ES-301 Administrative Topics Outline Form ES-301-1 Facility:
Perry Nuclear Power Plant Date of Examination:
2/08/2021 Examination Level: RO SRO Operating Test Number:
2021-301 Administrative Topic (see Note)
Type Code*
Describe activity to be performed Conduct of Operations N, R Calculate DW Average Temperature IAW TS Rounds.
JPM OT3701ADM_034_RO 2.1.18 / 3.6 Ability to make accurate, clear, and concise logs, records, status boards, and reports.
Conduct of Operations N, R Determine the amount of Decay Heat in the Core and if ADHR is Adequate JPM OT3701ADM_035_RO 2.1.20 / 4.6 Ability to interpret and execute procedure steps.
Equipment Control D, R Identify boundary for leaking fire protection system component JPM OT3701ADM_026_RO 2.2.15 / 3.9 Ability to determine the expected plant configuration using design and configuration control documentation, such as drawings, line-ups, tag-outs, etc.
Radiation Control D, R Determine Stay Time to Complete Tagout JPM OT-3701ADM_004_RO 2.3.12 / 3.2 Knowledge of radiological safety principles pertaining to licensed operator duties, such as containment entry requirements, fuel handling responsibilities, access to locked high-radiation areas, aligning filters, etc.
Emergency Plan NOTE: All items (five total) are required for SROs. RO applicants require only four items unless they are retaking only the administrative topics (which would require all five items).
- Type Codes and Criteria:
(C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs; 4 for SROs and RO retakes)
(N)ew or (M)odified from bank ( 1)
(P)revious 2 exams ( 1, randomly selected)
ES-301 Administrative Topics Outline Form ES-301-1 Facility:
Perry Nuclear Power Plant Date of Examination:
2/08/2021 Examination Level: RO SRO Operating Test Number:
2021-301 Administrative Topic (see Note)
Type Code*
Describe activity to be performed Conduct of Operations D, R Evaluation of Work Hours IAW 10CFR26 JPM OT-3701-ADM-028SRO 2.1.5 / 3.9 Ability to use procedures related to shift staffing, such as minimum crew complement, overtime limitations, etc.
Conduct of Operations D, R Determine actions required for Refuel Bridge PLC failure JPM OT-3701-ADM_017SRO 2.1.36 / 4.1 Knowledge of procedures and limitations involved in core alterations.
Equipment Control D, R Identify boundary for leaking fire protection system component and determine Required Actions for an Unplanned Fire Impairment.
JPM OT-3701-ADM_026SRO 2.2.41 / 3.9 Ability to obtain and interpret station electrical and mechanical drawings.
Radiation Control N, R Determine Required Actions per ODCM for non-functional Rad Monitor.
JPM OT-3701-ADM_034SRO 2.3.15 / 3.1 Knowledge of radiation monitoring systems, such as fixed radiation monitors and alarms, portable survey instruments, personnel monitoring equipment, etc.
Emergency Plan N, S Validate Notification form and Make Initial Notification to Off-site Facilities with All-Call Phone JPM OT-3701-ADM_323SRO 2.4.43 / 3.8 Knowledge of emergency communications systems and techniques.
NOTE: All items (five total) are required for SROs. RO applicants require only four items unless they are retaking only the administrative topics (which would require all five items).
- Type Codes and Criteria:
(C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs; 4 for SROs and RO retakes)
(N)ew or (M)odified from bank ( 1)