Summary of Public Meeting with Nuclear Management Co., Regarding the Nrc'S Assessment of the Monticello Nuclear Generating Plant Safety Performance for the Period from January 1 Through December 31, 2006
ML071060201
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 04/13/2007
From: Burgess B
NRC/RGN-III/DRP/RPB2
To:
References
Download: ML071060201 (5)


Text

April 13, 2007 LICENSEE: Nuclear Management Company FACILITY: Monticello Nuclear Generating Plant

SUBJECT:

SUMMARY

OF THE APRIL 4, 2007, PUBLIC MEETING TO DISCUSS THE MONTICELLO NUCLEAR GENERATING PLANT END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On April 4, 2007, the Nuclear Regulatory Commission (NRC) held a public meeting at the Monticello Community Center in Monticello, MN. The meeting was between NRC Region III management and Nuclear Management Company representatives to discuss the NRCs assessment of the Monticello Nuclear Generating Plants safety performance for the period from January 1 through December 31, 2006. The meeting notice can be found in ADAMS as Accession Number ML070710580 and the NRC presentation slides as ML071020489. A list of meeting participants can be found in the attached Enclosure.

The NRC began the meeting with an overview of the NRCs Reactor Oversight Process (ROP),

national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRCs assessment of the Monticello Nuclear Generating Plants performance in calendar year 2006, which was documented in the March 2, 2007, end-of-cycle assessment letter recorded in ADAMS as Accession Number ML070610192. The NRC also discussed upcoming inspections and activities at the Monticello Nuclear Generating Plant.

As part of this regulatory performance meeting, Nuclear Management Company responded to the NRCs assessment and discussed Monticello Nuclear Generating Plants plans for future improvements.

/RA/

Bruce L. Burgess, Chief Branch 2 Division of Reactor Projects Docket No. 50-263 License No. DPR-22

Enclosure:

Public Meeting Attendees DISTRIBUTION:

See next page

LICENSEE: Nuclear Management Company FACILITY: Monticello Nuclear Generating Plant

SUBJECT:

SUMMARY

OF THE APRIL 4, 2007, PUBLIC MEETING TO DISCUSS THE MONTICELLO NUCLEAR GENERATING PLANT END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT On April 4, 2007, the Nuclear Regulatory Commission (NRC) held a public meeting at the Monticello Community Center in Monticello, MN. The meeting was between NRC Region III management and Nuclear Management Company representatives to discuss the NRCs assessment of the Monticello Nuclear Generating Plants safety performance for the period from January 1 through December 31, 2006. The meeting notice can be found in ADAMS as Accession Number ML070710580 and the NRC presentation slides as ML071020489. A list of meeting participants can be found in the attached Enclosure.

The NRC began the meeting with an overview of the NRCs Reactor Oversight Process (ROP),

national ROP results, and the Action Matrix in general. This was followed by a discussion of the NRCs assessment of the Monticello Nuclear Generating Plants performance in calendar year 2006, which was documented in the March 2, 2007, end-of-cycle assessment letter recorded in ADAMS as Accession Number ML070610192. The NRC also discussed upcoming inspections and activities at the Monticello Nuclear Generating Plant.

As part of this regulatory performance meeting, Nuclear Management Company responded to the NRCs assessment and discussed Monticello Nuclear Generating Plants plans for future improvements.

Bruce L. Burgess, Chief Branch 2 Division of Reactor Projects Docket No. 50-263 License No. DPR-22

Enclosure:

Public Meeting Attendees DISTRIBUTION:

See next page DOCUMENT NAME:C:\FileNet\ML071060201.wpd G Publicly Available G Non-Publicly Available G Sensitive G Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII NAME CScott:dtp BBurgess DATE 04/13/2007 04/13/2007 OFFICIAL RECORD COPY

Nuclear Management Company cc w/encl:

Mr. John Conway, Site Vice President M. Sellman, President and Chief Executive Officer D. Cooper, Senior Vice President and Chief Nuclear Officer Manager, Nuclear Safety Assessment J. Rogoff, Vice President, Counsel, and Secretary Nuclear Asset Manager, Xcel Energy, Inc.

State Liaison Officer, Minnesota Department of Health R. Nelson, President Minnesota Environmental Control Citizens Association (MECCA)

Commissioner, Minnesota Pollution Control Agency D. Gruber, Auditor/Treasurer, Wright County Government Center Commissioner, Minnesota Department of Commerce Manager - Environmental Protection Division Minnesota Attorney Generals Office Chairman, Wright County Board Mayor of Monticello Chairperson, Sherburne County Administrator, City of Monticello INPO

Nuclear Management Company DISTRIBUTION:

HKN PST TEB RidsNrrDirslpab JLC1 GEG KGO GLS RML2 SAM9 SRI Monticello DRPIII DRSIII PLB1 TXN

Enclosure PUBLIC MEETING PRINCIPAL ATTENDEES April 4, 2007 NRC M Satorius, Director, Division of Reactor Projects, Region III B. Burgess, Chief, Branch 2, Division of Reactor Projects, Region III K. Riemer, Chief, Plant Support Branch, Division of Reactor Safety, Region III C. Thomas, Senior Resident Inspector, Monticello L. Haeg, Resident Inspector, Monticello Nuclear Management Company J. Conway, Site Vice President, Monticello B. Sawatzke, Plant Manager, Monticello R. Baumer, Compliance Engineering Analyst, Monticello A. Datu, Public Affairs Officer, Hudson Xcel Energy C. Bomberger, Nuclear Asset Manager, T. Pickens, Manager, Nuclear Regulatory Policy Members of the Public M. Ryan, Time Staff Writer, St.Cloud Times Enclosure 1