LICENSEE:
Northern States Power Company, Minnesota FACILITIES:
Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant
SUBJECT:
SUMMARY
OF THE MAY 3, 2022, PUBLIC OUTREACH TO DISCUSS THE NRC 2021 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF MONTICELLO NUCLEAR GENERATING PLANT AND PRARIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 On May 3, 2022, from 5:00 p.m. to 6:00 p.m. (CDT), an information meeting with a question-and-answer session was held by representatives of the U.S. Nuclear Regulatory Commission (NRC) to provide the public with information on the 2021 End-of-Cycle plant performance assessment of the Monticello Nuclear Generating Plant and Prairie Island Nuclear Generating Plant, and with general information on the NRC. The open house was held virtually via Microsoft Teams. The NRC representatives discussed plant performance with members of the public and of the Prairie Island Indian Community. Representatives from Northern States Power Company were also present at the event.
The NRC discussed their assessment of Monticello and Prairie Islands performance during the public outreach. The assessment information was documented in the March 2, 2022, End-of-Cycle Assessment Letter (ADAMS Accession No. ML22055A713 and ML22055A739, respectively). Representatives from the NRC made links to those letters, inspection reports, fact sheets and brochures, and other public documents available to those in attendance. The presentation for this webinar is available in ADAMS, Accession Number ML22130A585.
H. Peterson, Branch Chief Branch 3 Division of Reactor Projects Docket Nos. 05000263 (Monticello);
05000282,05000306, and 07200010 (Prairie Island)
License Nos. DPR-22 (Monticello);
DPR-42, and DPR-60 (Prairie Island) cc: Distribution via LISTSERV May 10, 2022 Signed by Peterson, Hironori on 05/10/22
SUBJECT:
SUMMARY
OF THE MAY 3, 2022, PUBLIC OUTREACH TO DISCUSS THE NRC 2021 END-OF-CYCLE PLANT PERFORMANCE ASSESSMENT OF MONTICELLO NUCLEAR GENERATING PLANT AND PRARIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 DISTRIBUTION:
Jessie Quichocho Robert Orlikowski RidsNrrDorlLpl3 RidsNrrPMMonticello RidsNrrPMPrairieIsland Resource RidsNrrDroIrib Resource John Giessner Mohammed Shuaibi Shelbie Lewman Allan Barker Prema Chandrathil Viktoria Mitlyng DRPIII DRSIII ROPassessment.Resource@nrc.gov ADAMS Accession Number: ML22130A717 OFFICE RIII RIII NAME RNg:ve HPeterson DATE 05/10/2022 05/10/2022 OFFICIAL RECORD COPY
Enclosure PUBLIC MEETING ATTENDEES May 3, 2022 U.S. Nuclear Regulatory Commission H. Peterson, Chief, Division of Reactor Projects (DRP), Branch 3, Region III R. Ng, Senior Project Engineer, DRP, Branch 4, Region III N. Shah, Senior Project Engineer, DRP, Branch 1, Region III R. Edwards, Senior Health Physicist, DNMS, Region III A. Demeter, Project Engineer, DRP, Branch 3, Region III C. Norton, Senior Resident Inspector, Monticello T. McGowan, Resident Inspector, Monticello D. Tesar, Senior Resident Inspector, Prairie Island K. Pusateri, Resident Inspector, Prairie Island A. Barker, Government Liaison Officer, Region III P. Chandrathil, Senior Public Affairs Officer, Region III D. Bogedain, Resident Inspector Office Assistant, Monticello N. Koester, Resident Inspector Office Assistant, Prairie Island Northern States Power Company, Minnesota (Xcel)
C. Domingos G. Hernandez S. Hafen J. Bremer K. Nyberg D. Mienke S. Skoyen S. McCall M. Kelly Prairie Island Indian Community H. Westra Members of the Public J. Pfabe Jesse Mike