October 17, 2024
SUBJECT:
BEAVER VALLEY POWER STATION, UNIT 1 - LICENSE RENEWAL
PHASE IV INSPECTION REPORT 05000334/2024011
Dear Barry Blair:
On September 26, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Beaver Valley Power Station, Unit 1 and discussed the results of this inspection with Will Cothen, Site Engineering Director and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Mel Gray, Chief Engineering Branch 1 Division of Operating Reactor Safety
Docket No. 05000334 License No. DPR-66
Enclosure:
As stated
Inspection Report
Docket Number:
05000334
License Number:
Report Number:
Enterprise Identifier: I-2024-011-0015
Licensee:
Vistra Operations Company, LLC
Facility:
Beaver Valley Power Station, Unit 1
Location:
Shippingport, PA
Inspection Dates:
September 9, 2024 to September 26, 2024
Inspectors:
L. Dumont, Senior Reactor Inspector
N. Floyd, Senior Reactor Inspector
K. Mangan, Senior Reactor Inspector
J. Schoppy, Senior Reactor Inspector
Approved By:
Mel Gray, Chief
Engineering Branch 1
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a license renewal Phase IV inspection at Beaver Valley Power Station, Unit 1, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
OTHER ACTIVITIES
- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL
===71003 - Post-Approval Site Inspection for License Renewal
The team conducted a Phase IV license renewal inspection as outlined in NRC IP 71003. The team selected seven aging management programs for evaluation based on risk insights and programs that were enhanced or new under the renewed operating license. The team also considered for selection those programs with monitoring results that were performed for the first time or those that identified examination or test results not experienced in the past. For the aging management programs selected, the team reviewed records, interviewed plant staff, and conducted plant walk downs to evaluate whether aging management program elements were being implemented in accordance with NRC requirements. The team evaluated the following elements of the aging management programs: scope, preventive actions, parameters monitored or inspected, detection of aging effects, monitoring and trending, acceptance criteria, corrective actions, confirmation process, administrative controls, and operating experience.
The following aging management programs were evaluated by the team:
Post-Approval Site Inspection for License Renewal===
- (1) External Surfaces Monitoring Program
- (2) Inspection of Internal Surfaces in Miscellaneous Piping and Ducting Components Program
- (3) Buried Piping and Tanks Inspection Program
- (4) Selective Leaching Program
- (5) Structures Monitoring Program
- (6) Electrical Cables and Connections Not Subject to 10 CFR 50.49 Environmental Qualification Requirements Program
- (7) Inaccessible Medium Voltage Cables Not Subject to 10 CFR 50.49 Environmental Qualification Requirements Program
INSPECTION RESULTS
Observation: Wetted cables during annual manhole inspection 71003 The inspectors reviewed the licensee's implementation of the Inaccessible Medium Voltage Cables Not Subject to 10 CFR 50.49 Environmental Qualification Requirements Program. The inspectors selected a random sample of manhole inspections from the past three years. The licensee discovered high water levels, sometimes on a repeated basis, during the manhole inspections where the cables were submerged (i.e., wetted). During each occurrence, the licensee drained the water from the manhole, but did not take actions to adjust the frequency to minimize the exposure to moisture as required by procedure 1/2-ADM-2404, Revision 5. The Unit 1 cables in-scope for license renewal under the aging management program are the three river water pumps 1A/B/C and the emergency response facility feeder cable FDR-1/2. The licensee generated condition report CR-2024-7442 to identify the trend in high water level for two of the manholes. The inspectors noted that repeated wetting of the electrical cables could result in long-term degradation of cable insulation. The inspectors determined the issue was minor because the licensee had performed periodic electrical testing (i.e., megger) of these cables which served to monitor the capability of the cable insulation. The inspectors reviewed the most recent test results and noted the acceptance criteria had been met.
Observation: Selective leaching commitment change 71003 The inspectors observed that the licensee changed their license renewal commitment for the selective leaching program in 2020 to perform no additional inspections of the gray cast iron buried components, and instead, to manage the effects of aging under the fire protection program. The basis was condition monitoring of above ground components would be an effective alternative monitoring method. However, the inspectors determined there was not guidance in the fire protection program for sampling or monitoring for selective leaching. The licensee had identified this performance deficiency and entered it into their corrective action program during a July 2024 self-assessment. The inspectors determined this issue was minor because the previous guidance remained available under the active procedure 1/2-ADM-2303, Revision 2, Selective Leaching of Materials Inspection Program. The inspectors also noted that the licensee performed an opportunistic inspection of a buried gray cast iron component in 2017 after a fire protection pipe failure occurred, which met this license renewal commitment prior to its change.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On September 26, 2024, the inspectors presented the license renewal Phase IV inspection results to Will Cothen, Site Engineering Director and other members of the licensee staff.
- On September 12, 2024, the inspectors presented the preliminary inspection results to Barry Blair, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71003
Corrective Action
Documents
2011-88208
2011-88526
2011-89071
2013-10003
2014-14741
2015-06897
2015-07232
2015-16701
2016-12299
2016-13869
2017-06835
2017-11716
2018-06897
2019-07458
20-06001
20-09472
22-01806
22-02887
22-06387
22-09674
23-02483
23-05234
23-05612
23-06071
23-08366
24-01211
24-01268
24-01534
24-07093
24-07094
24-07095
Corrective Action
24-07186
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Documents
Resulting from
Inspection
24-07215
24-07254
24-07257
24-07258
24-07259
24-07260
24-07262
24-07263
24-07264
24-07270
24-07275
24-07281
24-07282
24-07284
24-07290
24-07345
24-07348
24-07349
24-07353
24-07357
24-07359
24-07361
24-07370
24-07393
24-07432
24-07442
Drawings
8700-RM-118
Arrgt - Personnel Access Between Buildings 735 6
Revision 15
Engineering
Evaluations
Report No.
1300105.402
Beaver Valley Power Station Cathodic Protection Study
Revision 0
Miscellaneous
Structural Monitoring Inspections of BVPS Structures, Forth
Five Year Cycle Report - 2017
09/29/2021
Structural Monitoring Inspections of BVPS Structures, Fifth
Five Year Cycle Report - 2023
03/20/2024
Beaver Valley Underground Piping and Tanks Integrity Asset
06/06/2024
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Management Plan
Change Notice
20-092
BV1 UFSAR Section 16.1.36 "Selective Leaching of
Materials Inspection Program"
09/29/2020
LRBV-EAMR-001
BVPS License Renewal Project Document
Revision 9
Procedures
1/2-ADM-1900
Revision 52
1/2-ADM-2016
General Area Structural Inspections
Revision 7
1/2-ADM-2098
System Walkdowns
Revision 3
1/2-ADM-2100
Inspection of Internal Surfaces Program
Revision 2
1/2-ADM-2147
Electrical Cables and Connections not Subject to 10 CFR
50.49 Environmental Qualification Requirements Program
Revision 2
1/2-ADM-2304
Inaccessible Medium-Voltage Cables not Subject to 10CFR
50.49 Environmental Qualification Requirements
Revision 5
BVRM-ENG-0004
Unit 1 Inspection of Internal Surfaces Program Components
Revision 1
NOBP-ER-3103
Plant Walkdown for Inspection of Potential Adverse
Localized Environments for Electrical Cables and
Connections
Revision 0
NOP-ER-3100
Cable Aging Management Program
Revision 2
NORM-E-3112
Cable Monitoring
Revision 2
Self-Assessments
BV License Renewal 71003 Inspection Self-Assessment
(2024)
07/18/2024
ATL-2020-0580-
ATA-10
Selective Leaching of Materials Inspection Program Self-
Assessment
11/05/2020
ATL-2020-0580-
ATA-12
Complete Self Assessment for License Renewal Aging
Management Program B.2.11-XI.E1 Elec Cables
10/31/2020
Work Orders
200383105
200417271
200472313
200505561
200519852
200535974
200535975
200558917
200590732
200621089
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
200622336
200634676
200645298
200645567
200664410
200665714
200668504
200694327
200720825
200745594
200756674
200760421
200764762
200799122
200800858
200803685
200803907
200807947
200808174
200808186
200811580
200813173
200817514
200819961
200825758
200825780
200828150
200828151
200828717
200831740
200833551
200833641
200833730
200833731
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
200833734
200834173
200834249
200834639
200834741
200835894
200836415
200841448
200845125
200847506
200847991
200848673
200852041
200853481
200853482
200856637
200856640
200857240
200858708
200859080
200879234
200880213
200880581
200880582
200880712
200880713
200880781
200880782
200880785
200881287
200881614
200881618
200883446
200894130
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
200894845
200898198
200898199
200898200
200898201
200898204
200898206
200898207
200898208
200898209
200898739
200917779
200919151
200944127