MONTHYEARPMNS20230213, Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application2023-03-14014 March 2023 Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application Project stage: Meeting ML23110A0132023-03-14014 March 2023, 22 March 2023, 18 April 2023, 1 May 2023 Public March 22 Public Meeting Summary Project stage: Request ML23081A0392023-03-22022 March 2023 Presentation Slide for Monticello Public Scoping Meeting, March 22, 2023 Project stage: Request PMNS20230237, Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application2023-03-28028 March 2023 Environmental Scoping Meeting Related to the Monticello Nuclear Generating Plant Subsequent License Renewal Application Project stage: Meeting ML23108A3132023-04-18018 April 2023 March 22, 2023, Monticello Nuclear Generating Plant, Unit 1, Subsequent License Renewal Application Public Environmental Scoping Meeting Transcript Project stage: Meeting ML23110A0152023-05-0101 May 2023 Summary March 22, 2023, Monticello Units 1 Subsequent License Renewal Application Public Environmental Scoping Meeting Project stage: Meeting ML23115A4382023-05-0101 May 2023 March 29, 2023, Meeting Summary for Environmental Review of Subsequent License Renewal Application for Monticello Nuclear Generating Plant, Unit 1 Project stage: Meeting ML23110A0142023-05-0101 May 2023 Memo March 22, 2023, Monticello Unit 1, Subsequent License Renewal Application Public Environmental Scoping Meeting Project stage: Meeting ML23047A1182023-06-0202 June 2023 Notice of Intent to Conduct Scoping Process and Prepare an EIS Project stage: Other ML23199A2802023-07-0303 July 2023 Request for Scoping Comments Concerning the Environmental Review of Monticello Nuclear Generating Plant, Unit 1, Subsequent License Renewal Application Wright and Sherburne Counties, Minnesota Project stage: Request ML23215A1312023-08-0909 August 2023 – License Renewal Regulatory Audit Regarding the Environmental Review of the Subsequent License Renewal Application Project stage: Approval ML23291A1102023-10-23023 October 2023 Environmental Audit Summary and RCIs and RAIs Project stage: Other ML24059A2882024-03-18018 March 2024, 31 March 2024 Scoping Summary Project stage: Request ML24059A3292024-03-18018 March 2024 Scoping Summary Report Cover Letter Project stage: Other ML24059A3422024-03-31031 March 2024 Scoping Summary Report Project stage: Request ML24312A1732024-11-18018 November 2024 Ltr. to Shawn Hafen, Site Vice President, Monticello Nuclear Generating Plant, Re., NOA of the Final EIS for the Monticello Nuclear Generating Plant, Unit 1 SLR Project stage: Other 2023-05-01
[Table View] |
Text
.
MEMORANDUM TO:
Theodore Smith, Chief Environmental Review License Renewal Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards FROM:
Jessica M. Umana, Project Manager Environmental Review License Renewal Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards
SUBJECT:
MEETING
SUMMARY
- PUBLIC SCOPING MEETING FOR THE ENVIRONMENTAL REVIEW OF THE SUBSEQUENT LICENSE RENEWAL APPLICATION FOR MONTICELLO NUCLEAR GENERATING PLANT, UNIT 1 (EPID NO.: L-2023-SLE-0000)
On March 29, 2023, the NRC staff conducted a scoping webinar to gather information necessary to prepare an environmental impact statement to evaluate the environmental impacts for the subsequent license renewal of the operating license for Monticello Nuclear Generating Plant, Unit 1. Enclosed is the meeting summary. If you have any questions or comments, please contact me via e-mail at Jessica.Umana@nrc.gov.
Docket No. 50-263
Enclosures:
1.
Meeting Summary 2.
List of Attendees 3.
NRC slide presentation 4.
Meeting transcript cc: w/encls: Listserv CONTACT:
Jessica Umana, NMSS/REFS 301-415-5207 May 1, 2023 Signed by Umana, Jessica on 05/01/23
T. Smith 2
SUBJECT:
MEETING
SUMMARY
- PUBLIC SCOPING MEETING FOR THE ENVIRONMENTAL REVIEW OF THE SUBSEQUENT LICENSE RENEWAL APPLICATION FOR MONTICELLO NUCLEAR GENERATING PLANT UNIT 1 (EPID NO.: L-2023-SLE-0000)
DATED:
May 1, 2023 DISTRIBUTION:
PUBLIC RidsNrrDnrl Resource RidsNrrDnrl Resource THerrera, OEDO RidsACRS_MailCTR Resource MBailey, OEDO/AO RidsRgn3MailCenter Resource DRoth, OGC RidsRgn3Dnms Resource CWolf, OCA RidsRgn3Drp Resource TMcGowan, RIII/DORS RidsRgn3Drs Resource CNorton, RIII/DORS RidsRgn3Ora Resource HPeterson, RIII/DORS RidsRgn3Opa Resource NFeliz-Adorno, RIII/DORS RidsNrrOd Resource MDomke, RIII/DORS LGibson, NRR/DNRL ABarker, RIII/FCO JHammock, NRR/DNRL HLogaras, RIII/FCO JUmana, NMSS/REFS VMitlyng, RIII/OPA TSmith, NMSS/REFS PChandrathil, RIII/OPA BSmith, NRR/DNRL BThomson, NRR/DNRL Max.W.Smith@xcelenergy.com JUmana, NMSS/REFS paul.b.young@xcelenergy.com BBallard, NRR/DORL stephen.sollom@xcelenergy.com NSalgado, NRR/DORL ADAMS Accession No(s).: ML23115A452 (pkg)*concurred via email OFFICE PM/ELRB/REFS LA/ERMB/REFS BC/ELRB/REFS PM/ELRB/REFS NAME Jumana*
AWalker-Smith*
TSmith*
Jumana*
DATE 4/27/23 4/28/23 5/1/23 5/1/23