IR 05000440/2013407

From kanterella
Jump to navigation Jump to search
IR 05000440-13-407; 09/30/2013 - 10/03/2013; Perry Nuclear Power Plant; Routine Security Baseline Inspection (Cover Letter Only)
ML13319A160
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 11/14/2013
From: Richard Skokowski
Plant Support Branch II
To: Harkness E
FirstEnergy Nuclear Operating Co
Nathan Egan
References
IR-13-407
Download: ML13319A160 (4)


Text

UNITED STATES mber 14, 2013

SUBJECT:

PERRY NUCLEAR POWER PLANT UNIT 1, NRC SECURITY BASELINE INSPECTION REPORT 05000440/2013407

Dear Mr. Harkness:

On October 3, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Perry Nuclear Power Plant, Unit 1. The inspection covered one or more of the key attributes of the security cornerstone of the NRCs Reactor Oversight Process. The enclosed inspection report documents the inspection results, which were discussed on October 3, 2013, with Mr. M. Fox and other members of your staff.

The inspection examined activities conducted under your license as they relate to security and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspector reviewed selected procedures and records, observed activities, and interviewed personnel.

No findings were identified during this inspection.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

However, the material enclosed herewith contains Security-Related Information in accordance with 10 CFR 2.390(d)(1) and its disclosure to unauthorized individuals could present a security vulnerability. Therefore, the material in the enclosure will not be made available electronically for public inspection in the NRC Public Document Room or from the PARS component of NRCs ADAMS. If you choose to provide a response and Security-Related Enclosure contains Sensitive Unclassified Non-Safeguards Information. When separated from enclosure, this transmittal document is decontrolled. Information is necessary to provide an acceptable response, please mark your entire response Security-Related Information Withhold from public disclosure under 10 CFR 2.390 in accordance with 10 CFR 2.390(d)(1) and follow the instructions for withholding in 10 CFR 2.390 (b)(1). In accordance with 10 CFR 2.390(b)(1)(ii), the NRC is waiving the affidavit requirements for your response.

Should you have any questions concerning this inspection, we will be pleased to discuss them with you.

Sincerely,

/RA By B. Dickson Acting For/

Richard A. Skokowski, Chief Plant Support Branch Division of Reactor Safety Docket No. 50-440 License No. NPF-58 Nonpublic Enclosure: Inspection Report 05000440/2013407 w/Attachment: Supplemental Information cc w/encl: S. Coker, NSIR/DSO/DDSO/ST R. Albert, NSIR T. Dimitriadis, RI B. Desai, RII M. Haire, RIV M. Bear, Radiological Branch Ohio Emergency Management Agency