MONTHYEARL-23-146, License Renewal Application for the Perry Nuclear Power Plant2023-07-0303 July 2023 License Renewal Application for the Perry Nuclear Power Plant Project stage: Request ML23249A1032023-10-0303 October 2023 Letter to Rod L. Penfield, Site Vice President-Perry Nuclear Power Plant, Unit 1-Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement Project stage: Other ML23249A0962023-10-0303 October 2023, 4 October 2023 Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement Project stage: Request ML23249A1042023-10-0404 October 2023 Federal Register Notice: Notice of Intent to Conduct Scoping Process and Prepare an Environmental Impact Statement-Perry Nuclear Power Plant, Unit 1 Project stage: Request ML23291A0702023-10-18018 October 2023 Environmental Scoping Meeting Related to the Perry Nuclear Power Plant, Unit 1 License Renewal Application - In-person Meeting Slides Project stage: Meeting ML23303A0682023-10-19019 October 2023 October 2023 Enviro Scoping Meetings Re Perry Nuclear Power Plant License Renewal Application 10/19/2023 Transcript Project stage: Meeting PMNS20230994, Environmental Scoping Meeting Related to the Perry Nuclear Power Plant License Renewal Application2023-10-24024 October 2023 Environmental Scoping Meeting Related to the Perry Nuclear Power Plant License Renewal Application Project stage: Meeting ML23303A0672023-10-25025 October 2023 October 2023 Environmental Scoping Meetings Re Perry Nuclear Power Plant License Renewal Application Summary Project stage: Meeting ML23291A0572023-10-25025 October 2023 Environmental Scoping Meeting Related to the Perry Nuclear Power Plant, Unit 1 License Renewal Application - Virtual Meeting Slides Project stage: Meeting ML23303A0662023-11-0606 November 2023 October 2023 Environmental Scoping Meetings Re Perry Nuclear Power Plant License Renewal Application Meeting Summary Memo Project stage: Meeting ML23303A0692023-11-0909 November 2023 October 2023 Enviro Scoping Meetings Re Perry Nuclear Power Plant License Renewal Application 10-25-23 Transcript Project stage: Meeting ML24064A2212024-03-14014 March 2024 Letter to Rod L. Penfield-Perry Nuclear Power Plant Unit 1 - Summary of the Jan-Feb 2024 Environmental Audit Related to the Review of the License Renewal Application Environmental Report Project stage: Approval ML24064A2202024-03-14014 March 2024 PNPP Unit 1 LRA Environmental Review RCI and RAI-Enclosure 2 Project stage: Other L-24-083, Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification2024-04-15015 April 2024 Response to License Renewal Environmental Report Requests for Additional Information and Request for Clarification Project stage: Request L-24-116, Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification2024-05-16016 May 2024 Response to License Renewal Environmental Report Severe Accident Mitigation Alternatives Requests for Additional Information and Request for Clarification Project stage: Request ML24150A2022024-07-25025 July 2024 Letter to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-License Renewal Scoping Summary Rpt Project stage: Other ML24228A1702024-09-0303 September 2024 Ltr to Rod L. Penfield-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants Project stage: Draft Other ML24228A1712024-09-0303 September 2024 Ltr to Brian Dickens, EPA-Perry Nuclear Power Plant Unit 1-Notice of Avail of the Draft Supp 61 to the GEIS for License Renew of Nuclear Plants Project stage: Draft Other ML24284A0382024-10-22022 October 2024 Public Meetings to Receive Comments on the Draft Perry Plant EIS Meetings Summary Memo ML25098A0932025-05-0808 May 2025 Letter to Rod L. Penfield Notice of Availability of the Final Supplement 61 to the Generic Environmental Impact Statement for License Renewal Project stage: Other 2023-11-09
[Table View] |
Similar Documents at Perry |
|---|
|
Text
Rod L. Penfield Site Vice President Vistra Operations Company, LLC Perry Nuclear Power Plant P.O. Box 97, Mail Stop A-PY-A290 Perry, Ohio 44081-0097
SUBJECT:
ISSUANCE OF ENVIRONMENTAL SCOPING
SUMMARY
REPORT ASSOCIATED WITH THE U.S. NUCLEAR REGULATORY COMMISSION STAFFS REVIEW OF THE PERRY NUCLEAR POWER PLANT UNIT 1, SUBSEQUENT LICENSE RENEWAL APPLICATION (EPID NO. L-2023-LNE-0002) (DOCKET NO. 50-440)
Dear Rod L. Penfield:
Pursuant to Section 51.29 of Title 10 of the Code of Federal Regulations (10 CFR), the U.S. Nuclear Regulatory Commission (NRC) staff conducted the environmental scoping process and solicited public comments from October 10, 2023, to November 9, 2023. This process determined the scope of the staffs environmental review of the application for renewal of the renewed facility operating licenses for Perry Nuclear Power Plant, Unit No. 1 (Perry Plant). The scoping process is the first step in the development of a Perry Plant-specific supplement to NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants (Agencywide Documents Access and Management System (ADAMS) Accession Nos.
ML13106A241, ML13106A242, and ML13106A244).
At the conclusion of the scoping process, the staff prepared the enclosed environmental scoping summary report identifying comments received during the scoping period. In accordance with 10 CFR 51.29(b), the staff will send a copy of the scoping summary report to each participant in the scoping process.
July 25, 2024
R. Penfield 2
If you have any questions concerning the staffs environmental review of this license renewal application, please contact Lance Rakovan by telephone at 301-415-2589 or via e-mail at Lance.Rakovan@nrc.gov.
Sincerely, Stephen S. Koenick, Chief Environmental Project Management Branch 1 Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards Docket No. 50-440
Enclosure:
As stated cc: Listserv Signed by Koenick, Stephen on 07/25/24