04/04/2007 Summary of Public Meeting with Nuclear Management Co., Regarding the Nrc'S Assessment of the Monticello Nuclear Generating Plant Safety Performance for the Period from January 1 Through December 31, 2006
ML071060201
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 04/13/2007
From: Burgess B
NRC/RGN-III/DRP/RPB2
To:
References
Download: ML071060201 (5)


Text

April 13, 2007LICENSEE:Nuclear Management CompanyFACILITY:Monticello Nuclear Generating Plant

SUBJECT:

SUMMARY

OF THE APRIL 4, 2007, PUBLIC MEETING TO DISCUSS THEMONTICELLO NUCLEAR GENERATING PLANT END-OF-CYCLE PLANT PERFORMANCE ASSESSMENTOn April 4, 2007, the Nuclear Regulatory Commission (NRC) held a public meeting at theMonticello Community Center in Monticello, MN. The meeting was between NRC Region III management and Nuclear Management Company representatives to discuss the NRC's assessment of the Monticello Nuclear Generating Plant's safety performance for the period from January 1 through December 31, 2006. The meeting notice can be found in ADAMS as Accession Number ML070710580 and the NRC presentation slides as ML071020489. A list of meeting participants can be found in the attached Enclosure.The NRC began the meeting with an overview of the NRC's Reactor Oversight Process (ROP),national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRC's assessment of the Monticello Nuclear Generating Plant's performance in calendar year 2006, which was documented in the March 2, 2007, end-of-cycle assessment letter recorded in ADAMS as Accession Number ML070610192. The NRC also discussed upcoming inspections and activities at the Monticello Nuclear Generating Plant.As part of this regulatory performance meeting, Nuclear Management Company responded tothe NRC's assessment and discussed Monticello Nuclear Generating Plant's plans for future improvements. /RA/Bruce L. Burgess, ChiefBranch 2 Division of Reactor ProjectsDocket No. 50-263License No. DPR-22

Enclosure:

Public Meeting Attendees DISTRIBUTION:See next page LICENSEE:Nuclear Management CompanyFACILITY:Monticello Nuclear Generating Plant

SUBJECT:

SUMMARY

OF THE APRIL 4, 2007, PUBLIC MEETING TO DISCUSS THEMONTICELLO NUCLEAR GENERATING PLANT END-OF-CYCLE PLANT PERFORMANCE ASSESSMENTOn April 4, 2007, the Nuclear Regulatory Commission (NRC) held a public meeting at theMonticello Community Center in Monticello, MN. The meeting was between NRC Region III management and Nuclear Management Company representatives to discuss the NRC's assessment of the Monticello Nuclear Generating Plant's safety performance for the period from January 1 through December 31, 2006. The meeting notice can be found in ADAMS as Accession Number ML070710580 and the NRC presentation slides as ML071020489. A list of meeting participants can be found in the attached Enclosure.The NRC began the meeting with an overview of the NRC's Reactor Oversight Process (ROP),national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRC's assessment of the Monticello Nuclear Generating Plant's performance in calendar year 2006, which was documented in the March 2, 2007, end-of-cycle assessment letter recorded in ADAMS as Accession Number ML070610192. The NRC also discussed upcoming inspections and activities at the Monticello Nuclear Generating Plant.As part of this regulatory performance meeting, Nuclear Management Company responded tothe NRC's assessment and discussed Monticello Nuclear Generating Plant's plans for future improvements. Bruce L. Burgess, ChiefBranch 2 Division of Reactor ProjectsDocket No. 50-263License No. DPR-22

Enclosure:

Public Meeting Attendees DISTRIBUTION:See next pageDOCUMENT NAME:C:\FileNet\ML071060201.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-SensitiveTo receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copyOFFICERIIIRIIINAMECScott:dtpBBurgessDATE04/13/200704/13/2007OFFICIAL RECORD COPY Nuclear Management Companycc w/encl:Mr. John Conway, Site Vice President M. Sellman, President and Chief Executive Officer D. Cooper, Senior Vice President and Chief Nuclear Officer Manager, Nuclear Safety Assessment J. Rogoff, Vice President, Counsel, and Secretary Nuclear Asset Manager, Xcel Energy, Inc.

State Liaison Officer, Minnesota Department of Health R. Nelson, President Minnesota Environmental Control Citizens Association (MECCA)

Commissioner, Minnesota Pollution Control Agency D. Gruber, Auditor/Treasurer, Wright County Government Center Commissioner, Minnesota Department of Commerce Manager - Environmental Protection Division Minnesota Attorney General's Office Chairman, Wright County Board Mayor of Monticello Chairperson, Sherburne County Administrator, City of Monticello INPO Nuclear Management CompanyDISTRIBUTION

HKN PST TEB RidsNrrDirslpab

JLC1 GEG KGO GLS RML2 SAM9 SRI Monticello DRPIII DRSIII PLB1 TXN EnclosurePUBLIC MEETING PRINCIPAL ATTENDEESApril 4, 2007 NRCM Satorius, Director, Division of Reactor Projects, Region IIIB. Burgess, Chief, Branch 2, Division of Reactor Projects, Region III K. Riemer, Chief, Plant Support Branch, Division of Reactor Safety, Region III C. Thomas, Senior Resident Inspector, Monticello L. Haeg, Resident Inspector, Monticello Nuclear Management CompanyJ. Conway, Site Vice President, Monticello B. Sawatzke, Plant Manager, Monticello R. Baumer, Compliance Engineering Analyst, Monticello A. Datu, Public Affairs Officer, HudsonXcel EnergyC. Bomberger, Nuclear Asset Manager, T. Pickens, Manager, Nuclear Regulatory PolicyMembers of the PublicM. Ryan, Time Staff Writer, St.Cloud Times