IR 05000440/2013301: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 19: Line 19:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 April 24, 2013  
{{#Wiki_filter:ril 24, 2013


Mr. Vito Kaminskas Site Vice President
==SUBJECT:==
 
PERRY NUCLEAR POWER PLANT NRC INITIAL LICENSE EXAMINATION REPORT 05000440/2013301
FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant P. O. Box 97, 10 Center Road, A-PY-A290 Perry, OH 44081-0097
 
SUBJECT: PERRY NUCLEAR POWER PLANT NRC INITIAL LICENSE EXAMINATION REPORT 05000440/2013301


==Dear Mr. Kaminskas:==
==Dear Mr. Kaminskas:==
On March 14, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed the initial operator licensing examination process for license applicants employed at your Perry Nuclear Power Plant. The enclosed report documents the results of those examinations. Preliminary observations noted during the examination process were discussed on March 6, 2013, with you and other members of your staff. An exit meeting was conducted by telephone on April 4, 2013, between Mr. A. Mueller, Training Manager, of your staff, and Mr. M. Bielby, Chief Examiner, to review the proposed final grading of the written examination for the license applicants. During the telephone conversation, the NRC resolutions of the station's post-examination comments, initially received by the NRC on March 14, 2013, were discussed. The NRC examiners administered an initial license examination operating test during the weeks of February 25 and March 4, 2013. The written examination was administered by Perry Nuclear Power Plant training department personnel on March 6, 2013. Nine Senior Reactor Operator and three Reactor Operator applicants were administered license examinations. The results of the examinations were finalized on April 5, 2013. Three applicants failed the senior operator portion of the administered written examination and were issued a proposed license denial letter. Nine applicants passed all sections of their respective examinations; five applicants were issued senior operator licenses; and three applicants were issued operator licenses. In accordance with NRC policy, the license for the remaining senior operator applicant is being withheld pending the outcome of any written examination appeal that may be initiated. The written examination and other related written examination documentation will not be withheld from public disclosure. When an applicant receives a proposed license denial letter because of a written examination grade that is less than 80.0%, the applicant will be provided a copy of the written examination. For examination security purposes, your staff should consider that written examination uncontrolled and exposed to the public. In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosures will be ava ilable electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
On March 14, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed the initial operator licensing examination process for license applicants employed at your Perry Nuclear Power Plant. The enclosed report documents the results of those examinations. Preliminary observations noted during the examination process were discussed on March 6, 2013, with you and other members of your staff. An exit meeting was conducted by telephone on April 4, 2013, between Mr. A. Mueller, Training Manager, of your staff, and Mr. M. Bielby, Chief Examiner, to review the proposed final grading of the written examination for the license applicants. During the telephone conversation, the NRC resolutions of the stations post-examination comments, initially received by the NRC on March 14, 2013, were discussed.


Sincerely,
The NRC examiners administered an initial license examination operating test during the weeks of February 25 and March 4, 2013. The written examination was administered by Perry Nuclear Power Plant training department personnel on March 6, 2013. Nine Senior Reactor Operator and three Reactor Operator applicants were administered license examinations. The results of the examinations were finalized on April 5, 2013. Three applicants failed the senior operator portion of the administered written examination and were issued a proposed license denial letter. Nine applicants passed all sections of their respective examinations; five applicants were issued senior operator licenses; and three applicants were issued operator licenses.
/RA/ By Bruce Palagi Acting For/


Hironori Peterson, Chief
In accordance with NRC policy, the license for the remaining senior operator applicant is being withheld pending the outcome of any written examination appeal that may be initiated.


Operations Branch
The written examination and other related written examination documentation will not be withheld from public disclosure. When an applicant receives a proposed license denial letter because of a written examination grade that is less than 80.0%, the applicant will be provided a copy of the written examination. For examination security purposes, your staff should consider that written examination uncontrolled and exposed to the public. In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRC's
"Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).


Division of Reactor Safety Docket No. 50-440 License No. NPF-58  
Sincerely,
/RA/ By Bruce Palagi Acting For/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No. 50-440 License No. NPF-58


===Enclosures:===
===Enclosures:===
1. Operator Licensing Examination Report 05000440/2013301 w/Attachment: Supplemental Information 2. Simulation Facility Report 3. Written Examination Post-Examination Comment Resolution  
1. Operator Licensing Examination Report 05000440/2013301 w/Attachment: Supplemental Information 2. Simulation Facility Report 3. Written Examination Post-Examination Comment Resolution


REGION III Docket No: 50-440 License No: NPF-58 Report No: 05000440/2013301 Licensee: FirstEnergy Nuclear Operating Company (FENOC) Facility: Perry Nuclear Power Plant Location: Perry, Ohio Dates: February 25 - March 14, 2013 Inspectors: M. Bielby, Chief Examiner R. Baker, Examiner D. Oliver, Examiner
REGION III==
Docket No: 50-440 License No: NPF-58 Report No: 05000440/2013301 Licensee: FirstEnergy Nuclear Operating Company (FENOC)
Facility: Perry Nuclear Power Plant Location: Perry, Ohio Dates: February 25 - March 14, 2013 Inspectors: M. Bielby, Chief Examiner R. Baker, Examiner D. Oliver, Examiner Approved by: H. Peterson, Chief Operations Branch Division of Reactor Safety Enclosure 1


Approved by: H. Peterson, Chief Operations Branch Division of Reactor Safety
=SUMMARY OF FINDINGS=
ER 05000440/2013301; 02/25/2013 - 03/14/2013; FirstEnergy Nuclear Operating Company,


1 Enclosure 1
Perry Nuclear Power Plant; Initial License Examination Report.


=SUMMARY OF FINDINGS=
The announced initial operator licensing examination was conducted by regional Nuclear Regulatory Commission (NRC) examiners in accordance with the guidance of NUREG-1021,
ER 05000440/2013301; 02/25/2013 - 03/14/2013; FirstEnergy Nuclear Operating Company, Perry Nuclear Power Plant; Initial License Examination Report. The announced initial operator licensing examination was conducted by regional Nuclear Regulatory Commission (NRC) examiners in accordance with the guidance of NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 9, Supplement 1. Examination Summary Nine of twelve applicants passed all sections of their respective examinations. Five applicants were issued senior operator licenses and three applicants were issued operator licenses.
Operator Licensing Examination Standards for Power Reactors, Revision 9, Supplement 1.
 
Examination Summary Nine of twelve applicants passed all sections of their respective examinations. Five applicants were issued senior operator licenses and three applicants were issued operator licenses.


Three applicants failed the administered senior operator section of the written examination and were issued proposed license denials. The license for the remaining senior operator applicant is being held and may be issued pending the outcome of any written examination appeal(s).  (Section 4OA5.1).
Three applicants failed the administered senior operator section of the written examination and were issued proposed license denials. The license for the remaining senior operator applicant is being held and may be issued pending the outcome of any written examination appeal(s).


1
(Section 4OA5.1).


=REPORT DETAILS=
=REPORT DETAILS=
Line 63: Line 67:


====a. Examination Scope====
====a. Examination Scope====
The NRC examiners and members of the facility licensee's staff used the guidance prescribed in NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," Revision 9-Supplement 1, to develop, validate, administer, and grade the written examination and operating test. Members of the facility licensee's staff prepared  
The NRC examiners and members of the facility licensees staff used the guidance prescribed in NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 9-Supplement 1, to develop, validate, administer, and grade the written examination and operating test. Members of the facility licensees staff prepared the outline and developed the written examination and operating test. The NRC examiners validated the proposed examination during the week of February 4, 2013, with the assistance of members of the facility licensees staff. During the on-site validation week, the examiners audited three license applications for accuracy.


the outline and developed the written ex amination and operating test. The NRC examiners validated the proposed examination during the week of February 4, 2013, with the assistance of members of the facility licensee's staff. During the on-site validation week, the examiners audited three license applications for accuracy. The NRC examiners, with the assistance of members of the facility licensee's staff, administered the operating test, consisting of job performance measures and dynamic simulator scenarios, during the period of February 25 through March 5, 2013. The facility licensee administered the written examination on March 6, 2013.
The NRC examiners, with the assistance of members of the facility licensees staff, administered the operating test, consisting of job performance measures and dynamic simulator scenarios, during the period of February 25 through March 5, 2013. The facility licensee administered the written examination on March 6, 2013.


====b. Findings====
====b. Findings====
: (1) Written Examination The NRC examiners determined that the written examination, as proposed by the licensee, was within the range of acceptability expected for a proposed examination.
: (1) Written Examination The NRC examiners determined that the written examination, as proposed by the licensee, was within the range of acceptability expected for a proposed examination.


Less than 20% of the proposed examination questions were determined to be unsatisfactory and required modification or replacement.
Less than 20% of the proposed examination questions were determined to be unsatisfactory and required modification or replacement. All changes made to the proposed written examination, were made in accordance with NUREG-1021, "Operator Licensing Examination Standards for Power Reactors, and documented on Form ES-401-9, Written Examination Review Worksheet, which will be available electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's Agencywide Documents Access and Management System (ADAMS). On March 14, 2013, the licensee submitted documentation noting that there were seven post-examination comments for consideration by the NRC examiners when grading the written examination. Additional supporting information was submitted to the NRC examiners on April 3, 2013, based on discussions with the licensee. The post-examination comments and the NRC resolution for the post-examination comments are included in Enclosure 3 of this report. The final as-administered examination and answer key (ADAMS Accession Number ML13113A060), will be available electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's ADAMS.
 
All changes made to the proposed written examination, were made in accordance with NUREG-1021, "Operator Licensing Examination Standards for Power Reactors," and documented on Form ES-401-9, "Written Examination Review Worksheet," which will be available electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's Agency wide Documents Access and Management System (ADAMS). On March 14, 2013, the licensee submitted documentation noting that there were seven post-examination comments for consideration by the NRC examiners when grading the written examination. Additional supporting information was submitted to the NRC examiners on April 3, 2013, based on discussions with the licensee. The post-examination comments and the NRC resolution for the post-examination comments are included in Enclosure 3 of this report. The final as-administered examination and answ er key (ADAMS Accession Number ML13113A060), will be available electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's ADAMS.


The NRC examiners graded the written examination on April 5, 2013, and conducted a review of each missed question to determine the accuracy and validity of the examination questions.
The NRC examiners graded the written examination on April 5, 2013, and conducted a review of each missed question to determine the accuracy and validity of the examination questions.
: (2) Operating Test In general, the overall operating test submitted by the licensee met the NRC expectations; however, the proposed Job Performance Measure (JPM) test items did not
: (2) Operating Test In general, the overall operating test submitted by the licensee met the NRC expectations; however, the proposed Job Performance Measure (JPM) test items did not meet the NRCs expectations and additional attention in this area is warranted. Four JPMs were significantly modified or replaced. Two system JPMs were replaced during validation because they lacked significant evaluation steps to be performed by the applicant. One system JPM was not considered an alternate path as written, and was modified to make it alternate path. Another system JPM was changed from having the applicant verbally perform it in the control room to requiring the applicant to actually manipulate the controls in the simulator. Several other JPMs were modified to add more significance to the task required to be performed. One additional administrative JPM was developed, validated and administered to one applicant when it was discovered that the applicant had been released into a group of applicants that had completed one JPM not previously administered to the applicant. This was considered an examination security issue. Several modifications were made to the dynamic simulator scenarios to enhance evaluation of performance. Changes made to the operating test, documented in a document titled, Operating Test Comments, as well as the final as-administered dynamic simulator scenarios and JPMs, are available electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's ADAMS.
 
meet the NRC's expectations and additional attention in this area is warranted. Four JPMs were significantly modified or replaced. Two system JPMs were replaced during validation because they lacked significant evaluation steps to be performed by the applicant. One system JPM was not considered an alternate path as written, and was modified to make it alternate path. Another system JPM was changed from having the applicant verbally perform it in the control room to requiring the applicant to actually manipulate the controls in the simulator. Several other JPMs were modified to add more significance to the task required to be per formed. One additional administrative JPM was developed, validated and administered to one applicant when it was discovered that the applicant had been released into a group of applicants that had completed one JPM not previously administered to the applicant. This was considered an examination security issue. Several modifications were made to the dynamic simulator scenarios to enhance evaluation of performance. Changes made to the operating test, documented in a document titled, Operating Test Comments, as well as the final as-administered dynamic simulator scenarios and JPMs, are av ailable electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's ADAMS.


The NRC examiners completed operating test grading on April 5, 2013.
The NRC examiners completed operating test grading on April 5, 2013.
: (3) Examination Results Nine applicants at the Senior Reactor Operator (SRO) level and three applicants at the Reactor Operator (RO) level were administered written examinations and operating tests. Nine applicants passed all portions of their examinations and were issued their respective operating licenses. Three applicants failed the administered SRO portion of the written examination and were issued proposed license denials. One applicant passed all portions of the license examination, but received an SRO written test grade  
: (3) Examination Results Nine applicants at the Senior Reactor Operator (SRO) level and three applicants at the Reactor Operator (RO) level were administered written examinations and operating tests. Nine applicants passed all portions of their examinations and were issued their respective operating licenses. Three applicants failed the administered SRO portion of the written examination and were issued proposed license denials. One applicant passed all portions of the license examination, but received an SRO written test grade below 74 percent. In accordance with NRC policy, the applicants license will be withheld until any written examination appeal possibilities by other applicants have been resolved. If the applicants grade is still equal to or greater than 70 percent after any appeal resolution, the applicant will be issued a senior operator license. If the applicants SRO written grade has declined below 70 percent, the applicant will be issued a proposed license denial letter and offered the opportunity to appeal any questions the applicant feels were graded incorrectly.
 
below 74 percent. In accordance with NRC policy, the applicant's license will be withheld until any written examination appeal possibilities by other applicants have been resolved. If the applicant's grade is still equal to or greater than 70 percent after any appeal resolution, the applicant will be issued a senior operator license. If the applicant's SRO written grade has declined below 70 percent, the applicant will be issued a proposed license denial letter and offered the opportunity to appeal any questions the applicant feels were graded incorrectly.


===.2 Examination Security===
===.2 Examination Security===


====a. Scope====
====a. Scope====
The NRC examiners reviewed and observed the licensee's implementation of examination security requirements during the examination validation and administration to assure compliance with Title10 of the Code of Federal Regulations, Section 55.49, Integrity of Examinations and Tests. The examiners used the guidelines provided in NUREG -1021, "Operator Licensing Exami nation Standards for Power Reactors," to determine acceptability of the licensee's examination security activities.
The NRC examiners reviewed and observed the licensee's implementation of examination security requirements during the examination validation and administration to assure compliance with Title10 of the Code of Federal Regulations, Section 55.49, Integrity of Examinations and Tests. The examiners used the guidelines provided in NUREG -1021, "Operator Licensing Examination Standards for Power Reactors, to determine acceptability of the licensees examination security activities.


====b. Findings====
====b. Findings====
One examination security concern was identified during the process of administering the JPM examination. The licensee's security policy was not to mix applicants that had performed JPMs with those that had not performed the same JPMs. One applicant that had completed all but one of his JPMs for the day was released from the simulator into a
One examination security concern was identified during the process of administering the JPM examination. The licensees security policy was not to mix applicants that had performed JPMs with those that had not performed the same JPMs. One applicant that had completed all but one of his JPMs for the day was released from the simulator into a sequestered classroom and was inadvertently allowed to mingle with other applicants that had completed all of their JPMs for the day. The Chief Examiner determined that there was no evidence of examination compromise based on the short time period until discovery, and interviews with the applicants that were directly involved in the incident who indicated no JPMs had been discussed. However, to insure there was no unfair advantage to the applicant, another administrative JPM was developed and validated with concurrence of the regional Branch Chief, and administered to the applicant to replace the JPM in question. This was considered to be an examination security issue.
 
sequestered classroom and was inadvertently allowed to mingle with other applicants that had completed all of their JPMs for the day. The Chief Examiner determined that there was no evidence of examination compromise based on the short time period until discovery, and interviews with the applicants that were directly involved in the incident who indicated no JPMs had been discussed. However, to insure there was no unfair advantage to the applicant, another administrative JPM was developed and validated with concurrence of the regional Branch Chief, and administered to the applicant to replace the JPM in question. This was considered to be an examination security issue.


{{a|4OA6}}
{{a|4OA6}}
Line 99: Line 95:
===.1 Debrief===
===.1 Debrief===


The chief examiner presented the examinat ion team's preliminary observations and findings on March 6, 2013, to Mr. V. Kaminskas, Site Vice President, and other members of the Perry Operations and Training Department staff.
The chief examiner presented the examination team's preliminary observations and findings on March 6, 2013, to Mr. V. Kaminskas, Site Vice President, and other members of the Perry Operations and Training Department staff.
 
===.2 Exit Meeting===


===.2 Exit Meeting The chief examiner conducted an exit meeting on April 4, 2013, with Mr. T. Mueller, Training Manager, by telephone.===
The chief examiner conducted an exit meeting on April 4, 2013, with Mr. T. Mueller, Training Manager, by telephone. The NRCs final disposition of the stations post-examination comments were disclosed and discussed with Mr. T. Mueller during the telephone discussion. The examiners asked the licensee whether any of the material used to develop or administer the examination should be considered proprietary. No proprietary or sensitive information was identified during the examination or debrief/exit meetings.
The NRC's fi nal disposition of the station's post-examination comments were disclosed and discussed with Mr. T. Mueller during the telephone discussion. The examiners asked the licensee whether any of the material used to develop or administer the examination should be considered proprietary. No proprietary or sensitive information was identified during the examination or debrief/exit meetings.


ATTACHMENT:
ATTACHMENT:  


=SUPPLEMENTAL INFORMATION=
=SUPPLEMENTAL INFORMATION=


Attachment SUPPLEMENTAL INFORMATION KEY POINTS OF CONTACT Licensee  
Enclosure 1
: [[contact::V. Kaminskas]], Site Vice President-Nuclear  
SUPPLEMENTAL INFORMATION
: [[contact::R. Brooks]], Lead-Fleet Exam Development Team  
KEY POINTS OF CONTACT
: [[contact::H. Hanson Jr.]], Director-Performance Improvement  
Licensee
: [[contact::J. Kelly]], Lead-Initial Licensed Operator Training  
: [[contact::V. Kaminskas]], Site Vice President-Nuclear
: [[contact::T. Mueller]], Manager-Training  
: [[contact::R. Brooks]], Lead-Fleet Exam Development Team
: [[contact::D. O'Donnell]], Shift Manager-Facility Reviewer  
: [[contact::H. Hanson Jr.]], Director-Performance Improvement
: [[contact::J. Pelcic]], Engineer-Regulatory Compliance  
: [[contact::J. Kelly]], Lead-Initial Licensed Operator Training
: [[contact::R. Strohl]], Superintendent-Operator Training  
: [[contact::T. Mueller]], Manager-Training
: [[contact::R. Torres]], Fleet Training Exam Author  
: [[contact::D. ODonnell]], Shift Manager-Facility Reviewer
: [[contact::J. Tufts]], Manager-Operations  
: [[contact::J. Pelcic]], Engineer-Regulatory Compliance
 
: [[contact::R. Strohl]], Superintendent-Operator Training
NRC  
: [[contact::R. Torres]], Fleet Training Exam Author
: [[contact::M. Marshfield]], Senior Resident Inspector  
: [[contact::J. Tufts]], Manager-Operations
: [[contact::J. Nance]], Resident Inspector  
NRC
: [[contact::M. Bielby]], Chief Examiner  
: [[contact::M. Marshfield]], Senior Resident Inspector
: [[contact::R. Baker]], Examiner  
: [[contact::J. Nance]], Resident Inspector
: [[contact::D. Oliver]], Examiner ITEMS OPENED, CLOSED, AND DISCUSSED
: [[contact::M. Bielby]], Chief Examiner
: [[contact::R. Baker]], Examiner
: [[contact::D. Oliver]], Examiner
ITEMS OPENED, CLOSED, AND DISCUSSED
Opened/Closed
Opened/Closed
None
None
Attachment
Attachment
LIST OF ACRONYMS USED ADAMS Agencywide Document Access and Management System ATWS Anticipated Transient Without Scram
LIST OF ACRONYMS USED
CFR Code of Federal Regulations
ADAMS Agencywide Document Access and Management System
DRS Division of Reactor Safety DG Diesel Generator ECCS Emergency Core Cooling Systems
ATWS Anticipated Transient Without Scram
EOF Emergency Operating Facility
CFR   Code of Federal Regulations
EOP Emergency Operating Procedures
DRS   Division of Reactor Safety
ER Examination Report ERO Emergency Response Organization HCL Heat Capacity Limit
DG   Diesel Generator
HPCS High Pressure Core Spray
ECCS Emergency Core Cooling Systems
IAW in accordance with
EOF   Emergency Operating Facility
JPM Job Performance Measures
EOP   Emergency Operating Procedures
LOCA Loss of Coolant Accident LOOP Loss-of-Offsite-Power LPCI Low Pressure Coolant Injection
ER   Examination Report
LPCS Low Pressure Core Spray
ERO   Emergency Response Organization
MSIV Main Steam Isolation Valve
HCL   Heat Capacity Limit
NRC U.S. Nuclear Regulatory Commission OPRM Oscillation Power Range Monitor PARS Publicly Available Records System
HPCS High Pressure Core Spray
RHR Residual Heat Removal
IAW   in accordance with
RO Reactor Operator
JPM   Job Performance Measures
RPV Reactor Pressure Vessel
LOCA Loss of Coolant Accident
SAG Severe Accident Guideline SDC Shutdown Cooling SRO Senior Reactor Operator
LOOP Loss-of-Offsite-Power
SRV Safety Relief Valve
LPCI Low Pressure Coolant Injection
SIMULATION FACILITY REPORT Facility Licensee:   Perry Nuclear Power Plant Facility Docket No:   50-440
LPCS Low Pressure Core Spray
Operating Tests Administered: Weeks of February 25 and March 4, 2013
MSIV Main Steam Isolation Valve
The following documents observations made by the NRC examination team during the initial operator license examination. These observations do not constitute audit or inspection findings and are not, without further verification and review, indicative of non-compliance with 10 CFR
NRC   U.S. Nuclear Regulatory Commission
OPRM Oscillation Power Range Monitor
PARS Publicly Available Records System
RHR   Residual Heat Removal
RO   Reactor Operator
RPV   Reactor Pressure Vessel
SAG   Severe Accident Guideline
SDC   Shutdown Cooling
SRO   Senior Reactor Operator
SRV   Safety Relief Valve
Attachment
SIMULATION FACILITY REPORT
Facility Licensee:                     Perry Nuclear Power Plant
Facility Docket No:                     50-440
Operating Tests Administered:           Weeks of February 25 and March 4, 2013
The following documents observations made by the NRC examination team during the initial
operator license examination. These observations do not constitute audit or inspection findings
and are not, without further verification and review, indicative of non-compliance with 10 CFR
55.45(b). These observations do not affect NRC certification or approval of the simulation
55.45(b). These observations do not affect NRC certification or approval of the simulation
facility other than to provide information which may be used in future evaluations. No licensee action is required in response to these observations. During the conduct of the simulator portion of the operating tests, the following items were
facility other than to provide information which may be used in future evaluations. No licensee
action is required in response to these observations.
During the conduct of the simulator portion of the operating tests, the following items were
observed:
observed:
ITEM DESCRIPTION
ITEM                                       DESCRIPTION
Simulator Lockup, CR 2013-02777 During the examination administration of the second set of Scenario 1 on February 25, 2013, a simulator lockup (IO quit responding)
Simulator Lockup,       During the examination administration of the second set of Scenario 1
occurred after Event 2, Raise Reactor Power With Flow to 100%. Simulator was re-booted and reset to just before the lockup point and the scenario resumed. There were no further lockup occurrences
CR 2013-02777            on February 25, 2013, a simulator lockup (IO quit responding)
occurred after Event 2, Raise Reactor Power With Flow to 100%.
Simulator was re-booted and reset to just before the lockup point and
the scenario resumed. There were no further lockup occurrences
during the examination administration.
during the examination administration.
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 RO Question 40: The plant was operating at rated power.
RO Question 40:
The plant was operating at rated power.
An inadvertent initiation of Low Pressure Core Spray occurred due to failure of the DW pressure
An inadvertent initiation of Low Pressure Core Spray occurred due to failure of the DW pressure
trip units.
trip units.
Only the Immediate Actions of ONI-E12-1, Inadvertent Initiation of ECCS or RCIC were
Only the Immediate Actions of ONI-E12-1, Inadvertent Initiation of ECCS or RCIC were
performed and were successful.  
performed and were successful.
 
Subsequently, a loss of offsite power occurred coincident with a LOC
Subsequently, a loss of offsite power occurred coincident with a LOCA.
: [[contact::A.
When power is restored to the divisional buses by the diesel generators, LPCS will _____.
When power is restored to the divisional buses by the diesel generators]], LPCS will _____.
a. not automatically restart
a. not automatically restart
b. automatically restart immediately
b. automatically restart immediately
c. automatically restart in 10 seconds
c. automatically restart in 10 seconds
d. automatically restart in 15 seconds
d. automatically restart in 15 seconds
Answer: a.  
Answer: a.
(The following candidate comment and station proposed resolution are directly copied from the post-examination comment submission.)
(The following candidate comment and station proposed resolution are directly copied from the
post-examination comment submission.)
Candidate Comments:
Candidate Comments:
1. The question asks how the LPCS pump will respond following a LOOP/LOCA actuation signal if the pump initiation logic had been previously overridden. 2. The answer key incorrectly lists distracter 'A' as the correct answer.
1. The question asks how the LPCS pump will respond following a LOOP/LOCA actuation
3. Per plant drawings 208-0060-00004, Revision AA and 208-0060-00008, Revision DD, the LPCS Override Logic Seal-in will de-energize during a Loss of Offsite Power and when power is restored the LPCS pump will automatically restart with no time delay. 4. Amend the answer key to list distracter 'B' as the correct answer.
signal if the pump initiation logic had been previously overridden.
2. The answer key incorrectly lists distracter A as the correct answer.
3. Per plant drawings 208-0060-00004, Revision AA and 208-0060-00008, Revision DD,
the LPCS Override Logic Seal-in will de-energize during a Loss of Offsite Power and
when power is restored the LPCS pump will automatically restart with no time delay.
4. Amend the answer key to list distracter B as the correct answer.
Candidate Justification:
Candidate Justification:
a. Incorrect answer - The LPCS pump will automatically restart, the override seal-in logic de-energizes during a LOOP.
a. Incorrect answer - The LPCS pump will automatically restart, the override seal-in logic
de-energizes during a LOOP.
b. Correct answer - The LPCS pump will automatically restart without time delay.
b. Correct answer - The LPCS pump will automatically restart without time delay.
c. Incorrect answer - The LPCS pump will automatically restart without time delay, 10 seconds is the time allowed for the DG to energize the bus. a loss of offsite power
c. Incorrect answer - The LPCS pump will automatically restart without time delay,
seconds is the time allowed for the DG to energize the bus. a loss of offsite power
occurred coincident with a LOCA.
occurred coincident with a LOCA.
d. Incorrect answer - The LPCS pump will automatically restart without time delay. The 15 second time delay is for a LOCA only without a LOOP.
d. Incorrect answer - The LPCS pump will automatically restart without time delay.
The 15 second time delay is for a LOCA only without a LOOP.
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3
Recommendation: Amend the Answer Key to list Answer B as the correct answer.
Recommendation: Amend the Answer Key to list 'Answer B' as the correct answer.
References: Plant drawings 208-0060-00004, Revision AA, and 208-0060-00008,
References:
Revision DD.
Plant drawings 208-0060-00004, Revision AA, and 208-0060-00008, Revision DD.
Station Proposed Resolution:
Station Proposed Resolution:
The station agrees with the above candidate Comments, Justification and Recommendation.
The station agrees with the above candidate Comments, Justification and Recommendation.
NRC Resolution: The NRC agrees with the applicant's comment. The question basically asks how the LPCS pump will start when power restored by the Diesel Generators after the LPCS pump was placed
NRC Resolution:
The NRC agrees with the applicants comment. The question basically asks how the LPCS
pump will start when power restored by the Diesel Generators after the LPCS pump was placed
in STOP followed by a LOOP/LOCA occurrence. Reference to the Power Monitor and LPCS
in STOP followed by a LOOP/LOCA occurrence. Reference to the Power Monitor and LPCS
Pump 1E21-C001, Control portion of plant drawing, 208-0060-00004, and plant drawing 208-
Pump 1E21-C001, Control portion of plant drawing, 208-0060-00004, and plant drawing 208-
0060-00008, support the following relay actuations and contact development which indicate an automatic LPCS pump start without time delay:
0060-00008, support the following relay actuations and contact development which indicate an
INITIAL CONDITIONS 1R22-27X1A and S13 closed energizing K1 and K1B. Pump control switch (S6) in AUTO; K13 is deenergized (Manual Override is NOT
automatic LPCS pump start without time delay:
active). K1 contact M1-T1 is closed; K10 contact M2-T2 is open (no LOCA); K13 contact M1-R1 is closed (M1-T1 is open) resulting in relays K12 and K12A being deenergized. K1B contact (3-5) is open (opened 19 seconds after bus was energized); K12 contact (1-5) is open; K12A contact M3-T3 is open.
INITIAL CONDITIONS
INADVERTENT LOCA (seals in) K10 contact M2-T2 closes energizing relays K12 and K12A; K12A contact M3-T3 closes immediately but does not start pump since K1B contact 3-5 is open; K12 contact 1-5 closes after a 15 second time delay, starting the LPCS pump. Per ONI immediate actions pump is stopped (Manual Override) by momentarily placing pump control switch (S6) in STOP tripping the pump breaker and removing the auto start signal by energizing relay K13; K13 contact M1-T1 closes (seals in
1R22-27X1A and S13 closed energizing K1 and K1B.
Manual Override) and K13 contact M1-R1 opens deenergizing relays K12 and K12A opening relay K12 contact 1-5 and K12A contact 3-5.
Pump control switch (S6) in AUTO; K13 is deenergized (Manual Override is NOT
SUBSEQUENT LOOP (LOCA signal still sealed in) 1R22-27X1A opens de-energizing relays K1 and K1B; relay K1 contact M1-T1 opens de-energizing relay K13; K13 contact M1-T1 opens (breaking the seal-in on for the Manual Override) and K13 contact M1-R1 closes.
active).
OFFSITE POWER RESTORED 1R22-27X1A and S13 closed energizing K1 and K1B. Pump control switch (S6) in AUTO; K13 is deenergized (Manual Override is NOT
K1 contact M1-T1 is closed; K10 contact M2-T2 is open (no LOCA); K13 contact
active). K1 contact M1-T1 is closed; K10 contact M2-T2 is closed (LOCA is sealed-in); K13 contact M1-R1 is closed (M1-T1 is open) Relays K12 and K12A energize;
M1-R1 is closed (M1-T1 is open) resulting in relays K12 and K12A being
deenergized.
K1B contact (3-5) is open (opened 19 seconds after bus was energized); K12
contact (1-5) is open; K12A contact M3-T3 is open.
INADVERTENT LOCA (seals in)
K10 contact M2-T2 closes energizing relays K12 and K12A; K12A contact M3-T3
closes immediately but does not start pump since K1B contact 3-5 is open; K12
contact 1-5 closes after a 15 second time delay, starting the LPCS pump.
Per ONI immediate actions pump is stopped (Manual Override) by momentarily
placing pump control switch (S6) in STOP tripping the pump breaker and removing
the auto start signal by energizing relay K13; K13 contact M1-T1 closes (seals in
Manual Override) and K13 contact M1-R1 opens deenergizing relays K12 and K12A
opening relay K12 contact 1-5 and K12A contact 3-5.
SUBSEQUENT LOOP (LOCA signal still sealed in)
1R22-27X1A opens de-energizing relays K1 and K1B; relay K1 contact M1-T1 opens
de-energizing relay K13; K13 contact M1-T1 opens (breaking the seal-in on for the
Manual Override) and K13 contact M1-R1 closes.
OFFSITE POWER RESTORED
1R22-27X1A and S13 closed energizing K1 and K1B.
Pump control switch (S6) in AUTO; K13 is deenergized (Manual Override is NOT
active).
K1 contact M1-T1 is closed; K10 contact M2-T2 is closed (LOCA is sealed-in);
K13 contact M1-R1 is closed (M1-T1 is open) Relays K12 and K12A energize;
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 K12 contact is open (closes after 15 seconds), but K12A contact M3-T3 closes; the LPCS pump starts without any delay.
K12 contact is open (closes after 15 seconds), but K12A contact M3-T3 closes;
Additionally, the NRC reviewed the questions ask
the LPCS pump starts without any delay.
ed by the applicants concerning this question and found that there were none asked. The answer key was amended to accept distracter b. as
Additionally, the NRC reviewed the questions asked by the applicants concerning this question
and found that there were none asked. The answer key was amended to accept distracter b. as
the only correct answer.
the only correct answer.
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 RO Question 66: The plant was operating at rated power when the following occurred: The reactor was scrammed 20 minutes ago due to a problem with the pressure regulator system. During the transient, both Reactor Recirculation Pumps tripped off. Current RPV pressure is 600 psig and lowering at 2.5 psig/minute. The scram has just been reset. RPV Bottom Head Drain temperature is 445°F. RPV Vessel Head Flange temperature is 500°F.
RO Question 66:
Based on these conditions, bulk RPV water temperature currently is approximately ___(1)___. If cooldown is allowed to continue at the present rate, Tech Spec cooldown rate ___(2)___
The plant was operating at rated power when the following occurred:
Exceeded.  
The reactor was scrammed 20 minutes ago due to a problem with the pressure regulator
    (1)                                     (2)
system.
a. 44°F > Bottom Head Drain will
During the transient, both Reactor Recirculation Pumps tripped off.
b. 16&deg;F < Vessel Head Flange will
Current RPV pressure is 600 psig and lowering at 2.5 psig/minute.
c. 44&deg;F > Bottom Head Drain will not
The scram has just been reset.
d. 16&deg;F < Vessel Head Flange   will not
RPV Bottom Head Drain temperature is 445&deg;F.
Answer: c.  
RPV Vessel Head Flange temperature is 500&deg;
 
: [[contact::F.
The following candidate comment and station proposed resolution are directly copied from the post-examination comment submission.
Based on these conditions]], bulk RPV water temperature currently is approximately ___(1)___.
If cooldown is allowed to continue at the present rate, Tech Spec cooldown rate ___(2)___
Exceeded.
                    (1)                       (2)
a. 44&deg;F > Bottom Head Drain             will
b. 16&deg;F < Vessel Head Flange           will
c. 44&deg;F > Bottom Head Drain             will not
d. 16&deg;F < Vessel Head Flange           will not
Answer: c.
The following candidate comment and station proposed resolution are directly copied from the
post-examination comment submission.
Candidate Comments:
Candidate Comments:
1. The question asks what the temperature difference is between bulk reactor coolant and the RPV skin and whether the Technical Specification cooldown rate has been exceeded when cooling down at 2.5 psig per minute. The answer key should be changed for
1. The question asks what the temperature difference is between bulk reactor coolant and
newly discovered technical information. 2. A cooldown rate maintained at a constant 2.5 psig/minute (150 psig/hr) will exceed the Technical Specification cooldown limit of < 100 degrees F per hour. 3. During the one hour period pressure is reduced from 175 psig to 25 psig the cooldown rate is 100 degrees F exceeding the Technical Specification Limit.
the RPV skin and whether the Technical Specification cooldown rate has been exceeded
Time Pressure (psig) Temperature (&deg;F) Delta (&deg;F) T + 2 hr 10 min 325 429 T + 3 hr 10 min 175 377 52 T + 4 hr 10 min 25 267 110  
when cooling down at 2.5 psig per minute. The answer key should be changed for
 
newly discovered technical information.
2. A cooldown rate maintained at a constant 2.5 psig/minute (150 psig/hr) will exceed the
Technical Specification cooldown limit of < 100 degrees F per hour.
3. During the one hour period pressure is reduced from 175 psig to 25 psig the cooldown
rate is 100 degrees F exceeding the Technical Specification Limit.
Time               Pressure (psig)   Temperature (&deg;F)       Delta (&deg;F)
T + 2 hr 10 min         325                   429
T + 3 hr 10 min         175                   377                 52
T + 4 hr 10 min           25                   267                 110
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3
Candidate Justification:
Candidate Justification:  
                                                    (1)                               (2)
  (1) (2)
Correct
a. Correct Answer 44&deg;F > Bottom Head Drain will Justification The saturated temperature of 600 psig (~615 psia) is ~490&deg;F (489), which is about 44&deg;F > the bottom head temp in this case
a.                                 44&deg;F > Bottom Head Drain                       will
Tech Spec cooldown
Answer
rate Exceeded 110&deg;F
The saturated temperature of 600 psig (~615
b. Incorrect
Answer 16&deg;F < Vessel Head Flange will  Justification 16&deg;F < Vessel Head Flange is temperature calculated if psia is calculated backwards
Tech Spec cooldown
rate Exceeded 110&deg;F
c Incorrect
Answer 44&deg;F > Bottom Head Drain will not  Justification The saturated temperature of 600 psig (~615 psia) is ~490&deg;F (489), which is about 44&deg;F > the bottom head temp in this case
Tech Spec cooldown
Tech Spec cooldown
Justification      psia) is ~490&deg;F (489), which is about 44&deg;F >
rate Exceeded 110&deg;F
rate Exceeded 110&deg;F
d. Incorrect
the bottom head temp in this case
Answer 16&deg;F < Vessel Head Flange will not  Justification 16&deg;F < Vessel Head Flange is temperature calculated if psia is calculated backwards
Incorrect
b.                                  16&deg;F < Vessel Head Flange                       will
Answer
16&deg;F < Vessel Head Flange is temperature       Tech Spec cooldown
Justification
calculated if psia is calculated backwards     rate Exceeded 110&deg;F
Incorrect
c                                  44&deg;F > Bottom Head Drain                    will not
Answer
The saturated temperature of 600 psig (~615
Tech Spec cooldown
Tech Spec cooldown
Justification      psia) is ~490&deg;F (489), which is about 44&deg;F >
rate Exceeded 110&deg;F
rate Exceeded 110&deg;F
Recommendation: Amend the Answer Key to list 'Answer A' as the only correct answer.
the bottom head temp in this case
Incorrect
d.                                  16&deg;F < Vessel Head Flange                    will not
Answer
16&deg;F < Vessel Head Flange is temperature      Tech Spec cooldown
Justification
calculated if psia is calculated backwards    rate Exceeded 110&deg;F
Recommendation: Amend the Answer Key to list Answer A as the only correct answer.
Station Proposed Resolution:
Station Proposed Resolution:
Station agrees with the above candidate Comments, Justification and Recommendation.
Station agrees with the above candidate Comments, Justification and Recommendation.
NRC Resolution:
NRC Resolution:
The NRC agrees with the candidate's comment and station proposed resolution. After reviewing the calculations it was discovered that the cooldown rate will exceed the Technical
The NRC agrees with the candidates comment and station proposed resolution. After
Specification limit at the time specified
reviewing the calculations it was discovered that the cooldown rate will exceed the Technical
by the candidate comment. Additionally, the NRC reviewed the questions asked by the applicants concerning this question and found that none
Specification limit at the time specified by the candidate comment. Additionally, the NRC
were asked. The answer key was amended to accept distracter a. as the only correct answer.  
reviewed the questions asked by the applicants concerning this question and found that none
 
were asked. The answer key was amended to accept distracter a. as the only correct answer.
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 SRO Question 1:   A loss of Hot Surge Tank level occurred.
SRO Question 1:
A loss of Hot Surge Tank level occurred.
The following conditions now exist:
The following conditions now exist:
Operating in EOP-01, RPV Control. RPV level is -46 inches and lowering. RPV pressure is 5 psig. HPCS pump shaft has broken. LPCS pump is tagged out for motor replacement with motor removed. RHR A pump is degraded. EH12 has a Bus lockout. No Alternate Injection Subsystems can be lined up. The EOF is operational.
Operating in EOP-01, RPV Control.
As the Shift Manager, you would notify the Emergency Response Organization that entry into ___(1)___ is required.
RPV level is -46 inches and lowering.
EOP actions are   (2)   after the SAGs are entered.  
RPV pressure is 5 psig.
    (1)       (2)
HPCS pump shaft has broken.
a. SAG-1, Primary Containment Flooding Continued
LPCS pump is tagged out for motor replacement with motor removed.
b. SAG-1, Primary Containment Flooding Exited  
RHR A pump is degraded.
 
EH12 has a Bus lockout.
c. SAG-2, RPV, Containment, and Continued
No Alternate Injection Subsystems can be lined up.
The EOF is operational.
As the Shift Manager, you would notify the Emergency Response Organization that entry into
___(1)___ is required.
EOP actions are     (2) after the SAGs are entered.
                    (1)                                       (2)
a. SAG-1, Primary Containment Flooding                 Continued
b. SAG-1, Primary Containment Flooding                 Exited
c. SAG-2, RPV, Containment, and                       Continued
Radioactivity Release Control
Radioactivity Release Control
d. SAG-2, RPV, Containment, and Exited
d. SAG-2, RPV, Containment, and                       Exited
Radioactivity Release Control
Radioactivity Release Control
Answer: b.
Answer: b.
The following candidate comment and station proposed resolution are directly copied from the
The following candidate comment and station proposed resolution are directly copied from the
post-examination comment submission.
post-examination comment submission.
Candidate Comments:
Candidate Comments:
1. The question asks the required Shift Manager actions after the determination that adequate core cooling no longer exists and the required status of the Emergency
1. The question asks the required Shift Manager actions after the determination that
Operating Procedures when transitioning to the Severe Accident guidelines. 2. The answer key states SAG-1, Primary Containment Flooding is the required SAG actions. 3. The bases for EOP-1, Step ALC-15, states that "Transition to the SAGs is completed by the Shift Manager notification to the ERO that Primary Containment Flooding is
adequate core cooling no longer exists and the required status of the Emergency
required."
Operating Procedures when transitioning to the Severe Accident guidelines.
2. The answer key states SAG-1, Primary Containment Flooding is the required SAG
actions.
3. The bases for EOP-1, Step ALC-15, states that Transition to the SAGs is completed by
the Shift Manager notification to the ERO that Primary Containment Flooding is
required.
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 4. The bases for SAG-1 states that "The requirements for Primary Containment flooding in the RPV Control, EOP-1, Level Power Control, EOP-1A, RPV Flooding, EOP04-4,
4. The bases for SAG-1 states that The requirements for Primary Containment flooding in
flowcharts are directed through concurrent transitions to the Primary Containment Flooding, SAG-1 and RPV, Primary Containment, and Radioactivity Release Control, SAG-2 Flowcharts." 5. The SAG-1 bases clearly states "The RPV and Primary Containment Flooding guideline and the Primary Containment and Radioactivity Release Control guideline are entered and executed concurrently. 6. Answer 'D' SAG-2, RPV, Containment, and Radioactivity Release Control for part 1 and Exited for part 2 is a correct answer since we have 'newly discovered technical
the RPV Control, EOP-1, Level Power Control, EOP-1A, RPV Flooding, EOP04-4,
information that supports a change in the answer key." 7. References, EOP-1 pg 61, SAG-1 bases pg 6 and SAG-2 pg 8 are attached.
flowcharts are directed through concurrent transitions to the Primary Containment
Flooding, SAG-1 and RPV, Primary Containment, and Radioactivity Release Control,
SAG-2 Flowcharts.
5. The SAG-1 bases clearly states The RPV and Primary Containment Flooding guideline
and the Primary Containment and Radioactivity Release Control guideline are entered
and executed concurrently.
6. Answer D SAG-2, RPV, Containment, and Radioactivity Release Control for part 1 and
Exited for part 2 is a correct answer since we have newly discovered technical
information that supports a change in the answer key.
7. References, EOP-1 pg 61, SAG-1 bases pg 6 and SAG-2 pg 8 are attached.
Candidate Justification:
Candidate Justification:
As the Shift Manager, you would notify the Emergency Response Organization that entry in     (1)   is required.
As the Shift Manager, you would notify the Emergency Response Organization that entry
EOP actions are   (2)   after the SAGs are entered.  
in (1) is required.
  (1) (2) a. Incorrect answer SAG-1, Primary Containment Flooding Continued
EOP actions are     (2)   after the SAGs are entered.
Correct - Primary Containment (SG-1) and
                                                  (1)                               (2)
Radioactivity Release Control guideline  
a. Incorrect answer     SAG-1, Primary Containment Flooding           Continued
(SAG-2) are entered and executed
Correct - Primary Containment (SG-1) and     Incorrect - EOP
concurrently Incorrect - EOP
Radioactivity Release Control guideline       Actions are
Actions are
                              (SAG-2) are entered and executed             discontinued when
discontinued when SAGs are entered. b. Correct answer SAG-1 Primary Containment Flooding Exited
concurrently                                 SAGs are entered.
Correct - Primary Containment (SG-1) and
b. Correct answer       SAG-1 Primary Containment Flooding           Exited
Radioactivity Release Control guideline (SAG-2) are entered and executed
Correct - Primary Containment (SG-1) and     Correct - EOP
concurrently
Radioactivity Release Control guideline       Actions are
Correct - EOP
                              (SAG-2) are entered and executed             discontinued when
Actions are discontinued when
concurrently                                  SAGs are entered.
SAGs are entered.
Incorrect answer     SAG-2, RPV, Containment, and Radioactivity   Continued
c. Incorrect answer SAG-2, RPV, Containment, and Radioactivity
c.
Release Control
Release Control
Continued
Correct - Primary Containment (SAG-1) and     Incorrect - EOP
Correct - Primary Containment (SAG-1) and
Radioactivity Release Control guideline       Actions are
Radioactivity Release Control guideline  
                              (SAG-2) are entered and executed             discontinued when
(SAG-2) are entered and executed
concurrently                                  SAGs are entered.
concurrently Incorrect - EOP
Correct answer       SAG-2, RPV, Containment, and Radioactivity   Exited
Actions are
d.
discontinued when
Release Control
SAGs are entered.
Correct - Primary Containment (SAG-1) and     Correct - EOP
d. Correct answer SAG-2, RPV, Containment, and Radioactivity
Radioactivity Release Control guideline       Actions are
Release Control Exited  Correct - Primary Containment (SAG-1) and
                              (SAG-2) are entered and executed             discontinued when
Radioactivity Release Control guideline (SAG-2) are entered and executed
concurrently                                 SAGs are entered.
concurrently
Recommendation: Amend the Answer Key to list Answer D as a correct answer also, in
Correct - EOP
addition to Answer  
Actions are discontinued when SAGs are entered.
: [[contact::B.
Recommendation: Amend the Answer Key to list 'Answer D' as a correct answer also, in
References: EOP bases]], EOP-1 pg 61, SAG bases, SAG-1 bases pg 6, and SAG-2 pg 8.
addition to 'Answer B'.
Enclosure 3
References: EOP bases, EOP-1 pg 61, SAG bases, SAG-1 bases pg 6, and SAG-2 pg 8.
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 Station Proposed Resolution:
Station Proposed Resolution:
Station agrees with the above candidate Comments, Justifications and Recommendation. The question did not ask for all the required procedures. Therefore, the justification supports 2 correct answers.
Station agrees with the above candidate Comments, Justifications and Recommendation.
The question did not ask for all the required procedures. Therefore, the justification supports
correct answers.
NRC Resolution:
NRC Resolution:
The NRC disagrees with the candidate's commen
The NRC disagrees with the candidates comment/justification and station proposed resolution
t/justification and station proposed resolution that both answers b. and d. are correct. The question asks for the required Shift Manager
that both answers b. and d. are correct. The question asks for the required Shift Manager
actions after the determination that adequate core cooling no longer exists and the required
actions after the determination that adequate core cooling no longer exists and the required
status of the Emergency Operating Procedures (EOPs) when transitioning to the Severe
status of the Emergency Operating Procedures (EOPs) when transitioning to the Severe
Accident Guidelines (SAGs). The EOP-1, RPV Control; EOP-1A, Level Power Control; and
Accident Guidelines (SAGs). The EOP-1, RPV Control; EOP-1A, Level Power Control; and
EOP 04-4, RPV Flooding, flowcharts do not direct concurrent entry into SAG-1, Primary Containment Flooding, and SAG-2, Primary Contai
EOP 04-4, RPV Flooding, flowcharts do not direct concurrent entry into SAG-1, Primary
nment and Radioactivity Release Control, as stated by the candidate and supported by the station proposed resolution. The EOP-1, EOP-1A and EOP 04-4 flowcharts direct transition to Primary Containment Flooding which is SAG-1.
Containment Flooding, and SAG-2, Primary Containment and Radioactivity Release Control, as
stated by the candidate and supported by the station proposed resolution. The EOP-1, EOP-1A
and EOP 04-4 flowcharts direct transition to Primary Containment Flooding which is SAG-1.
Once the SAG-1 flowchart is entered, a subsequent step directs entry into SAG-2 and both
Once the SAG-1 flowchart is entered, a subsequent step directs entry into SAG-2 and both
SAGs are performed concurrently. Once transition to the SAGs is performed, the EOPs are
SAGs are performed concurrently. Once transition to the SAGs is performed, the EOPs are
exited. Additionally, the NRC reviewed the questions ask
exited.
ed by the applicants concerning this question
Additionally, the NRC reviewed the questions asked by the applicants concerning this question
and found that none were asked. Based upon the above discussion, the NRC did not modify the answer key and retained choice b. as the only correct answer to the question.
and found that none were asked. Based upon the above discussion, the NRC did not modify
the answer key and retained choice b. as the only correct answer to the question.
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 SRO Question 8: The following conditions exist:
SRO Question 8:
The plant is operating at 98% power. Core flow is 103 Mlbs/Hr. OPRMs are INOPERABLE. Alternate methods to detect and suppress thermal hydraulic instability oscillations have been initiated IAW 3.3.1.3 OPRM Instrumentation.
The following conditions exist:
Reactor Recirculation Pump B then trips.  
The plant is operating at 98% power.
 
Core flow is 103 Mlbs/Hr.
In accordance with ONI-C51, Unplanned Changes Reactor Power or Reactivity, the Unit Supervisor will direct           .
OPRMs are INOPERABLE.
Alternate methods to detect and suppress thermal hydraulic instability oscillations have
been initiated IAW 3.3.1.3 OPRM Instrumentation.
Reactor Recirculation Pump B then trips.
In accordance with ONI-C51, Unplanned Changes Reactor Power or Reactivity, the Unit
Supervisor will direct       .
a. Inserting Cram Rods IAW FTI-B002, Control Rod Movements
a. Inserting Cram Rods IAW FTI-B002, Control Rod Movements
b. restarting Recirc Pump B IAW SOI-B33, Reactor Recirculation
b. restarting Recirc Pump B IAW SOI-B33, Reactor Recirculation
c. Inserting a manual reactor scram IAW ONI-C71-1, Reactor Scram
c. Inserting a manual reactor scram IAW ONI-C71-1, Reactor Scram
d. shutting Recirc Pump B FCV IAW ONI-SPI G-2, Single Pump Operation
d. shutting Recirc Pump B FCV IAW ONI-SPI G-2, Single Pump Operation
Answer: a.  
Answer: a.
 
Candidate Comments:
Candidate Comments:
1. The question asks what actions are required for a trip of a Reactor Recirculation pump per ONI-C51. The stem of the question does not provide all the necessary information
1. The question asks what actions are required for a trip of a Reactor Recirculation pump
to answer the question. ONI-C51 FLOWCHART step C51-4 If while Executing step refers the operator to the Core Flow Caution. This step is applicable at all times the operator is using this procedure. 2. ONI-C51 FLOWCHART Core Flow Caution requires the operator to determine the actual core flow using core plate P which is not provided. Core Flow - During single Recirculation pump operation the core flow instrument may not indicate properly. Actual core flow may be determined using: Core plate P and the curve in PDB-A0015. A core plate P of 2.25 psid is approximately 42 Mblm(sic)/Hr
per ONI-C51. The stem of the question does not provide all the necessary information
core flow. SPDS screen CFLOW
to answer the question. ONI-C51 FLOWCHART step C51-4 If while Executing step
: [[contact::V. 3. The procedure direct that core flow be determined using core plate delta pressure which then outlines the correct course of action taken by the Unit Supervisor]], core plate delta
refers the operator to the Core Flow Caution. This step is applicable at all times the
pressure was not provided.  
operator is using this procedure.
 
2. ONI-C51 FLOWCHART Core Flow Caution requires the operator to determine the actual
core flow using core plate P which is not provided.
Core Flow - During single Recirculation pump operation the core flow instrument
may not indicate properly. Actual core flow may be determined
using:
Core plate P and the curve in PDB-A0015.
A core plate P of 2.25 psid is approximately 42 Mblm(sic)/Hr
core flow.
SPDS screen CFLOWV.
3. The procedure direct that core flow be determined using core plate delta pressure which
then outlines the correct course of action taken by the Unit Supervisor, core plate delta
pressure was not provided.
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3
Candidate Justification:
Candidate Justification:
a. Incorrect answer - Actual core flow is indeterminate, inserting Cram Rods IAW FTI-B002, Control Rod is required when operating in the Controlled Entry/Immediate
a. Incorrect answer - Actual core flow is indeterminate, inserting Cram Rods IAW
Exit region. b. Incorrect answer - Actual core flow is indeterminate, restarting Recirc Pump B IAW SOI-B33, Reactor Recirculation may be a correct answer if core flow is known to not be
FTI-B002, Control Rod is required when operating in the Controlled Entry/Immediate
in the Backup Stability Protection Regions - Two Loop Power - Flow Map Manual Scram Required region. c. Incorrect answer - Actual core flow is indeterminate, inserting a manual reactor scram IAW ONI-C71-1, Reactor is a non-conservative action if core flow is >42 Mlbm/hr. d. Incorrect answer - Actual core flow is indeterminate - shutting Recirc Pump B FCV IAW ONI-SPI G-2, Single Pump Operation is not directed by ONI-C51 FLOWCHART or by
Exit region.
b. Incorrect answer - Actual core flow is indeterminate, restarting Recirc Pump B IAW
SOI-B33, Reactor Recirculation may be a correct answer if core flow is known to not be
in the Backup Stability Protection Regions - Two Loop Power - Flow Map Manual
Scram Required region.
c. Incorrect answer - Actual core flow is indeterminate, inserting a manual reactor scram
IAW ONI-C71-1, Reactor is a non-conservative action if core flow is >42 Mlbm/hr.
d. Incorrect answer - Actual core flow is indeterminate - shutting Recirc Pump B FCV IAW
ONI-SPI G-2, Single Pump Operation is not directed by ONI-C51 FLOWCHART or by
ONI-SPI G-2. ONI- SPI G-2 directs closure of the B Recirc Pump Suction valve.
ONI-SPI G-2. ONI- SPI G-2 directs closure of the B Recirc Pump Suction valve.
Recommendations: Delete the question from the exam, there is no correct answer.
Recommendations: Delete the question from the exam, there is no correct answer.
Station Proposed Resolution:
Station Proposed Resolution:
Delete question from exam, there is no correct answer since this was "a question with an unclear stem that confused the applicants or did not provide all the necessary information."
Delete question from exam, there is no correct answer since this was a question with an
unclear stem that confused the applicants or did not provide all the necessary information.
NRC Resolution:
NRC Resolution:
The NRC disagrees with both 1) the candidate's comment/justification, to delete the question because an actual core flow value following the Reactor Recirculation Pump (RRP), which is not provided, is required in order to determine and perform any actions in accordance with (IAW)
The NRC disagrees with both 1) the candidates comment/justification, to delete the question
ONI-C51; and 2) the facility's proposed resolution to delete the question because this was a
because an actual core flow value following the Reactor Recirculation Pump (RRP), which is not
provided, is required in order to determine and perform any actions in accordance with (IAW)
ONI-C51; and 2) the facilitys proposed resolution to delete the question because this was a
question with an unclear stem that confused the applicants or did not provide all the necessary
question with an unclear stem that confused the applicants or did not provide all the necessary
information.
information.
The question asked which of the four options listed would be directed by the Unit Supervisor,
The question asked which of the four options listed would be directed by the Unit Supervisor,
given the plant conditions stated in the stem and the direction provided by ONI-C51. Since no additional failures beyond the trip of the 'B' RRP were presented, and the plant is expected to
given the plant conditions stated in the stem and the direction provided by ONI-C51. Since no
additional failures beyond the trip of the B RRP were presented, and the plant is expected to
respond as anticipated for a loss of one RRP, entry into ONI-C51 is required due to the RRP
respond as anticipated for a loss of one RRP, entry into ONI-C51 is required due to the RRP
trip. ONI-C51 directs performance of the immediate and supplemental actions IAW ONI-C51 flowchart revision  
trip. ONI-C51 directs performance of the immediate and supplemental actions IAW ONI-C51
: [[contact::J. Once immediate actions have been verified complete]], steps C51-2, C51-3, and C51-4 are completed in series. These actions may be performed without an actual core
flowchart revision  
: [[contact::J. Once immediate actions have been verified complete]], steps C51-2, C51-3,
and C51-4 are completed in series. These actions may be performed without an actual core
flow value being known since core flow will be greater than 42 Mlbm/hr based upon the
flow value being known since core flow will be greater than 42 Mlbm/hr based upon the
conditions provided in the stem. The flowchart then directs the supplemental actions of steps
conditions provided in the stem. The flowchart then directs the supplemental actions of steps
C51-4 and C51-12 be executed concurrently. Step C51-12 directs the operator to
C51-4 and C51-12 be executed concurrently. Step C51-12 directs the operator to GO TO Step
GO TO Step C51-21 if either RRP has tripped and single loop operation is required, which will subsequently direct the operator to verify loop parameters within limits for single RRP operation and, within
C51-21 if either RRP has tripped and single loop operation is required, which will subsequently
direct the operator to verify loop parameters within limits for single RRP operation and, within
hour insert control rods to lower reactor power below 66.5% (2500 MWth). None of these
hour insert control rods to lower reactor power below 66.5% (2500 MWth). None of these
required supplemental actions necessitate knowing the actual core flow prior to performance.
required supplemental actions necessitate knowing the actual core flow prior to performance.
As discussed above, the stated assumption made by the applicant that an actual core flow value is required before any actions may be performed IAW ONI-C51 is incorrect. Therefore, the
As discussed above, the stated assumption made by the applicant that an actual core flow value
NRC does not agree with deleting the question because no action IAW ONI-C51 is possible without being given a value for actual core flow. Also, even though having the core plate P value following the RRP trip, along with the curve, PDB-A0015, would allow an actual core flow
is required before any actions may be performed IAW ONI-C51 is incorrect. Therefore, the
NRC does not agree with deleting the question because no action IAW ONI-C51 is possible
without being given a value for actual core flow. Also, even though having the core plate P
value following the RRP trip, along with the curve, PDB-A0015, would allow an actual core flow
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 value to be determined, this would simply be additional information to confirm the expected position on the Power-to-Flow map. Therefore, the NRC does not agree with the licensee's
value to be determined, this would simply be additional information to confirm the expected
resolution to delete the question because the question did not provide all necessary information in the stem and the stem was unclear and confused the applicants. The only related question asked by any of the applicants during the examination dealt with a clarification on completion of
position on the Power-to-Flow map. Therefore, the NRC does not agree with the licensees
resolution to delete the question because the question did not provide all necessary information
in the stem and the stem was unclear and confused the applicants. The only related question
asked by any of the applicants during the examination dealt with a clarification on completion of
the required Technical Specification actions for the inoperable Oscillating Power Range
the required Technical Specification actions for the inoperable Oscillating Power Range
Monitors (OPRMs); no questions were raised concerning actual core flow values.
Monitors (OPRMs); no questions were raised concerning actual core flow values.
Although the NRC believes that adequate information to answer the question was provided in the question stem, the NRC has now identified an issue stemming from the validation of the
Although the NRC believes that adequate information to answer the question was provided in
question when the original examination was submitted and approved. Based upon the station's
the question stem, the NRC has now identified an issue stemming from the validation of the
training, the applicants were expected to recognize that the trip of the 'B' RRP would lower core
question when the original examination was submitted and approved. Based upon the stations
training, the applicants were expected to recognize that the trip of the B RRP would lower core
flow to less than 50% rated core flow, based upon the initial condition given that core flow was
flow to less than 50% rated core flow, based upon the initial condition given that core flow was
103 Mlbm/hr. The applicant would have to assess the situation, using the provided PDB-A06, Power-to-Flow Map (modified), realize this would result in operation in the Controlled Entry/Immediate Exit Region of the Backup Stability Protection (OPRM INOP) Power-to-Flow map, and direct actions IAW the ONI-C51 Flow Chart - Insert cram rods IAW FTI-B002, Control
103 Mlbm/hr. The applicant would have to assess the situation, using the provided PDB-A06,
Rod - to lower power to exit this region.
Power-to-Flow Map (modified), realize this would result in operation in the Controlled
Per the NRC's request, the licensee provided additional reference material that indicates the expected actual plant core flow value will be in excess of 50%, and operation will be outside and to the right of the Controlled Entry/Immediate Exit Region of the Backup Stability Protection (OPRM INOP) Power-to-Flow map. The correct
Entry/Immediate Exit Region of the Backup Stability Protection (OPRM INOP) Power-to-Flow
map, and direct actions IAW the ONI-C51 Flow Chart - Insert cram rods IAW FTI-B002, Control
Rod - to lower power to exit this region. Per the NRCs request, the licensee provided
additional reference material that indicates the expected actual plant core flow value will be in
excess of 50%, and operation will be outside and to the right of the Controlled Entry/Immediate
Exit Region of the Backup Stability Protection (OPRM INOP) Power-to-Flow map. The correct
action to be directed by the operator IAW ONI-C51 is to verify loop parameters within limits for
action to be directed by the operator IAW ONI-C51 is to verify loop parameters within limits for
single RRP operation and, within 1 hour insert control rods as necessary to lower reactor power
single RRP operation and, within 1 hour insert control rods as necessary to lower reactor power
Line 390: Line 553:
Based upon the newly discovered technical information, this question does not have a correct
Based upon the newly discovered technical information, this question does not have a correct
answer, and the NRC has changed the answer key to delete this question.
answer, and the NRC has changed the answer key to delete this question.
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 SRO Question 14: The plant was operating at rated power. A manual Rx scram was inserted due to a loss of main condenser vacuum.
SRO Question 14:
The plant was operating at rated power.
A manual Rx scram was inserted due to a loss of main condenser vacuum.
The transient resulted in the following conditions:
The transient resulted in the following conditions:
An ATWS is in progress. MSIVs are shut. RPV water level is 65 inches and stable. RPV pressure is 960 psig and stable. 2 SRVs are open. Suppression Pool Temperature is 116&deg;F and rising slowly. Suppression Pool Level 18.1' and lowering due to a leak. The margin to exceeding HCL is 3&deg;F.
An ATWS is in progress.
MSIVs are shut.
RPV water level is 65 inches and stable.
RPV pressure is 960 psig and stable.
SRVs are open.
Suppression Pool Temperature is 116&deg;F and rising slowly.
Suppression Pool Level 18.1 and lowering due to a leak.
The margin to exceeding HCL is 3&deg;F.
What is the action that the Unit Supervisor would order first?
What is the action that the Unit Supervisor would order first?
a. Open an additional SRV to lower RPV pressure
a. Open an additional SRV to lower RPV pressure
Line 399: Line 572:
c. Transition to EOP 4-2, Emergency Depressurization
c. Transition to EOP 4-2, Emergency Depressurization
d. Anticipate Emergency Depressurization IAW EOP-02, Containment Control
d. Anticipate Emergency Depressurization IAW EOP-02, Containment Control
Answer: a.
Answer: a.
Candidate Comments:
Candidate Comments:
1. The answer key states answer (a.). Open additional SRV to lower RPV pressure. This answer is correct in accordance with EOP-1A, Step LPC/P - Answer (c.) is also correct. Though the EOP-SPI Supplement Figure 4 was not given to the students, if one were to plot the given conditions on Figure 4, HCL would already be in the UNSAFE region requiring immediate Emergency Depressurization (ED) per EOP Bases, EOP-1A, EOP-2 and Hardcards (OAI-1703). The stem of the question notes a rapidly deteriorating HCL challenge. HCL is normally attempted to be maintained between 5-10&deg;F if ordered. This information was not in the stem. The EOP flowcharts were also not available to the students
1. The answer key states answer (a.). Open additional SRV to lower RPV pressure. This
answer is correct in accordance with EOP-1A, Step LPC/P - Answer (c.) is also correct.
Though the EOP-SPI Supplement Figure 4 was not given to the students, if one
were to plot the given conditions on Figure 4, HCL would already be in the
UNSAFE region requiring immediate Emergency Depressurization (ED) per EOP
Bases, EOP-1A, EOP-2 and Hardcards (OAI-1703).
The stem of the question notes a rapidly deteriorating HCL challenge. HCL is
normally attempted to be maintained between 5-10&deg;F if ordered. This information
was not in the stem. The EOP flowcharts were also not available to the students
which are not required to be known by memory. The stem states a 3&deg;F margin to
which are not required to be known by memory. The stem states a 3&deg;F margin to
HCL which is very narrow as seen in simulator scenarios. Because this band is
HCL which is very narrow as seen in simulator scenarios. Because this band is
not being maintained, the deteriorating challenge can be immediately deduced. The deteriorating challenge also includes a lowering Suppression Pool Level due to a pipe break of unknown size or unknown level change rate. Figure 4, Heat Capacity Limit, shows that as Suppression Pool Level lowers, HCL is further challenged as there is less water to absorb heat causing heatup rate to raise
not being maintained, the deteriorating challenge can be immediately deduced.
more. Due to the lowering level in the suppression pool, another challenge is immediately deduced that also leads to Emergency Depressurization per EOP-02, Step SPL-5. OAI-1703, Hardcard states "ED required at
The deteriorating challenge also includes a lowering Suppression Pool Level due
OR before 14.25 feet."
to a pipe break of unknown size or unknown level change rate. Figure 4, Heat
Capacity Limit, shows that as Suppression Pool Level lowers, HCL is further
challenged as there is less water to absorb heat causing heatup rate to raise
more.
Due to the lowering level in the suppression pool, another challenge is
immediately deduced that also leads to Emergency Depressurization per
EOP-02, Step SPL-5. OAI-1703, Hardcard states ED required at OR before
14.25 feet.
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3  Transient Strategies and Mitigating Actions (PYBP-POS-0030) state that suppression pool heatup rate is approximately 3F/minute/SR
Transient Strategies and Mitigating Actions (PYBP-POS-0030) state that
: [[contact::V. With 2 SRVs open]], this is a 6F/minute heatup rate, accelerated by 3, above, that would cause
suppression pool heatup rate is approximately 3F/minute/SRV. With 2 SRVs
open, this is a 6F/minute heatup rate, accelerated by 3, above, that would cause
HCL to be violated in less than 30 seconds (if not already violated per 1. above).
HCL to be violated in less than 30 seconds (if not already violated per 1. above).
A decision that HCL cannot be maintained and that Emergency Depressurization is required can be made at that point also and allow proceeding into Emergency
A decision that HCL cannot be maintained and that Emergency Depressurization
Depressurization from below the hold box of step STC-5 or within LPC/P-2  
is required can be made at that point also and allow proceeding into Emergency
(EOP-1A Pressure Control).
Depressurization from below the hold box of step STC-5 or within LPC/P-2
                (EOP-1A Pressure Control).
Candidate Justification:
Candidate Justification:
a. Correct answer - With SP temp rising and SP level lowering, the margin to HCL is shrinking. IAW EOP-01A, the SRO would direct the RO to lower RPV pressure by
a. Correct answer - With SP temp rising and SP level lowering, the margin to HCL is
shrinking. IAW EOP-01A, the SRO would direct the RO to lower RPV pressure by
opening an additional SRV to maintain margin to HC
opening an additional SRV to maintain margin to HC
: [[contact::L. b. Incorrect answer - With the main condenser not available]], opening the MSIVs would not
: [[contact::L.
be appropriate. c. Correct answer - The deteriorating challenge can be immediately deduced. Due to the lowering level in the suppression pool, another challenge is immediately deduced that
b. Incorrect answer - With the main condenser not available]], opening the MSIVs would not
also leads to Emergency Depressurization per EOP-02. d. Incorrect answer - Anticipating ED is no appropriate during an ATWS.
be appropriate.
Recommendation:
c. Correct answer - The deteriorating challenge can be immediately deduced. Due to the
Modify the answer key to show two correct answers.
lowering level in the suppression pool, another challenge is immediately deduced that
also leads to Emergency Depressurization per EOP-02.
d. Incorrect answer - Anticipating ED is no appropriate during an ATWS.
Recommendation: Modify the answer key to show two correct answers.
Station Proposed Resolution:
Station Proposed Resolution:
The station does not support the candidate's basis and this question does, in fact, have only
The station does not support the candidates basis and this question does, in fact, have only
one correct answer.
one correct answer.
Step LPC/P-2 states that if HCL cannot be maintained below the limits of Figure 4, then the
Step LPC/P-2 states that if HCL cannot be maintained below the limits of Figure 4, then the
operator is directed to maintain RPV pressure below the HCL limit. As stated in the candidate's
operator is directed to maintain RPV pressure below the HCL limit. As stated in the candidates
response, the normal pressure band directed is 5 to 10&deg;F below HCL. The information given in
response, the normal pressure band directed is 5 to 10&deg;F below HCL. The information given in
the stem indicates that there is currently only 3&deg;F margin to HCL; therefore, the first appropriate action directed by the Unit Supervisor is to open additional SRVs to restore within the assigned pressure band. It is true that lowering suppression pool level due to a leak adds another layer
the stem indicates that there is currently only 3&deg;F margin to HCL; therefore, the first appropriate
action directed by the Unit Supervisor is to open additional SRVs to restore within the assigned
pressure band. It is true that lowering suppression pool level due to a leak adds another layer
of complexity however Emergency Depressurization due to lowering suppression pool level is
of complexity however Emergency Depressurization due to lowering suppression pool level is
required before 14.25 feet and the stem provides information that this level is not currently
required before 14.25 feet and the stem provides information that this level is not currently
Line 434: Line 631:
In addition, EOP Step STC-5 requires Emergency Depressurization when HCL cannot be
In addition, EOP Step STC-5 requires Emergency Depressurization when HCL cannot be
restored and maintained below the limits of Figure 4. EOP Bases defines Restore and Maintain
restored and maintained below the limits of Figure 4. EOP Bases defines Restore and Maintain
as taking actions using available systems to restore a parameter to within a desired band or condition and maintain it there which includes actions to bring on additional equipment.
as taking actions using available systems to restore a parameter to within a desired band or
Definition includes a note that states a parameter can be considered to be restored and maintained even if the parameter exceeds the limit multiple times as long as the majority of the time is spent within the limit.  
condition and maintain it there which includes actions to bring on additional equipment.
 
Definition includes a note that states a parameter can be considered to be restored and
maintained even if the parameter exceeds the limit multiple times as long as the majority of the
time is spent within the limit.
With the conditions stated in the stem there are additional actions that can be taken to restore
With the conditions stated in the stem there are additional actions that can be taken to restore
and maintain RPV pressure within the limits of HCL, Figure 4 and should be directed first by the Unit Supervisor which requires opening an additional SRV to lower RPV pressure.
and maintain RPV pressure within the limits of HCL, Figure 4 and should be directed first by the
Unit Supervisor which requires opening an additional SRV to lower RPV pressure.
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3
NRC Resolution:
NRC Resolution:
The NRC agrees with the licensee proposed resolution that there is only one correct answer to this question. The candidate incorrectly states that plotting the given conditions would place HCL in the UNSAFE region of the HCL curve. As stated by the station proposed resolution with
The NRC agrees with the licensee proposed resolution that there is only one correct answer to
this question. The candidate incorrectly states that plotting the given conditions would place
HCL in the UNSAFE region of the HCL curve. As stated by the station proposed resolution with
the conditions stated in the stem, there are additional actions that can be taken to restore and
the conditions stated in the stem, there are additional actions that can be taken to restore and
maintain RPV pressure within the limits of HCL, Figure 4, and should be directed by the Unit
maintain RPV pressure within the limits of HCL, Figure 4, and should be directed by the Unit
Supervisor. The first of these requires opening an additional SRV to lower RPV pressure to restore RPV pressure within the pressure band and below the HCL limit. As stated by the station, the question stem indicates that the lowering suppression pool level is well above the
Supervisor. The first of these requires opening an additional SRV to lower RPV pressure to
required Emergency Depressurization level of 14.25 feet.  
restore RPV pressure within the pressure band and below the HCL limit. As stated by the
 
station, the question stem indicates that the lowering suppression pool level is well above the
required Emergency Depressurization level of 14.25 feet.
As stated by the station, Emergency Depressurization is required when HCL cannot be restored
As stated by the station, Emergency Depressurization is required when HCL cannot be restored
and maintained below the limits of Figure 4. EOP Bases defines Restore and Maintain as taking actions using available systems to restore a parameter to within a desired band or condition and maintain it there which includes actions to bring on additional equipment.
and maintained below the limits of Figure 4. EOP Bases defines Restore and Maintain as
taking actions using available systems to restore a parameter to within a desired band or
condition and maintain it there which includes actions to bring on additional equipment.
Definition includes a note that states a parameter can be considered to be restored and
Definition includes a note that states a parameter can be considered to be restored and
maintained even if the parameter exceeds the limit multiple times as long as the majority of the time is spent within the limit. Additionally, the NRC reviewed the questions ask
maintained even if the parameter exceeds the limit multiple times as long as the majority of the
ed by the applicants concerning this question and found that none were asked. The answer key was not modified and choice a. is the only correct answer to the question.  
time is spent within the limit.
 
Additionally, the NRC reviewed the questions asked by the applicants concerning this question
and found that none were asked. The answer key was not modified and choice a. is the only
correct answer to the question.
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 SRO Question 15: The plant was operating at full power when the following occurred:
SRO Question 15:
Both Feedwater Pump turbines tripped. The Motor Feed Pump failed to start. The reactor automatically scrammed. One Control Rod is at position 48. All other Control Rods are fully inserted. HPCS initiation raised RPV Water Level from 110 inches. HPCS was manually overridden OFF as RPV Water Level reached 210 inches.
The plant was operating at full power when the following occurred:
Both Feedwater Pump turbines tripped.
The Motor Feed Pump failed to start.
The reactor automatically scrammed.
One Control Rod is at position 48.
All other Control Rods are fully inserted.
HPCS initiation raised RPV Water Level from 110 inches.
HPCS was manually overridden OFF as RPV Water Level reached 210 inches.
Current Plant conditions are:
Current Plant conditions are:
Reactor pressure 700 psig, rising at 10 psig per minute. MSIVs are open. The operating CRD Pump tripped.
Reactor pressure 700 psig, rising at 10 psig per minute.
Over the next ten minutes RPV Water Level will   (1)   . The procedure used to control RPV Water Level is   (2)   .  
MSIVs are open.
(1) (2) a. rise due to swell EOP-1, RPV Control
The operating CRD Pump tripped.
b. rise due to swell EOP-1A, Level Power Control
Over the next ten minutes RPV Water Level will (1) .
c. lower due to shrink EOP-1, RPV Control
The procedure used to control RPV Water Level is (2) .
d. lower due to shrink EOP-1A, Level Power Control
                (1)                   (2)
Answer: a.
a. rise due to swell           EOP-1, RPV Control
b. rise due to swell           EOP-1A, Level Power Control
c. lower due to shrink         EOP-1, RPV Control
d. lower due to shrink         EOP-1A, Level Power Control
Answer: a.
Candidate Comments:
Candidate Comments:
1. The question describes a situation in which most sources of injection to the RPV are not operating. A significant volume of relatively cold water has been injected to the RPV, and is heating up as indicated by the rising pressure. No information is
1. The question describes a situation in which most sources of injection to the RPV are
not operating. A significant volume of relatively cold water has been injected to the
RPV, and is heating up as indicated by the rising pressure. No information is
provided about the status of RCIC, but the stem indicates that RPV water level did
provided about the status of RCIC, but the stem indicates that RPV water level did
fall below the automatic initiation setpoint for RCIC. The stem of the question also
fall below the automatic initiation setpoint for RCIC. The stem of the question also
does not indicate that any operator action was taken with respect to the multiple drain lines that would normally be open under the stated conditions. Therefore, there are multiple competing effect on RPV water level.
does not indicate that any operator action was taken with respect to the multiple
2. Within the industry, the terms shrink and swell are commonly used to describe water level effects associated with changes in steam flow. Since this is not occurring, the
drain lines that would normally be open under the stated conditions. Therefore, there
terms as commonly used do not apply. Additionally, these terms are not specifically defined in the BWR General Fundamentals reference material. Therefore, the terms shrink and swell must be interpreted according to their generic definitions.  
are multiple competing effect on RPV water level.
 
2. Within the industry, the terms shrink and swell are commonly used to describe water
level effects associated with changes in steam flow. Since this is not occurring, the
terms as commonly used do not apply. Additionally, these terms are not specifically
defined in the BWR General Fundamentals reference material. Therefore, the terms
shrink and swell must be interpreted according to their generic definitions.
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 3. A rise in level can be anticipated based on the heating of the water injected by HPCS. A drop in level can also be anticipated based on RPV inventory loss through
3. A rise in level can be anticipated based on the heating of the water injected by
the open drain lines. A simulator scenario utilizing the same initial conditions outlined in the stem of the question was run to validate the plant response. Over the 10 minute time frame specified in the question, RPV water level displayed both rising
HPCS. A drop in level can also be anticipated based on RPV inventory loss through
the open drain lines. A simulator scenario utilizing the same initial conditions
outlined in the stem of the question was run to validate the plant response. Over the
minute time frame specified in the question, RPV water level displayed both rising
and lowering trends.
and lowering trends.
Candidate Justification:
Candidate Justification:
a. Correct - RPV water level does exhibit a rising trend within the 10 minute time frame due (SIC) the heat-up of the colder water, as well as the continued
a. Correct - RPV water level does exhibit a rising trend within the 10 minute time
frame due (SIC) the heat-up of the colder water, as well as the continued
injection from RCI
injection from RCI
: [[contact::C. Since the reactor is shutdown under all conditions]], EOP-1
: [[contact::C. Since the reactor is shutdown under all conditions]], EOP-1
RPV control is the correct procedure.
RPV control is the correct procedure.
b. Incorrect answer - The stem of the question states that only 1 control rod is not fully inserted, which meets the criteria for the reactor being shutdown under all
b. Incorrect answer - The stem of the question states that only 1 control rod is not
fully inserted, which meets the criteria for the reactor being shutdown under all
conditions. Therefore, EOP-1A, Level Power Control, is not the correct
conditions. Therefore, EOP-1A, Level Power Control, is not the correct
procedure.
procedure.
c. Correct - RPV water level does exhibit a lowering trend within the 10 minute time frame due to the rising pressure, as well as the inventory loss through the drain
c. Correct - RPV water level does exhibit a lowering trend within the 10 minute time
frame due to the rising pressure, as well as the inventory loss through the drain
lines. Since the reactor is shutdown under all conditions, EOP-1 RPV control is
lines. Since the reactor is shutdown under all conditions, EOP-1 RPV control is
the correct procedure.
the correct procedure.
d. Incorrect answer - The stem of the question states that only 1 control rod is not fully inserted, which meets the criteria for the reactor being shutdown under all conditions. Therefore, EOP-1A, Level Power Control, is not the correct
d. Incorrect answer - The stem of the question states that only 1 control rod is not
fully inserted, which meets the criteria for the reactor being shutdown under all
conditions. Therefore, EOP-1A, Level Power Control, is not the correct
procedure.
procedure.
Recommendation: Allow two correct answers, (a.) and (c.) correct.
Recommendation: Allow two correct answers, (a.) and (c.) correct.
Station Proposed Resolution:
Station Proposed Resolution:
The station staff does not support the candidate's basis and this question does, in fact, have
The station staff does not support the candidates basis and this question does, in fact, have
only one correct answer.
only one correct answer.
While it is true over the next 10 minutes RPV Water level both rises and lowers, the causes indicate there is only one correct answer. The injection of cold water from HPCS causes level
While it is true over the next 10 minutes RPV Water level both rises and lowers, the causes
indicate there is only one correct answer. The injection of cold water from HPCS causes level
to rise due to swell as the cold water injected begins to heat up and expand making answer (a.)
to rise due to swell as the cold water injected begins to heat up and expand making answer (a.)
the correct answer. RPV Water Level begins to lower later in the ten minute period however the
the correct answer. RPV Water Level begins to lower later in the ten minute period however the
cause is a loss of inventory due to open main steam line drains which makes (c.) an incorrect
cause is a loss of inventory due to open main steam line drains which makes (c.) an incorrect
answer. NRC Resolution:
answer.
The NRC agrees that choice a. is the only corre
NRC Resolution:
ct answer to this question. The question asks for two distinct pieces of information, (1) what will be the effect on RPV level over the next 10 minutes due to the effects of shrink and swell; and (2) which is the correct procedure used to
The NRC agrees that choice a. is the only correct answer to this question. The question asks
for two distinct pieces of information, (1) what will be the effect on RPV level over the next
minutes due to the effects of shrink and swell; and (2) which is the correct procedure used to
control RPV level given the plant conditions stated in the stem. Distracters b. and d. are
control RPV level given the plant conditions stated in the stem. Distracters b. and d. are
incorrect because they specify an incorrect procedure (EOP-1A, Level Power Control) for
incorrect because they specify an incorrect procedure (EOP-1A, Level Power Control) for
controlling RPV level. The RPV level will change due to two discrete effects. One is a change
controlling RPV level. The RPV level will change due to two discrete effects. One is a change
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 in the inventory of fluid in the RPV, i.e., steam being removed by the MSL drains or water injected by high pressure sources. The other is a change in RPV level due to a change in the
in the inventory of fluid in the RPV, i.e., steam being removed by the MSL drains or water
RPV water's density from changes in the water's temperature. As the colder water injected by HPCS is heated, and RPV pressure and temperature rise, RPV level will continue to rise. Since the question only asks for the change in RPV level due to the effects of shrink and swell,
injected by high pressure sources. The other is a change in RPV level due to a change in the
any change in RPV level due to a change in inventory does not factor in to the answer.  
RPV waters density from changes in the waters temperature. As the colder water injected by
 
HPCS is heated, and RPV pressure and temperature rise, RPV level will continue to rise.
Additionally, the NRC reviewed the questions ask
Since the question only asks for the change in RPV level due to the effects of shrink and swell,
ed by the applicants concerning this question and found that one applicant asked if he was predicting the correct answer to the question based on the terms "shrink" and "swell.The other applicant asked if RCIC had initiated. The
any change in RPV level due to a change in inventory does not factor in to the answer.
Additionally, the NRC reviewed the questions asked by the applicants concerning this question
and found that one applicant asked if he was predicting the correct answer to the question
based on the terms shrink and swell. The other applicant asked if RCIC had initiated. The
proctor directed the applicant in each case to attempt to answer the question based on the
proctor directed the applicant in each case to attempt to answer the question based on the
information provided in the question stem.  
information provided in the question stem.
 
Based upon the above discussion, the NRC did not modify the answer key and retained choice
Based upon the above discussion, the NRC did not modify the answer key and retained choice
a. as the only correct answer to the question.
a. as the only correct answer to the question.
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 SRO Question 18:   The plant is in shutdown with the following conditions:   Average Reactor Coolant temperature is 190&deg;
SRO Question 18:
: [[contact::F. RHR A loop placed in Shutdown Cooling (SDC) Mode of operation IAW SOI-E12. Based on this information]], the LPCI mode of RHR A system is _______. a. NOT affected, since it is NOT required to be OPERABLE with the current plant conditions. b. INOPERABLE, since the RHR Minimum Flow Valve is de-energized closed for SDC
The plant is in shutdown with the following conditions:
Operations. c. INOPERABLE, since the system must be manually realigned when required. d. OPERABLE, provided the system c
Average Reactor Coolant temperature is 190&deg;F.
an be manually realigned when required.
RHR A loop placed in Shutdown Cooling (SDC) Mode of operation IAW SOI-E12.
Answer: d.
Based on this information, the LPCI mode of RHR A system is _______.
a. NOT affected, since it is NOT required to be OPERABLE with the current plant
conditions.
b. INOPERABLE, since the RHR Minimum Flow Valve is de-energized closed for SDC
Operations.
c. INOPERABLE, since the system must be manually realigned when required.
d. OPERABLE, provided the system can be manually realigned when required.
Answer: d.
Candidate Comments:
Candidate Comments:
1. The question asks how the LPCI mode of operation is impacted when a train of the Residual Heat Removal System is placed in the Shutdown Cooling Mode of operation. 2. In Mode 4, only 2 ECCS injection/spray subsystems shall be OPERABLE (TS 3.5.2). 3. Per TS 3.5.2 Bases, one LPCI subsystem may be considered operable during alignment or operation for decay heat removal in Mode 4 or 5, if capable of being manually
1. The question asks how the LPCI mode of operation is impacted when a train of the
realigned to the LPCI mode. 4. Candidates are instructed prior to the test (NUREG-1021, Appendix E) not to make assumptions regarding conditions that were no specified in the question unless they occurred as a consequence of other conditions that were stated in the question. 5. Stem of the question does not identify any other systems as being INOPERABLE, ALL ECCS systems are OPERABLE; therefore, LPCI A is NOT required to be OPERABLE.
Residual Heat Removal System is placed in the Shutdown Cooling Mode of operation.
2. In Mode 4, only 2 ECCS injection/spray subsystems shall be OPERABLE (TS 3.5.2).
3. Per TS 3.5.2 Bases, one LPCI subsystem may be considered operable during alignment
or operation for decay heat removal in Mode 4 or 5, if capable of being manually
realigned to the LPCI mode.
4. Candidates are instructed prior to the test (NUREG-1021, Appendix E) not to make
assumptions regarding conditions that were no specified in the question unless they
occurred as a consequence of other conditions that were stated in the question.
5. Stem of the question does not identify any other systems as being INOPERABLE, ALL
ECCS systems are OPERABLE; therefore, LPCI A is NOT required to be OPERABLE.
Candidate Justification:
Candidate Justification:
a. Correct answer - LPCI A is NOT required to OPERABLE with the current plant conditions. In Mode 4, only 2 ECCS injection/spray subsystems shall be OPERABLE (TS 3.5.2). Stem does not identify any other systems as being INOPERABL
a. Correct answer - LPCI A is NOT required to OPERABLE with the current plant
: [[contact::E. b. Incorrect answer - INOPERABLE]], the RHR Minimum Flow Valve de-energized closed for SDC Operations does not make the system INOPERABL
conditions. In Mode 4, only 2 ECCS injection/spray subsystems shall be OPERABLE
      (TS 3.5.2). Stem does not identify any other systems as being INOPERABL
: [[contact::E.
b. Incorrect answer - INOPERABLE]], the RHR Minimum Flow Valve de-energized closed
for SDC Operations does not make the system INOPERABL
: [[contact::E. TS 3.5.2 Bases]], one
: [[contact::E. TS 3.5.2 Bases]], one
LPCI subsystem may be considered operable during alignment or operation for decay heat removal in Mode 4 or 5, if capable of being manually realigned to the LPCI mode. c. Incorrect answer - INOPERABLE, since the system must be manually realigned when required. TS 3.5.2 Bases, one LPCI subsystem may be considered operable during
LPCI subsystem may be considered operable during alignment or operation for decay
heat removal in Mode 4 or 5, if capable of being manually realigned to the LPCI mode.
c. Incorrect answer - INOPERABLE, since the system must be manually realigned when
required. TS 3.5.2 Bases, one LPCI subsystem may be considered operable during
Enclosure 3
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
POST-EXAMINATION COMMENTS WITH NRC RESOLUTION
Enclosure 3 alignment or operation for decay heat removal in Mode 4 or 5, if capable of being manually realigned to the LPCI mode.
alignment or operation for decay heat removal in Mode 4 or 5, if capable of being
manually realigned to the LPCI mode.
d. Correct answer - OPERABLE, provided the system can be manually realigned when
d. Correct answer - OPERABLE, provided the system can be manually realigned when
required, TS 3.5.2 Bases, one LPCI subsystem may be considered operable during
required, TS 3.5.2 Bases, one LPCI subsystem may be considered operable during
alignment or operation for decay heat removal in Mode 4 or 5, if capable of being manually realigned to the LPCI mode.
alignment or operation for decay heat removal in Mode 4 or 5, if capable of being
Recommendation: Amend the Answer Key to list 'Answer A' as a correct answer, in addition
manually realigned to the LPCI mode.
to 'Answer D'
Recommendation: Amend the Answer Key to list Answer A as a correct answer, in addition
to Answer D
Station Proposed Resolution:
Station Proposed Resolution:
Station agrees with the above candidate Comments, Justification and Recommendation since
Station agrees with the above candidate Comments, Justification and Recommendation since
we have provided "newly discovered technical information that supports a change in the answer
we have provided newly discovered technical information that supports a change in the answer
key."
key.
NRC Resolution:
NRC Resolution:
The NRC disagrees with both 1) the candidate's comm
The NRC disagrees with both 1) the candidates comment/justification, that since only 2 ECCS
ent/justification, that since only 2 ECCS injection/spray subsystems are required to be OPERABLE given the conditions stated in the
injection/spray subsystems are required to be OPERABLE given the conditions stated in the
stem, the LPCI mode of RHR A system is NOT affected; and 2) the station's proposed resolution to accept two correct answers based upon newly discovered technical information that supports a change in the answer key. The question asks whether, based upon the conditions given in the stem, the LPCI mode of RHR A system is considered OPERABLE per Technical Specifications. Just because a subsystem is not required to be OPERABLE for a given plant condition does not mean the  
stem, the LPCI mode of RHR A system is NOT affected; and 2) the stations proposed
"operability" of the subsystem is NOT affected by the given plant condition. Therefore, the
resolution to accept two correct answers based upon newly discovered technical information
candidate's comment/justification is incorrect. The licensee submitted the associated portions of the facility's Technical Specifications, including the bases, for ECCS systems - Shutdown, which does not provide any additional nor newly discovered technical information to support a
that supports a change in the answer key.
change to the answer key. Additionally, the NRC reviewed the questions asked by the applicants concerning this question and found that none were asked. Based upon the above discussion, the NRC did not modify the answer key and retained choice
The question asks whether, based upon the conditions given in the stem, the LPCI mode of
RHR A system is considered OPERABLE per Technical Specifications. Just because a
subsystem is not required to be OPERABLE for a given plant condition does not mean the
operability of the subsystem is NOT affected by the given plant condition. Therefore, the
candidates comment/justification is incorrect. The licensee submitted the associated portions
of the facilitys Technical Specifications, including the bases, for ECCS systems - Shutdown,
which does not provide any additional nor newly discovered technical information to support a
change to the answer key. Additionally, the NRC reviewed the questions asked by the
applicants concerning this question and found that none were asked.
Based upon the above discussion, the NRC did not modify the answer key and retained choice
d. as the only correct answer to the question.
d. as the only correct answer to the question.
V. Kaminskas     -2-
Enclosure 3
In accordance with Title 10, Code of Federal Regulations (CFR), Part 50, Section 2.390 of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any), will be
V. Kaminskas                                       -2-
available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
In accordance with Title 10, Code of Federal Regulations (CFR), Part 50, Section 2.390 of the
Sincerely,
NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any), will be
/RA/ By Bruce Palagi Acting For/  
available electronically for public inspection in the NRC Public Document Room or from the
 
Publicly Available Records System (PARS) component of NRC's Agencywide Documents
Access and Management System (ADAMS), accessible from the NRC Web site at
http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
                                                    /RA/ By Bruce Palagi Acting For/
Hironori Peterson, Chief
Hironori Peterson, Chief
Operations Branch
Operations Branch
Division of Reactor Safety
Division of Reactor Safety
Docket No. 50-440
Docket No. 50-440
License No. NPF-58  
License No. NPF-58
Enclosures:
1. Operator Licensing Examination Report 05000440/2013301
w/Attachment: Supplemental Information
2. Simulation Facility Report
3. Written Examination Post-Examination Comment Resolution
cc w/encl:        Distribution via ListServ'
: [[contact::A. Mueller]], Training Manager, Perry Nuclear Power Plant


Enclosures: 1. Operator Licensing Examination Report 05000440/2013301 w/Attachment:  Supplemental Information 2. Simulation Facility Report 3. Written Examination Post-Examination Comment Resolution cc w/encl: Distribution via ListServ&#x17d;
: [[contact::A. Mueller]], Training Manager, Perry Nuclear Power Plant
}}
}}

Latest revision as of 19:18, 4 November 2019

Er 05000440-13-301; 02/25/2013 - 03/14/2013; Firstenergy Nuclear Operating Company, Perry Nuclear Power Plant, Initial License Examination Report
ML13114A983
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 04/24/2013
From: Hironori Peterson
Operations Branch III
To: Kaminskas V
FirstEnergy Nuclear Operating Co
Shared Package
ML12236A337 List:
References
50-440/13-301
Download: ML13114A983 (31)


Text

ril 24, 2013

SUBJECT:

PERRY NUCLEAR POWER PLANT NRC INITIAL LICENSE EXAMINATION REPORT 05000440/2013301

Dear Mr. Kaminskas:

On March 14, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed the initial operator licensing examination process for license applicants employed at your Perry Nuclear Power Plant. The enclosed report documents the results of those examinations. Preliminary observations noted during the examination process were discussed on March 6, 2013, with you and other members of your staff. An exit meeting was conducted by telephone on April 4, 2013, between Mr. A. Mueller, Training Manager, of your staff, and Mr. M. Bielby, Chief Examiner, to review the proposed final grading of the written examination for the license applicants. During the telephone conversation, the NRC resolutions of the stations post-examination comments, initially received by the NRC on March 14, 2013, were discussed.

The NRC examiners administered an initial license examination operating test during the weeks of February 25 and March 4, 2013. The written examination was administered by Perry Nuclear Power Plant training department personnel on March 6, 2013. Nine Senior Reactor Operator and three Reactor Operator applicants were administered license examinations. The results of the examinations were finalized on April 5, 2013. Three applicants failed the senior operator portion of the administered written examination and were issued a proposed license denial letter. Nine applicants passed all sections of their respective examinations; five applicants were issued senior operator licenses; and three applicants were issued operator licenses.

In accordance with NRC policy, the license for the remaining senior operator applicant is being withheld pending the outcome of any written examination appeal that may be initiated.

The written examination and other related written examination documentation will not be withheld from public disclosure. When an applicant receives a proposed license denial letter because of a written examination grade that is less than 80.0%, the applicant will be provided a copy of the written examination. For examination security purposes, your staff should consider that written examination uncontrolled and exposed to the public. In accordance with Title 10 of the Code of Federal Regulations, Section 2.390 of the NRC's

"Rules of Practice," a copy of this letter and its enclosures will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/ By Bruce Palagi Acting For/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket No. 50-440 License No. NPF-58

Enclosures:

1. Operator Licensing Examination Report 05000440/2013301 w/Attachment: Supplemental Information 2. Simulation Facility Report 3. Written Examination Post-Examination Comment Resolution

REGION III==

Docket No: 50-440 License No: NPF-58 Report No: 05000440/2013301 Licensee: FirstEnergy Nuclear Operating Company (FENOC)

Facility: Perry Nuclear Power Plant Location: Perry, Ohio Dates: February 25 - March 14, 2013 Inspectors: M. Bielby, Chief Examiner R. Baker, Examiner D. Oliver, Examiner Approved by: H. Peterson, Chief Operations Branch Division of Reactor Safety Enclosure 1

SUMMARY OF FINDINGS

ER 05000440/2013301; 02/25/2013 - 03/14/2013; FirstEnergy Nuclear Operating Company,

Perry Nuclear Power Plant; Initial License Examination Report.

The announced initial operator licensing examination was conducted by regional Nuclear Regulatory Commission (NRC) examiners in accordance with the guidance of NUREG-1021,

Operator Licensing Examination Standards for Power Reactors, Revision 9, Supplement 1.

Examination Summary Nine of twelve applicants passed all sections of their respective examinations. Five applicants were issued senior operator licenses and three applicants were issued operator licenses.

Three applicants failed the administered senior operator section of the written examination and were issued proposed license denials. The license for the remaining senior operator applicant is being held and may be issued pending the outcome of any written examination appeal(s).

(Section 4OA5.1).

REPORT DETAILS

4OA5 Other Activities

.1 Initial Licensing Examinations

a. Examination Scope

The NRC examiners and members of the facility licensees staff used the guidance prescribed in NUREG-1021, Operator Licensing Examination Standards for Power Reactors, Revision 9-Supplement 1, to develop, validate, administer, and grade the written examination and operating test. Members of the facility licensees staff prepared the outline and developed the written examination and operating test. The NRC examiners validated the proposed examination during the week of February 4, 2013, with the assistance of members of the facility licensees staff. During the on-site validation week, the examiners audited three license applications for accuracy.

The NRC examiners, with the assistance of members of the facility licensees staff, administered the operating test, consisting of job performance measures and dynamic simulator scenarios, during the period of February 25 through March 5, 2013. The facility licensee administered the written examination on March 6, 2013.

b. Findings

(1) Written Examination The NRC examiners determined that the written examination, as proposed by the licensee, was within the range of acceptability expected for a proposed examination.

Less than 20% of the proposed examination questions were determined to be unsatisfactory and required modification or replacement. All changes made to the proposed written examination, were made in accordance with NUREG-1021, "Operator Licensing Examination Standards for Power Reactors, and documented on Form ES-401-9, Written Examination Review Worksheet, which will be available electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's Agencywide Documents Access and Management System (ADAMS). On March 14, 2013, the licensee submitted documentation noting that there were seven post-examination comments for consideration by the NRC examiners when grading the written examination. Additional supporting information was submitted to the NRC examiners on April 3, 2013, based on discussions with the licensee. The post-examination comments and the NRC resolution for the post-examination comments are included in Enclosure 3 of this report. The final as-administered examination and answer key (ADAMS Accession Number ML13113A060), will be available electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's ADAMS.

The NRC examiners graded the written examination on April 5, 2013, and conducted a review of each missed question to determine the accuracy and validity of the examination questions.

(2) Operating Test In general, the overall operating test submitted by the licensee met the NRC expectations; however, the proposed Job Performance Measure (JPM) test items did not meet the NRCs expectations and additional attention in this area is warranted. Four JPMs were significantly modified or replaced. Two system JPMs were replaced during validation because they lacked significant evaluation steps to be performed by the applicant. One system JPM was not considered an alternate path as written, and was modified to make it alternate path. Another system JPM was changed from having the applicant verbally perform it in the control room to requiring the applicant to actually manipulate the controls in the simulator. Several other JPMs were modified to add more significance to the task required to be performed. One additional administrative JPM was developed, validated and administered to one applicant when it was discovered that the applicant had been released into a group of applicants that had completed one JPM not previously administered to the applicant. This was considered an examination security issue. Several modifications were made to the dynamic simulator scenarios to enhance evaluation of performance. Changes made to the operating test, documented in a document titled, Operating Test Comments, as well as the final as-administered dynamic simulator scenarios and JPMs, are available electronically in the NRC Public Document Room or from the Publicly Available Records component of NRC's ADAMS.

The NRC examiners completed operating test grading on April 5, 2013.

(3) Examination Results Nine applicants at the Senior Reactor Operator (SRO) level and three applicants at the Reactor Operator (RO) level were administered written examinations and operating tests. Nine applicants passed all portions of their examinations and were issued their respective operating licenses. Three applicants failed the administered SRO portion of the written examination and were issued proposed license denials. One applicant passed all portions of the license examination, but received an SRO written test grade below 74 percent. In accordance with NRC policy, the applicants license will be withheld until any written examination appeal possibilities by other applicants have been resolved. If the applicants grade is still equal to or greater than 70 percent after any appeal resolution, the applicant will be issued a senior operator license. If the applicants SRO written grade has declined below 70 percent, the applicant will be issued a proposed license denial letter and offered the opportunity to appeal any questions the applicant feels were graded incorrectly.

.2 Examination Security

a. Scope

The NRC examiners reviewed and observed the licensee's implementation of examination security requirements during the examination validation and administration to assure compliance with Title10 of the Code of Federal Regulations, Section 55.49, Integrity of Examinations and Tests. The examiners used the guidelines provided in NUREG -1021, "Operator Licensing Examination Standards for Power Reactors, to determine acceptability of the licensees examination security activities.

b. Findings

One examination security concern was identified during the process of administering the JPM examination. The licensees security policy was not to mix applicants that had performed JPMs with those that had not performed the same JPMs. One applicant that had completed all but one of his JPMs for the day was released from the simulator into a sequestered classroom and was inadvertently allowed to mingle with other applicants that had completed all of their JPMs for the day. The Chief Examiner determined that there was no evidence of examination compromise based on the short time period until discovery, and interviews with the applicants that were directly involved in the incident who indicated no JPMs had been discussed. However, to insure there was no unfair advantage to the applicant, another administrative JPM was developed and validated with concurrence of the regional Branch Chief, and administered to the applicant to replace the JPM in question. This was considered to be an examination security issue.

4OA6 Management Meetings

.1 Debrief

The chief examiner presented the examination team's preliminary observations and findings on March 6, 2013, to Mr. V. Kaminskas, Site Vice President, and other members of the Perry Operations and Training Department staff.

.2 Exit Meeting

The chief examiner conducted an exit meeting on April 4, 2013, with Mr. T. Mueller, Training Manager, by telephone. The NRCs final disposition of the stations post-examination comments were disclosed and discussed with Mr. T. Mueller during the telephone discussion. The examiners asked the licensee whether any of the material used to develop or administer the examination should be considered proprietary. No proprietary or sensitive information was identified during the examination or debrief/exit meetings.

ATTACHMENT:

SUPPLEMENTAL INFORMATION

Enclosure 1

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

V. Kaminskas, Site Vice President-Nuclear
R. Brooks, Lead-Fleet Exam Development Team
H. Hanson Jr., Director-Performance Improvement
J. Kelly, Lead-Initial Licensed Operator Training
T. Mueller, Manager-Training
D. ODonnell, Shift Manager-Facility Reviewer
J. Pelcic, Engineer-Regulatory Compliance
R. Strohl, Superintendent-Operator Training
R. Torres, Fleet Training Exam Author
J. Tufts, Manager-Operations

NRC

M. Marshfield, Senior Resident Inspector
J. Nance, Resident Inspector
M. Bielby, Chief Examiner
R. Baker, Examiner
D. Oliver, Examiner

ITEMS OPENED, CLOSED, AND DISCUSSED

Opened/Closed

None

Attachment

LIST OF ACRONYMS USED

ADAMS Agencywide Document Access and Management System

ATWS Anticipated Transient Without Scram

CFR Code of Federal Regulations

DRS Division of Reactor Safety

DG Diesel Generator

ECCS Emergency Core Cooling Systems

EOF Emergency Operating Facility

EOP Emergency Operating Procedures

ER Examination Report

ERO Emergency Response Organization

HCL Heat Capacity Limit

HPCS High Pressure Core Spray

IAW in accordance with

JPM Job Performance Measures

LOCA Loss of Coolant Accident

LOOP Loss-of-Offsite-Power

LPCI Low Pressure Coolant Injection

LPCS Low Pressure Core Spray

MSIV Main Steam Isolation Valve

NRC U.S. Nuclear Regulatory Commission

OPRM Oscillation Power Range Monitor

PARS Publicly Available Records System

RHR Residual Heat Removal

RO Reactor Operator

RPV Reactor Pressure Vessel

SAG Severe Accident Guideline

SDC Shutdown Cooling

SRO Senior Reactor Operator

SRV Safety Relief Valve

Attachment

SIMULATION FACILITY REPORT

Facility Licensee: Perry Nuclear Power Plant

Facility Docket No: 50-440

Operating Tests Administered: Weeks of February 25 and March 4, 2013

The following documents observations made by the NRC examination team during the initial

operator license examination. These observations do not constitute audit or inspection findings

and are not, without further verification and review, indicative of non-compliance with 10 CFR 55.45(b). These observations do not affect NRC certification or approval of the simulation

facility other than to provide information which may be used in future evaluations. No licensee

action is required in response to these observations.

During the conduct of the simulator portion of the operating tests, the following items were

observed:

ITEM DESCRIPTION

Simulator Lockup, During the examination administration of the second set of Scenario 1

CR 2013-02777 on February 25, 2013, a simulator lockup (IO quit responding)

occurred after Event 2, Raise Reactor Power With Flow to 100%.

Simulator was re-booted and reset to just before the lockup point and

the scenario resumed. There were no further lockup occurrences

during the examination administration.

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

RO Question 40:

The plant was operating at rated power.

An inadvertent initiation of Low Pressure Core Spray occurred due to failure of the DW pressure

trip units.

Only the Immediate Actions of ONI-E12-1, Inadvertent Initiation of ECCS or RCIC were

performed and were successful.

Subsequently, a loss of offsite power occurred coincident with a LOC

A.

When power is restored to the divisional buses by the diesel generators, LPCS will _____.

a. not automatically restart

b. automatically restart immediately

c. automatically restart in 10 seconds

d. automatically restart in 15 seconds

Answer: a.

(The following candidate comment and station proposed resolution are directly copied from the

post-examination comment submission.)

Candidate Comments:

1. The question asks how the LPCS pump will respond following a LOOP/LOCA actuation

signal if the pump initiation logic had been previously overridden.

2. The answer key incorrectly lists distracter A as the correct answer.

3. Per plant drawings 208-0060-00004, Revision AA and 208-0060-00008, Revision DD,

the LPCS Override Logic Seal-in will de-energize during a Loss of Offsite Power and

when power is restored the LPCS pump will automatically restart with no time delay.

4. Amend the answer key to list distracter B as the correct answer.

Candidate Justification:

a. Incorrect answer - The LPCS pump will automatically restart, the override seal-in logic

de-energizes during a LOOP.

b. Correct answer - The LPCS pump will automatically restart without time delay.

c. Incorrect answer - The LPCS pump will automatically restart without time delay,

seconds is the time allowed for the DG to energize the bus. a loss of offsite power

occurred coincident with a LOCA.

d. Incorrect answer - The LPCS pump will automatically restart without time delay.

The 15 second time delay is for a LOCA only without a LOOP.

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

Recommendation: Amend the Answer Key to list Answer B as the correct answer.

References: Plant drawings 208-0060-00004, Revision AA, and 208-0060-00008,

Revision DD.

Station Proposed Resolution:

The station agrees with the above candidate Comments, Justification and Recommendation.

NRC Resolution:

The NRC agrees with the applicants comment. The question basically asks how the LPCS

pump will start when power restored by the Diesel Generators after the LPCS pump was placed

in STOP followed by a LOOP/LOCA occurrence. Reference to the Power Monitor and LPCS

Pump 1E21-C001, Control portion of plant drawing, 208-0060-00004, and plant drawing 208-

0060-00008, support the following relay actuations and contact development which indicate an

automatic LPCS pump start without time delay:

INITIAL CONDITIONS

1R22-27X1A and S13 closed energizing K1 and K1B.

Pump control switch (S6) in AUTO; K13 is deenergized (Manual Override is NOT

active).

K1 contact M1-T1 is closed; K10 contact M2-T2 is open (no LOCA); K13 contact

M1-R1 is closed (M1-T1 is open) resulting in relays K12 and K12A being

deenergized.

K1B contact (3-5) is open (opened 19 seconds after bus was energized); K12

contact (1-5) is open; K12A contact M3-T3 is open.

INADVERTENT LOCA (seals in)

K10 contact M2-T2 closes energizing relays K12 and K12A; K12A contact M3-T3

closes immediately but does not start pump since K1B contact 3-5 is open; K12

contact 1-5 closes after a 15 second time delay, starting the LPCS pump.

Per ONI immediate actions pump is stopped (Manual Override) by momentarily

placing pump control switch (S6) in STOP tripping the pump breaker and removing

the auto start signal by energizing relay K13; K13 contact M1-T1 closes (seals in

Manual Override) and K13 contact M1-R1 opens deenergizing relays K12 and K12A

opening relay K12 contact 1-5 and K12A contact 3-5.

SUBSEQUENT LOOP (LOCA signal still sealed in)

1R22-27X1A opens de-energizing relays K1 and K1B; relay K1 contact M1-T1 opens

de-energizing relay K13; K13 contact M1-T1 opens (breaking the seal-in on for the

Manual Override) and K13 contact M1-R1 closes.

OFFSITE POWER RESTORED

1R22-27X1A and S13 closed energizing K1 and K1B.

Pump control switch (S6) in AUTO; K13 is deenergized (Manual Override is NOT

active).

K1 contact M1-T1 is closed; K10 contact M2-T2 is closed (LOCA is sealed-in);

K13 contact M1-R1 is closed (M1-T1 is open) Relays K12 and K12A energize;

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

K12 contact is open (closes after 15 seconds), but K12A contact M3-T3 closes;

the LPCS pump starts without any delay.

Additionally, the NRC reviewed the questions asked by the applicants concerning this question

and found that there were none asked. The answer key was amended to accept distracter b. as

the only correct answer.

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

RO Question 66:

The plant was operating at rated power when the following occurred:

The reactor was scrammed 20 minutes ago due to a problem with the pressure regulator

system.

During the transient, both Reactor Recirculation Pumps tripped off.

Current RPV pressure is 600 psig and lowering at 2.5 psig/minute.

The scram has just been reset.

RPV Bottom Head Drain temperature is 445°F.

RPV Vessel Head Flange temperature is 500°

F.

Based on these conditions, bulk RPV water temperature currently is approximately ___(1)___.

If cooldown is allowed to continue at the present rate, Tech Spec cooldown rate ___(2)___

Exceeded.

(1) (2)

a. 44°F > Bottom Head Drain will

b. 16°F < Vessel Head Flange will

c. 44°F > Bottom Head Drain will not

d. 16°F < Vessel Head Flange will not

Answer: c.

The following candidate comment and station proposed resolution are directly copied from the

post-examination comment submission.

Candidate Comments:

1. The question asks what the temperature difference is between bulk reactor coolant and

the RPV skin and whether the Technical Specification cooldown rate has been exceeded

when cooling down at 2.5 psig per minute. The answer key should be changed for

newly discovered technical information.

2. A cooldown rate maintained at a constant 2.5 psig/minute (150 psig/hr) will exceed the

Technical Specification cooldown limit of < 100 degrees F per hour.

3. During the one hour period pressure is reduced from 175 psig to 25 psig the cooldown

rate is 100 degrees F exceeding the Technical Specification Limit.

Time Pressure (psig) Temperature (°F) Delta (°F)

T + 2 hr 10 min 325 429

T + 3 hr 10 min 175 377 52

T + 4 hr 10 min 25 267 110

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

Candidate Justification:

(1) (2)

Correct

a. 44°F > Bottom Head Drain will

Answer

The saturated temperature of 600 psig (~615

Tech Spec cooldown

Justification psia) is ~490°F (489), which is about 44°F >

rate Exceeded 110°F

the bottom head temp in this case

Incorrect

b. 16°F < Vessel Head Flange will

Answer

16°F < Vessel Head Flange is temperature Tech Spec cooldown

Justification

calculated if psia is calculated backwards rate Exceeded 110°F

Incorrect

c 44°F > Bottom Head Drain will not

Answer

The saturated temperature of 600 psig (~615

Tech Spec cooldown

Justification psia) is ~490°F (489), which is about 44°F >

rate Exceeded 110°F

the bottom head temp in this case

Incorrect

d. 16°F < Vessel Head Flange will not

Answer

16°F < Vessel Head Flange is temperature Tech Spec cooldown

Justification

calculated if psia is calculated backwards rate Exceeded 110°F

Recommendation: Amend the Answer Key to list Answer A as the only correct answer.

Station Proposed Resolution:

Station agrees with the above candidate Comments, Justification and Recommendation.

NRC Resolution:

The NRC agrees with the candidates comment and station proposed resolution. After

reviewing the calculations it was discovered that the cooldown rate will exceed the Technical

Specification limit at the time specified by the candidate comment. Additionally, the NRC

reviewed the questions asked by the applicants concerning this question and found that none

were asked. The answer key was amended to accept distracter a. as the only correct answer.

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

SRO Question 1:

A loss of Hot Surge Tank level occurred.

The following conditions now exist:

Operating in EOP-01, RPV Control.

RPV level is -46 inches and lowering.

RPV pressure is 5 psig.

HPCS pump shaft has broken.

LPCS pump is tagged out for motor replacement with motor removed.

RHR A pump is degraded.

EH12 has a Bus lockout.

No Alternate Injection Subsystems can be lined up.

The EOF is operational.

As the Shift Manager, you would notify the Emergency Response Organization that entry into

___(1)___ is required.

EOP actions are (2) after the SAGs are entered.

(1) (2)

a. SAG-1, Primary Containment Flooding Continued

b. SAG-1, Primary Containment Flooding Exited

c. SAG-2, RPV, Containment, and Continued

Radioactivity Release Control

d. SAG-2, RPV, Containment, and Exited

Radioactivity Release Control

Answer: b.

The following candidate comment and station proposed resolution are directly copied from the

post-examination comment submission.

Candidate Comments:

1. The question asks the required Shift Manager actions after the determination that

adequate core cooling no longer exists and the required status of the Emergency

Operating Procedures when transitioning to the Severe Accident guidelines.

2. The answer key states SAG-1, Primary Containment Flooding is the required SAG

actions.

3. The bases for EOP-1, Step ALC-15, states that Transition to the SAGs is completed by

the Shift Manager notification to the ERO that Primary Containment Flooding is

required.

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

4. The bases for SAG-1 states that The requirements for Primary Containment flooding in

the RPV Control, EOP-1, Level Power Control, EOP-1A, RPV Flooding, EOP04-4,

flowcharts are directed through concurrent transitions to the Primary Containment

Flooding, SAG-1 and RPV, Primary Containment, and Radioactivity Release Control,

SAG-2 Flowcharts.

5. The SAG-1 bases clearly states The RPV and Primary Containment Flooding guideline

and the Primary Containment and Radioactivity Release Control guideline are entered

and executed concurrently.

6. Answer D SAG-2, RPV, Containment, and Radioactivity Release Control for part 1 and

Exited for part 2 is a correct answer since we have newly discovered technical

information that supports a change in the answer key.

7. References, EOP-1 pg 61, SAG-1 bases pg 6 and SAG-2 pg 8 are attached.

Candidate Justification:

As the Shift Manager, you would notify the Emergency Response Organization that entry

in (1) is required.

EOP actions are (2) after the SAGs are entered.

(1) (2)

a. Incorrect answer SAG-1, Primary Containment Flooding Continued

Correct - Primary Containment (SG-1) and Incorrect - EOP

Radioactivity Release Control guideline Actions are

(SAG-2) are entered and executed discontinued when

concurrently SAGs are entered.

b. Correct answer SAG-1 Primary Containment Flooding Exited

Correct - Primary Containment (SG-1) and Correct - EOP

Radioactivity Release Control guideline Actions are

(SAG-2) are entered and executed discontinued when

concurrently SAGs are entered.

Incorrect answer SAG-2, RPV, Containment, and Radioactivity Continued

c.

Release Control

Correct - Primary Containment (SAG-1) and Incorrect - EOP

Radioactivity Release Control guideline Actions are

(SAG-2) are entered and executed discontinued when

concurrently SAGs are entered.

Correct answer SAG-2, RPV, Containment, and Radioactivity Exited

d.

Release Control

Correct - Primary Containment (SAG-1) and Correct - EOP

Radioactivity Release Control guideline Actions are

(SAG-2) are entered and executed discontinued when

concurrently SAGs are entered.

Recommendation: Amend the Answer Key to list Answer D as a correct answer also, in

addition to Answer

B.

References: EOP bases, EOP-1 pg 61, SAG bases, SAG-1 bases pg 6, and SAG-2 pg 8.

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

Station Proposed Resolution:

Station agrees with the above candidate Comments, Justifications and Recommendation.

The question did not ask for all the required procedures. Therefore, the justification supports

correct answers.

NRC Resolution:

The NRC disagrees with the candidates comment/justification and station proposed resolution

that both answers b. and d. are correct. The question asks for the required Shift Manager

actions after the determination that adequate core cooling no longer exists and the required

status of the Emergency Operating Procedures (EOPs) when transitioning to the Severe

Accident Guidelines (SAGs). The EOP-1, RPV Control; EOP-1A, Level Power Control; and

EOP 04-4, RPV Flooding, flowcharts do not direct concurrent entry into SAG-1, Primary

Containment Flooding, and SAG-2, Primary Containment and Radioactivity Release Control, as

stated by the candidate and supported by the station proposed resolution. The EOP-1, EOP-1A

and EOP 04-4 flowcharts direct transition to Primary Containment Flooding which is SAG-1.

Once the SAG-1 flowchart is entered, a subsequent step directs entry into SAG-2 and both

SAGs are performed concurrently. Once transition to the SAGs is performed, the EOPs are

exited.

Additionally, the NRC reviewed the questions asked by the applicants concerning this question

and found that none were asked. Based upon the above discussion, the NRC did not modify

the answer key and retained choice b. as the only correct answer to the question.

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

SRO Question 8:

The following conditions exist:

The plant is operating at 98% power.

Core flow is 103 Mlbs/Hr.

OPRMs are INOPERABLE.

Alternate methods to detect and suppress thermal hydraulic instability oscillations have

been initiated IAW 3.3.1.3 OPRM Instrumentation.

Reactor Recirculation Pump B then trips.

In accordance with ONI-C51, Unplanned Changes Reactor Power or Reactivity, the Unit

Supervisor will direct .

a. Inserting Cram Rods IAW FTI-B002, Control Rod Movements

b. restarting Recirc Pump B IAW SOI-B33, Reactor Recirculation

c. Inserting a manual reactor scram IAW ONI-C71-1, Reactor Scram

d. shutting Recirc Pump B FCV IAW ONI-SPI G-2, Single Pump Operation

Answer: a.

Candidate Comments:

1. The question asks what actions are required for a trip of a Reactor Recirculation pump

per ONI-C51. The stem of the question does not provide all the necessary information

to answer the question. ONI-C51 FLOWCHART step C51-4 If while Executing step

refers the operator to the Core Flow Caution. This step is applicable at all times the

operator is using this procedure.

2. ONI-C51 FLOWCHART Core Flow Caution requires the operator to determine the actual

core flow using core plate P which is not provided.

Core Flow - During single Recirculation pump operation the core flow instrument

may not indicate properly. Actual core flow may be determined

using:

Core plate P and the curve in PDB-A0015.

A core plate P of 2.25 psid is approximately 42 Mblm(sic)/Hr

core flow.

SPDS screen CFLOWV.

3. The procedure direct that core flow be determined using core plate delta pressure which

then outlines the correct course of action taken by the Unit Supervisor, core plate delta

pressure was not provided.

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

Candidate Justification:

a. Incorrect answer - Actual core flow is indeterminate, inserting Cram Rods IAW

FTI-B002, Control Rod is required when operating in the Controlled Entry/Immediate

Exit region.

b. Incorrect answer - Actual core flow is indeterminate, restarting Recirc Pump B IAW

SOI-B33, Reactor Recirculation may be a correct answer if core flow is known to not be

in the Backup Stability Protection Regions - Two Loop Power - Flow Map Manual Scram Required region.

c. Incorrect answer - Actual core flow is indeterminate, inserting a manual reactor scram

IAW ONI-C71-1, Reactor is a non-conservative action if core flow is >42 Mlbm/hr.

d. Incorrect answer - Actual core flow is indeterminate - shutting Recirc Pump B FCV IAW

ONI-SPI G-2, Single Pump Operation is not directed by ONI-C51 FLOWCHART or by

ONI-SPI G-2. ONI- SPI G-2 directs closure of the B Recirc Pump Suction valve.

Recommendations: Delete the question from the exam, there is no correct answer.

Station Proposed Resolution:

Delete question from exam, there is no correct answer since this was a question with an

unclear stem that confused the applicants or did not provide all the necessary information.

NRC Resolution:

The NRC disagrees with both 1) the candidates comment/justification, to delete the question

because an actual core flow value following the Reactor Recirculation Pump (RRP), which is not

provided, is required in order to determine and perform any actions in accordance with (IAW)

ONI-C51; and 2) the facilitys proposed resolution to delete the question because this was a

question with an unclear stem that confused the applicants or did not provide all the necessary

information.

The question asked which of the four options listed would be directed by the Unit Supervisor,

given the plant conditions stated in the stem and the direction provided by ONI-C51. Since no

additional failures beyond the trip of the B RRP were presented, and the plant is expected to

respond as anticipated for a loss of one RRP, entry into ONI-C51 is required due to the RRP

trip. ONI-C51 directs performance of the immediate and supplemental actions IAW ONI-C51

flowchart revision

J. Once immediate actions have been verified complete, steps C51-2, C51-3,

and C51-4 are completed in series. These actions may be performed without an actual core

flow value being known since core flow will be greater than 42 Mlbm/hr based upon the

conditions provided in the stem. The flowchart then directs the supplemental actions of steps

C51-4 and C51-12 be executed concurrently. Step C51-12 directs the operator to GO TO Step

C51-21 if either RRP has tripped and single loop operation is required, which will subsequently

direct the operator to verify loop parameters within limits for single RRP operation and, within

hour insert control rods to lower reactor power below 66.5% (2500 MWth). None of these

required supplemental actions necessitate knowing the actual core flow prior to performance.

As discussed above, the stated assumption made by the applicant that an actual core flow value

is required before any actions may be performed IAW ONI-C51 is incorrect. Therefore, the

NRC does not agree with deleting the question because no action IAW ONI-C51 is possible

without being given a value for actual core flow. Also, even though having the core plate P

value following the RRP trip, along with the curve, PDB-A0015, would allow an actual core flow

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

value to be determined, this would simply be additional information to confirm the expected

position on the Power-to-Flow map. Therefore, the NRC does not agree with the licensees

resolution to delete the question because the question did not provide all necessary information

in the stem and the stem was unclear and confused the applicants. The only related question

asked by any of the applicants during the examination dealt with a clarification on completion of

the required Technical Specification actions for the inoperable Oscillating Power Range

Monitors (OPRMs); no questions were raised concerning actual core flow values.

Although the NRC believes that adequate information to answer the question was provided in

the question stem, the NRC has now identified an issue stemming from the validation of the

question when the original examination was submitted and approved. Based upon the stations

training, the applicants were expected to recognize that the trip of the B RRP would lower core

flow to less than 50% rated core flow, based upon the initial condition given that core flow was

103 Mlbm/hr. The applicant would have to assess the situation, using the provided PDB-A06,

Power-to-Flow Map (modified), realize this would result in operation in the Controlled

Entry/Immediate Exit Region of the Backup Stability Protection (OPRM INOP) Power-to-Flow

map, and direct actions IAW the ONI-C51 Flow Chart - Insert cram rods IAW FTI-B002, Control

Rod - to lower power to exit this region. Per the NRCs request, the licensee provided

additional reference material that indicates the expected actual plant core flow value will be in

excess of 50%, and operation will be outside and to the right of the Controlled Entry/Immediate

Exit Region of the Backup Stability Protection (OPRM INOP) Power-to-Flow map. The correct

action to be directed by the operator IAW ONI-C51 is to verify loop parameters within limits for

single RRP operation and, within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> insert control rods as necessary to lower reactor power

below 66.5% (2500 MWth). However, this action was not listed as one of the distracters for this

question.

Based upon the newly discovered technical information, this question does not have a correct

answer, and the NRC has changed the answer key to delete this question.

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

SRO Question 14:

The plant was operating at rated power.

A manual Rx scram was inserted due to a loss of main condenser vacuum.

The transient resulted in the following conditions:

An ATWS is in progress.

MSIVs are shut.

RPV water level is 65 inches and stable.

RPV pressure is 960 psig and stable.

SRVs are open.

Suppression Pool Temperature is 116°F and rising slowly.

Suppression Pool Level 18.1 and lowering due to a leak.

The margin to exceeding HCL is 3°F.

What is the action that the Unit Supervisor would order first?

a. Open an additional SRV to lower RPV pressure

b. Open MSIVs IAW EOP-SPI 9.2, Opening MSIVs

c. Transition to EOP 4-2, Emergency Depressurization

d. Anticipate Emergency Depressurization IAW EOP-02, Containment Control

Answer: a.

Candidate Comments:

1. The answer key states answer (a.). Open additional SRV to lower RPV pressure. This

answer is correct in accordance with EOP-1A, Step LPC/P - Answer (c.) is also correct.

Though the EOP-SPI Supplement Figure 4 was not given to the students, if one

were to plot the given conditions on Figure 4, HCL would already be in the

UNSAFE region requiring immediate Emergency Depressurization (ED) per EOP

Bases, EOP-1A, EOP-2 and Hardcards (OAI-1703).

The stem of the question notes a rapidly deteriorating HCL challenge. HCL is

normally attempted to be maintained between 5-10°F if ordered. This information

was not in the stem. The EOP flowcharts were also not available to the students

which are not required to be known by memory. The stem states a 3°F margin to

HCL which is very narrow as seen in simulator scenarios. Because this band is

not being maintained, the deteriorating challenge can be immediately deduced.

The deteriorating challenge also includes a lowering Suppression Pool Level due

to a pipe break of unknown size or unknown level change rate. Figure 4, Heat

Capacity Limit, shows that as Suppression Pool Level lowers, HCL is further

challenged as there is less water to absorb heat causing heatup rate to raise

more.

Due to the lowering level in the suppression pool, another challenge is

immediately deduced that also leads to Emergency Depressurization per

EOP-02, Step SPL-5. OAI-1703, Hardcard states ED required at OR before

14.25 feet.

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

Transient Strategies and Mitigating Actions (PYBP-POS-0030) state that

suppression pool heatup rate is approximately 3F/minute/SRV. With 2 SRVs

open, this is a 6F/minute heatup rate, accelerated by 3, above, that would cause

HCL to be violated in less than 30 seconds (if not already violated per 1. above).

A decision that HCL cannot be maintained and that Emergency Depressurization

is required can be made at that point also and allow proceeding into Emergency

Depressurization from below the hold box of step STC-5 or within LPC/P-2

(EOP-1A Pressure Control).

Candidate Justification:

a. Correct answer - With SP temp rising and SP level lowering, the margin to HCL is

shrinking. IAW EOP-01A, the SRO would direct the RO to lower RPV pressure by

opening an additional SRV to maintain margin to HC

L.

b. Incorrect answer - With the main condenser not available, opening the MSIVs would not

be appropriate.

c. Correct answer - The deteriorating challenge can be immediately deduced. Due to the

lowering level in the suppression pool, another challenge is immediately deduced that

also leads to Emergency Depressurization per EOP-02.

d. Incorrect answer - Anticipating ED is no appropriate during an ATWS.

Recommendation: Modify the answer key to show two correct answers.

Station Proposed Resolution:

The station does not support the candidates basis and this question does, in fact, have only

one correct answer.

Step LPC/P-2 states that if HCL cannot be maintained below the limits of Figure 4, then the

operator is directed to maintain RPV pressure below the HCL limit. As stated in the candidates

response, the normal pressure band directed is 5 to 10°F below HCL. The information given in

the stem indicates that there is currently only 3°F margin to HCL; therefore, the first appropriate

action directed by the Unit Supervisor is to open additional SRVs to restore within the assigned

pressure band. It is true that lowering suppression pool level due to a leak adds another layer

of complexity however Emergency Depressurization due to lowering suppression pool level is

required before 14.25 feet and the stem provides information that this level is not currently

challenged.

In addition, EOP Step STC-5 requires Emergency Depressurization when HCL cannot be

restored and maintained below the limits of Figure 4. EOP Bases defines Restore and Maintain

as taking actions using available systems to restore a parameter to within a desired band or

condition and maintain it there which includes actions to bring on additional equipment.

Definition includes a note that states a parameter can be considered to be restored and

maintained even if the parameter exceeds the limit multiple times as long as the majority of the

time is spent within the limit.

With the conditions stated in the stem there are additional actions that can be taken to restore

and maintain RPV pressure within the limits of HCL, Figure 4 and should be directed first by the

Unit Supervisor which requires opening an additional SRV to lower RPV pressure.

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

NRC Resolution:

The NRC agrees with the licensee proposed resolution that there is only one correct answer to

this question. The candidate incorrectly states that plotting the given conditions would place

HCL in the UNSAFE region of the HCL curve. As stated by the station proposed resolution with

the conditions stated in the stem, there are additional actions that can be taken to restore and

maintain RPV pressure within the limits of HCL, Figure 4, and should be directed by the Unit

Supervisor. The first of these requires opening an additional SRV to lower RPV pressure to

restore RPV pressure within the pressure band and below the HCL limit. As stated by the

station, the question stem indicates that the lowering suppression pool level is well above the

required Emergency Depressurization level of 14.25 feet.

As stated by the station, Emergency Depressurization is required when HCL cannot be restored

and maintained below the limits of Figure 4. EOP Bases defines Restore and Maintain as

taking actions using available systems to restore a parameter to within a desired band or

condition and maintain it there which includes actions to bring on additional equipment.

Definition includes a note that states a parameter can be considered to be restored and

maintained even if the parameter exceeds the limit multiple times as long as the majority of the

time is spent within the limit.

Additionally, the NRC reviewed the questions asked by the applicants concerning this question

and found that none were asked. The answer key was not modified and choice a. is the only

correct answer to the question.

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

SRO Question 15:

The plant was operating at full power when the following occurred:

Both Feedwater Pump turbines tripped.

The Motor Feed Pump failed to start.

The reactor automatically scrammed.

One Control Rod is at position 48.

All other Control Rods are fully inserted.

HPCS initiation raised RPV Water Level from 110 inches.

HPCS was manually overridden OFF as RPV Water Level reached 210 inches.

Current Plant conditions are:

Reactor pressure 700 psig, rising at 10 psig per minute.

MSIVs are open.

The operating CRD Pump tripped.

Over the next ten minutes RPV Water Level will (1) .

The procedure used to control RPV Water Level is (2) .

(1) (2)

a. rise due to swell EOP-1, RPV Control

b. rise due to swell EOP-1A, Level Power Control

c. lower due to shrink EOP-1, RPV Control

d. lower due to shrink EOP-1A, Level Power Control

Answer: a.

Candidate Comments:

1. The question describes a situation in which most sources of injection to the RPV are

not operating. A significant volume of relatively cold water has been injected to the

RPV, and is heating up as indicated by the rising pressure. No information is

provided about the status of RCIC, but the stem indicates that RPV water level did

fall below the automatic initiation setpoint for RCIC. The stem of the question also

does not indicate that any operator action was taken with respect to the multiple

drain lines that would normally be open under the stated conditions. Therefore, there

are multiple competing effect on RPV water level.

2. Within the industry, the terms shrink and swell are commonly used to describe water

level effects associated with changes in steam flow. Since this is not occurring, the

terms as commonly used do not apply. Additionally, these terms are not specifically

defined in the BWR General Fundamentals reference material. Therefore, the terms

shrink and swell must be interpreted according to their generic definitions.

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

3. A rise in level can be anticipated based on the heating of the water injected by

HPCS. A drop in level can also be anticipated based on RPV inventory loss through

the open drain lines. A simulator scenario utilizing the same initial conditions

outlined in the stem of the question was run to validate the plant response. Over the

minute time frame specified in the question, RPV water level displayed both rising

and lowering trends.

Candidate Justification:

a. Correct - RPV water level does exhibit a rising trend within the 10 minute time

frame due (SIC) the heat-up of the colder water, as well as the continued

injection from RCI

C. Since the reactor is shutdown under all conditions, EOP-1

RPV control is the correct procedure.

b. Incorrect answer - The stem of the question states that only 1 control rod is not

fully inserted, which meets the criteria for the reactor being shutdown under all

conditions. Therefore, EOP-1A, Level Power Control, is not the correct

procedure.

c. Correct - RPV water level does exhibit a lowering trend within the 10 minute time

frame due to the rising pressure, as well as the inventory loss through the drain

lines. Since the reactor is shutdown under all conditions, EOP-1 RPV control is

the correct procedure.

d. Incorrect answer - The stem of the question states that only 1 control rod is not

fully inserted, which meets the criteria for the reactor being shutdown under all

conditions. Therefore, EOP-1A, Level Power Control, is not the correct

procedure.

Recommendation: Allow two correct answers, (a.) and (c.) correct.

Station Proposed Resolution:

The station staff does not support the candidates basis and this question does, in fact, have

only one correct answer.

While it is true over the next 10 minutes RPV Water level both rises and lowers, the causes

indicate there is only one correct answer. The injection of cold water from HPCS causes level

to rise due to swell as the cold water injected begins to heat up and expand making answer (a.)

the correct answer. RPV Water Level begins to lower later in the ten minute period however the

cause is a loss of inventory due to open main steam line drains which makes (c.) an incorrect

answer.

NRC Resolution:

The NRC agrees that choice a. is the only correct answer to this question. The question asks

for two distinct pieces of information, (1) what will be the effect on RPV level over the next

minutes due to the effects of shrink and swell; and (2) which is the correct procedure used to

control RPV level given the plant conditions stated in the stem. Distracters b. and d. are

incorrect because they specify an incorrect procedure (EOP-1A, Level Power Control) for

controlling RPV level. The RPV level will change due to two discrete effects. One is a change

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

in the inventory of fluid in the RPV, i.e., steam being removed by the MSL drains or water

injected by high pressure sources. The other is a change in RPV level due to a change in the

RPV waters density from changes in the waters temperature. As the colder water injected by

HPCS is heated, and RPV pressure and temperature rise, RPV level will continue to rise.

Since the question only asks for the change in RPV level due to the effects of shrink and swell,

any change in RPV level due to a change in inventory does not factor in to the answer.

Additionally, the NRC reviewed the questions asked by the applicants concerning this question

and found that one applicant asked if he was predicting the correct answer to the question

based on the terms shrink and swell. The other applicant asked if RCIC had initiated. The

proctor directed the applicant in each case to attempt to answer the question based on the

information provided in the question stem.

Based upon the above discussion, the NRC did not modify the answer key and retained choice

a. as the only correct answer to the question.

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

SRO Question 18:

The plant is in shutdown with the following conditions:

Average Reactor Coolant temperature is 190°F.

RHR A loop placed in Shutdown Cooling (SDC) Mode of operation IAW SOI-E12.

Based on this information, the LPCI mode of RHR A system is _______.

a. NOT affected, since it is NOT required to be OPERABLE with the current plant

conditions.

b. INOPERABLE, since the RHR Minimum Flow Valve is de-energized closed for SDC

Operations.

c. INOPERABLE, since the system must be manually realigned when required.

d. OPERABLE, provided the system can be manually realigned when required.

Answer: d.

Candidate Comments:

1. The question asks how the LPCI mode of operation is impacted when a train of the

Residual Heat Removal System is placed in the Shutdown Cooling Mode of operation.

2. In Mode 4, only 2 ECCS injection/spray subsystems shall be OPERABLE (TS 3.5.2).

3. Per TS 3.5.2 Bases, one LPCI subsystem may be considered operable during alignment

or operation for decay heat removal in Mode 4 or 5, if capable of being manually

realigned to the LPCI mode.

4. Candidates are instructed prior to the test (NUREG-1021, Appendix E) not to make

assumptions regarding conditions that were no specified in the question unless they

occurred as a consequence of other conditions that were stated in the question.

5. Stem of the question does not identify any other systems as being INOPERABLE, ALL

ECCS systems are OPERABLE; therefore, LPCI A is NOT required to be OPERABLE.

Candidate Justification:

a. Correct answer - LPCI A is NOT required to OPERABLE with the current plant

conditions. In Mode 4, only 2 ECCS injection/spray subsystems shall be OPERABLE

(TS 3.5.2). Stem does not identify any other systems as being INOPERABL

E.

b. Incorrect answer - INOPERABLE, the RHR Minimum Flow Valve de-energized closed

for SDC Operations does not make the system INOPERABL

E. TS 3.5.2 Bases, one

LPCI subsystem may be considered operable during alignment or operation for decay

heat removal in Mode 4 or 5, if capable of being manually realigned to the LPCI mode.

c. Incorrect answer - INOPERABLE, since the system must be manually realigned when

required. TS 3.5.2 Bases, one LPCI subsystem may be considered operable during

Enclosure 3

POST-EXAMINATION COMMENTS WITH NRC RESOLUTION

alignment or operation for decay heat removal in Mode 4 or 5, if capable of being

manually realigned to the LPCI mode.

d. Correct answer - OPERABLE, provided the system can be manually realigned when

required, TS 3.5.2 Bases, one LPCI subsystem may be considered operable during

alignment or operation for decay heat removal in Mode 4 or 5, if capable of being

manually realigned to the LPCI mode.

Recommendation: Amend the Answer Key to list Answer A as a correct answer, in addition

to Answer D

Station Proposed Resolution:

Station agrees with the above candidate Comments, Justification and Recommendation since

we have provided newly discovered technical information that supports a change in the answer

key.

NRC Resolution:

The NRC disagrees with both 1) the candidates comment/justification, that since only 2 ECCS

injection/spray subsystems are required to be OPERABLE given the conditions stated in the

stem, the LPCI mode of RHR A system is NOT affected; and 2) the stations proposed

resolution to accept two correct answers based upon newly discovered technical information

that supports a change in the answer key.

The question asks whether, based upon the conditions given in the stem, the LPCI mode of

RHR A system is considered OPERABLE per Technical Specifications. Just because a

subsystem is not required to be OPERABLE for a given plant condition does not mean the

operability of the subsystem is NOT affected by the given plant condition. Therefore, the

candidates comment/justification is incorrect. The licensee submitted the associated portions

of the facilitys Technical Specifications, including the bases, for ECCS systems - Shutdown,

which does not provide any additional nor newly discovered technical information to support a

change to the answer key. Additionally, the NRC reviewed the questions asked by the

applicants concerning this question and found that none were asked.

Based upon the above discussion, the NRC did not modify the answer key and retained choice

d. as the only correct answer to the question.

Enclosure 3

V. Kaminskas -2-

In accordance with Title 10, Code of Federal Regulations (CFR), Part 50, Section 2.390 of the

NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any), will be

available electronically for public inspection in the NRC Public Document Room or from the

Publicly Available Records System (PARS) component of NRC's Agencywide Documents

Access and Management System (ADAMS), accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/ By Bruce Palagi Acting For/

Hironori Peterson, Chief

Operations Branch

Division of Reactor Safety

Docket No. 50-440

License No. NPF-58

Enclosures:

1. Operator Licensing Examination Report 05000440/2013301

w/Attachment: Supplemental Information

2. Simulation Facility Report

3. Written Examination Post-Examination Comment Resolution

cc w/encl: Distribution via ListServ'

A. Mueller, Training Manager, Perry Nuclear Power Plant