc to ground of safety-related DC breaker 72-118, subsequent unanticipated opening of valve CV-0910 "CCW Supply to Containment" and valve CV-0911 "CCW from Containment" due to a loss of power, standby CCW pump start, and consequential tank T-3, "Component Cooling Water Surge Tank," level drop requiring entry into AOP-36, "Loss of Component Cooling Water (CCW)."

Additional Tracking Items

Type Issue Number Title Report Section Status LER 05000255/2020-002-00 LER 2020-002-00 for Palisades Nuclear Plant,

Indications Identified in Reactor Pressure Vessel Head Nozzle Penetrations 71153 Closed

PLANT STATUS

The plant began the inspection period shutdown in mode 6 for a refueling outage. On October 20, 2020, the plant was taken critical and successfully synced to the grid on October 21, 2020. The plant achieved rated thermal power on October 27, 2020, and remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

Starting on March 20, 2020, in response to the National Emergency declared by the President of the United States on the public health risks of the Coronavirus Disease 2019 (COVID-19), resident inspectors were directed to begin telework and to remotely access licensee information using available technology. During this time, the resident inspectors performed periodic site visits each week; conducted plant status activities as described in IMC 2515, Appendix D, Plant Status; observed risk-significant activities; and completed onsite portions of IPs. In addition, resident and regional baseline inspections were evaluated to determine if all or portions of the objectives and requirements stated in the IP could be performed remotely. If the inspections could be performed remotely, they were conducted per the applicable IP. In some cases, portions of an IP were completed remotely and onsite. The inspections documented below met the objectives and requirements for completion of the IP.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures for the following systems on December 1, 2020
  • Spent fuel pool

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Component cooling water (CCW) on November 9, 2020
(2) Left train auxiliary feedwater (AFW) on November 17, 2020 (3)7B service water pump system on November 24, 2020

Complete Walkdown Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated system configurations during a complete walkdown of the 1D 2.4KV electrical bus system on December 11, 2020.

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Station Battery Room, Fire Area 11, on November 16, 2020
(2) Station Battery Room, Fire Area 12, on November 16, 2020
(3) Mechanical Equipment Rooms, Fire Area 30, on November 23, 2020
(4) Mechanical Equipment Rooms, Fire Area 31, on November 23, 2020

Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the onsite fire brigade training and performance during an annual fire drill on December 3, 2020.

71111.06 - Flood Protection Measures

Inspection Activities - Internal Flooding (IP Section 03.01) (1 Sample)

The inspectors evaluated internal flooding mitigation protections in the:

(1) 1C Switchgear Room on December 22, 2020

71111.07A - Heat Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) VHX027A Engineering Safeguards Room cooling coil on December 4, 2020

===71111.08P - Inservice Inspection Activities (PWR)

PWR Inservice Inspection Activities Sample (IP Section 03.01)===

(1) The inspectors documented a partial completion of this inspection procedure in inspection report 05000255/2020003. During this inspection period, the inspectors reviewed the licensees actions to address a flaw which was below recordable threshold during the last outage. The licensee reexamined the nozzle, identified the flaw had grown, and repaired the nozzle.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the Control Room during vacuum fill on October 15, 2020.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated SER-406, Revision 2 on November 23, 2020.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Radiation monitoring system during the week of December 14, 2020

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1)125 VDC vital power system during the week of November 23, 2020

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Elevated risk during planned maintenance on battery charger #2 and right train AFW flow control valve testing on October 26, 2020.

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) Technical specification sodium tetraborate basket weight evaluation on October 7, 2020
(2) CV-0826 past operability evaluation on October 9, 2020
(3) Core exit thermocouple cabling evaluation on October 21, 2020
(4) Service water to containment air cooling system evaluation on November 20, 2020

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (1 Sample)

The inspectors evaluated the following temporary or permanent modifications:

(1) Engineering Change (EC) 84697: Thermal margin monitor system channel D display replacement modification on December 17, 2020.

71111.19 - Post-Maintenance Testing

Post-Maintenance Test Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the following post-maintenance test activities to verify system operability and functionality:

(1) Control rod testing on October 28, 2020
(2) Control rod number 2 maintenance and testing on October 29, 2020
(3) Battery charger number 2 testing on November 18, 2020
(4) P-52C CCW pump maintenance and testing on December 16, 2020
(5) P-55C charging pump maintenance and testing on December 22, 2020

71111.20 - Refueling and Other Outage Activities

Refueling/Other Outage Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated refueling outage 1R27 activities from August 30 to October 27, 2020.

71111.22 - Surveillance Testing

The inspectors evaluated the following surveillance tests:

Surveillance Tests (other) (IP Section 03.01)

(1) Quarterly 7C service water pump test on November 19, 2020

Containment Isolation Valve Testing (IP Section 03.01) (1 Sample)

(1) Local leak rate testing on November 12, 2020

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors completed an evaluation of submitted Emergency Action Level and Emergency Plan changes on December 10, 2020. This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) Evaluated exercise on October 27, 2020

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated:

(1) Tabletop exercise on November 10,

RADIATION SAFETY

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation

Waste Characterization and Classification (IP Section 03.03) (3 Samples)

The inspectors evaluated the licensee's characterization of the following radioactive waste shipments:

(1)2020-RW-003; Clean Radwaste Filters (2)2020-RW-004; Primary Purification Filter (3)2020-RW-006; Primary Purification Resin

Shipping Records (IP Section 03.05) (3 Samples)

The inspectors evaluated the following non-excepted radioactive material shipments through a record review:

(1)2020-RW-003; Clean Radwaste Filters Shipped as LSA-II (2)2020-RW-004; Primary Purification Filter Shipped as Type B (3)2020-RW-006; Primary Purification Resin Shipped as Type B

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification

The inspectors verified licensee performance indicators submittals listed below:

MS06: Emergency AC Power Systems (IP Section 02.05)===

(1) Unit 1 (October 1, 2019-September 30, 2020)

MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)

(1) Unit 1 (October 1, 2019-September 30, 2020)

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)

(1) Unit 1 (April 1, 2019-September 30, 2020)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) April 1, 2019-September 30, 2020

PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)

(1) April 1, 2019-September 30, 2020

71152 - Problem Identification and Resolution

Semiannual Trend Review (IP Section 02.02) (1 Sample)

(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in equipment reliability that might be indicative of a more significant safety issue on December 10, 2020.

Annual Follow-up of Selected Issues (IP Section 02.03) (2 Samples)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1)1-2 EDG starting air system leak evaluation as documented in CR-PLP-2020-00239 on December 21, 2020

(2) Electrical maintenance near miss arc fault evaluation as documented in CR-PLP-2020-3261 on November 24, 2020

71153 - Follow-up of Events and Notices of Enforcement Discretion Event Report (IP Section 03.02)

The inspectors evaluated the following licensee event reports (LERs):

(1) LER 05000255/2020-002-00, Indications Identified in Reactor Pressure Vessel Head Nozzle Penetrations (ADAMS Accession No. ML20314A143). The inspectors determined that it was not reasonable to foresee or correct the cause discussed in the LER and therefore no performance deficiency was identified. The inspectors did not identify a violation of NRC requirements.

INSPECTION RESULTS

Failure to Follow Procedure Results in an Arc to Ground and Entry into Abnormal Operating Procedure (AOP) 36 "Loss of Component Cooling Water (CCW)"

Cornerstone Significance Cross-Cutting Aspect Report Section Initiating Events

Green NCV 05000255/2020004-01 Open/Closed

[H.11] -

Challenge the Unknown 71152 A self-revealed Green finding and associated non-cited violation (NCV) of Technical Specification 5.4.1a occurred on September 9, 2020, when the licensee failed to follow plant procedure EN-MA-101, "Conduct of Maintenance." Specifically, the licensee's failure to correctly implement step 5.3.2c of procedure EN-MA-101 resulted in the supervisor getting involved in the hands-on work. This resulted in an arc to ground of safety-related DC breaker 72-118, subsequent unanticipated opening of valve CV-0910 "CCW Supply to Containment" and valve CV-0911 "CCW from Containment" due to a loss of power, standby CCW pump start, and consequential tank T-3, "Component Cooling Water Surge Tank," level drop requiring entry into AOP-36, "Loss of Component Cooling Water (CCW)."

Description:

On September 9, 2020, with the unit shutdown in mode 6, the site attempted to remove a temporary modification that powered up selected ED-11-2, 125 VDC Panel, breaker loads. In preparation to remove the jumper on 13-TV4 terminal 120 from a lug, a supervisor observing the work asked to take a closer look to help gather more information. As the supervisor looked, he accidentally touched a wire which contacted an energized component and caused an arc to ground. In their review, the inspectors noted that the supervisor helping to gather more information by getting involved in the hands-on work was contrary to step 5.3.2c of procedure EN-MA-101, which states, "ensure that the oversight role of the supervisor is maintained and not compromised by getting involved with the hands-on work." As a result, the arc to ground resulted in safety-related direct current (DC) breaker 72-118 tripping open.

The breaker opening resulted in the loss of the 125V DC power supplied to CCW containment isolation valves CV-0910 and CV-0911, which immediately opened per design.

This configuration change allowed the CCW system to fill a previously drained portion of CCW piping inside containment. The unanticipated CCW inventory movement resulted in CCW standby pump autostart, subsequent tank T-3 level drop to 2 percent, resultant low-level alarm in Control Room, and actuation of the autofill system per design. In response, the site entered AOP-36, "Loss of CCW," for tank T-3 low-level alarm and verified autofill system restored T-3 inventory to the normal level.

The inspectors reviewed the associated apparent cause analysis for the event, maintenance rule evaluation, control room logs, and interviewed operations, engineering, and maintenance personnel. In their review, the inspectors noted that CCW supply header pressure and temperature remained constant during the CCW system inventory movement and the autofill system functioned as designed. The inspectors also noted that the licensee determined the movement of CCW inventory to be a maintenance rule functional failure because the autofill system is not safety-related and could not be relied upon to mitigate the unanticipated movement of inventory. Specifically, the T-3 inventory capacity was significantly less than the volume of drained CCW piping inside containment, and the autofill system was not a credited makeup source. As a result, if the autofill system had failed to actuate, a loss of CCW net positive suction head to the CCW pumps would have likely occurred. Therefore, the inspectors concluded, the loss of DC and resultant movement of CCW inventory presented a potential challenge to the CCW system operability that could upset plant stability and challenge critical safety functions during shutdown operations.

Corrective Actions: The licensee entered AOP-36 "Loss of CCW," ensured water level was restored to tank T-3, and performed an apparent cause analysis (ACA) for the event. In addition, the licensee conducted a stand down with all electrical maintenance supervisors to discuss and reinforce supervisor roles and responsibilities.

Corrective Action References: CR-PLP-2020-3261, CR-PLP-2020-3262

Performance Assessment:

Performance Deficiency: The inspectors determined that the licensee's failure to ensure a supervisor stay in role and not get involved in the hands-on work of gathering information on a jumper the workers were attempting to remove in accordance with EN-MA-101 step 5.3.2c was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Human Performance attribute of the Initiating Events cornerstone and adversely affected the cornerstone objective to limit the likelihood of events that upset plant stability and challenge critical safety functions during shutdown as well as power operations.

Significance: The inspectors assessed the significance of the finding using Appendix G, Shutdown Safety SDP. Using IMC 0609, Appendix G, Attachment 1, Exhibit 2, the inspectors screened the finding as Green because it did not increase the likelihood of a shutdown initiating event, did not result in a loss of coolant or inventory, did not involve a loss of offsite power, did not involve a loss of residual heat removal or level control, and did not increase the likelihood of a fire, flood, or other external event.

Cross-Cutting Aspect: H.11 - Challenge the Unknown: Individuals stop when faced with uncertain conditions. Risks are evaluated and managed before proceeding. Specifically, the licensee did not stop work when they were unable to remove the jumper from the temporary modification. This resulted in the licensee supervisor performing hands-on data gathering which caused an energized component to make contact with a grounded component and the DC breaker tripping open.

Enforcement:

Violation: Technical Specification Section 5.4.1a requires, in part, that written procedures shall be established, implemented, and maintained covering the applicable procedures recommended in Regulatory Guide 1.33, Revision 2, Appendix A, February,1978. NRC Regulatory Guide 1.33, Revision 2, Appendix A, Section 1 addresses Administrative Procedures. The licensee established Procedure EN-MA-101, Revision 33 to address conduct of maintenance while performing work on safety-related equipment, including jumpers.

Contrary to the above, on September 9, 2020, the licensee failed to implement step 5.3.2c of EN-MA-101. Specifically, the licensee supervisor got involved in hands-on work which resulted in an arc to ground and DC breaker 72-118 tripping open. DC breaker 72-118 tripping open then opened two containment isolation valves, CV-0910 and CV-0911, which allowed water to fill a previously drained portion of CCW, T-3 low-level alarm, and entry into AOP-36.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

Observation: 1-2 Emergency Diesel Generator Starting Air System Leak Causal Evaluation Review 71152 The inspectors reviewed the associated causal evaluation, extent of condition review, and corrective actions taken associated with an air leak identified on PCV-1490, "1-2 EDG 'B' Starting Air Pressure Control Valve." The inspectors noted the direct cause was improper diaphragm seating resulting from improper manufacturing/assembly at the manufacturer. In their review, the inspectors concluded that the air leak identification, causal evaluation, extent of condition, and subsequent valve replacement were all completed in a timely and effective manner commensurate with safety significance. No issues of significance were identified.

Observation: Semiannual Trend Review 71152 The inspectors' review focused on equipment reliability and considered the results of daily inspector Corrective Action Program (CAP) item screening and licensee trending efforts. The inspectors' review nominally considered the six months of July 2020 through December 2020, although some examples expanded beyond those dates when warranted by the trend's scope.

The inspectors reviewed condition reports, trend reports, and engineering calculations addressing human performance and equipment reliability at the site. During the inspection period, the NRC inspectors noted a few challenges to equipment reliability. Specifically, the inspectors observed and reviewed activities associated with the "B" primary coolant pump (PCP) seal degradation, elevated control rod drive (CRD) leakage trends and temperatures leading into the refueling outage, and "B" main feed pump (MFP) thrust bearing spurious elevated vibration alarms.

The inspectors noted that the licensee identified and monitored the PCP seal degradation.

Also, the inspectors noted that the licensee performed a weekly trend analysis of the seal pressures. Regarding the CRD leakage trends and temperatures leading into the refueling outage, the licensee monitored the parameters and then performed maintenance during the outage on the CRDs. The inspectors also noted for the B MFP thrust bearing vibration alarms that the licensee performed an engineering calculation and then a temporary modification to address the issue. Although these issues illustrated a challenge to equipment reliability, the inspectors did not identify an adverse trend during this assessment period.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 21, 2021, the inspectors presented the integrated inspection results to Mr. D. Corbin, Site Vice President Operations, and other members of the licensee staff.
  • On November 19, 2020, the inspectors presented the radiation protection inspection results to Mr. D. Lucy, General Manager Plant Operations, and other members of the licensee staff.
  • On December 10, 2020, the inspectors presented the emergency action level and emergency plan changes inspection results to Mr. D. Malone, Emergency Planning Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.01

Corrective Action

Documents

CR-PLP-2020-

04621

Notification from the National Weather Service of a High

Wind Warning for Van Buren County

11/14/2020

CR-PLP-2020-

04749

Cold Weather Checklist-1 (SOP-23, Attachment 8) was

Submitted for the Official Record with Missing Signatures

11/30/2020

CR-PLP-2020-

04851

During Rounds, NPO noticed V-32B, Screen House Roof

Vent Fan, Making Excessive Noise

2/11/2020

Procedures

SOP-23

Plant Heating System

71111.04

Corrective Action

Documents

CR-PLP-2020-

03646

EX-02, Station Power Transformer No. 1-2

09/19/2020

CR-PLP-2020-

03981

Received Alarm EK-0547, 125 Volt DC Bus Ground,

Unexpectedly

10/04/2020

CR-PLP-2020-

03983

South End Ball of E-54A Surface Corrosion

10/04/2020

CR-PLP-2020-

04389

CRD-18 (Control Rod Drive Mechanism) Seal Leak Off

Temperature

10/27/2020

CR-PLP-2020-

04390

Primary Coolant Gas Vent System

10/27/2020

CR-PLP-2020-

04430

V-24D, Diesel Generator Room Supply Fan

10/29/2020

Corrective Action

Documents

Resulting from

Inspection

CR-PLP-2020-

04912

NRC Identified Some Wads of Insulation on Top of a Cable

Tray in "C" Switchgear Room

2/17/2020

Procedures

SOP-12

Auxiliary Feedwater System Checklist

SOP-15

Service Water System Checklist

SOP-16

Component Cooling System Checklist

71111.05

Corrective Action

Documents

CR-PLP-2020-

04801

During the Combined Fire and EP Medical Drill on

December 3rd, Objective Element L.2.1 was Rated Not

Observed

2/03/2020

CR-PLP-2020-

04861

P-9B, Diesel Driven Fire Pump

2/11/2020

Fire Plans

Pre-Fire Plan Fire

Battery Rooms Elevation 607' 6"

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Area 11 & 12

Pre-Fire Plan Fire

Area 30 & 31

Mechanical Equipment Rooms

Miscellaneous

PLDRL-FBT-Fire

drill

4th Quarter 2020 Fire Brigade Drill (Unannounced) Shift #1

2/03/2020

PLDRL-FBT-Fire

drill

4th Quarter 2020 Fire Brigade Drill (Announced) Shift #2

11/29/2020

71111.06

Engineering

Evaluations

EA-C-PAL-95-

26-01

Palisades Nuclear Plant Analysis Continuation Sheet

3a

EA-C-PAL-95-

26-01

Palisades Nuclear Plant Analysis Continuation Sheet

Miscellaneous

DBD-7.08

Plant Protection Against Flooding

Procedures

SOP-17C

Non-Radioactive Waste

Work Orders

2856590 01

Bus 1C; Inspection and Pump Out of Manholes

04/08/2020

71111.07A

Corrective Action

Documents

CR-PLP-2020-

03509

Unable to Isolate Service Water to VHX-27A

09/15/2020

Work Orders

2860413

VHX027A Engineering Safeguards Room Cooling Coil

09/15/2020

71111.08P

Corrective Action

Documents

CR-PLP-2020-

03380

Ultrasonic Data Analysis of a Relevant Indication on

Penetration 34 on the Reactor Vessel Head

09/11/2020

CR-PLP-2020-

03427

Ultrasonic Data Analysis of a Relevant Indication on

Penetration 17 on the Reactor Vessel Head

09/13/2020

Miscellaneous

51-9318377-000

Palisades Steam Generator Condition Monitoring for 1R27

and Preliminary Operational Assessment for Cycle 28

PAL1R27 ETSS

  1. 1

Examination Technique Specification Sheet

PAL1R27 ETSS

  1. 2

Examination Technique Specification Sheet

PAL1R27 ETSS

  1. 3

Examination Technique Specification Sheet

PAL1R27 ETSS

  1. 4

Examination Technique Specification Sheet

PLP-RPT-18-

00027

1R26 Palisades Steam Generator Degradation Assessment

PLP-RPT-19-

Palisades Steam Generator Condition Monitoring for 1R26

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

00020

and Final Operational Assessment for Cycle 27

Procedures

54-ISI-400-023

Multi-Frequency Eddy Current Examination of Tubing

54-ISI-400-023

NONDESTRUCTIVE EXAMINATION PROCEDURE

Multi-Frequency Eddy Current Examination of SG Tubing

2/12/2018

54-ISI-619-000

Automated Ultrasonic Examination of Open Tube RPV

Closure Head Penetrations-Palisades Specific

07/30/2020

CEP-NDE-0955

Visual Examination (VE) of Bare-Metal Surfaces

307

LMT-10-PAUT-

007

Fully Encoded Phased Array Ultrasonic Examination of

Dissimilar Metal Piping Welds

SEP-BAC-PLP-

001

Boric Acid Corrosion Control Program Engineering Nuclear

Programs Applicable Sites

71111.11Q Procedures

SES-406

As Found Scenario

SOP-1C

Primary Coolant System - Heatup

71111.12

Corrective Action

Documents

CR-PLP-2020-

04092

The Main Feedwater System in Maintenance Rule Near

(a)(1)

10/10/2020

CR-PLP-2020-

04185

25V DC Bus Ground, Unexpectedly on DC Bus #1

10/16/2020

CR-PLP-2020-

224

DC Bus #1

10/18/2020

CR-PLP-2020-

232

CRD-41 (Control Rod Drive Mechanism) Seal Leakoff

Temperature Indication

10/18/2020

CR-PLP-2020-

04455

Exceeded Maintenance Rule Performance Criteria on

PCS/PZR for Reliability Events

10/30/2020

CR-PLP-2020-

04697

25 Volt DC Bus Ground, #1 DC Bus

11/20/2020

Engineering

Changes

EC# 0000081574

ED-01 and ED-02: Evaluate Station Battery Remaining Life

Capacity Relative to Ambient Temperature

2/21/2019

Miscellaneous

Q1-2020 System

Health Report

RIA - Radiation Monitoring System

2/29/2020

Q2-2020 System

Health Report

RIA - Radiation Monitoring System

2/29/2020

Q2-2020 System

Health Report

EDC - 125V Vital DC Power

11/20/2020

Q4-2020 System

RIA - Radiation Monitoring System

2/29/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Health Report

Procedures

PLP-1-2020-0024

Risk Assessment, Station Battery Debris, Cracks

QE-35B

ED-02 Battery Checks - Quarterly

Work Orders

5411188 01

2-15A ED-15 Charger Outlet Breaker Adjustable Trip

Setting

03/18/2020

71111.13

Procedures

4.11

Safety Function Determination Program

RE-134

Performance Test - Battery Charger No 2 (ED-16)

71111.15

Calculations

1R27 NaTB-

Analysis

Sodium Tetraborate Basket Weight Calculation Analysis

Corrective Action

Documents

CR-PLP-2020-

03608

While Installing Incore Detectors Under Work Order 287985-28 Three Incore Detectors were Unable to be

Installed

09/18/2020

CR-PLP-2020-

03882

Crack in the Outer Sheathing of the Cable for CET #32

09/29/2020

CR-PLP-2020-

03895

Sodium Tetraborate Basket Weights

09/30/2020

CR-PLP-2020-

04060

Breaker 52-187, Boric Acid Gravity Feed MO-2170

10/08/2020

CR-PLP-2020-

04076

Engineering Safeguards Room Cooling System

10/09/2020

CR-PLP-2020-

04505

Traveling Screen's Falk Drive a Severity Level 2 Oil Leak

was Noted

11/04/2020

CR-PLP-2020-

04746

P-50B Lower (First) Seal Stage has a Lowering Trend

11/30/2020

Engineering

Changes

EC 88139

1R27 Results from RM-124 Sodium Tetraborate Basket

Weights

EC-88128

Evaluation of Leakage Past E-50A Feed Reg Bypass Valve

CV-0735

Miscellaneous

Adverse

Condition

Monitoring and

Contingency Plan

Primary Coolant Pump, P-50B, Rising Seal Pressure

11/04/2020

Procedures

RC-123

Sodium Tetraborate Decahydrate Buffering Tests

RM-124

Sodium Tetraborate Basket Weights

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Work Orders

2871120 01

RC-123 - Sodium Tetraborate Decahydrate Buffering Test

09/08/2020

71111.18

Corrective Action

Documents

CR-PLP-2020-

00017

Thermal Margin Monitor (TMM) PY-0102C Repeat

Functional Failure

01/10/2020

CR-PLP-2020-

00716

B Thermal Margin Monitor (TMM) Screen has Gone Blank

03/31/2020

CR-PLP-2020-

00752

TMM Channel 'A' Screen Degraded

03/09/2020

CR-PLP-2020-

01320

Thermal Margin Monitor (TMM) PY-0102C Repeat

Functional Failure

04/30/2020

CR-PLP-2020-

04892

PY-0102B, B Channel Thermal Margin Monitor/Flux Delta T

Power Comparator

2/15/2020

CR-PLP-2020-

04898

Isolate MV-CD146, T-2 Cond Return from Boilers & B/D

Demins

2/16/2020

CR-PLP-2020-

04973

EK-0604D Nuclear-OT Power Deviation/T-Inlet Off-

Normal/Calculator Trouble Channel B Unexpectedly

2/30/2020

Engineering

Changes

EC-84697

PY-0102D: TMM D Channel - Change Drawer CRT Video

Display Monitor to a New LCD Video Display Monitor

2/03/2019

Procedures

RI-23D

Functional Testing of Thermal Margin Monitor - Channel D

2/14/2018

71111.19

Corrective Action

Documents

CR-PLP-2020-

2795

Rod Deviation Alarms Were Received

08/30/2020

CR-PLP-2020-

04151

Inspection and Testing of RSPT 40 Cable

10/14/2020

CR-PLP-2020-

04172

Received Alarm EK-0918, PIP Trouble, Unexpectedly

10/16/2020

CR-PLP-2020-

04174

Secondary Position Indication (SPI) on the PPC is Not

Indicating Properly

10/16/2020

CR-PLP-2020-

04178

CRD-32, Control Rod Drive Mechanism, Primary Indication

Processor (PIP)

10/16/2020

CR-PLP-2020-

248

Control Rod Drive (CRD) #29

10/19/2020

CR-PLP-2020-

275

Rod #2 Withdrew to 6" and Back to the Lower Electrical Limit 10/19/2020

CR-PLP-2020-

290

Matrix Light on EC-12 Associated with CRD-17 was Not

Illuminated When Expected

10/20/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-PLP-2020-

04394

Found Green Corrosion on Right Positive Post of Cell #9

10/27/2020

CR-PLP-2020-

04890

Door-142 (Turbine Building Access to the 1-C Switchgear

Room)

2/15/2020

CR-PLP-2020-

04942

PMT for RV-0915, Component Cooling Surge Tank T-3

Relief

2/23/2020

Procedures

CVCO-4

Periodic Test Procedure - Charging Pumps

EN-MA-105

Control of Measuring and Test Equipment (MT&E)

MSI-I-16

Permanent Maintenance Procedure; Nonintrusive Diagnostic

Check Valve Test Procedure

2/15/2020

QO-15

Inservice Test Procedure - Component Cooling Water

Pumps

2/15/2020

RO-19

Control Rod Position Verification

10/17/2020

Work Orders

2876642 01

RO-19 - Control Rod Position Verification

10/14/2020

2890314 01

RV-0915, Component Cooling Surge Tank T-3 Relief

2/23/2020

2927113 01

CK-CC944, Nonintrusive Check Valve Test: I&C Support

2/15/2020

71111.20

Corrective Action

Documents

CR-PLP-2020-

2795

Rod Deviation Alarms were Received

08/30/2020

CR-PLP-2020-

03847

Unexpected Rising Trend on the "A" Steam Generator after

Preparing to Start Condensate P-2B

09/27/2020

CR-PLP-2020-

04026

Liquid Penetrant (PT) Examination of the Reactor Vessel

CROM Penetration #34 Nozzle Repair Weld

10/06/2020

CR-PLP-2020-

04104

NPOs had to be Removed from Covered Work to Perform

Decontamination Activities in the Reactor Cavity

10/12/2020

CR-PLP-2020-

04124

CCW hose for CRD Position 42 on the Reactor Head was

Found Frayed and Needs to be Replaced

10/13/2020

CR-PLP-2020-

04137

CRD-45, Control Rod Drive Mechanism

10/14/2020

CR-PLP-2020-

04180

CRD-28, Control Rod Drive Mechanism

10/16/2020

CR-PLP-2020-

04195

Validation Confirmed CET 27 is Failed

10/17/2020

CR-PLP-2020-

204

Identified Exposed Insulation on "A" SIG Cold Leg

10/17/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CR-PLP-2020-

205

P-80B AC Lift Pump Start Permissive was Erratic

10/17/2020

CR-PLP-2020-

210

P-50B, Primary Coolant Pump, has Evidence of Prior Oil

Leakage in its Drip Trays

10/17/2020

CR-PLP-2020-

232

CRD-41 (Control Rod Drive Mechanism) Seal Leakoff

Temperature Indication

10/18/2020

CR-PLP-2020-

243

During Containment Walkdown Identified P-50D Primary

Coolant Pump Motor Upper Oil Reservoir Line Leaking

10/19/2020

Corrective Action

Documents

Resulting from

Inspection

CR-PLP-2020-

285

NRC Walked Down Containment

10/20/2020

Procedures

GOP-3

Mode 3 = 525°F to Mode 2

GOP-4

Mode 2 to Mode 1

10/21/2020

71111.22

Corrective Action

Documents

CR-PLP-2020-

03987

CV-0847, SW Supply to Cont (MZ-12), the Open Stroke

Time was Outside of the Acceptable Stroke Time

10/04/2020

CR-PLP-2020-

04583

P-8C Initial Vibrations Taken on the Pump Inboard Bearing

Were High Out of Specifications

11/11/2020

CR-PLP-2020-

04613

P-8B, Steam Driven Auxiliary Feedwater Pump

11/13/2020

CR-PLP-2020-

04840

QO-14C Performance

2/10/2020

Procedures

QO-14

Inservice Test Procedure - Service Water Pumps

11/18/2020

RO-145

Comprehensive Pump Test Procedure Auxiliary Feedwater

Pumps P-8A, P-8B, and P-8C

11/11/2020

RO-32

LLRT - Local Leak Rate Test

11/04/2020

Work Orders

00506694 01

P-7C; Replace Packing Shaft

11/18/2020

2878522 03

RO-145C -P-8C, AFW Comprehensive Pump Test

10/21/2020

71114.04

Miscellaneous

CFR 50.54(Q)(2) Screening - EI-1, Emergency

Classification and Actions Revision 60

09/23/2019

CFR 50.54(Q)(2) Screening - EI-1, Emergency

Classification and Actions Revision 61

06/11/2020

CFR 50.54(Q)(2) Screening - EI-2.2, Emergency Staff

Augmentation Revision 22

10/07/2019

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CFR 50.54(Q)(2) Screening - EI-2.2, Emergency Staff

Augmentation Revision 23

03/20/2020

CFR 50.54(Q)(2) Screening - EI-3, Communications and

Notifications Revision 36

09/23/2019

CFR 50.54(Q)(2) Screening - EI-3, Communications and

Notifications Revision 37

01/23/2020

CFR 50.54(Q)(2) Screening - EI-4.1, Technical Support

Center Activation Revision 26

10/21/2019

CFR 50.54(Q)(2) Screening - EI-4.1, Technical Support

Center Activation Revision 27

01/27/2020

CFR 50.54(Q)(2) Screening - EI-4.2, Operations Support

Center Activation Revision 27

10/21/2019

CFR 50.54(Q)(2) Screening - EI-4.3, Emergency

Operations Facility Activation Revision 30

01/19/2019

CFR 50.54(Q)(2) Screening - EI-4.3, Emergency

Operations Facility Activation Revision 31

05/14/2020

CFR 50.54(Q)(2) Screening - EI-5.0, Reentry Revision

07/29/2019

CFR 50.54(Q)(2) Screening - EI-6.0, Rapid Dose

Calculation Revision 19

2/05/2019

CFR 50.54(Q)(2) Screening - EI-6.0, Rapid Dose

Calculation Revision 20

04/22/2020

CFR 50.54(Q)(2) Screening - EI-6.1, Release Rate

Determination from Stack Gas Monitors Revision 10

2/05/2019

CFR 50.54(Q)(2) Screening - EI-6.9, Automated Dose

Assessment Program Revision 14

04/22/2020

CFR 50.54(Q)(2) Screening - EI-6.13, Protective Action

Recommendations for Offsite Populations Revision 26

2/17/2019

CFR 50.54(Q)(2) Screening - EI-16.1, Maintenance of

Emergency Equipment Revision 34

11/26/2019

CFR 50.54(Q)(2) Screening - EN-EP-604, Emergency

Classifications Revision 0

06/08/2020

CFR 50.54(Q)(2) Screening - EN-EP-609 Emergency

Operations Facility (EOF) Operations Revision 6

2/18/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

CFR 50.54(Q)(2) Screening - EN-EP-801, Emergency

Response Organization Revision 17

10/29/2019

CFR 50.54(Q)(3) Screening - PAL PWS, Public Warning

System Operating Procedures Revision 23

08/28/2019

CFR 50.54(Q)(3) Evaluation - PAL PWS, Public Warning

System Operating Procedures Revision 23

08/29/2019

CFR 50.54(Q)(3) Screening -PWS Design Report, Public

Warning System Design Report Changes

08/28/2019

CFR 50.54(Q)(3) Evaluation - PWS Design Report,

Public Warning System Design Report Changes

08/28/2019

CFR 50.54(Q)(3) Screening -SEP, Site Emergency Plan

Revision 32

09/18/2019

CFR 50.54(Q)(3) Evaluation -SEP, Site Emergency Plan

Revision 32

09/18/2019

Procedures

EN-EP-305

Emergency Planning 10CFR50.54(q) Review Program

SEP

Site Emergency Plan

SEP

Site Emergency Plan

71124.08

Corrective Action

Documents

CR-PLP-2020-

03997

EN-RW-102 Attachment 20 Incorrect Radiological Data

10/05/2020

Miscellaneous

Filter Characterization Report for F-57 Filters

06/05/2019

GEL Laboratories Part 61 Report for Primary Resin

07/13/2020

GEL Laboratories Part 61 Report for Filter 54A

11/25/2019

Shipping Records 2020-RW-003

Clean Radwaste F-57 Filters

2/11/2020

20-RW-004

Primary Purification Filter F54A

05/05/2020

20-RW-006

Primary Purification Resin

07/20/2020

71151

Miscellaneous

NRC Performance Indicator Data; Mitigating Systems -

Mitigating Systems Performance Indicator for Cooling Water

Support Systems

10/01/2019 -

09/30/2020

NRC Performance Indicator Data; Mitigating Systems -

Mitigating Systems Performance Index for Emergency AC

Power Systems

10/01/2019 -

09/30/2020

71152

Corrective Action

Documents

CR-PLP-2020-

261

Ground Fault Experienced During Removal of Jumper

09/10/2020

CR-PLP-2020-

Control Room Entered AOP-36, "Loss of Component

09/10/2020

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

262

Cooling Water"

Engineering

Changes

84321

K-7A, K-7B, Eliminate MFW PP Trip on Turbine Axial Thrust

Position (Base EC)

Miscellaneous

ACA Arc Fault Event

10/14/2020

DPRM/APRM Report

08/2020

Primary Coolant Pump Trends

2/16/2020

Procedures

AOP-36

Loss of Component Cooling Water

2