IR 05000334/2024010

From kanterella
Jump to navigation Jump to search
Comprehensive Engineering Team Inspection - Inspection Report 05000334/2024010 and 05000412/2024010
ML24232A192
Person / Time
Site: Beaver Valley
Issue date: 08/20/2024
From: Mel Gray
Division of Operating Reactors
To: Blair B
Vistra Operations Company
References
IR 2024010
Download: ML24232A192 (1)


Text

August 20, 2024

SUBJECT:

BEAVER VALLEY POWER STATION, UNITS 1 AND 2 - COMPREHENSIVE ENGINEERING TEAM INSPECTION - INSPECTION REPORT 05000334/2024010 AND 05000412/2024010

Dear Barry Blair:

On August 1, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Beaver Valley Power Station, Units 1 and 2 and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Mel Gray, Chief Engineering Branch 1 Division of Operating Reactor Safety

Docket Nos. 05000334 and 05000412 License Nos. DPR-66 and NPF-73

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000334 and 05000412

License Numbers:

DPR-66 and NPF-73

Report Numbers:

05000334/2024010 and 05000412/2024010

Enterprise Identifier: I-2024-010-0025

Licensee:

Vistra Operations Company, LLC

Facility:

Beaver Valley Power Station, Units 1 and 2

Location:

Shippingport, PA

Inspection Dates:

July 15, 2024 to August 1, 2024

Inspectors:

J. Brand, Senior Reactor Inspector

P. Cataldo, Senior Reactor Inspector

J. Lilliendahl, Senior Emergency Response Coordinator

K. Mangan, Senior Reactor Inspector

D. McHugh, Reactor Inspector

J. Schoppy, Senior Reactor Inspector

A. Turilin, Reactor Inspector

Approved By:

Mel Gray, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a comprehensive engineering team inspection at Beaver Valley Power Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Comprehensive Engineering Team Inspection

The inspectors evaluated the following components and listed applicable attributes, permanent modifications, Title 10 of the Code of Federal Regulations (10 CFR) 50.59 screening and/or evaluations, and operating experience:

Structures, Systems, and Components (SSCs) (IP section 03.01)===

For each component or operator action sample listed below, the team reviewed licensing and design basis documents and a sampling of applicable operator actions, periodic testing results, corrective action program documents, internal and external operating experience, preventive and corrective maintenance work orders, modifications, and aging management programs. Additionally, the team performed walkdowns of the component or procedure and conducted interviews with licensee personnel.

The team used the attributes contained in IP 71111.21M, Appendix A, Component Review Attributes, such as those listed below as guidance. Specifically, the team evaluated these attributes as per 71111.21M, Appendix B, Component Design Review Considerations and

===71111.21M, Appendix C, Component Walkdown Considerations.

(1) Risk significant operator action - Unit 1 weather-related Loss-of-Offsite Power
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Components installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.
(2) Unit 1 Power-Operated Relief Valve, 1-PCV-1RC-456
  • Air and nitrogen will be available and unimpeded during accident/event conditions.
  • Air, nitrogen, and electric, including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Heat will be adequately removed from major components.
  • Components installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment qualification is suitable for the environment expected under all conditions.
  • Equipment is adequately protected from environmental hazards.
  • Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
  • Performance capability of selected components have not been degraded through modifications.
(3) Unit 1 Recirculation Spray Heat Exchanger "1D," River Water Inlet Isolation Valve, MOV-1RW-104D
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Components installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment qualification is suitable for the environment expected under all conditions.
  • Equipment is adequately protected from environmental hazards.
  • Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
  • Performance capability of selected components have not been degraded through modifications.
(4) Unit 1 Quench Spray Pump, 1QS-P1A
  • Process medium (water) will be available and unimpeded during accident/event conditions.
  • Energy sources (electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Heat will be adequately removed from major components.
  • Components installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.
  • Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
  • Performance capability of selected components have not been degraded through modifications.
(5) Unit 1 Safety-Related 125 VDC Battery, No. 1-2 (Bus 1-2)
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Components installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment qualification is suitable for the environment expected under all conditions.
  • Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
(6) Unit 2 Emergency Diesel Generator, 2-2
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Heat will be adequately removed from major components.
  • Installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Performance capability of selected components have not been degraded through modifications.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment qualification is suitable for the environment expected under all conditions.
  • Equipment is adequately protected from environmental hazards.
(7) Unit 2 Low Head Safety Injection Pump, 2SIS-P21A
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Heat will be adequately removed from major components.
  • Components installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment qualification is suitable for the environment expected under all conditions.
  • Equipment is adequately protected from environmental hazards.
  • Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
  • Performance capability of selected components have not been degraded through modifications.
(8) Unit 2 Charging Pump, 2CHS-P21A
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
  • Components installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.
(9) Unit 2 Turbine-Driven Auxiliary Feedwater Pump, 2FWE-P22
  • Water will be available and unimpeded during accident/event conditions.
  • Steam supply will be available and adequate during accident/event conditions.
  • Component controls will be functional and provide desired control during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Heat will be adequately removed from major components.
  • Components installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment is adequately protected from environmental hazards.
  • Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
  • Performance capability of selected components have not been degraded through modifications.
(10) Unit 2 Recirculation Spray Heat Exchanger, 2RSS-E21B
  • Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
  • Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
  • Instrumentation and alarms are available to operators for making necessary decisions.
  • Heat will be adequately removed from major components.
  • Components installed configuration will support its design basis function under accident/event conditions.
  • Component operation and alignments are consistent with design and licensing basis assumptions.
  • Design bases and design assumptions have been appropriately translated into design calculations and procedures.
  • Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
  • Tests and/or analyses validate component operation under accident/event conditions.
  • Potential degradation is monitored or prevented.
  • Equipment qualification is suitable for the environment expected under all conditions.
  • Equipment is adequately protected from environmental hazards.
  • Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
  • Performance capability of selected components have not been degraded through modifications.

Modifications (IP section 03.02)===

(1) Unit 1 EC-20-0012-002: Overload Heater Replacement for MCC-1-41-1M
(2) Unit 1 EC-21-0022-001: Upgrade MCC-1-1-Q Cutler Hammer Components
(3) Unit 1 EC-24-1071: WR-89 Slip-on Flange Installation for Repair
(4) Unit 2 EC-22-1072-001: Thermal Shield Support Block Bolt Bore Internal Thread Staking
(5) Unit 2 EC-22-1046-001: Through-wall Defect Removal, Line BV-WR-20-151-Q3

10 CFR 50.59 Evaluations/Screening (IP section 03.03) (10 Samples)

(1)18-00478: Implementation of License Amendment /Setting Changes for BV1 Degraded Voltage and Loss of Voltage Protection (2)22-0086-001/2/3: Piping Material Change Downstream of Unit 1 AFWP Restricting Orifices (3)22-0073-001/002: U1 Diesel Tank Level Setpoint Change (4)22-1073-001: Tubing Downstream of 1RC-272 Support Relocation (5)22-1076-001: Installation of Permanent Shielding at 1SW-24 (6)22-0049-001/002/003: Pressure Switch Setpoint Changes for U1 FWIV HYV-1FW-100A/B/C (7)20-0117-001: Replace U2 SWS Emergency Diesel Generator Heat Exchanger Inlet Valves (8)21-0077-001: Protect Fire Protection Lines from Future Wear

(9) Unit 2, PAF-17-00193/Screen 17-00374/16-00913: Associated with CR-2023-05501 (10)50.59 associated with Compensatory Measure to Maintain Operability for U2 RWST 2QSS-TK21, from CR-2023-06404

Operating Experience Samples (IP section 03.04) (3 Samples)

(1) NRC IN 2020-04: Operating Experience Regarding Failure of Fire Protection Main Yard Piping
(2) NRC IN 2021-03: Operating Experience Related to DAEC Derecho Event on August 10, 2020
(3) NRC IN 2023-01: Risk Insights for High Energy Arcing Faults Operating Experience and Analyses

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On August 1, 2024, the inspectors presented the comprehensive engineering team inspection results to Barry Blair, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M Calculations

10080-E-048

Emergency Diesel Generator Loading with Station Blackout

Revision 16

10080-N-862

Auxiliary Feedwater Pump Performance

Revision 0

211-N-423

Determine the Available NPSH for Low Head Safety

Injection (LHSI) Pumps at Design Flow

Revision 0

8700-DMC-3523

Quench Spray System Performance

Revision 2

8700-E-202

DC System Management Battery 1-2 - Battery Charger 1-2

Revision 3

BV-10080-N-824

Recirculation Spray Heat Exchanger Inputs for MAAP

Containment Analysis

Revision 1

DMC-1516

Determination of the Valve Total Required Thrust, Actuator

Capability and Margin Assessment for AOVs PCV-1RC-

455C, D & 456

Revision 2,

Addendum 1

Corrective Action

Documents

CR-

2011-05786

2013-00419

2017-07594

2018-07705

20-04803

20-06052

20-08083

20-09580

21-08267

21-09187

22-00253

22-00542

22-01653

22-05250

22-05564

22-07907

22-08878

23-00246

23-01707

23-02575

23-03005

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

23-03077

23-03128

23-03906

23-04171

23-04462

23-05492

23-05501

23-05660

23-06861

23-09188

24-00897

24-00966

24-02299

24-02955

24-02967

24-02972

24-02973

24-03488

24-03785

24-04511

Corrective Action

Documents

Resulting from

Inspection

CR-2024-

05832

05844

05850

05884

05887

05902

05904

05917

05918

05921

05934

05935

05936

05996

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

06010

06012

06040

06041

06054

06074

06164

06166

06168

06170

06192

06196

06197

201

Drawings

RE-0001V

25DC One Line Diagram, Sheet 1

Revision 37

Engineering

Evaluations

2-04

CFR Part 21 Masoneilan Evaluation

2/04/2012

EER-601419582

U1/U2 RWST Boron/Instrument Mission Time

Revision 0

EER-601448014

Evaluate Out-of-Tolerance PCV-1RC-456

05/02/2024

Miscellaneous

1OST-13

Quench Spray Pump [QS-P-1A] Test

07/07/2022

1OST-13.1

Quench Spray Pump [1QS-P1A] Test

07/29/2024

1OST-47.03G

Containment Isolation and ASME Sections XI Test

07/29/2024

2502.190-230-

001

Operation and Maintenance Manual for Emergency Diesel

Generators

08/07/2019

2OST-11.01

LHSI Pump Full Flow Test

2/26/2023

2OST-36.2

Emergency Diesel Generator [2EGS*EG2-2] Monthly Test

06/26/2024

2OST-36.2

Emergency Diesel Generator [2EGS*EG2-2] Monthly Test

07/24/2024

2OST-36.23

EDG Simultaneous Start Test

10/30/2021

2OST-36.2A

Emergency Diesel Generator [2EGS*EG2-2] 9-Hour Test

05/13/2023

NUREG-1929

Safety Evaluation Report Related to the License Renewal of

Beaver Valley Power Station

October

2009

RAD/50.59

Screen 23-01338

RWST Level Sensing Lines Cold Weather Protection

Verification

Revision 0

NDE Reports

Eddy Current

Report 55140680

U2 RSS-E21B, 1R22

10/25/2021

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Procedures

BVBP-OPS-0029

Control of Critical Actions

Revision 12

NOP-OP-1013-02 Time Critical Operator Actions for Actuating CREVs

Revision 0

NOP-OP-1013-02 Time Critical Operator Actions for Terminating Uncontrolled

Charging flow to the RCS

Revision 0

Work Orders

200557370

200761059

200943046

200837181

200476965

200800869

200848185

200849618

200849729

200849744

200850565

200853218

200744228

200795833

200797763

200832743

200650530