05000010/LER-1995-001, Provides Addl Info Re Commitments in LER 95-01 to Submit Amend Request.Ts Amend Request Will Be Submitted No Later than 961127

From kanterella
Jump to navigation Jump to search
Provides Addl Info Re Commitments in LER 95-01 to Submit Amend Request.Ts Amend Request Will Be Submitted No Later than 961127
ML20128H264
Person / Time
Site: Dresden Constellation icon.png
Issue date: 10/04/1996
From: Jamila Perry
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
JSPLTR#96-0178, JSPLTR#96-178, NUDOCS 9610090292
Download: ML20128H264 (2)


LER-2095-001, Provides Addl Info Re Commitments in LER 95-01 to Submit Amend Request.Ts Amend Request Will Be Submitted No Later than 961127
Event date:
Report date:
0102095001R00 - NRC Website

text

_ .

. Commonwcalth 1:dison Compan) a 1)resden Generating Station MOO North Dresden Road Morris. II. N) ISO Tcl Mi 5-9 62 2920 October 4,1996 JSPLTR #96-0178 U. S. Nuclear Regulatory Commission Washington, D. C. 20555-0001 Attention: Document Control Desk

Subject:

Dresden Nuclear Power Station, Revision to commitment date made in LER 95-01, NRC Docket No.50-010

Reference:

T..amas P. Joyce (Comed) to U.S. NRC letter dated July 15,1995, transmitting License Event Report 95-01, Docket No.50-010 The purpose of this letter (as discussed in previous telephone conversations) is to provide additional information regarding Dresden Station's commitment in LER 95-01 to submit a Dresden Unit 1 Technical Specification Amendment request. The commitment was to modify the adnunistrative section of Dresden Unit 1 Technical Specifications to be similar to that of Units 2 and 3.

The commitment to have the Technical Specification submitted to the NRC by September,1996 was not met. This is primarily due to a new Comed organizational restructuring that requires revisions to the Decommissioning Plan and the Quality Assurance Topical Report. Additionally, a Corporate Memorandum of Understanding is currently under review that defines roles and responsibilities regarding decommissioning activities. It is anticipated that these administrative changes will be completed during the month of October and therefore the Technical Specification Amendment Request will be submitted no later than November 27,1996.

09004g WVY 9610090292 961004 PDR ADOCK 05000010 S PDR A rnicom compan>

October 4,1996 JSPLTR #96-0178 Page 2 of 2 If there are any questions concerning this letter, please refer them to Charles Allen, Dresden Station Unit 1 Licensing Director, at (815) 942-2920, extension 2857.

Sincerely,

'h Ste he ry Site Vice President Dresden Station JSP/CA:Id cc: A. W. Beach, Regional Administrator, Rlli P. L. Hiland, Branch Chief, DRPS, Rlli M. Webb, Project Manager, NRR (Unit 2/3)

C. L. Vanderniet, Senior Resident inspector, Dresden J. A. Gavula, Region Ill.

Office of Nuclear Facility Safety - IDNS

.