ES-301 Control Room/In-Plant Systems Outline Form ES-301-2

Facility: Perry Nuclear Power Plant Date of Examination: 2/08/2021 Exam Level: RO S -I SRO-U Operating Test Number: 2021-301

Control Room Systems:

  • 8 for RO, 7 for SRO-I, and 2 or 3 for SRO-U

System/JPM Title Type Code* Safety Function

a. 202001 A2.03 / 3.6 JPM OT-3701-B33_504_RO Startup Idle RR N, A, L, S 1 Pump with High Vibes requiring Manual Pump Trip (Alternate Path)
b. 209001 A4.02 / 3.5 JPM OT-3701-E21_001_RO Quarterly LPCS N, S 2 Suction Valve Surveillance
c. 241000 A4.06 / 3.9 JPM OT-3701-C85_501_RO Perform Main N, A, S 3 Turbine Bypass Valve Cycle Test (Alternate Path)
d. 204000 A4.01 / 3.1 JPM OT-3701-G33_003_RO Restart of RWCU N, S 4 Pumps Following RWCU Pump trip.
e. 217000 2.1.23 / 4.3 JPM OT -3701-E12_507_RO Secure RHR N, A, EN, L, S 5 Cont Spray->SPC w/trip of ECCS pump->manual realign LPCI (Alternate Path)
f. 201005 A2.06 3.2 / JPM OT -3701-C11_010_RO Bypass a Control D, S 7 Rod in the Rod Control System Cabinets
g. 400000 A2.01 3.3 / JPM OT -3701-P43_502_RO Swap Running N, E, A, S 8 CCW Pumps with Other CCW Pump Trip (Alternate Path)
h. 288000 A4.01 2.9 / JPM OT -3701-M13_501_RO Swap Trains in N, A, S 9 Single Train Drywell Ventilation Mode (Alternate Path)

In-Plant Systems:* 3 for RO, 3 for SRO-I, and 3 or 2 for SRO-U

i. 295016 AA1.06 4.3* / JPM OT -3701-C61_110_RO Start RCIC and D, L, E 2 control RPV Water level from Division 1 Remote Shutdown Panel
j. 262002 A4.01 / 2.8 JPM OT-3701-R14_501_RO Startup Static D, A 6 Inverter and Transfer Loads to the Preferred Source (Alternate Path)
k. 286000 A1.05 / 3.2 JPM OT-3701-P54_004_RO Align Fire Water N, E, R, L 8 for injection via LPCS
  • All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions, all five SRO-U systems must serve different safety functions, and in-plant systems and functions may overlap those tested in the control room.

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2

  • Type Codes Criteria for R /SRO-I/SRO -U

(A)lternate path 4-6/4-6 /2-3 (C)ontrol room (D)irect from bank 9/ 8/ 4 (E)mergency or abnormal in-plant 1/ 1/ 1 (EN)gineered safety feature 1/ 1/ 1 (control room system)

(L)ow-Power/Shutdown 1/ 1/ 1 (N)ew or (M)odified from bank including 1(A) 2/ 2/ 1 (P)revious 2 exams 3/ 3/ 2 (randomly selected)

(R)CA 1/ 1/ 1 (S)imulator

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2

Facility: Perry Nuclear Power Station Date of Examination: 2/08/2021 Exam Level: RO SRO-I O - Operating Test Number: 2021-301

Control Room Systems:* 8 for RO, 7 for SRO-I, and 2 or 3 for SRO-U

System/JPM Title Type Code* Safety Function

a. 202001 A2.03 / 3.6 JPM OT-3701-B33_504_RO Startup Idle RR N, A, L, S 1 Pump with High Vibes requiring Manual Pump Trip (Alternate Path)
b. N/A N/A -
c. 241000 A4.06 / 3.9 JPM OT-3701-C85_501_RO Perform Main N, A, S 3 Turbine Bypass Valve Cycle Test (Alternate Path)
d. 204000 A4.01 / 3.1 JPM OT-3701-G33_003_RO Restart of RWCU N, S 4 Pumps Following RWCU Pump trip.
e. 217000 2.1.23 / 4.3 JPM OT-3701-E12_507_RO Secure RHR N, A, EN, L, S 5 Cont Spray->SPC w/trip of ECCS pump->manual realign LPCI (Alternate Path)
f. 201005 A2.06 3.2 / JPM OT-3701-C11_010_RO Bypass a Control D, S 7 Rod in the Rod Control System Cabinets
g. 400000 A2.01 3.3 / JPM OT-3701-P43_502_RO Swap Running N, E, A, S 8 CCW Pumps with Other CCW Pump Trip (Alternate Path)
h. 288000 A4.01 2.9 / JPM OT-3701-M13_501_RO Swap Trains in N, A, S 9 Single Train Drywell Ventilation Mode (Alternate Path)

In-Plant Systems:* 3 for RO, 3 for SRO-I, and 3 or 2 for SRO-U

i. 295016 AA1.06 4.3* / JPM OT-3701-C61_110_RO Start RCIC and D, L, E 2 control RPV Water level from Division 1 Remote Shutdown Panel
j. 262002 A4.01 / 2.8 JPM OT-3701-R14_501_RO Startup Static D, A 6 Inverter and Transfer Loads to the Preferred Source (Alternate Path)
k. 286000 A1.05 / 3.2 JPM OT-3701-P54_004_RO Align Fire Water N, E, R, L 8 for injection via LPCS
  • All RO and SRO-I control room (and in-plant) systems must be different and serve different safety functions, all five SRO-U systems must serve different safety functions, and in-plant systems and functions may overlap those tested in the control room.
  • Type Codes Criteria for R /SRO-I/SRO -U ES-301 Control Room/In-Plant Systems Outline Form ES-301-2

(A)lternate path 4-6/4-6 /2-3 (C)ontrol room (D)irect from bank 9/ 8/ 4 (E)mergency or abnormal in-plant 1/ 1/ 1 (EN)gineered safety feature 1/ 1/ 1 (control room system)

(L)ow-Power/Shutdown 1/ 1/ 1 (N)ew or (M)odified from bank including 1(A) 2/ 2/ 1 (P)revious 2 exams 3/ 3/ 2 (randomly selected)

(R)CA 1/ 1/ 1 (S)imulator

ES-301 Control Room/In-Plant Systems Outline Form ES-301-2

Facility: Perry Nuclear Power Station Date of Examination: 2/08/2021 Exam Level: RO SRO-I SRO-U Operit Nber: 21-301

Controloom Systems:

System/JPM Title Ty Sa Function A N -

A N -

c N N -

A N -

70023 /.M -- E12_507O Secure RHR N, AEN 5 Cont ->C/tripf CS pum p ->nualeiPCI (Altne Pat

f. 201005 A02 / JP -- C11_0O Bypassor D S 7 Rod in tontrol Systabinets

A N -

A N -

-Plantystems:

2950 AA 4. 3 * / JP -- C61_110O SttCICnd D, LE 2 contrPV lelrom DivisiShutdP

262002 A01 /.JP -- R14_5O Starttic D, A 6 It and Transf Loadso the Prred Source (Altnate P

k 05 / 3. J -- P54_004O Aliire N ER, L 8 ftiia LPCS

  • AllORO -I ctrmd in-a)ysts mt be diffend svffenty functis,llive SRO-U syems ster fftafy functis,n-antystems functis erlse tested in the contro.
  • yodes Ctea for RO -I/SRO -U ES-301 Control Room/In-Plant Systems Outline Form ES-301-2

(A)lternate path 4-6/4-6 /2-3 (C)ontrol room (D)irect from bank 9/ 8/ 4 (E)mergency or abnormal in-plant 1/ 1/ 1 (EN)gineered safety feature 1/ 1/ 1 (control room system)

(L)ow-Power/Shutdown 1/ 1/ 1 (N)ew or (M)odified from bank including 1(A) 2/ 2/ 1 (P)revious 2 exams 3/ 3/ 2 (randomly selected)

(R)CA 1/ 1/ 1 (S)imulator