MONTHYEARML23192A7552023-07-14014 July 2023 July 14, 2023 Alternative Request to Defer Pvt of MO-2397 Pre-submittal Meeting Slides Project stage: Meeting ML23200A2602023-07-20020 July 2023 Summary of July 14, 2023, Public Meeting with Northern States Power Company Regarding Proposed Alternative to Defer Periodic Verification Testing of Reactor Water Clean-Up Inboard Isolation Valve Project stage: Meeting 2023-07-14
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML23313A1592023-11-0909 November 2023 U.S. Nuclear Regulatory Commission Summary of the October 10, 2023, Public Meeting to Discuss Monticello'S Condensate Backwash Receiving Tank Fatigue Evaluation ML23275A0222023-10-0505 October 2023 Summary of September 21, 2023, Public Meeting with Northern States Power Company Regarding Proposed License Amendment Request to Revise the Pressure Temperature Limits Report ML23200A2602023-07-20020 July 2023 Summary of July 14, 2023, Public Meeting with Northern States Power Company Regarding Proposed Alternative to Defer Periodic Verification Testing of Reactor Water Clean-Up Inboard Isolation Valve ML23157A0432023-06-0808 June 2023 Summary of Public Outreach to Discuss the NRC 2022 End-Of-Cycle Plant Performance Assessment of Monticello Nuclear Generating Plant ML23110A0142023-05-0101 May 2023 Memo March 22, 2023, Monticello Unit 1, Subsequent License Renewal Application Public Environmental Scoping Meeting ML23110A0152023-05-0101 May 2023 Summary March 22, 2023, Monticello Units 1 Subsequent License Renewal Application Public Environmental Scoping Meeting ML23115A4382023-05-0101 May 2023 March 29, 2023, Meeting Summary for Environmental Review of Subsequent License Renewal Application for Monticello Nuclear Generating Plant, Unit 1 ML23115A4642023-05-0101 May 2023 Summary, March 29, 2023, Monticello Units 1 Subsequent License Renewal Application Public Environmental Scoping Meeting ML23074A1212023-04-0303 April 2023 March 8, 2023, Summary of Public Meeting with Northern States Power Company Regarding Monticello Nuclear Generating Plant Alternative Request PR-08 to Defer Quarterly Testing of Components of High Pressure Coolant Injection System ML22292A0122022-10-24024 October 2022 Meeting Summary for Environmental Pre Submittal Meeting for Subsequent License Renewal Application, on September 13, 2022 ML22208A2192022-08-0303 August 2022 Summary of July 25, 2022, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to the Amendment to Adopt Advanced Framatome Inc. Methodology for Determining Core Operating Limits for Monticello Plant ML22208A1952022-08-0303 August 2022 Summary of July 26, 2022, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to the Alternative Request for Excess Flow Check Valves at Monticello Nuclear Generating Plant ML22130A7172022-05-10010 May 2022 Summary of the May 3, 2022, Public Outreach to Discuss the NRC 2021 End-Of-Cycle Plant Performance Assessment of Monticello and Prairie Island Nuclear Generating Plant, Units 1 and 2 ML22084A3852022-03-31031 March 2022 Meeting Summary for Environmental Pre Submittal Meeting for Subsequent License Renewal Application on March 15, 2022 ML22032A0112022-02-0303 February 2022 Summary of January 27, 2022, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned Relief Request to Test Excess Flow Check Valve ML21285A0312021-10-15015 October 2021 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to Planned License Amendment to Extend Allowed Outage Time for Fuel Oil Storage Tank for Monticello Nuclear Plant ML21167A1842021-06-16016 June 2021 Summary of the June 9, 2021, Public Outreach to Discuss the NRC 2020 End-Of-Cycle Plant Performance Assessment of Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant, Units 1 and 2 ML21098A0742021-04-13013 April 2021 Summary of March 25, 2021, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned License Amendment to Adopt Advanced Framatome Methods ML21040A4612021-02-11011 February 2021 Summary of February 3, 2021, Meeting with Northern States Power Company, Doing Business as Xcel Energy, Related to a Planned License Amendment to Combine the Emergency Plans and Create a Common Emergency Operations Facility ML20281A5092020-10-16016 October 2020 Summary of October 2, 2020, Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential Amendment to Revise the Safety Limit Minimum Critical Power Ratio for Monticello Nuclear Generating Plant ML20218A4462020-08-0505 August 2020 Summary of the July 16, 2020 Public Outreach to Discuss the NRC 2019 End-of-Cycle Plant Performance Assessment of Monticello Nuclear Generating Plant ML20077L8312020-03-20020 March 2020 Summary of February 27, 2020, Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment to Adopt TSTF-505 Provide Risk-Informed Completion Times - RITSTF Initiative 4b ML19130A1672019-05-14014 May 2019 May 8, 2019 Summary of Teleconference with Northern States Power Company, Doing Business as Xcel Energy, to Discuss a Response to a Request for Additional Information Related to the License Amendment Request to Adopt 10 CFR 50.69 ML18046B2072018-02-26026 February 2018 Summary of February 8, 2018, Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential Exemption from Fire Protection Requirements at Monticello Nuclear Generating Plant Units 1 and 2 ML17353A0242018-01-0202 January 2018 Summary of December 12, 2017, Teleconference with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment Request to Adopt TSTF-425 ML17341A1292017-12-11011 December 2017 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Changes to the Security Plans at the Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant, Units 1 and 2 ML17300A0362017-10-31031 October 2017 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment Request Related to Emergency Diesel Generator Technical Specifications ML17270A0072017-09-29029 September 2017 Summary of Teleconference with Northern States Power Company, Doing Business as Xcel Energy, on Potential License Amendment Request to Adopt TSTF-542 Reactor Pressure Vessel Water Inventory Control ML17235B1542017-08-23023 August 2017 July 11, 2017,Summary of the Open House to Discuss the 2016 End-Of-Cycle Plant Performance Assessment of Monticello ML17090A2442017-04-0606 April 2017 Summary of February 28, 2017, Meeting with Northern States Power Company, Doing Business as Xcel Energy, on the Integrated Leak Rate Test License Amendment Request for Monticello Nuclear Generating Plant CAC No. MF7359) ML17034A1202017-02-0909 February 2017 Summary of January 24, 2017, Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential Revision to the Emergency Action Level ML16334A0112016-12-0606 December 2016 Summary of Meeting with Northern States Power Company, Doing Business as Xcel Energy, on Potential Exemption Request from Fire Protection Requirements ML16172A0662016-06-20020 June 2016 Summary of the May 26, 2016, Monticello Public Meeting ML15271A2072015-10-0202 October 2015 July 9, 2015 Summary of Closed Meeting Between Representatives of the U.S. Army Corps of Engineers, U.S, Nuclear Regulatory Commission and Northern States Power Company- Minnesota to Discuss Flood Analysis Associated with Monticello Nuclear ML15195A4472015-08-0505 August 2015 Summary of Public Meeting with Xcel Energy and Areva to Discuss Changes to the Proposed Technical Specifications and COLR in Support of the Areva Extended Flow Window License Amendment Request ML15093A2342015-04-0303 April 2015 Summary of Monticello Public Meeting ML14297A1272014-10-31031 October 2014 Summary of October 1, 2014, Public Meeting with NSPM and Areva to Discuss Areva Fuel Transition License Amendment Request and Future License Amendment Application Regarding Use of Areva Atrium 10XM Fuel in Extended Flow Window Domain ML14220A2832014-09-0808 September 2014 Summary of August 5, 2014, Closed Meeting Between Representatives of the U.S. Army Corps of Engineers, NRC, and Northern States Power Company - Minnesota to Discuss Flooding Analysis Associated with Monticello and Prairie Island Nuclear Gen ML14153A0252014-06-20020 June 2014 Meeting Summary - Public Meeting on May 16, 2014, to Discuss Xcel Energy'S Flood Hazard Reevaluation Extension Request for the Monticello and Prairie Island Nuclear Generating Plants ML14168A0182014-05-16016 May 2014 Xcel Energy Responses to NRC Questions Regarding Flood Hazard Reevaluation Report Extension Requests ML14111A0352014-04-21021 April 2014 Summary of Monticello Public Meeting to Discuss the 2013 Annual Assessment Results ML13351A3422013-12-30030 December 2013 December 4, 2013 Summary of Public Meeting with Northern States Power Company of Minnesota to Discuss the Future License Amendment Application Regarding the Use of Areva Atrium 10XM Fuel in Extended Flow Window Operating Domain ML13171A1522013-06-24024 June 2013 April 24, 2013, Summary of Public Meeting in City of Kewaunee to Make Post-Shutdown Decommissioning of Activities Report (PSDAR) Available for Public Comment ML13169A0352013-06-14014 June 2013 Email Miller to Wilson Summary of Call with Monticello Flooding Audit ML13135A0312013-05-31031 May 2013 Summary of May 3,2013, Conference Call with Northern States Power Company - Minnesota (NSPM) to Discuss Application of 10 CFR 26.205(d)(6) During the Current Refueling Outage ML12338A0062012-12-13013 December 2012 November 20, 2012, Summary of Public Meeting with Northern States Power Company of Minnesota to Discuss the Extended Power Uprate Gap Analysis ML12188A2582012-07-20020 July 2012 Summary of Meeting with Monticello Regarding a Future Amendment to Approve Use of Areva Atrium 10XM Fuel ML12093A4772012-05-0101 May 2012 April 2, 2012, Summary of Meeting with NSPM to Discuss Issue Related to Containment Accident Pressure Credit for Extended Power Uprate Operation ML12017A0852012-02-10010 February 2012 1/17/12 Summary of Meeting with Monticello a Future Application for Amendment Concerning Stored Fuel Criticality Analysis ML11292A1612011-10-20020 October 2011 Summary of Meeting with Beyond Nuclear Regarding Their 10 CFR 2.206 Petition to Suspend Operating Licenses of General Electric Mark I Boiling Water Reactors 2023-07-20
[Table view]Some use of "" in your query was not closed by a matching "". |
Text
July 20, 2023 LICENSEE: Northern States Power Company FACILITY: Monticello Nuclear Generating Plant
SUBJECT:
SUMMARY
OF JULY 14, 2023, PUBLIC MEETING WITH NORTHERN STATES POWER COMPANY REGARDING PROPOSED ALTERNATIVE TO DEFER PERIODIC VERIFICATION TESTING OF REACTOR WATER CLEAN-UP INBOARD ISOLATION VALVE (EPID L-2023-LRM-0045)
On July 14, 2023, a public meeting via webinar was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Northern States Power Company, a Minnesota corporation (NSPM, the licensee), doing business as Xcel Energy. The purpose of the preapplication meeting was to discuss a proposed alternative, under Title 10 of the Code of Federal Regulations (10 CFR) 50.55a(z)(2), to the American Society of Mechanical Engineers (ASME) 2017 Operations and Maintenance (OM) Code for the periodic verification testing (PVT) of motor-operated valve MO-2397 (reactor water clean-up inboard isolation valve). The meeting notice and agenda, dated May 24, 2023, are available in the Agencywide Documents Access and Management System (ADAMS) Accession No. ML23180A168. A copy of NSPMs presentation is also available in ADAMS at ML23192A755. A list of attendees is enclosed.
During the meeting, NSPM presented information regarding the planned alternative request to perform the PVT of MO-2397 at a frequency of 12 years. The next test would be performed during the 2025 refueling outage. The licensee discussed the following topics as part of its presentation:
Applicable Inservice Testing Requirements The licensee stated the following ASME OM Code requirements were applicable to the proposed alternative:
- Mandatory appendix III-3300
- Mandatory appendix III-3310
- Mandatory appendix III-3722 Proposed Alternative The licensee discussed the alternative request, which is to defer PVT of MO-2397 to the 2025 refueling outage because the licensee stated performing the test would present a hardship without a compensating increase in quality and safety. Deferring the test would result in a test frequency of 12 years and avoid a forced shutdown. The licensee stated the MO-2397 is in a locked high radiation area, requiring a forced outage to access and significant dose accumulation and increase industrial safety risk.
Background
The licensee stated the last as-found PVT for MO-2397 was conducted in 2013, and the PVT was required during the 2023 refueling outage to satisfy the 10-year frequency requirement. An error resulted in maintenance performed on the valve without first conducting the as-found PVT. The licensee stated the valve actuator was replaced in 2017 with as-left functional margin greater than 10 percent.
Schedule The licensee discussed its planned submittal schedule and requested approval date.
The NRC staff provided feedback on the planned submittal and asked questions throughout the presentation. The NRC staff asked the licensee to discuss the following items in more detail during the meeting:
Discuss if the submittal will propose alternatives or exemptions to any appendix J requirements.
The licensee stated all appendix J requirements will be met and no alternative or exemption is needed.
Discuss if the alternative will be a one-time deferment, and if the licensee will return to the 10-year requirement of appendix III following the 2025 refueling outage.
The licensee stated they will return to the 10-year requirement of appendix III following the one-time deferment of the PVT until the 2025 refueling outage.
Discuss the reason for the missed test. Was it a procedural issue or human performance?
The licensee stated the PVT for MO-2397 was scheduled for the 2023 refueling outage in accordance with appendix III requirements. A human performance error resulted in maintenance being conducted on the valve before the test. The error was entered into the licensees corrective action program. The error was not a programmatic error.
Discuss if MO-2397 is torque or limit controlled, and if a more precise measure of margin can be provided.
The licensee stated MO-2397 is torque controlled to open and limit controlled to close. The safety function of the valve is in the closed direction only. The licensee stated they will include information on the valve margin in their submittal.
No regulatory decisions were made during the meeting. Members of the public were in attendance as indicated on the enclosed list of attendees. No comments or questions from the public were received during the meeting. Public Meeting Feedback forms were not received.
Please direct any inquiries regarding this meeting summary to me at 301-415-0680 or Brent.Ballard@nrc.gov.
Sincerely,
/RA/
Brent T. Ballard, Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No(s). 50-263
Enclosures:
List of Attendees cc: Listserv
LIST OF ATTENDEES JULY 14, 2023, PUBLIC MEETING WITH NORTHERN STATES POWER COMPANY MONTICELLO NUCLEAR GENERATING PLANT PROPOSED ALTERNATIVE TO DEFER PERIODIC VERIFICATION TESTING OF REACTOR WATER CLEAN-UP INBOARD ISOLATION VALVE Name Organization Brent Ballard U.S. Nuclear Regulatory Commission (NRC)
Brian Lee NRC Tom McGowan NRC Hironori Peterson NRC Thomas Scarbrough NRC Jeff Whited NRC Katherine Brandtjen Northern States Power Company (NSPM)
Bobbi Jo Halvorson NSPM Gustavo Hernandez NSPM Ronald Jacobson NSPM Michael Miller NSPM Nicholas Oakley NSPM Sara Scott NSPM
/ Shinya Ito Public, Japan Nuclear Regulation Authority (JNRA)
/ Shinichi Murata Public, JNRA Enclosure
ML23200A260 OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA NRR/DORL/LPL3/BC NRR/DORL/LPL3/PM NAME BBallard SRohrer JWhited BBallard DATE 7/14/2023 7/20/2023 7/20/2023 7/20/2023