IR 05000334/2020006

From kanterella
Jump to navigation Jump to search
Annual Assessment Letter for Beaver Valley Power Station, Units 1 and 2 (Reports 05000334/2020006 and 05000412/2020006)
ML21061A086
Person / Time
Site: Beaver Valley
Issue date: 03/03/2021
From: Matt Young
NRC/RGN-I/DRP/PB5
To: Grabnar J
Energy Harbor Nuclear Corp
Young M
References
IR 2020006
Download: ML21061A086 (6)


Text

March 3, 2021

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR BEAVER VALLEY POWER STATION, UNITS 1 AND 2 (REPORTS 05000334/2020006 AND 05000412/2020006)

Dear Mr. Grabnar:

The U.S. Nuclear Regulatory Commission (NRC) has completed its end-of-cycle performance assessment of Beaver Valley Power Station (Beaver Valley), Units 1 and 2, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2020 through December 31, 2020. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety. The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.

The NRC determined the performance at Beaver Valley, Units 1 and 2, during the most recent quarter was within the Licensee Response Column (Column 1) of the NRCs Reactor Oversight Process (ROP) Action Matrix in Inspection Manual Chapter 0305, Operating Reactor Assessment Program, because all inspection findings had very low safety significance (i.e.,

Green), and all PIs were within the expected range (i.e., Green). Therefore, the NRC plans to conduct ROP baseline inspections at Beaver Valley, Units 1 and 2.

The enclosed inspection plan lists the inspections scheduled through December 31, 2022.

The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In response to the COVID-19 public health emergency (PHE), the NRC is adjusting inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. Each planned inspection is being carefully reviewed in order to determine if any portions of the inspection can be performed remotely, how best to perform on-site portions to minimize personnel health risks, and adjust inspection schedules if needed. This is done in accordance with guidance contained in the February 1, 2021 memo, Calendar Year 2021 Inspection Guidance During COVID-19 Telework Restrictions (ML21027A274). For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here:

https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.

Additionally, during this period the NRC will perform inspections per Temporary Instruction 2515/194, Inspection of the Licensees Implementation of Industry Initiative Associated with the Open Phase Condition Design Vulnerability in Electrical Power Systems (NRC Bulletin 2012-01).

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRCs Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact me at 610-337-5205 with any questions you have regarding this letter.

Sincerely, X /RA/

Signed by: Matthew R. Young

Matthew R. Young, Chief Reactor Projects Branch 5 Division of Reactor Projects

Docket Nos. 05000334 and 05000412 License Nos. DPR-66 and NPF-73

Enclosure:

As stated

cc w/ encl: Distribution via ListServ

ML21061A086

SUNSI Review

Non-Sensitive Sensitive

Publicly Available Non-Publicly Available

OFFICE RI/DRP RI/DRP

NAME LCline MYoung

DATE 3/2/21 3/3/21

Beaver Valley 01/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count FY21 Beaver Valley 1 Initial Examination

1 01/31/2021 02/06/2021 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

02/28/2021 03/13/2021 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

PI&R BIENNIAL - BV

1, 2 02/08/2021 02/12/2021 IP 71152B 000747 Problem Identification and Resolution 1, 2 02/22/2021 02/26/2021 IP 71152B 000747 Problem Identification and Resolution PI&R Sample - Werkheiser - Cyber Security Followup

1, 2 02/15/2021 02/19/2021 IP 71152 000748 Problem Identification and Resolution Rad Safety Inspection - In-Plant Airborne

1, 2 03/08/2021 03/12/2021 IP 71124.03 000727 In-Plant Airborne Radioactivity Control and Mitigation Inservice Inspection - Unit 1 1R27

1 04/18/2021 05/01/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

Rad Safety Inspection 71124.01

1, 2 04/19/2021 04/23/2021 IP 71124.01 000725 Radiological Hazard Assessment and Exposure Controls EP PROGRAM INSPECTION - BEAVER VALLEY

1, 2 06/07/2021 06/11/2021 IP 71114.02 000717 Alert and Notification System Testing 1, 2 06/07/2021 06/11/2021 IP 71114.03 000718 Emergency Response Organization Staffing and Augmentation System 1, 2 06/07/2021 06/11/2021 IP 71114.04 000719 Emergency Action Level and Emergency Plan Changes 1, 2 06/07/2021 06/11/2021 IP 71114.05 000720 Maintenance of Emergency Preparedness 1, 2 06/07/2021 06/11/2021 IP 71151 001397 Performance Indicator Verification Rad Safety Inspection - ALARA

1, 2 07/08/2021 07/20/2021 IP 71124.02 000726 Occupational ALARA Planning and Controls 1, 2 07/12/2021 07/16/2021 IP 71151 000746 Performance Indicator Verification BV2 Requal Inspection with P/F Results

1 07/12/2021 07/16/2021 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance

07/12/2021 07/16/2021 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance MATERIAL CONTROL AND ACCOUNTABILITY

1, 2 07/18/2021 07/24/2021 IP 71130.11 000742 Material Control and Accounting (MC&A)

2/5/2021 1:34:31 PM Page 1 of 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

Beaver Valley 01/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count Access Control, Protective Strategy, TSR, SPR

1, 2 08/02/2021 08/06/2021 IP 71130.02 000734 Access Control 1, 2 08/02/2021 08/06/2021 IP 71130.05 000737 Protective Strategy Evaluation 1, 2 08/02/2021 08/06/2021 IP 71130.09 001656 Security Plan Changes 1, 2 08/02/2021 08/06/2021 IP 71130.14 000743 Review of Power Reactor Target Sets 1, 2 08/02/2021 08/06/2021 IP 71151 001338 Performance Indicator Verification Fire Protection - Beaver Valley

1, 2 08/30/2021 09/03/2021 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

1, 2 09/13/2021 09/17/2021 IP 71111.21N.05 001646 Fire Protection Team Inspection (FPTI)

TI-194 Open Phase Condition Inspection - BV

1, 2 09/13/2021 09/17/2021 TI 2515/194 000512 Inspection of the Licensees Implementation of Industry Initiative Associated With the Open Phase Condition Design Vulnerabilities In Electric Power Systems (NRC Bulletin 2012-01)

Inservice Inspection - Beaver Valley Unit 2

2 10/25/2021 11/12/2021 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

DBAI - Power Operated Valve - Beaver Valley

1, 2 03/14/2022 04/01/2022 IP 71111.21N.02 001645 Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements FORCE-ON-FORCE PLANNING AND EXERCISE WEEKS - BV

1, 2 03/14/2022 03/18/2022 IP 71130.03 000735 Contingency Response - Force-On-Force Testing 1, 2 04/04/2022 04/08/2022 IP 71130.03 000735 Contingency Response - Force-On-Force Testing FY22 BV2 Initial Operator Licensing Exam

2 03/20/2022 03/25/2022 OV 000956 VALIDATION OF INITIAL LICENSE EXAMINATION (OV)

04/17/2022 04/29/2022 EXAD 000500 LICENSE EXAM ADMINISTRATION (EXAD)

Triennial Heat Sink - Beaver Valley

1, 2 05/09/2022 05/13/2022 IP 71111.07T 000700 Heat Sink Performance EP EXERCISE INSPECTION - BEAVER VALLEY

1, 2 06/06/2022 06/10/2022 IP 71114.07 000722 Exercise Evaluation - Hostile Action (HA) Event 1, 2 06/06/2022 06/10/2022 IP 71151 001397 Performance Indicator Verification 2/5/2021 1:34:31 PM Page 2 of 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report

Beaver Valley 01/01/2021 - 12/31/2022 Unit Start End Activity CAC Title Staff Count BV1 Requal Inspection with P/F Results

1 06/20/2022 06/24/2022 IP 71111.11A 000703 Licensed Operator Requalification Program and Licensed Operator Performance

06/20/2022 06/24/2022 IP 71111.11B 000704 Licensed Operator Requalification Program and Licensed Operator Performance RP REMP 71124.07

1, 2 07/11/2022 07/15/2022 IP 71124.07 000731 Radiological Environmental Monitoring Program 50.59 Inspection - Beaver Valley

1, 2 07/17/2022 07/23/2022 IP 71111.17T 000709 Evaluations of Changes, Tests, and Experiments ISI Inspection - Beaver Valley Unit 1 1R28

1 10/17/2022 10/28/2022 IP 71111.08P 000702 Inservice Inspection Activities (PWR)

Access Auth, Access Control, FFD, SPR, PI-BV

1, 2 12/05/2022 12/09/2022 IP 71130.01 000733 Access Authorization 1, 2 12/05/2022 12/09/2022 IP 71130.02 000734 Access Control 1, 2 12/05/2022 12/09/2022 IP 71130.08 000740 Fitness For Duty Program 1, 2 12/05/2022 12/09/2022 IP 71130.09 001656 Security Plan Changes 1, 2 12/05/2022 12/09/2022 IP 71151 001338 Performance Indicator Verification 2/5/2021 1:34:31 PM Page 3 of 3 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

IP 22 Inspection Activity Plan Report