A03719, Provides Info for Resolution of Open Items in Amend 89 to License DPR-65 Re Repair of Degraded Steam Generator Tubes by Combining Current Repair Method of Plugging Tubes W/New Method of Installing Metal Tubes

From kanterella
Jump to navigation Jump to search

Provides Info for Resolution of Open Items in Amend 89 to License DPR-65 Re Repair of Degraded Steam Generator Tubes by Combining Current Repair Method of Plugging Tubes W/New Method of Installing Metal Tubes
ML20091L880
Person / Time
Site: Millstone Dominion icon.png
Issue date: 05/25/1984
From: Counsil W
NORTHEAST NUCLEAR ENERGY CO., NORTHEAST UTILITIES
To: John Miller
Office of Nuclear Reactor Regulation
References
A03719, A3719, TAC-54741, TAC-65852, TAC-66116, NUDOCS 8406080239
Download: ML20091L880 (8)


Text

__

{

General Offices

'****N"***"*"

q P.O. BOX 270

[Z,"[7"" HARTFORD. CONNECTICUT 06141-0270 L t  ; :::=l; r,-- ( ) SS8*"

May 25,1984 Docket No. 50-336 A03719 Director of Nuclear Reactor Regulation Attn: Mr. James R. Miller, Chief Operating Reactors Branch #3 U. S. Nuclear Regulatory Ccmmission Washington, D. C. 20555

References:

(1) K. L. Heitner letter to W. G. Counsil, dated December 30, 1983.

(2) W. G. Counsil letter to R. A. Clark, dated June 3,1983.

Gentlemen:

Millstone Nuclear Power Station, Unit No. 2 Resolution of Open items Amendment 89 to DPR-65 Amendment No. 89 to DPR-65 for Millstone Unit No. 2 was issued by the NRC Staff in Reference (1). The amendment allows repair of degraded steam generator tubes by installing metal sleeves together with the current repair method which involves plugging the tube.

The Reference (1) transmittal letter and safety evaluation report identified two items for which the Staff requested additional confirmatory documentation.

Specifically, the Staff requested NNECO to justify the 40% plugging criterion for degraded sleeves proposed in Reference (2) and to provide a status repore on the efforts to more accurately determine primary-to-secondary leakage.

The information requested by the Staff is provided in the attachment hereto. It is concluded that the 40% plugging limit for degraded sleeves is appropriate t

,s

(._ ,

! based on the evaluation conducted in accordance with Regulatory Guide 1.121.

.We trust you find it responsive to your requests. My Staff remains available to

. assist you in your review of this matter.

Very truly yours, NORTHEAST NUCLEAR ENERGY COMPANY W. G. Counsil Senior Vice President J

+-.'Mo

(

f n , _

ha m

4

.=

Docket No. 50-336 R

L.

Attachment Millstone Nuclear Power Station, Unit No. 2 Resolution of Open Items Amendment 89 to DPR-65

o

\

i s

- l 1

l,

.H

& i ^g,

    • .Ir e - May,1984
s. . v..
y- ,

s , t i

?

Y -

f .

.' , jl' ( 1.'. 1 T , '; ' , -}

Q,

~

,. ; \ .1. ..

'l, 7' v_ ;- V %, ..

i<J. ; :., , 4, s -

  • -g 1 . , . .

f, .,

c:1

-, u + s , ' ,t

.* .V

'm)

.s

i 4

Confirmation of Sleeve Plugging Limit Section 4.2 of the NRC Safety Evaluation Report (l) supporting Amendment No.

89_ to Operating License No. DPR-65 for Millstone Unit No. 2 discusses allowable steam generator pigeve degradation. Northeast Nuclear Energy Company (NNECO) proposedt2i that steam generator tubes with sleeves degraded forty percent (40%) through wall would be plugged. The NRC Staff requested NNECO to establish equivalency in bending strengths for a tube and sleeve degraded forty percent through wall to support the proposed plugging limit for sleeves.

NNECO conducted reviews in accordance with the guidance of Regulatory Guide 1.121 to determine the appropriate plugging limit for the sleeves. Bending stresses were determined for both tubes and sleeves under normal and accident conditions. The following discussion addresses the issue of bending strength of steam generator tubes and tube sleeves as it relates to the proposed plugging criterion for sleeves.

Millstone Unit No. 2 employs a Combustion Engineering design nuclear steam supply system. Each of the two steam generators contain 8519 tubes in a U-bend configuration. The tubes are arranged in a triangular pitch. The tube sheet is 21.5 inches thick and 14 feet in diameter. Since the pressure is normally higher on the primary side of the tube sheet than on the secondary side, the tube sheet becomes concave upward. The tube sheet flexes further during a main steamline break due to the larger pressure differential between the primary and secondary sides of the steam generator. Design features have been incorporated into the steam generator to limit the tube sheet deflection. The most notable feature of the Millstone Unit No. 2 steam generator design is the stay cylinder depicted in Figure 4.3-2 of the FSAR included herein.

The loading conditions imposed on the tubes and sleeves during a main steam line break (MSLB) include the following. The pressure differential across the tube sheet during a MSLB causes the tube sheet to become concave upward. This flexure induces an end rotation on the sleeves and tubes. . Crossflow conditions from the fluid flow from the downcomer into the tube bundle will impart a transverse load to the peripheral tubes. However, this load is not of concern to sleeves since the peripheral tubes (first three rows) are not sleeved due to the geometry of the steam generator channel head (sleeves cannot be inserted into peripheral tubes). Internal tubes containing sleeves will be shielded from the cross flow by the peripheral tubes and the sleeves themselves will be shielded by their parent tube. As such the cross flow loads will not be imparted to sleeves.

Uplift forces on the tube bundle will exist due to the large steam flow resulting from the MSLB. Wese forces translate to an' axial pull-out force in the area of the tube bundle containing the sleeves. Moments imparted to the' tubes as a -

result of the uplift -forces will be mitigated by the multiple ; tube supports between the- top of the tube _ bundle and the tube sheet. Differential thermal expansion between the tubes / sleeves and the steam generator shell due to -

material property differences will impose an axial load on the tubes and sleeves.

In addition to the loads described above, the tubes and sleeves have a differential

. pressure across their boundary _which produces an additionalload.

De tube sheet will deflect due to the pressure differential regardless of the presence of a sleeve in al degraded steam generator tube. This deflection will rotate the steam generator tubes protruding from the top of the tube sheet from e

, ,,~v e,-,--, ,,  %. , .-% .

y - - , , , , - - ,, f --- . ,-

vertical. This tube rotation imparts a bending stress in the tube or tube / sleeve arrangement. The ability of the steam generator to perform its function under both normal and accident conditions is influenced by the capability of the tubes and/or ' sleeves . to accommodate the bending imposed by - the tube sheet

. deflection. In this regard the stiffness of the tube and sleeve material will determine what level of bending stress is imposed on the tube and/or sleeve by ,

the tube sheet deflection. l The sleeve design is such that it is not as stiff as the parent tube. As such, the sleeve will accommodate the tube sheet deflection better than the original tube.

This is demonstrated in Section 6.3.3 of Reference (2) where for normal operation, the bending stress for a sleeve is less than for a tube. This relationship holds true for accident conditions also.

NNECO has evaluated the stresses which will be imposed on a tube or a sleeve under the main steam line break accident. Under these conditions, stresses will result from the tube sheet rotation (bending), axial compression (assuming the tube is fixed at the first egg crate support), and thermal growth differences due to the different materials used for tubes, sleeves and the steam generator shell.

The maximum stress in.a degraded sleeve under these conditions is less than the yield strength of the sleeve by more than a factor of three.

The ' fact that the tubesheet deflection occurs regardless of the material properties or design of the tubes or sleeves renders a bending strength comparison immaterial. Margin to burst is the appropriate measure assuring steam generator integrity when evaluating a plygging limit for steam generator tubes and sleeves. It has been demonstratedu/ that a sleeve degraded 40%

through . wall has a factor of safety of 3 or more against burst under all conditions specified in Regulatory Guide 1.121. As such, the proposed plugging limit has been appropriately supported.

Primary-to-Secondary Leak Rate Determinations The accompanying letter to Amendment No. 89 to DPR-65 requested NNECO to c provide a status report of actions taken to more accurately determine primary-to-secondary leakage. .

NNECO initiated actions to improve primary-to-secondary leakage rate determinations following the conclusion in early 1983 that leakage rates

. measured by(3)(41isotppic. analysis of the blowdown system effluents were- non-conservative. These actions included the use of the steam jet air ejector radiation monitors and the reactor coolant system mass balance determination.

4 Leak rates utilizing the steam jet air ejector discharge flow have been

. performed since the plant returned to service'in March,1983. This technique was included in the leak rate procedures'during'3anuary,1984. Experience has been ~ gained in utilizing this more sensitive' measurement technique with leak rates calculated from the . isotopes of Xenon 133 and 135. 'In addition, the reactor coolant system 1(RCS) leak rate program has been. reviewed and operational techniques for. identifying sources of leakage improved. This has resulted in increased confidence 'in the ability to identify sources of RCS leakage, including possible primary-to-secondary leakage, w2 w'

^'

t k -

v~ + y 4 e , +m ,

The increased ability to more accurately determine primary-to-secondary leakage rates has not been quantified due to the improved performance of the steam generators since the March,1983 outage. The lack of a primary-to-secondary leak during the remainder of Cycle 5 and the start of Cycle 6 make it impossible to verify any improvements. However, the confidence in the ability to measure leakage has increased due to the two refinements discussed above.

During future periods of significant steam generator leakage (greater than 0.1 gallons per minute) the steam generator blowdown calculation and the steam jet air ejector calculation will provide measurement of the leakage. The steam jet air ejector calculation will provide a total leakage number which will be matched against the sum of the individual blowdown leak rates. As an additional check, if tne above leak rates are not compatible, the primary-to-secondary leak rates can be compared to the RCS leak rate with other known leakage subtracted.

This program has been formalized in Inservice Test T84-il and will be implemented when leakage exceeds 0.1 gallons per minute. The results will be utilized to determine the most effective and accurate measurement technique.

l l

, . l References

' (1) K. L. Heitner letter to W. G. Counsil, dated December 30, 1983.

- (2) W. G. Counsil letter to R. A. C! ark, dated June 3,1983.

(3) E. J. Mroczka letter to R. C. Haynes, dated March 31, 1983.

(4) ' W. G. Counsit letter to R. A. Clark, dated March 14, 1983.

'_s ; 2.

-k M" Y m; .._ :

.. a ..

Stcom

- . Outist .

Nozzle i,

\ Deflector Top j 126 Steam Head i - Dryers data m_c ESt ma E -

'l li" \

/ liil ]" Level Secondary 32 Steam . j Indication Manway Dryer Weins - i e ,

" Nozzle '

(2 Req'd ) I kndho Ste,om

, , , _ (4 Reg'd )

(2 Req'd )  :-

Surface

  • [y z Brocke (2 Req'd )

Fee z}e ater (2 Req'd ) i ..

J ..

{

I \ . -

levis Brocket i

1 " Level (4 Reg'd )

Indication Nozzles / 1 " Level i .

/ Indication l Instrument Nozzle Nonles  ; ""-*

e.

'""~ ~

j (4 Req'd )

's - 8485 -

1 " Level I 3/4 " O. D.

Indication Pr.imary gozzie, Tubes Inlet Nozzle f Primary Bottom View A. A Nozzle 165 O. D. - -- 749a Blowdown and Drain

. (62'- 5 ")

Secondary Bottom l I Handhole Blowdown (2 Req'd ) Pipe i Bottom - -B I

m -

/ (ff and owdown Bl Drain fA l I

1 Nozzle Primary '

Instrument w a Head -- - Nozzle I

! _ (4 Reg'd )

Primary Manway .

Outlet (2 Req'd ) )l Divider Plate *]g, )( Nozzle

\ ,A Support / \ (2 Req d ) ',

Skirt Q

Section B- B - -

l 1 Millstone Figure Nuclear P er Station ,

$leam Generator '

43-2