MONTHYEARHL-5845, Monthly Operating Repts for Sept 1999 for Ei Hatch Nuclear Plant.With1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Ei Hatch Nuclear Plant.With HL-5836, Monthly Operating Repts for Aug 1999 for Edwin I Hatch Nuclear Plant.With1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Edwin I Hatch Nuclear Plant.With HL-5818, Monthly Operating Repts for July 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5805, Monthly Operating Repts for June 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5795, Monthly Operating Repts for May 1999 for Ehnp Units 1 & 2. with1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Ehnp Units 1 & 2. with HL-5784, Monthly Operating Repts for Apr 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5766, Monthly Operating Repts for Mar 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5755, Monthly Operating Repts for Feb 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5726, Monthly Operating Repts for Dec 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With1998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5714, Monthly Operating Repts for Nov 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With1998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5706, Monthly Operating Repts for Oct 1998 for Hatch Nuclear Plant Units 1 & 2.With1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Hatch Nuclear Plant Units 1 & 2.With HL-5691, Monthly Operating Repts for Sept 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5675, Monthly Operating Repts for Aug 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5667, Monthly Operating Repts for July 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5653, Monthly Operating Repts for June 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5640, Monthly Operating Repts for May 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5628, Monthly Operating Repts for Apr 1998 for Ei Hatch Nuclear Plant1998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Ei Hatch Nuclear Plant HL-5604, Monthly Operating Repts for Mar 1998 for Edwin I Hatch Nuclear Plant,Units 1 & 21998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Edwin I Hatch Nuclear Plant,Units 1 & 2 HL-5585, Monthly Operating Repts for Feb 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5571, Monthly Operating Repts for Jan 1998 for Edwin I Hatch Nuclear Plant,Unit 11998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Edwin I Hatch Nuclear Plant,Unit 1 HL-5551, Monthly Operating Repts for Dec 1997 for Ei Hatch Nuclear Plant,Units 1 & 21997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5533, Monthly Operating Repts for Nov 1997 for Ei Hatch Nuclear Plant,Units 1 & 21997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5514, Monthly Operating Repts for Oct 1997 for Edwin I Hatch Nuclear Plant,Units 1 & 21997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Edwin I Hatch Nuclear Plant,Units 1 & 2 HL-5493, Monthly Operating Repts for Sept 1997 for Ei Hatch Nuclear Plant1997-09-30030 September 1997 Monthly Operating Repts for Sept 1997 for Ei Hatch Nuclear Plant HL-5475, Monthly Operating Repts for Aug 1997 for Ei Hatch Nuclear Plant,Units 1 & 21997-08-31031 August 1997 Monthly Operating Repts for Aug 1997 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5447, Monthly Operating Repts for July 1997 for Edwin I Hatch Nuclear Plant,Units 1 & 21997-07-31031 July 1997 Monthly Operating Repts for July 1997 for Edwin I Hatch Nuclear Plant,Units 1 & 2 HL-5416, Monthly Operating Repts for May 1997 for Ei Hatch Nuclear Plant Units 1 & 21997-05-31031 May 1997 Monthly Operating Repts for May 1997 for Ei Hatch Nuclear Plant Units 1 & 2 HL-5393, Monthly Operating Repts for Apr 1997 for Ei Hatch Nuclear Plant Units 1 & 21997-04-30030 April 1997 Monthly Operating Repts for Apr 1997 for Ei Hatch Nuclear Plant Units 1 & 2 HL-5364, Monthly Operating Repts for Mar 1997 for Ei Hatch Npp,Units 1 & 21997-03-31031 March 1997 Monthly Operating Repts for Mar 1997 for Ei Hatch Npp,Units 1 & 2 HL-5332, Monthly Operating Repts for Feb 1997 for Ei Hatch Nuclear Plant1997-02-28028 February 1997 Monthly Operating Repts for Feb 1997 for Ei Hatch Nuclear Plant HL-5314, Monthly Operating Repts for Jan 1997 for Ei Hatch Nuclear Plant1997-01-31031 January 1997 Monthly Operating Repts for Jan 1997 for Ei Hatch Nuclear Plant HL-5296, Monthly Operating Repts for Dec 1996 for Ei Hatch Nuclear Plant,Units 1 & 21996-12-31031 December 1996 Monthly Operating Repts for Dec 1996 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5283, Monthly Operating Repts for Nov 1996 for Edwin I Hatch Nuclear Plant,Unit 1 & 21996-11-30030 November 1996 Monthly Operating Repts for Nov 1996 for Edwin I Hatch Nuclear Plant,Unit 1 & 2 HL-5265, Monthly Operating Repts for Oct 1996 for Ei Hatch Nuclear Plant Units 1 & 21996-10-31031 October 1996 Monthly Operating Repts for Oct 1996 for Ei Hatch Nuclear Plant Units 1 & 2 HL-5249, Monthly Operating Repts for Sept 1996 for Ei Hatch Nuclear Plant Unit 1 & 21996-09-30030 September 1996 Monthly Operating Repts for Sept 1996 for Ei Hatch Nuclear Plant Unit 1 & 2 HL-5237, Monthly Operating Repts for Aug 1996 for Ei Hatch Nuclear Plant Units 1 & 21996-08-31031 August 1996 Monthly Operating Repts for Aug 1996 for Ei Hatch Nuclear Plant Units 1 & 2 ML20116J3821996-07-31031 July 1996 Monthly Operating Repts for Jul 1996 for Ei Hatch Nuclear Plant Units 1 & 2 HL-5202, Monthly Operating Repts for June 1996 for Ei Hatch Nuclear Plant Units 1 & 21996-06-30030 June 1996 Monthly Operating Repts for June 1996 for Ei Hatch Nuclear Plant Units 1 & 2 ML20112J0661996-05-31031 May 1996 Monthly Operating Repts for May 1996 for Ehnp ML20116J3971996-05-31031 May 1996 Revised MOR for May 1996 for Ei Hatch Nuclear Plant Unit 1 ML20112J0691996-04-30030 April 1996 Revised MOR for April 1996 for Ei Hatch Nuclear Plant ML20116J3901996-04-30030 April 1996 Revised MOR for April 1996 for Ei Hatch Nuclear Plant Unit 1 ML20111B0061996-04-30030 April 1996 Monthly Operating Repts for April 1996 for Ei Hatch Nuclear Plant HL-5144, Monthly Operating Repts for Mar 1996 for Ei Hatch Nuclear Plant1996-03-31031 March 1996 Monthly Operating Repts for Mar 1996 for Ei Hatch Nuclear Plant ML20111B0131996-03-31031 March 1996 Revised Pages E2-4 for March 1996 for Ei Hatch Nuclear Plant Unit 2 ML20101B1911996-02-29029 February 1996 Monthly Operating Repts for Feb 1996 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5111, Monthly Operating Repts for Jan 1996 for Ei Hatch Nuclear Plant1996-01-31031 January 1996 Monthly Operating Repts for Jan 1996 for Ei Hatch Nuclear Plant ML20101B2001996-01-31031 January 1996 Revised Page E1-2 for Monthly Operating Rept for Jan 1996 for Ei Hatch Unit 1 HL-5098, Monthly Operating Repts for Dec 1995 for Ei Hatch Nuclear Plant1995-12-31031 December 1995 Monthly Operating Repts for Dec 1995 for Ei Hatch Nuclear Plant HL-5085, Monthly Operating Repts for Nov 1995 for Ei Hatch Nuclear Plant1995-11-30030 November 1995 Monthly Operating Repts for Nov 1995 for Ei Hatch Nuclear Plant 1999-09-30
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARML20217D3061999-10-13013 October 1999 SER Accepting Licensee Proposed Changes to Edwin I Hatch Nuclear Plant Emergency Classification Scheme to Add Emergency Action Levels Related to Operation of Independent Spent Fuel Storage Installation HL-5845, Monthly Operating Repts for Sept 1999 for Ei Hatch Nuclear Plant.With1999-09-30030 September 1999 Monthly Operating Repts for Sept 1999 for Ei Hatch Nuclear Plant.With ML20217A1691999-09-22022 September 1999 Part 21 Rept Re Engine Sys,Inc Controllers,Manufactured Between Dec 1997 & May 1999,that May Have Questionable Soldering Workmanship.Caused by Inadequate Personnel Training.Sent Rept to All Nuclear Customers ML20212A6641999-09-13013 September 1999 Safety Evaluation Authorizing Relief Request RR-V-16 for Third 10 Yr Interval Inservice Testing Program HL-5836, Monthly Operating Repts for Aug 1999 for Edwin I Hatch Nuclear Plant.With1999-08-31031 August 1999 Monthly Operating Repts for Aug 1999 for Edwin I Hatch Nuclear Plant.With ML20210J9631999-08-0202 August 1999 SER Finding That Licensee Established Acceptable Program to Verify Periodically design-basis Capability of safety-related MOVs at Edwin I Hatch Nuclear Plant,Units 1 & 2 ML20210J9271999-08-0202 August 1999 SER Finds That Licensee Performed Appropriate Evaluations of Operational Configurations of safety-related power-operated Gate Valves to Identify Valves at Plant,Susceptible to Pressure Locking or Thermal Binding HL-5818, Monthly Operating Repts for July 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-07-31031 July 1999 Monthly Operating Repts for July 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5805, Monthly Operating Repts for June 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-06-30030 June 1999 Monthly Operating Repts for June 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With ML20207E7631999-06-0303 June 1999 Safety Evaluation Concluding That Licensee Proposed Alternative to Use Code Case N-509 Contained in RR-4 Provides Acceptable Level of Quality & Safety.Considers Rev 2 to RR-4 & RR-6 Acceptable HL-5795, Monthly Operating Repts for May 1999 for Ehnp Units 1 & 2. with1999-05-31031 May 1999 Monthly Operating Repts for May 1999 for Ehnp Units 1 & 2. with ML20206G1691999-05-0404 May 1999 SER Approving Requirements of Istb 4.6.2(b) Pursuant to 10CFR50.55a(a)(3)(ii) HL-5784, Monthly Operating Repts for Apr 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-04-30030 April 1999 Monthly Operating Repts for Apr 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5766, Monthly Operating Repts for Mar 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-03-31031 March 1999 Monthly Operating Repts for Mar 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With ML20207M1891999-03-11011 March 1999 SER Accepting Relief Request for Authorization of Alternative Reactor Pressure Vessel Exam for Circumferential Weld HL-5755, Monthly Operating Repts for Feb 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With1999-02-28028 February 1999 Monthly Operating Repts for Feb 1999 for Ei Hatch Nuclear Plant,Units 1 & 2.With ML20206P6981999-01-0707 January 1999 Ehnp Intake Structure Licensing Rept HL-5726, Monthly Operating Repts for Dec 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With1998-12-31031 December 1998 Monthly Operating Repts for Dec 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With ML20196J4931998-12-0707 December 1998 Safety Evaluation Accepting Proposed Alternatives in Relief Requests RR-V-12,RR-V-15,RR-P-15,RR-V-7,RR-V-12,RR-V-14 & RR-V-15 HL-5714, Monthly Operating Repts for Nov 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With1998-11-30030 November 1998 Monthly Operating Repts for Nov 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With HL-5706, Monthly Operating Repts for Oct 1998 for Hatch Nuclear Plant Units 1 & 2.With1998-10-31031 October 1998 Monthly Operating Repts for Oct 1998 for Hatch Nuclear Plant Units 1 & 2.With ML20155B6121998-10-28028 October 1998 Safety Evaluation of TR SNCH-9501, BWR Steady State & Transient Analysis Methods Benchmarking Topical Rept. Rept Acceptable HL-5691, Monthly Operating Repts for Sept 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With1998-09-30030 September 1998 Monthly Operating Repts for Sept 1998 for Ei Hatch Nuclear Plant,Units 1 & 2.With ML20153G2481998-09-24024 September 1998 SE Concluding That Licensee Implementation Program to Resolve USI A-46 at Plant Adequately Addressed Purpose of 10CFR50.54(f) Request ML20239A2531998-09-0303 September 1998 SER Accepting Licensee Request for Relief Numbers RR-17 & RR-18 for Edwin I Hatch Nuclear Plant,Units 1 & 2.Technical Ltr Rept on Third 10-year Interval ISI Request for Reliefs for Plant,Units 1 & 2 Encl HL-5675, Monthly Operating Repts for Aug 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-08-31031 August 1998 Monthly Operating Repts for Aug 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 ML20238F7131998-08-31031 August 1998 9,change 2 to QAP 1.0, Organization HL-5667, Monthly Operating Repts for July 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-07-31031 July 1998 Monthly Operating Repts for July 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5657, Ro:On 980626,noted That Pami Channels Had Been Inoperable for More than Thirty Days.Cause Indeterminate.Licensee Will Replace Automatic Function W/Five Other Qualified Pamis of Like Kind in Drywell & Revised Procedures1998-07-30030 July 1998 Ro:On 980626,noted That Pami Channels Had Been Inoperable for More than Thirty Days.Cause Indeterminate.Licensee Will Replace Automatic Function W/Five Other Qualified Pamis of Like Kind in Drywell & Revised Procedures ML20236W3441998-07-30030 July 1998 Safety Evaluation Accepting Relief Requests for Second 10-yr ISI for Plant,Units 1 & 2 ML20236V5191998-07-28028 July 1998 Safety Evaluation Accepting Proposed License Amend Power Uprate Review ML20236N6751998-07-0909 July 1998 Part 21 & Deficiency Rept Re Notification of Potential Safety Hazard from Breakage of Cast Iron Suction Heads in Apkd Type Pumps.Caused by Migration of Suction Head Journal Sleeve Along Lower End of Pump Shaft.Will Inspect Pumps ML20236L1821998-07-0707 July 1998 Safety Evaluation Accepting 980428 Proposed Alternative to ASME Boiler & Pressure Vessel Code,Section Xi,Repair & Replacement Requirements Under 10CFR50.55a(a)(3) HL-5653, Monthly Operating Repts for June 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-06-30030 June 1998 Monthly Operating Repts for June 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5640, Monthly Operating Repts for May 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-05-31031 May 1998 Monthly Operating Repts for May 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 ML20248B8651998-05-15015 May 1998 Quadrennial Simulator Certification Rept HL-5628, Monthly Operating Repts for Apr 1998 for Ei Hatch Nuclear Plant1998-04-30030 April 1998 Monthly Operating Repts for Apr 1998 for Ei Hatch Nuclear Plant HL-5604, Monthly Operating Repts for Mar 1998 for Edwin I Hatch Nuclear Plant,Units 1 & 21998-03-31031 March 1998 Monthly Operating Repts for Mar 1998 for Edwin I Hatch Nuclear Plant,Units 1 & 2 ML20216B2711998-02-28028 February 1998 Extended Power Uprate Safety Analysis Rept for Ei Hatch Plant,Units 1 & 2 HL-5585, Monthly Operating Repts for Feb 1998 for Ei Hatch Nuclear Plant,Units 1 & 21998-02-28028 February 1998 Monthly Operating Repts for Feb 1998 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5571, Monthly Operating Repts for Jan 1998 for Edwin I Hatch Nuclear Plant,Unit 11998-01-31031 January 1998 Monthly Operating Repts for Jan 1998 for Edwin I Hatch Nuclear Plant,Unit 1 HL-5551, Monthly Operating Repts for Dec 1997 for Ei Hatch Nuclear Plant,Units 1 & 21997-12-31031 December 1997 Monthly Operating Repts for Dec 1997 for Ei Hatch Nuclear Plant,Units 1 & 2 ML20199B0561997-12-31031 December 1997 Rev 0 GE-NE-B13-01869-122, Jet Pump Riser Weld Flaw Evaluation Handbook for Hatch Unit 1 HL-5581, Annual Operating Rept for 1997, for Ei Hatch Nuclear Plant Units 1 & 21997-12-31031 December 1997 Annual Operating Rept for 1997, for Ei Hatch Nuclear Plant Units 1 & 2 HL-5533, Monthly Operating Repts for Nov 1997 for Ei Hatch Nuclear Plant,Units 1 & 21997-11-30030 November 1997 Monthly Operating Repts for Nov 1997 for Ei Hatch Nuclear Plant,Units 1 & 2 HL-5514, Monthly Operating Repts for Oct 1997 for Edwin I Hatch Nuclear Plant,Units 1 & 21997-10-31031 October 1997 Monthly Operating Repts for Oct 1997 for Edwin I Hatch Nuclear Plant,Units 1 & 2 ML20212A1981997-10-16016 October 1997 Safety Evaluation Denying Licensee Request for Relief from Implementation of 10CFR50.55a Requirements Re Use of 1992 Edition of ASME Code Section XI for ISI of Containments ML20211M6491997-10-0808 October 1997 Addenda 1 to Part 21 Rept Re Weldments on Opposed Piston & Coltec-Pielstick Emergency stand-by Diesel gen-set lube-oil & Jacket Water Piping Sys.Revised List of Potentially Affected Utils to Include Asterisked Utils,Submitted ML20211H5311997-10-0101 October 1997 Rev 2 to Unit 1,Cycle 17 Colr ML20211H5251997-10-0101 October 1997 Rev 3 to Unit 1,Cycle 17 Colr 1999-09-30
[Table view] |
Text
- _ . - - . - - - . - . -
. Georgia Power Company ,
40 int 4erness Center Parkway Post Offce Box 1295
! Birmingham, Alabama 35201 Telephone 205 877 7279 L
J. T. Beckham, Jr. Georgia Power
, Vice Preskjent Nuclear
! Hatch Project the sovinem ela:rre system June 13, 1994 l l
) Docket Nos. 50-321 Hle4616 j 50-366 000005 1
j 3
1
- U.S. Nuclear Regulatory Commission ATFN
- Document Control Desk i Washington, D.C. 20555 i
Edwin I. Hatch Nuclear Plant Afonthlv Operating Reports l Gentlemen:
, Enclosed are the May 1994 Monthly Operating Reports for Edwin I. Hatch Nuclear Plant - Unit 1, Docket No. 50-321, and Unit 2, Docket No. 50-366. These l reports are submitted in accordance with the requirements of Technical Specification i 6.9.1.10.
Sincerely,
'h A J. T. Beckham, Jr.
SRP/sp
Enclosures:
- 1. May Operating Report for Plant Hatch - Unit 1 !
- 2. May Operating Report for Plant Hatch - Unit 2 c: (See next page.)
I
-l 9406200006 94o531 PDR
/24,P R ADOCK 05000321 ~/ l (jf '
l PDR d- I
1 I Georgia Power d i
i i U.S. Nuclear Regulatory Commission Page 2 i June 13, 1994 1
i j
s c: Georvia Power Company 4
Mr. fl. L Sumner, Nuclear Plant General Manager NORMS
' U.S. Nuclear Reeulatory Commission. Washineton. D.C.
'; Mr. K. Jabbour, Licensing Project Manager - Ilatch i
i US. Nuclear Reeulatory Commission. Region II Mr. S. D, Ebneter, Regional Administrator Mr. B. L Holbrook, Senior Resident Inspector - Hatch k Utility Data Institute. Inc.
j Mr. Fred Yost, Director - Research Services i
4 l
i i
i i
i l
4 i
l' e
1 1
I k tilA616 000005 l
1-
9 Enclosure 1 Plant Hatch Unit 1 ,
Monthly Operating Report l May 1994 '
1 Table of Contents i
Page i Narrative Report El-1 Operating Data Report El-2 Average Daily Power Level El-3 Unit Shutdowns and Power Reductions El-4 l
o l
l 1
l
! I IIIA616 l
. .. ~ _ _ - .
PLANT E. I. HATCH - UNIT ONE DOCKET NO.: 50-321 DATE: JUNE 1, 1994 NARRATIVE REPORT COMPLETED BY: T. W. TIDWELL TELEPHONE: (912) 367-7781 x2878 l
MAY l 0000 Shift continued to maintain rated thermal power. .
1 I
MAY 7 1950 Shift began reducing load to approximately 600 GMWe to perform quarterly Turbine Control Valve and Turbine Bypass Valve Testing.
MAY 7 2318- Shift began ascension to rated thermal power. l MAY 8 0008 Rated thermal power was attained.
MAY 20 2200 Shift began reducing load to approximately 280 GMWe to repair steam leaks in the Condenser Bay located on the 10th Stage Extraction Steam Piping and manway covers on the Moisture Separator Reheaters. 1 While at reduced load, shift also performed monthly Turbine Control Valve and Turbine Bypass Valve Testing.
MAY 22 1500 Shift began ascension to rated thermal power.
MAY 23 1415 Rated thermal power was attained.
MAY 31 2400 Shift continued to maintain rated thermal power.
1 El-1 i
OPERATING DATA REPORT DOCKET NO.: 50-321 1 DATE: JUNE 1, 1994 COMPLETED BY: T. W. TIDWELL l OPERATING STATUS
- 1. UNIT NAME: E. I. HATCH - UNIT ONE
- 2. REPORT PERIOD: MAY 1994 MWt : 2436
- 3. LICENSED
- 4. NAMEPLATE THERMAL RATING (GROSS POWER (MWe : 850 l
- 5. DESIGN ELECTRICAL RATING N T MWe : 776.3
- 6. HAXIMUM DEPENDABLE CAPACI Y GROS MWe): 774
- 7. MAXIMUM DEPENDABLE CAPACITY NET MWe): 741
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS ITEMS 3 THROUGH 7 SINCE LAST REPORT, GIVE REASONS: NO CHANGES
- 9. WER LEVEL TO WHI H RESTRICTED, IF ANY (NET MWe): NO RESTRICTIONS
- 10. REASONS FOR RESTRICTION, IF ANY: N/A l THIS MONTH YEAR-TO-DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD: 744.0 3623 161422
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL: 744.0 3557.9 121561.3
- 13. REACTOR RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
- 14. HOURS GENERATOR ON LINE: 744.0 3539.4 116495.9
- 15. UNIT RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
- 16. GROSS THERMAL ENERGY GENERATED (MWHt): 1741162 8512071 261620605
- 17. GROSS ELECTRICAL ENERGY GENERATED (MWHe): 558490 2741530 84085860
- 18. NET ELECTRICAL ENERGY GENERATED (MWHe): 533647 2623578 80014072
- 19. UNIT SERVICE FACTOR: 100.0% 97.7% 72.2%
- 20. UNIT AVAILABILITY FACTOR: 100.0% 97.7% 72.2%
- 21. UNIT CAPACITY FACTOR USING MDC NET): 96.8% 97.7% 66.2%
- 22. UNIT CAPACITY FACTOR USING DER NET): 92.4% 93.3% 63.6%
- 23. UNIT FORCED OUTAGE RA E: 0.0% 2.3% 11.6%
- 24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH):
60 Day Refueling Outage tentatively scheduled for September 21, 1994.
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIPATED DATE OF STARTUP: N/A
- 26. UNITS IN TEST STATUS (PRIOR TO COMMERCIAL OPERATION): N/A El-2 l
l
D PLANT E. I. HATCH - UNIT ONE DOCKET NO.: 50-321 DATE: JUNE 1, 1994 AVERAGE DAILY POWER LEVEL COMPLETED BY: T. W. TIDWELL 1 TELEPHONE: (912) 367-7781 x2878 I I
MAY 1994 l l
DAY Net MWe 1 .............. 747 2 .............. 749
.- - 3 .............. 746 '
4 .............. 749 5 .............. 752 i 6 .............. 752 7 .............. 726 8 .............. 750 9 .............. 752 10 .............. 749 11 .. ........... 750 12 .............. 745 13 .............. 748 14 .............. 746 15 .............. 743 16 .............. 744 17 .............. 749 18 .............. 752 19 .............. 754 20 .............. 749 21 .............. 259 22 .............. 310 23 .............. 732 24 .............. 749 25 .............. 748 26 .............. 748 27 .............. 745 28 .............. 749 29 .............. 748 30 .............. 748 31 .............. 747 l
l l
i I
El-3
. . - - . - . . - ._ - .. - - - ... .._ - - . =. -- . -- ... . - .
i UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO.: 50-321 DATE: JUNE 1, 1994 UNIT NAME: E. I. HATCH - UNIT DNE COMPLETED BY: T. W. TIDWELL
! TELEPHONE: (912) 367-7781 x2878
- i REPORT MONTH
- MAY 1994 R M S E E Y SC
' A T LICENSEE T
Y S H EVENT T0 COMPONENT CAUSE & CORRECTIVE P DURATION 0 0 REPORT ED CODE ACTION TO NO. DATE E (HOURS) N D NUMBER HE (SUBCODE) PREVENT RECURRENCE
,94-002 940520 S_ 0.0 B 5 N/A HJ PIPEXX Shift reduced load to :
(E) approximately 280 GMWe to HTEXCH repair steam leaks in the (A). Condenser Bay located on the 10th Stage Extraction Steam Piping and the Moisture .
Separator Reheater manway l covers.
l i
i TYPE: REASON: METHOD: EVENTS REPORTED INVOLVE A GREATER THAN 20%
F-FORCED 1-MANUAL REDUCTION IN AVERAGE
. S-SCHEDULED A-EQUIPMENT B-MAINTENANCE OR TEST FAILURE (EXPLAIN) 2-MANUAL DAILY SCRAM POWER LEVEL FOR C-REFUELING 3-AUTOMATIC SCRAM THE PRECEDING 24 HOURS.
D-REGULATORY RESTRICTION 4-CONTINUATIONS E-0PERATOR TRAINING & LICENSE 5-LOAD REDUCTION F-ADMINISTRATIVE 9-0THER (EXPLAIN)
G-0PERATIONAL ERROR (EXPLAIN)
H-0THER (EXPLAIN)
El-4 4
_ . _ _ . , . . - ~ , - - , -. . . . . . - . . . _ , , . - - - , . - - , - - . . _ - . - _ --. .m -
l I
Enclosure 2 Plant Hatch Unit 2 Afonthly Operating Report Afav 1994 Table of Contents ele Narrative Report E2-1 Operating Data Report E2-2 Average Daily Power Level E2-3 Unit Shutdowns and Power Reductions E2-4 l
l l IHA616 I
PLANT E. I. HATCH - UNIT TWO DOCKET NO: 50-366 DATE: JUNE 1, 1994 NARRATIVE REPORT COMPLETED BY: T. W. TIDWELL TELEPHONE: (912) 367-7781 x2878 MAY I 0000 Shift maintained the unit in hot shutdown while repair of the Feedwater Injection Valve continued.
MAY 2 2257 Shift began withdrawing control rods for unit startup.
MAY 3 0230 Shift brought the reactor critical.
MAY 4 0525 Shift tied the unit to the grid and began ascension to rated thermal power. Fuel preconditioning measures were implemented to prevent fuel degradation during ascension to rated thermal -power.
MAY 8 0033 Shift began reducing load to approximately 550 GMWe to perform a Control Rod Pattern Adjustment.
MAY 8 1300 Shift began ascension to rated thermal power MAY 10 1420 The unit attained rated thermal power.
MAY 15 0020 ShiftbegodDriveExercises.an Control reducing load to approximately 780 GMWe to pe MAY 15 0116 Shift began ascension to rated thermal power. l MAY 15 0240 The unit attained rated thermal power.
MAY 22 0120 Shift began reducing load to approximately 780 GMWe to perform Control Rod Drive Exercises.
MAY 22 0204 Shift began ascension to rated thermal power.
MAY 22 0256 The unit attained rated thermal power.
MAY 28 0003 Shift began reducing load to approximately 560 GMWe to perform a Control Rod Pattern Adjustment and Turbine Control Valve and Turbine Bypass Valve Testing.
MAY 28 0433 Shift began ascension to rated thermal power.
MAY 29 1345 The unit attained rated thermal power.
MAY 29 2400 Shift continued to maintain rated thermal power.
E2-1
OPERATING DATA REPORT DOCKET NO: 50-366 DATE: JUNE I, 1994 COMPLETED BY: T. W. TIDWELL TELEPHONE: (912) 367-7781 x2878 OPERATING STATUS: 1
- 1. UNIT NAME: E. I. HATCH - UNIT TWO
- 2. REPORTING PERIOD: MAY 1994 i
- 3. LICENSED THERMAL POWER (MWt : 2436 l
- 4. NAMEPLATE RATING (GROSS MWe : 850 1
- 5. DESIGN ELECTRICAL RATING (N T MWe): 784
- 6. MAXIMUM DEPENDABLE CAPACITY (GROSS MWe): 798 ;
- 7. MAXIMUM DEPENDABLE CAPACITY (NET MWe): 765
- 8. IF CHANGES OCCUR IN CAPACITY RATINGS ,
(ITEMS 3 THROUGH 7) SINCE LAST REPORT, GIVE REASONS: NO CHANGES
- 9. NWER LEVEL TO WHICH RESTRICTED, IF ANY (NET MWe): NO RESTRICTIONS
- 10. REASONS FOR RESTRICTION, IF ANY: N/A THIS MONTH YEAR-TO-DATE CUMULATIVE
- 11. HOURS IN REPORTING PERIOD: 744.0 3623 129048
- 12. NUMBER OF HOURS REACTOR WAS CRITICAL: 693.5 2522.6 98262.8
- 13. REACTOR RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
- 14. HOURS GENERATOR ON LINE: 666.6 2450.1 94676.1
- 15. UNIT RESERVE SHUTDOWN HOURS: 0.0 0.0 0.0
- 1507003 4587549 208059424 16.GROSS
- 17. GROSS THERMAL ELECTRICAL ENERGY ENERGY GENERATED (HWGENERATED (MWHt)He):
496900 1490000 68104740 64842735
- 18. NET ELECTRICAL ENERGY GENERATED (MWHe): 474341 1408044
- 19. UNIT SERVICE FACTOR: 89.6% 67.6% 73.4%
- 20. UNIT AVAILABILITY FACTOR: 89.6% 67.6% 73.4%
- 21. UNIT CAPACITY FACTOR USING MDC NET): 83.3% 50.8% 65.8%
- 22. UNIT CAPACITY FACTOR USING DER NET): 81.3% 49.6% 64.1%
- 23. UNIT FORCED OUTAGE RA E: 10.4% 3.4% 7.4%
- 24. SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE, AND DURATION OF EACH): N/A
- 25. IF SHUTDOWN AT END OF REPORT PERIOD, ESTIMATED DATE OF STARTUP: N/A
- 26. UNITS IN TEST STATUS (PRIOR TO CDMMERCIAL OPERATION): N/A 1
E2-2 1
l 1
I t
I PLANT E. I. HATCH - UNIT TWO DOCKET N0: 50-366 DATE: JUNE 1, 1994 AVERAGE DAILY POWER LEVEL COMPLETED BY: T. W. TIDWELL TELEPHONE: (912) 367-7781 x2878 DAY Net MWe 1 .............. 0
. 2 .............. 0 3 .............. 0 4 .............. 121 5 .............. 452 6 .............. 633 7 .............. 660
-8 .............. 519 9 .............. 649 10 .............. 751 11 .............. 772 12 .............. 768 13 .............. 768 14 .............. 768 15 .............. 766-16 .............. 766 17 .............. 771 18 .............. 774 19 .............. 774 20 .............. 777 21 .............. 776 22 .............. 773 23 .............. 773 '
24 .............. 771 25 .............. 771 26 .............. 771 27 .............. 762 28 .............. 624 29 .............. 754 30 .............. 771 31 .............. 771 E2-3 4
- , - m., -. -- ,. - - , , ,y -. _ , . , - . , , . ~,-.p.,
l 1
UNIT SHUTDOWNS AND POWER REDUCTIONS DOCKET NO: 50-366 i DATE: JUNE 1, 1994 UNIT NAME: E. I. HATCH - UNIT TWO COMPLETED BY: T. W. TIDWELL TELEPHONE: (912) 367-7781 x2878 REPORT MONTH: MAY 1994 i
R H S E E Y Y A T LICENSEE SC
'; S H EVENT T0 COMP 0NENT CAUSE & CORRECTIVE P DURATION 0 0 REPORT ED CODE ACTION TO N0. DATE E (HOURS) N D NUMBER HE (SUBCODE) PREVENT RECURRENCE 94-004 940430 F 77.4 A 4 N/A CH VALVEX The unit was manually (E) scrammed to repair one of the Feedwater Injection Valves which was mechanically bound and would not open. The valve internals and stem were replaced, and a hole was drilled in the wedge to prevent pressure locking.94-005 940508 S 0.00 F 5 N/A RC FUELXX Unit load was reduced to approximately 550 GMWe to perform a rod pattern adjustment.94-006 940528 S 0.00 F 5 N/A RC FUELXX Unit load was reduced to approximately 560 GMWe to perform a rod pattern adjustment.
TYPE: REASON: METHOD: EVENTS REPORTED INVOLVE A GREATER THAN 20%
F-FORCED A-EQUIPMENT FAILURE (EXPLAIN) 1-MANUAL REDUCTION IN AVERAGE S-SCHEDULED B-MAINTENANCE OR TEST 2-MANUAL SCRAM DAILY POWER LEVEL FOR C-REFUELING 3-AUTOMATIC SCRAM THE PRECEDING 24 HOURS.
D-REGULATORY RESTRICTION 4-CONTINUATIONS E-0PERATOR TRAINING & LICENSE 5-LOAD REDUCTION F-ADMINISTRATIVE 9-0THER (EXPLAIN)
G-0PERATIONAL ERROR (EXPLAIN) i l
H-0THER (EXPLAIN)
E2-4 1