|
|
Line 18: |
Line 18: |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 September 1, 2015 Mr. Eric Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station P.O. Box 4 Shippingport, PA 15077-0004 SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 (REPORT 05000334/2015005 AND 05000412/2015005) | | {{#Wiki_filter:UNITED STATES ber 1, 2015 |
| | |
| | ==SUBJECT:== |
| | MID-CYCLE ASSESSMENT LETTER FOR BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 (REPORT 05000334/2015005 AND 05000412/2015005) |
|
| |
|
| ==Dear Mr. Larson:== | | ==Dear Mr. Larson:== |
| On August 13, 2015, the U. S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Beaver Valley Power Station, Unit Nos. 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2014 through June 30, 2015. This letter informs you of re inspections at your facility. The NRC determined that overall, Beaver Valley Power Station, Unit Nos. 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Beaver Valley Power Station Unit Nos. 1 and 2 during the most Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. The enclosed inspection plan lists the inspections scheduled through June 30, 2017. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. In addition to baseline inspections, the NRC ,and Temporary Instruction (TI) 2515-191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communications/ Staffing/Multi-Unit Dose Assessment Plans. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. In response to the accident at Fukushima, the Commission issued Order EA-12-Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-nce and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-iable Spent Fuel Pool wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. The on-site portion of the audit was completed at Beaver Valley Power Station, Unit Nos. 1 and 2, and the information gathered will aid staff in development of the Final Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing TI 191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communications/Staffing/Multi-Unit Dose Assessment Plans. In accordance with Title 10 of the Code of Federal RegulationsPublic Document Room or from the Publicly Available Records component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact me at (610) 337-5046 with any questions you have regarding this letter. | | On August 13, 2015, the U. S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Beaver Valley Power Station, Unit Nos. 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2014 through June 30, 2015. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. |
| | |
| | The NRC determined that overall, Beaver Valley Power Station, Unit Nos. 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Beaver Valley Power Station Unit Nos. 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility. |
| | |
| | The enclosed inspection plan lists the inspections scheduled through June 30, 2017. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. In addition to baseline inspections, the NRC will perform IP 71003, Post Approval Site Inspection for License Renewal, and Temporary Instruction (TI) 2515-191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communications/ |
| | Staffing/Multi-Unit Dose Assessment Plans. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. The on-site portion of the audit was completed at Beaver Valley Power Station, Unit Nos. 1 and 2, and the information gathered will aid staff in development of the Final Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing TI 191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communications/Staffing/Multi-Unit Dose Assessment Plans. |
| | |
| | In accordance with Title 10 of the Code of Federal Regulations, Part 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). |
| | |
| | Please contact me at (610) 337-5046 with any questions you have regarding this letter. |
|
| |
|
| Sincerely, | | Sincerely, |
| /RA/ Silas R. Kennedy, Chief Projects Branch 6 Division of Reactor Projects Docket Nos. 50-334, 50-412 License Nos. DPR-66, NPF-73 Enclosure: Beaver Valley Power Station Inspection/Activity Plan cc w/encl: Distribution via ListServ | | /RA/ |
| | Silas R. Kennedy, Chief Projects Branch 6 Division of Reactor Projects Docket Nos. 50-334, 50-412 License Nos. DPR-66, NPF-73 Enclosure: Beaver Valley Power Station Inspection/Activity Plan cc w/encl: Distribution via ListServ |
| | |
| | ML15229A116 SUNSI Review Non-Sensitive Publicly Available Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME JKrafty/ AVZ for via email AZiedonis/ AVZ SKennedy/ SRK DATE 08/ 25 /15 08/ 25 /15 08/ 25 /15 |
| | |
| | Page 1 of 3 Beaver Valley 08/25/2015 14:18:22 Inspection / Activity Plan Report 22 07/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EP - EP PROGRAM INSPECTION 1 1, 2 06/29/2015 07/02/2015 IP 7111402 Alert and Notification System Testing 1, 2 06/29/2015 07/02/2015 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 06/29/2015 07/02/2015 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies TRI FI - TRIENNIAL FIRE PROTECTION INSPECTION 5 1, 2 08/03/2015 08/07/2015 IP 7111105T Fire Protection [Triennial] |
| | 1, 2 08/17/2015 08/21/2015 IP 7111105T Fire Protection [Triennial] |
| | 12/7EXAM - U2 INITIAL OL EXAM 3 2 11/09/2015 11/13/2015 U01906 FY16-BV2 INITIAL OPERATOR LICENSING EXAM 2 12/07/2015 12/18/2015 U01906 FY16-BV2 INITIAL OPERATOR LICENSING EXAM 71003 - LR COMMITMENTS PHASE II TEAM INSP 5 1 08/31/2015 09/04/2015 IP 71003 Post-Approval Site Inspection for License Renewal 1 09/14/2015 09/18/2015 IP 71003 Post-Approval Site Inspection for License Renewal 7111108P - U2 INSERVICE INSPECTION 1 2 10/05/2015 10/16/2015 IP 7111108P Inservice Inspection Activities - PWR 71124 - RAD SAFETY INSP 1 1, 2 10/19/2015 10/23/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 10/19/2015 10/23/2015 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 10/19/2015 10/23/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/19/2015 10/23/2015 IP 71124.04 Occupational Dose Assessment 1, 2 10/19/2015 10/23/2015 IP 71124.05 Radiation Monitoring Instrumentation 71124.07 - RAD SAFETY INSPECTION 1 1, 2 11/30/2015 12/04/2015 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 11/30/2015 12/04/2015 IP 71151-OR01 Occupational Exposure Control Effectiveness 1, 2 11/30/2015 12/04/2015 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71124 - RAD SAFETY INSP 1 1, 2 12/14/2015 12/18/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 12/14/2015 12/18/2015 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 12/14/2015 12/18/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 12/14/2015 12/18/2015 IP 71124.04 Occupational Dose Assessment 1, 2 12/14/2015 12/18/2015 IP 71151 Performance Indicator Verification 71124 - RAD SAFETY INSPECTION 1 1, 2 03/07/2016 03/11/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 03/07/2016 03/11/2016 IP 71124.02 Occupational ALARA Planning and Controls This report does not include INPO and OUTAGE activities. |
| | |
| | This report shows only on-site and announced inspection procedures. |
| | |
| | Page 2 of 3 Beaver Valley 08/25/2015 14:18:22 Inspection / Activity Plan Report 22 07/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 71124 - RAD SAFETY INSPECTION 1 1, 2 03/07/2016 03/11/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 03/07/2016 03/11/2016 IP 71124.04 Occupational Dose Assessment EP - EP EXERCISE EVALUATION 4 1, 2 06/13/2016 06/17/2016 IP 7111401 Exercise Evaluation 7111107T - TRIENNIAL HEAT SINK 1 1, 2 05/16/2016 05/20/2016 IP 7111107T Heat Sink Performance EXM10/3 - BEAVER VALLEY 1 INITIAL EXAM 6 1 10/03/2016 10/07/2016 U01922 FY17-BV1 INITIAL OPERATOR LICENSING EXAM 1 10/31/2016 11/11/2016 U01922 FY17-BV1 INITIAL OPERATOR LICENSING EXAM 7111117T - PERMANENT PLANT MODIFICATIONS 3 1, 2 06/06/2016 06/10/2016 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 1, 2 06/20/2016 06/24/2016 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 7111111B - BV1 REQUAL INSP W/ P/F RESULTS 2 1 08/15/2016 08/19/2016 IP 7111111B Licensed Operator Requalification Program 71124 - RAD SAFETY INSPECTION 3 1, 2 07/11/2016 07/15/2016 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 07/11/2016 07/15/2016 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 07/11/2016 07/15/2016 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 07/11/2016 07/15/2016 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71124 - RAD SAFETY INSPECTION 1 1, 2 10/03/2016 10/07/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 10/03/2016 10/07/2016 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 10/03/2016 10/07/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/03/2016 10/07/2016 IP 71124.04 Occupational Dose Assessment 7111108P - BV U1 INSERVICE INSPECTION 1 1 10/03/2016 10/14/2016 IP 7111108P Inservice Inspection Activities - PWR 71124 - RAD SAFETY INSPECTION 1 1, 2 12/12/2016 12/16/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 12/12/2016 12/16/2016 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 12/12/2016 12/16/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 12/12/2016 12/16/2016 IP 71124.04 Occupational Dose Assessment 1, 2 12/12/2016 12/16/2016 IP 71151-OR01 Occupational Exposure Control Effectiveness This report does not include INPO and OUTAGE activities. |
|
| |
|
| ML15229A116 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP NAME JKrafty/ AVZ for via email AZiedonis/ AVZ SKennedy/ SRK DATE 08/ 25 /15 08/ 25 /15 08/ 25 /15 Page 1 of 3 08/25/2015 14:18:22 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteBeaver ValleyInspection / Activity Plan 07/01/2015-06/30/2017 EP-EP PROGRAM INSPECTION 1 1, 2 IP A lert and Notification System Testing7111402 06/29/2015 07/02/2015 1, 2 IP Emergency Preparedness Organization Staffing and Augmentation System7111403 06/29/2015 07/02/2015 1, 2 IP Correction of Emergency Preparedness Weaknesses and Deficiencies7111405 06/29/2015 07/02/2015 TRI FI-TRIENNIAL FIRE PROTECTION INSPECTION 5 1, 2 IP Fire Protection [Triennial]7111105T 08/03/2015 08/07/2015 1, 2 IP Fire Protection [Triennial]7111105T 08/17/2015 08/21/201512/7EXAM-U2 INITIAL OL EXAM 3 2 FY16-BV2 INITIAL OPERATOR LICENSING EXAM U0190611/09/201511/13/2015 2 FY16-BV2 INITIAL OPERATOR LICENSING EXAM U01906 12/07/2015 12/18/2015 71003-LR COMMITMENTS PHASE II TEAM INSP 5 1 IP Post-Approval Site Inspection for License Renewal 71003 08/31/2015 09/04/2015 1 IP Post-Approval Site Inspection for License Renewal 71003 09/14/2015 09/18/20157111108P-U2 INSERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR7111108P 10/05/2015 10/16/201571124-RAD SAFETY INSP 1 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 10/19/2015 10/23/2015 1, 2 IP Occupational ALARA Planning and Controls71124.02 10/19/2015 10/23/2015 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 10/19/2015 10/23/2015 1, 2 IP Occupational Dose Assessment71124.04 10/19/2015 10/23/2015 1, 2 IP Radiation Monitoring Instrumentation71124.05 10/19/2015 10/23/201571124.07-RAD SAFETY INSPECTION 1 1, 2 IP Radiological Environmental Monitoring Program71124.0711/30/2015 12/04/2015 1, 2 IP Occupational Exposure Control Effectiveness71151-OR0111/30/2015 12/04/2015 1, 2 IP RETS/ODCM Radiological Effluent Occurrences71151-PR0111/30/2015 12/04/201571124-RAD SAFETY INSP 1 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 12/14/2015 12/18/2015 1, 2 IP Occupational ALARA Planning and Controls71124.02 12/14/2015 12/18/2015 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 12/14/2015 12/18/2015 1, 2 IP Occupational Dose Assessment71124.04 12/14/2015 12/18/2015 1, 2 IP Performance Indicator Verification71151 12/14/2015 12/18/201571124-RAD SAFETY INSPECTION 1 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 03/07/201603/11/2016 1, 2 IP Occupational ALARA Planning and Controls71124.02 03/07/201603/11/2016 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
| | This report shows only on-site and announced inspection procedures. |
|
| |
|
| Page 2 of 3 08/25/2015 14:18:22 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteBeaver ValleyInspection / Activity Plan 07/01/2015-06/30/201771124-RAD SAFETY INSPECTION 1 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 03/07/201603/11/2016 1, 2 IP Occupational Dose Assessment71124.04 03/07/201603/11/2016 EP-EP EXERCISE EVALUATION 4 1, 2 IP Exercise Evaluation7111401 06/13/2016 06/17/20167111107T-TRIENNIAL HEAT SINK 1 1, 2 IP Heat Sink Performance7111107T 05/16/2016 05/20/2016 EXM10/3-BEAVER VALLEY 1 INITIAL EXAM 6 1 FY17-BV1 INITIAL OPERATOR LICENSING EXAM U01922 10/03/2016 10/07/2016 1 FY17-BV1 INITIAL OPERATOR LICENSING EXAM U01922 10/31/201611/11/20167111117T-PERMANENT PLANT MODIFICATIONS 3 1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 06/06/2016 06/10/2016 1, 2 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 06/20/2016 06/24/20167111111B-BV1 REQUAL INSP W/ P/F RESULTS 2 1 IP Licensed Operator Requalification Program7111111B 08/15/2016 08/19/201671124-RAD SAFETY INSPECTION 3 1, 2 IP Radiation Monitoring Instrumentation71124.0507/11/2016 07/15/2016 1, 2 IP Radioactive Gaseous and Liquid Effluent Treatment71124.0607/11/2016 07/15/2016 1, 2 IP Radiological Environmental Monitoring Program71124.0707/11/2016 07/15/2016 1, 2 IP RETS/ODCM Radiological Effluent Occurrences71151-PR0107/11/2016 07/15/201671124-RAD SAFETY INSPECTION 1 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 10/03/2016 10/07/2016 1, 2 IP Occupational ALARA Planning and Controls71124.02 10/03/2016 10/07/2016 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 10/03/2016 10/07/2016 1, 2 IP Occupational Dose Assessment71124.04 10/03/2016 10/07/20167111108P-BV U1 INSERVICE INSPECTION 1 1 IP Inservice Inspection Activities - PWR7111108P 10/03/2016 10/14/201671124-RAD SAFETY INSPECTION 1 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 12/12/2016 12/16/2016 1, 2 IP Occupational ALARA Planning and Controls71124.02 12/12/2016 12/16/2016 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 12/12/2016 12/16/2016 1, 2 IP Occupational Dose Assessment71124.04 12/12/2016 12/16/2016 1, 2 IP Occupational Exposure Control Effectiveness71151-OR01 12/12/2016 12/16/2016 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures. | | Page 3 of 3 Beaver Valley 08/25/2015 14:18:22 Inspection / Activity Plan Report 22 07/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 71124.08 - RADWASTE 1 1, 2 12/05/2016 12/09/2016 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124 - HP INSPECTION 1 1, 2 04/10/2017 04/14/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 04/10/2017 04/14/2017 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 04/10/2017 04/14/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 7111108P - U2 INSERVICE INSPECTION 1 2 04/10/2017 04/21/2017 IP 7111108P Inservice Inspection Activities - PWR 7111111B - BV2 REQUAL INSP WITH P/F RESULTS 2 2 06/19/2017 06/23/2017 IP 7111111B Licensed Operator Requalification Program TI-191 - FUKUSHIMA LESSONS-LEARNED 1 1, 2 05/15/2017 05/19/2017 IP 2515/191 Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 71124 - HP INSPECTION 1 1, 2 06/05/2017 06/09/2017 IP 71124.04 Occupational Dose Assessment 1, 2 06/05/2017 06/09/2017 IP 71124.05 Radiation Monitoring Instrumentation 71152B - PI&R BIENNIAL 2 1, 2 06/01/2017 06/05/2017 IP 71152B Problem Identification and Resolution 1, 2 06/15/2017 06/19/2017 IP 71152B Problem Identification and Resolution This report does not include INPO and OUTAGE activities. |
|
| |
|
| Page 3 of 3 08/25/2015 14:18:22 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteBeaver ValleyInspection / Activity Plan 07/01/2015-06/30/201771124.08-RADWASTE 1 1, 2 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.08 12/05/2016 12/09/201671124-HP INSPECTION 1 1, 2 IP Radiological Hazard Assessment and Exposure Controls71124.01 04/10/2017 04/14/2017 1, 2 IP Occupational ALARA Planning and Controls71124.02 04/10/2017 04/14/2017 1, 2 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 04/10/2017 04/14/20177111108P-U2 INSERVICE INSPECTION 1 2 IP Inservice Inspection Activities - PWR7111108P 04/10/2017 04/21/20177111111B-BV2 REQUAL INSP WITH P/F RESULTS 2 2 IP Licensed Operator Requalification Program7111111B 06/19/2017 06/23/2017TI-191-FUKUSHIMA LESSONS-LEARNED 1 1, 2 IP Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 2515/191 05/15/2017 05/19/201771124-HP INSPECTION 1 1, 2 IP Occupational Dose Assessment71124.04 06/05/2017 06/09/2017 1, 2 IP Radiation Monitoring Instrumentation71124.05 06/05/2017 06/09/201771152B-PI&R BIENNIAL 2 1, 2 IP Problem Identification and Resolution71152B 06/01/2017 06/05/2017 1, 2 IP Problem Identification and Resolution71152B 06/15/2017 06/19/2017 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
| | This report shows only on-site and announced inspection procedures. |
| }} | | }} |
|
---|
Category:Inspection Plan
MONTHYEARIR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) IR 05000334/20240102024-05-15015 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000334/2024010 and 05000412/2024010 IR 05000334/20230062024-02-28028 February 2024 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2023006 and 05000412/2023006) IR 05000334/20230052023-08-31031 August 2023 Updated Inspection Plan for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2023005 and 05000412/2023005) ML23090A0192023-03-31031 March 2023 Information Request for the Cyber Security Baseline Inspection; Notification to Perform Inspection 05000334/2023401 and 05000412/2023401 IR 05000334/20220062023-03-0101 March 2023 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2022006 and 05000412/2022006) IR 05000334/20220052022-08-31031 August 2022 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2022005 and 05000412/2022005) IR 05000334/20210062022-03-0202 March 2022 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2021006 and 05000412/2021006) IR 05000334/20210052021-09-0101 September 2021 Updated Inspection Plan for the Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2021005 and 05000412/2021005) ML21124A1322021-05-0404 May 2021 Notification of Conduct of a Fire Protection Team Inspection IR 05000334/20200062021-03-0303 March 2021 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2020006 and 05000412/2020006) IR 05000334/20200052020-08-31031 August 2020 Updated Inspection Plan (Inspection Report 05000334/2020005 and 05000412/2020005) IR 05000334/20190062020-03-0303 March 2020 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Report 05000334/2019006 and 05000412/2019006) IR 05000334/20190052019-08-28028 August 2019 Updated Inspection Plan Inspection Report 05000334/2019005 and 05000412/2019005 IR 05000334/20180062019-03-0404 March 2019 Annual Assessment Letter for Beaver Valley Power Station, Unit Nos. 1 and 2 (Reports 05000334/2018006 and 05000412/2018006) IR 05000334/20180052018-08-28028 August 2018 Updated Inspection Plan Inspection Report 05000334/2018005 and 05000412/2018005 IR 05000334/20170062018-02-28028 February 2018 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2(Reports 05000334/2017006 and 0500412/2017006; 05000334/2017402 and 05000412/2017402 and 05000334-2017501 and 05000412/2017501) ML17271A0662017-09-28028 September 2017 Information Request for the Cyber Security Baseline Inspection Notification to Perform Inspection 05000334/2018403 and 05000412/2018403 IR 05000334/20160062017-03-0101 March 2017 Annual Assessment Letter for Beaver Valley Power Station, Unit Nos. 1 and 2 (Report 05000334/2016006 and 05000412/2016006) with Report 22 IR 05000334/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Beaver Valley Power Station Units 1 and 2 (Report 05000334/2016005 and 05000412/2016005) IR 05000334/20150062016-03-0202 March 2016 ROP 16 Annual Assessment Letter for Beaver Valley Power Station, Units 1 & 2 (Report 05000334/2015006 and 05000412/2015006) IR 05000334/20150052015-09-0101 September 2015 ROP-16 Mid-Cycle Assessment Letter for Beaver Valley Power Station (Report 05000334/2015005 and 05000412/2015005) IR 05000334/20140012015-03-0404 March 2015 ROP 15 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2, (Report 05000334/2014001 and 05000412/2014001) IR 05000334/20140062014-09-0202 September 2014 ROP-15 Mid-Cycle Performance Review and Inspection Plan Report 05000334/2014006 and 05000412/2014006 IR 05000334/20130012014-03-0404 March 2014 ROP-14 2013 Beaver Valley Power Station Units 1 and 2, Annual Assessment Letter, Report 05000334/2013001 and 05000412/2013001, and Inspection Plan IR 05000334/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan Report 05000334/2013006 and 05000412/2013006 IR 05000334/20120012013-03-0404 March 2013 Annual Assessment Letter for Beaver Valley Units 1 and 2 (Report 05000334/2012001 and 05000412/2012001) IR 05000334/20120062012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan 2012 - Beaver Valley Power Station (Report 05000334/2012006 and 05000412/2012006) IR 05000334/20110012012-03-0505 March 2012 Annual Assessment Letter for Beaver Valley Power Station Units 1 and 2 (Report 05000334-11-001 and 05000412-11-001) ML1124206842011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - Beaver Valley Units 1 and 2 IR 05000334/20100012011-03-0404 March 2011 Annual Assessment Letter for Beaver Valley Units 1 and 2, EOC 11 (Report 05000334/2010001 and 05000412/2010001) ML1024406392010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - Beaver Valley Units 1 and 2 IR 05000334/20010012010-03-0303 March 2010 Annual Performance Review and Inspection Plan - Beaver Valley Power Station (Beaver Valley) Units 1 and 2 (05000334-01-001 and 05000412-01-001) ML0924401272009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - Beaver Valley Units 1 and 2 IR 05000334/20090012009-03-0404 March 2009 Annual Assessment Letter - Beaver Valley Power Station Units 1 and 2 (05000334/2009001 and 05000412/2009001) ML0824704722008-09-0202 September 2008 2008 Mid-Cycle Performance Review and Inspection Plan - Beaver Valley IR 05000334/20080012008-03-0303 March 2008 (05000334-08-001, 05000412-08-001), Annual Assessment Letter ML0734706972007-12-13013 December 2007 ROP 8 - Beaver Valley - Change to Inspection Plan, 12/13/07 ML0724309412007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan ML0706104772007-03-0202 March 2007 Annual Assessment Letter EOC 2006 - Beaver Valley Station ML0624305972006-08-31031 August 2006 Mid-cycle Performance Review and Inspection Plan - Beaver Valley Power Station Units 1 and 2 ML0606201582006-03-0202 March 2006 2006-001 - Annual Assessment Letter - Beaver Valley Power Station Units 1 and 2 (Reports 05-334-2006001 and 05-412-2006001) ML0524207222005-08-30030 August 2005 2005 Mid-Cycle Review and Inspection Plan - Beaver Valley ML0406301322004-03-0202 March 2004 2003-04 Annual Assessment Letter - Beaver Valley ML0323906412003-08-27027 August 2003 2003 Mid-Cycle Performance Review and Inspection Plan for Beaver Valley Power Station ML0306205872003-03-0303 March 2003 2003 Annual Assessment Letter - Beaver Valley Power Station, Units 1 & 2 IR 05000334/20020012002-03-0101 March 2002 2002 Annual Assessment Letter - Beaver Valley Power Station Units 1 & 2 (Report 50-334/02-01, 50-412/02-01) 2024-08-29
[Table view] Category:Letter
MONTHYEARIR 05000334/20240112024-10-17017 October 2024 License Renewal Phase IV Inspection Report 05000334/2024011 ML24134A1522024-09-17017 September 2024 Exemption from the Requirements of 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule (EPID L-2024-LLE-0005) - Letter L-24-038, License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References2024-09-17017 September 2024 License Amendment Request to Remove the Expired One-Time Action for Valve Leak Repair in Technical Specification (TS) 3.5.2 and to Correct Core Operating Limits Rep Ort (COLR) References L-24-015, Twenty-Ninth Refueling Outage Inservice Inspection Summary Report2024-09-17017 September 2024 Twenty-Ninth Refueling Outage Inservice Inspection Summary Report ML24260A1912024-09-16016 September 2024 Operator Licensing Examination Approval IR 05000334/20240052024-08-29029 August 2024 Updated Inspection Plan for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2024005 and 05000412/2024005) L-24-188, Submittal of Quality Assurance Program Manual, Revision 302024-08-27027 August 2024 Submittal of Quality Assurance Program Manual, Revision 30 L-24-199, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-08-22022 August 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 IR 05000334/20244022024-08-22022 August 2024 Security Baseline Inspection Report 05000334/2024402 and 05000412/2024402 (Cover Letter Only) L-24-186, Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 Response to RAI for Exemption Request from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule IR 05000334/20240022024-08-0505 August 2024 Integrated Inspection Report 05000334/2024002 and 05000412/2024002 ML24208A0462024-07-26026 July 2024 NRC Office of Investigations Case No. 1-2023-005 L-24-182, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-23023 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 L-24-161, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-07-19019 July 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 05000334/LER-2024-004, Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control2024-07-17017 July 2024 Reactor Trip Due to Bypass Feedwater Regulating Valve Failure to Control L-24-014, Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models2024-07-16016 July 2024 Annual 10 CFR 50.46 Report of Changes to or Errors in Emergency Core Cooling Svstem Evaluation Models ML24193A2912024-07-16016 July 2024 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule IR 05000334/20245012024-07-0808 July 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000334/2024501 and 05000412/2024501 05000334/LER-2024-003, Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping2024-07-0202 July 2024 Unanalyzed Containment Bypass Condition Due to Degraded River Water Piping L-24-164, BV-2, Post Accident Monitor Report2024-06-27027 June 2024 BV-2, Post Accident Monitor Report IR 05000334/20244012024-06-26026 June 2024 Material Control and Accounting Program Inspection Report 05000334/2024401 and 05000412/2024401 (Cover Letter Only) L-24-094, Reactor Vessel Surveillance Capsule Withdrawal Schedule2024-06-24024 June 2024 Reactor Vessel Surveillance Capsule Withdrawal Schedule L-24-152, Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations2024-06-17017 June 2024 Response to NRC Regulatory Issue Summary 2024-01 Preparation and Scheduling of Operator Licensing Examinations 05000334/LER-2024-002, Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation2024-06-11011 June 2024 Automatic Reactor Trip Due to Low Reactor Coolant Flow Caused by Transformer Overexcitation Protection Relay Actuation 05000334/LER-2024-001, Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification2024-06-0606 June 2024 Offsite AC Power Source Inoperable Due to Breaker Failure Resulting in Condition Prohibited by Technical Specification ML24135A2282024-05-29029 May 2024 Review of the Spring 2023 Outage Generic Letter 95-05 Voltage-Based Alternate Repair Criteria and Steam Generator F Star Reports ML24135A1702024-05-29029 May 2024 – Steam Generator Tube Inspection - Review of the Spring 2023 Tube Inspection Reports L-24-021, Cycle 30 Core Operating Limits Report2024-05-23023 May 2024 Cycle 30 Core Operating Limits Report L-24-121, Discharge Monitoring Report (NPDES) Permit No. PA00256152024-05-23023 May 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24141A1052024-05-20020 May 2024 Senior Reactor and Reactor Operator Initial License Examinations IR 05000334/20240102024-05-15015 May 2024 Information Request for Quadrennial Baseline Comprehensive Engineering Team Inspection; Notification to Perform Inspection 05000334/2024010 and 05000412/2024010 L-24-107, CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair2024-05-13013 May 2024 CFR 50.55a Request 1-TYP-5-RRP-l, for Alternative Method of Nondestructive Examination for River Water Outlet Piping Weld Repair IR 05000334/20240012024-05-0808 May 2024 Integrated Inspection Report 05000334/2024001 and 05000412/2024001 L-23-269, Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions2024-05-0707 May 2024 Application to Revise Technical Specifications to Adopt TSTF-569, Revision of Response Time Testing Definitions L-24-054, Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological)2024-04-29029 April 2024 Submittal of 2023 Annual Radioactive Effluent Release Report 2023 Annual Radiological Environmental Operating Report and 2023 Annual Environmental Operating Report (Non-Radiological) L-24-089, Emergency Preparedness Plan2024-04-23023 April 2024 Emergency Preparedness Plan L-24-088, Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 20242024-04-22022 April 2024 Discharge Monitoring Report (NPDES) Permit No. PA0025615 for March 2024 ML24101A2752024-04-10010 April 2024 Response to Request for Additional Information Regarding Spring 2023 180-Day Steam Generator Tube Inspection Report L-24-082, Withdrawal of Exemption Request2024-04-0303 April 2024 Withdrawal of Exemption Request L-24-013, Annual Notification of Property Insurance Coverage2024-03-26026 March 2024 Annual Notification of Property Insurance Coverage L-24-064, Submittal of Discharge Monitoring Report (NPDES) Permit No. PA00256152024-03-13013 March 2024 Submittal of Discharge Monitoring Report (NPDES) Permit No. PA0025615 ML24044A0662024-03-0404 March 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0083 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting ML24057A0752024-03-0101 March 2024 The Associated Independent Spent Fuel Storage Installations IR 05000334/20230062024-02-28028 February 2024 Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2023006 and 05000412/2023006) CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions L-23-264, Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule2024-02-23023 February 2024 Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Report Update Schedule L-24-050, Retrospective Premium Guarantee2024-02-22022 February 2024 Retrospective Premium Guarantee 05000412/LER-2023-003-01, Missile Barrier Door Left Open Resulting in a Loss of Safety Function2024-02-20020 February 2024 Missile Barrier Door Left Open Resulting in a Loss of Safety Function IR 05000334/20230042024-02-12012 February 2024 Integrated Inspection Report 05000334/2023004 and 05000412/2023004 ML24025A0922024-01-25025 January 2024 Requalification Program Inspection 2024-09-17
[Table view] |
Text
UNITED STATES ber 1, 2015
SUBJECT:
MID-CYCLE ASSESSMENT LETTER FOR BEAVER VALLEY POWER STATION, UNIT NOS. 1 AND 2 (REPORT 05000334/2015005 AND 05000412/2015005)
Dear Mr. Larson:
On August 13, 2015, the U. S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of Beaver Valley Power Station, Unit Nos. 1 and 2. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from July 1, 2014 through June 30, 2015. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, Beaver Valley Power Station, Unit Nos. 1 and 2 operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at Beaver Valley Power Station Unit Nos. 1 and 2 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green) safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through June 30, 2017. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. In addition to baseline inspections, the NRC will perform IP 71003, Post Approval Site Inspection for License Renewal, and Temporary Instruction (TI) 2515-191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communications/
Staffing/Multi-Unit Dose Assessment Plans. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security related inspections, which will be sent via separate, non-publicly available correspondence. In response to the accident at Fukushima, the Commission issued Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-design-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. The on-site portion of the audit was completed at Beaver Valley Power Station, Unit Nos. 1 and 2, and the information gathered will aid staff in development of the Final Safety Evaluation for the site. After the NRC staff receives the Final Compliance letter for the site, the Final Safety Evaluation will be issued. Then, the NRC staff will confirm through inspections the full implementation of the orders mentioned above by performing TI 191, Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communications/Staffing/Multi-Unit Dose Assessment Plans.
In accordance with Title 10 of the Code of Federal Regulations, Part 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (610) 337-5046 with any questions you have regarding this letter.
Sincerely,
/RA/
Silas R. Kennedy, Chief Projects Branch 6 Division of Reactor Projects Docket Nos. 50-334, 50-412 License Nos. DPR-66, NPF-73 Enclosure: Beaver Valley Power Station Inspection/Activity Plan cc w/encl: Distribution via ListServ
ML15229A116 SUNSI Review Non-Sensitive Publicly Available Sensitive Non-Publicly Available OFFICE RI/DRP RI/DRP NAME JKrafty/ AVZ for via email AZiedonis/ AVZ SKennedy/ SRK DATE 08/ 25 /15 08/ 25 /15 08/ 25 /15
Page 1 of 3 Beaver Valley 08/25/2015 14:18:22 Inspection / Activity Plan Report 22 07/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site EP - EP PROGRAM INSPECTION 1 1, 2 06/29/2015 07/02/2015 IP 7111402 Alert and Notification System Testing 1, 2 06/29/2015 07/02/2015 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 1, 2 06/29/2015 07/02/2015 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies TRI FI - TRIENNIAL FIRE PROTECTION INSPECTION 5 1, 2 08/03/2015 08/07/2015 IP 7111105T Fire Protection [Triennial]
1, 2 08/17/2015 08/21/2015 IP 7111105T Fire Protection [Triennial]
12/7EXAM - U2 INITIAL OL EXAM 3 2 11/09/2015 11/13/2015 U01906 FY16-BV2 INITIAL OPERATOR LICENSING EXAM 2 12/07/2015 12/18/2015 U01906 FY16-BV2 INITIAL OPERATOR LICENSING EXAM 71003 - LR COMMITMENTS PHASE II TEAM INSP 5 1 08/31/2015 09/04/2015 IP 71003 Post-Approval Site Inspection for License Renewal 1 09/14/2015 09/18/2015 IP 71003 Post-Approval Site Inspection for License Renewal 7111108P - U2 INSERVICE INSPECTION 1 2 10/05/2015 10/16/2015 IP 7111108P Inservice Inspection Activities - PWR 71124 - RAD SAFETY INSP 1 1, 2 10/19/2015 10/23/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 10/19/2015 10/23/2015 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 10/19/2015 10/23/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/19/2015 10/23/2015 IP 71124.04 Occupational Dose Assessment 1, 2 10/19/2015 10/23/2015 IP 71124.05 Radiation Monitoring Instrumentation 71124.07 - RAD SAFETY INSPECTION 1 1, 2 11/30/2015 12/04/2015 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 11/30/2015 12/04/2015 IP 71151-OR01 Occupational Exposure Control Effectiveness 1, 2 11/30/2015 12/04/2015 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71124 - RAD SAFETY INSP 1 1, 2 12/14/2015 12/18/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 12/14/2015 12/18/2015 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 12/14/2015 12/18/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 12/14/2015 12/18/2015 IP 71124.04 Occupational Dose Assessment 1, 2 12/14/2015 12/18/2015 IP 71151 Performance Indicator Verification 71124 - RAD SAFETY INSPECTION 1 1, 2 03/07/2016 03/11/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 03/07/2016 03/11/2016 IP 71124.02 Occupational ALARA Planning and Controls This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 2 of 3 Beaver Valley 08/25/2015 14:18:22 Inspection / Activity Plan Report 22 07/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 71124 - RAD SAFETY INSPECTION 1 1, 2 03/07/2016 03/11/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 03/07/2016 03/11/2016 IP 71124.04 Occupational Dose Assessment EP - EP EXERCISE EVALUATION 4 1, 2 06/13/2016 06/17/2016 IP 7111401 Exercise Evaluation 7111107T - TRIENNIAL HEAT SINK 1 1, 2 05/16/2016 05/20/2016 IP 7111107T Heat Sink Performance EXM10/3 - BEAVER VALLEY 1 INITIAL EXAM 6 1 10/03/2016 10/07/2016 U01922 FY17-BV1 INITIAL OPERATOR LICENSING EXAM 1 10/31/2016 11/11/2016 U01922 FY17-BV1 INITIAL OPERATOR LICENSING EXAM 7111117T - PERMANENT PLANT MODIFICATIONS 3 1, 2 06/06/2016 06/10/2016 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 1, 2 06/20/2016 06/24/2016 IP 7111117T Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications 7111111B - BV1 REQUAL INSP W/ P/F RESULTS 2 1 08/15/2016 08/19/2016 IP 7111111B Licensed Operator Requalification Program 71124 - RAD SAFETY INSPECTION 3 1, 2 07/11/2016 07/15/2016 IP 71124.05 Radiation Monitoring Instrumentation 1, 2 07/11/2016 07/15/2016 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 1, 2 07/11/2016 07/15/2016 IP 71124.07 Radiological Environmental Monitoring Program 1, 2 07/11/2016 07/15/2016 IP 71151-PR01 RETS/ODCM Radiological Effluent Occurrences 71124 - RAD SAFETY INSPECTION 1 1, 2 10/03/2016 10/07/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 10/03/2016 10/07/2016 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 10/03/2016 10/07/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 10/03/2016 10/07/2016 IP 71124.04 Occupational Dose Assessment 7111108P - BV U1 INSERVICE INSPECTION 1 1 10/03/2016 10/14/2016 IP 7111108P Inservice Inspection Activities - PWR 71124 - RAD SAFETY INSPECTION 1 1, 2 12/12/2016 12/16/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 12/12/2016 12/16/2016 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 12/12/2016 12/16/2016 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 1, 2 12/12/2016 12/16/2016 IP 71124.04 Occupational Dose Assessment 1, 2 12/12/2016 12/16/2016 IP 71151-OR01 Occupational Exposure Control Effectiveness This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.
Page 3 of 3 Beaver Valley 08/25/2015 14:18:22 Inspection / Activity Plan Report 22 07/01/2015 - 06/30/2017 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site 71124.08 - RADWASTE 1 1, 2 12/05/2016 12/09/2016 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124 - HP INSPECTION 1 1, 2 04/10/2017 04/14/2017 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 1, 2 04/10/2017 04/14/2017 IP 71124.02 Occupational ALARA Planning and Controls 1, 2 04/10/2017 04/14/2017 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 7111108P - U2 INSERVICE INSPECTION 1 2 04/10/2017 04/21/2017 IP 7111108P Inservice Inspection Activities - PWR 7111111B - BV2 REQUAL INSP WITH P/F RESULTS 2 2 06/19/2017 06/23/2017 IP 7111111B Licensed Operator Requalification Program TI-191 - FUKUSHIMA LESSONS-LEARNED 1 1, 2 05/15/2017 05/19/2017 IP 2515/191 Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 71124 - HP INSPECTION 1 1, 2 06/05/2017 06/09/2017 IP 71124.04 Occupational Dose Assessment 1, 2 06/05/2017 06/09/2017 IP 71124.05 Radiation Monitoring Instrumentation 71152B - PI&R BIENNIAL 2 1, 2 06/01/2017 06/05/2017 IP 71152B Problem Identification and Resolution 1, 2 06/15/2017 06/19/2017 IP 71152B Problem Identification and Resolution This report does not include INPO and OUTAGE activities.
This report shows only on-site and announced inspection procedures.