UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION I

2100 RENAISSANCE BLVD., Suite 100

KING OF PRUSSIA, PA 19406-2713

September 28, 2017

Mr. Richard Bologna

Site Vice President

First Energy Nuclear Operating Company

Beaver Valley Power Station

P. O. Box 4

Shippingport, PA 15077-0004

SUBJECT: BEAVER VALLEY POWER STATION UNITS 1 AND 2 - INFORMATION REQUEST

FOR THE CYBER-SECURITY BASELINE INSPECTION NOTIFICATION TO

PERFORM INSPECTION 05000334/2018403 AND 05000412/2018403

Dear Mr. Bologna:

On January 29, 2018, the U.S. Nuclear Regulatory Commission (NRC) will begin a baseline

inspection in accordance with Inspection Procedure (IP) 71130.10 Cyber-Security, issued

May 15, 2017 at the Beaver Valley Power Station, Units 1 and 2. The inspection will be

performed to evaluate and verify your ability to meet full implementation requirements of the

NRCs Cyber-Security Rule, Title 10, Code of Federal Regulations (CFR), Part 73, Section 54,

Protection of Digital Computer and Communication Systems and Networks. The onsite portion

of the inspection will take place during the weeks of January 29-February 2, 2018, and

February 12-16, 2018. Experience has shown that baseline inspections are extremely resource

intensive, both for the NRC inspectors and the licensee staff. In order to minimize the

inspection impact on the site and to ensure a productive inspection for both parties, we have

enclosed a request for documents needed for the inspection. These documents have been

divided into four groups.

The first group specifies information necessary to assist the inspection team in choosing the

focus areas (i.e., sample set) to be inspected by the cyber-security Inspection Procedure. This

information should be made available via compact disc and delivered to the regional office no

later than October 31, 2017. The inspection team will review this information and, by

November 17, 2017, will request the specific items that should be provided for review.

The second group of additional requested documents will assist the inspection team in the

evaluation of the critical systems and critical digital assets (CSs/CDAs), defensive architecture,

and the areas of your stations Cyber-Security Program selected for the cyber-security

inspection. This information will be requested for review in the regional office prior to the

inspection by December 11, 2017.

The third group of requested documents consists of those items that the inspection team will

review, or need access to, during the inspection.

Please have this information available by the first day of the onsite inspection,

January 29, 2018.

R. Bologna 2

The fourth group of information is necessary to aid the inspection team in tracking issues

identified as a result of the inspection. It is requested that this information be provided to the

lead inspector as the information is generated during the inspection. It is important that all of

these documents are up to date and complete in order to minimize the number of additional

documents requested during the preparation and/or the onsite portions of the inspection.

The lead inspector for this inspection is Mr. David Werkheiser. We understand that our

regulatory contact for this inspection is Mr. David Wacker of your organization. If there are any

questions about the inspection or the material requested, please contact the lead inspector at

610-337-5316 or via e-mail at David.Werkheiser@nrc.gov.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, control number

3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a

request for information or an information collection requirement unless the requesting document

displays a currently valid Office of Management and Budget control number.

This letter and its enclosure will be available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRCs Public Document Room in

accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Glenn T. Dentel, Chief

Engineering Branch 2

Division of Reactor Safety

Docket Nos. 50-334 and 50-412

License Nos. DPR-66 and NPF-73

Enclosure:

Beaver Valley Power Station, Units 1 and 2

Cyber-Security Inspection Document Request

cc w/encl: Distribution via ListServ

ML17271A066

SUNSI Review Non-Sensitive Publicly Available

Sensitive Non-Publicly Available

OFFICE RI DRS RI DRS

NAME DWerkheiser/DW GDentel/GD

DATE 09/28/17 09/28/17

BEAVER VALLEY POWER STATION

CYBER-SECURITY INSPECTION DOCUMENT REQUEST

Inspection Report: 05000334/2018403 and 05000412/2018403

Inspection Dates: January 29 - February 2, 2018 and February 12 - 16, 2018

Inspection Procedure: IP 71130.10, Cyber-Security, issue date May 15, 2017

Reference: Guidance Document for Development of the Request for

Information (RFI) and Notification Letter for Full-Implementation

of the Cyber - Security Inspection, issue date May 25, 2017

NRC Inspectors: David Werkheiser, Lead Jeff Rady

(610) 337-5316 (610) 337-5380

David.Werkheiser@nrc.gov Jeff.Rady@nrc.gov

NRC Contractors: John Walley Frederick Priester

(301) 287-3717 (301) 230-4590

John.Walley@nrc.gov Frederick.Priester@nrc.gov

I. Information Requested for In-Office Preparation

The initial request for information (i.e., first RFI) concentrates on providing the inspection team

with the general information necessary to select appropriate components and Cyber-Security

Program (CSP) elements to develop a site-specific inspection plan.

The first RFI is used to identify the list of critical systems and critical digital assets (CSs/CDAs)

plus operational and management (O&M) security control portions of the CSP to be chosen as

the sample set required to be inspected by the cyber-security IP. The first RFIs requested

information is specified below in Table RFI #1.

The Table RFI #1 information is requested to be provided to the regional office by

October 31, 2017, or sooner, to facilitate the selection of the specific items that will be reviewed

during the onsite inspection weeks. The inspection team will examine the returned

documentation from the first RFI and identify/select specific systems and equipment

(e.g., CSs/CDAs) to provide a more focused follow-up request to develop the second RFI.

The inspection team will submit the specific systems and equipment list to your staff by

November 17, 2017, which will identify the specific systems and equipment that will be utilized

to evaluate the CSs/CDAs, defensive architecture, and the areas of the licensees CSP selected

for the cyber-security inspection. We request that the additional information provided from the

second RFI be made available to the regional office prior to the inspection by December 11,

2017. All requests for information shall follow the Table RFI #1 and the guidance document

referenced above. The required Table RFI #1 information shall be provided on compact disc

(CD) to the lead inspector by October 31, 2017. Please provide four copies of each CD

submitted (i.e., one for each inspector/contactor). The preferred file format for all lists is a

searchable Excel spreadsheet file on a CD. These CDs should be indexed and hyper-linked to

facilitate ease of use. If you have any questions regarding this information, please call the

inspection team leader as soon as possible.

1 Enclosure

BEAVER VALLEY POWER STATION

CYBER-SECURITY INSPECTION DOCUMENT REQUEST

Table RFI #1

Reference Section 3 Paragraph Number / Title: Items

1. List all Identified Critical Systems and Critical Digital Assets All

2. List CDA Facility and Site Ethernet - Transmission Control Protocol / Internet All

Protocol (TCP/ IP) Based Local Area Networks (LANs) and identify those LANs that

have Non-CDAs on them

3. List CDA Facility and Site Non-Ethernet TCP / IP Based LANs including those All

Industrial Networks and Identify LANs that have Non-CDAs on them

4. Network Topology Diagrams (Be sure to include all Network Intrusion Detection All

Systems (NIDS) and Security Information and Event Management (SIEMS) for

Emergency Preparedness (EP) Networks and Security Level 3 and 4 Networks)

8. List all Network Security Boundary Devices for EP Networks and all Network Security All

Boundary Devices for Levels 3 and 4

9. List CDA Wireless Industrial Networks All

11. NIDS Documentation for Critical Systems that have CDAs associated with them 11.a.1)

11.a.2)

12. SIEM Documentation for Critical Systems that have CDAs associated with them 12.a.1)

12.a.2)

14. List EP and Security Onsite and Offsite Digital Communication Systems All

25. Cyber-Security Assessment and Cyber-Security Incident Response Teams All

In addition to the above information please provide the following:

1. Electronic copy of your current Cyber Security Plan.

2. Electronic copy of summary of changes (if any), including any 10 CFR 50.54p

analysis to support those changes, made to the originally approved Cyber Security

Plan.

3. Electronic copy of a matrix that summarizes what controls are in place to satisfy the

controls required by Policies and Procedures.

4. Electronic copy of the Updated Final Safety Analysis Report and technical

specifications.

5. Name(s) and phone numbers for the regulatory and technical contacts.

6. Current management and engineering organizational charts.

Based on this information, the inspection team will identify and select specific systems and

equipment (e.g., CSs/CDAs) from the information requested by Table RFI #1 and submit a list

of specific systems and equipment to your staff by November 17, 2017, for the second RFI

(i.e., Table RFI #2).

II. Additional Information Requested to be Available Prior to Inspection

As stated above, in Section I of this enclosure, the inspection team will examine the returned

documentation requested from Table RFI #1 and submit the list of specific systems and

equipment to your staff by November 17, 2017, for the second RFI (i.e., RFI #2).

The second RFI will request additional information required to evaluate the CSs/CDAs,

defensive architecture, and the areas of your stations CSP selected for the cyber-security

inspection. The additional information requested for the specific systems and equipment is

identified in Table RFI #2. All requested information shall follow the Table RFI #2 and the

guidance document referenced above.

2

BEAVER VALLEY POWER STATION

CYBER-SECURITY INSPECTION DOCUMENT REQUEST

The Table RFI #2 information shall be provided on CD to the lead inspector by

December 11, 2017. Please provide four copies of each CD submitted (i.e., one for each

inspector/contactor). The preferred file format for all lists is a searchable Excel spreadsheet file

on a CD. These CDs should be indexed and hyper-linked to facilitate ease of use. If you have

any questions regarding this information, please call the inspection team leader as soon as

possible.

Table RFI #2

Section 3 Paragraph Number / Title: Items

5. Plant Computer System Block Diagram (If Plant Computer System is selected for

All

Inspection)

6. Plant Security System Block Diagram (if Security Computer System is selected for

All

Inspection)

7. Systems that are Distributed Block Diagrams (For Systems selected for Inspection)

All

10. Host-Based Intrusion Detection System Documentation (for CDAs for Systems 10.a.1)

selected for Inspection) 10.a.2)

13. List all Maintenance and Test Equipment used on CDAs for Systems Selected for

All

Inspection

15. Configuration Management

All

16. Supply Chain Management 16.a.)

16.b.1)

16.b.5)

16.b.6)

17. Portable Media and Mobile Device Control

All

18. Software Management

All

20. Vendor Access and Monitoring

All

21. Work Control

All

22. Device access and Key Control

All

23. Password / Authenticator Policy

All

24. User Account / Credential Policy

All

26. Corrective Actions Since Last NRC Inspection

All

In addition to the above information please provide the following:

  • The documented CSP assessment and analysis for each CDA in each of the selected

systems.

3

BEAVER VALLEY POWER STATION

CYBER-SECURITY INSPECTION DOCUMENT REQUEST

III. Information Requested to be Available on First Day of Inspection

For the specific systems and equipment identified in this enclosuresSection II., provide the

following RFI (i.e., Table 1ST Week Onsite) on a CD by January 29, 2018, the first day of the

inspection. All requested information shall follow the Table 1ST Week Onsite and the guidance

document referenced above.

Please provide four copies of each CD submitted (i.e., one for each inspector/contactor). The

preferred file format for all lists is a searchable Excel spreadsheet file on a CD. These CDs

should be indexed and hyper-linked to facilitate ease of use. If you have any questions

regarding this information, please call the inspection team leader as soon as possible.

Table 1ST Week Onsite

Section 3 Paragraph Number / Title: Items

10. Host-Based Intrusion Detection System Documentation for CDAs for Systems 10.a.3)

selected for inspection thru

10.a.12)

11.a.3)

11. NIDS Documentation for Critical Systems that have CDAs associated with them

thru

11.a.15)

12.a.3)

12. SIEM Documentation for Critical Systems that have CDAs associated with them

thru

12.a.14)

16.b.2)

16. Supply Chain Management

16.b.3)

16.b.4)

All

19. Cyber-Security Event Notifications

In addition to the above information please provide the following:

1. Copies of the following documents do not need to be solely available to the inspection

team as long as the inspectors have easy and unrestrained access to them.

a. Original Final Safety Analysis Report Volumes;

b. Original Safety Evaluation Report and Supplements;

c. Final Safety Analysis Report Question and Answers;

d. Quality Assurance (QA) Plan;

e. Latest Individual Plant Examination for External Events / Probabilistic Risk

Assessment Report; and

f. Vendor Manuals

2. Assessment and Corrective Actions:

a. The most recent Cyber-Security QA audit and/or self-assessment; and

b. Corrective action documents (e.g., condition reports, including status of corrective

actions) generated as a result of the most recent Cyber-Security QA audit and/or

self-assessment.

4

BEAVER VALLEY POWER STATION

CYBER-SECURITY INSPECTION DOCUMENT REQUEST

IV. Information Requested To Be Provided Throughout the Inspection

1. Copies of any corrective action documents generated as a result of the inspection

teams questions or queries during the inspection.

2. Copies of the list of questions submitted by the inspection team members and the

status/resolution of the information requested (provided daily during the inspection to

each inspection team member).

If you have any questions regarding the information requested, please contact the inspection

team leader.

5