IR 05000334/2024010
| ML24232A192 | |
| Person / Time | |
|---|---|
| Site: | Beaver Valley |
| Issue date: | 08/20/2024 |
| From: | Mel Gray Division of Operating Reactors |
| To: | Blair B Vistra Operations Company |
| References | |
| IR 2024010 | |
| Download: ML24232A192 (1) | |
Text
August 20, 2024
SUBJECT:
BEAVER VALLEY POWER STATION, UNITS 1 AND 2 - COMPREHENSIVE ENGINEERING TEAM INSPECTION - INSPECTION REPORT 05000334/2024010 AND 05000412/2024010
Dear Barry Blair:
On August 1, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Beaver Valley Power Station, Units 1 and 2 and discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Mel Gray, Chief Engineering Branch 1 Division of Operating Reactor Safety
Docket Nos. 05000334 and 05000412 License Nos. DPR-66 and NPF-73
Enclosure:
As stated
Inspection Report
Docket Numbers:
05000334 and 05000412
License Numbers:
Report Numbers:
05000334/2024010 and 05000412/2024010
Enterprise Identifier: I-2024-010-0025
Licensee:
Vistra Operations Company, LLC
Facility:
Beaver Valley Power Station, Units 1 and 2
Location:
Shippingport, PA
Inspection Dates:
July 15, 2024 to August 1, 2024
Inspectors:
J. Brand, Senior Reactor Inspector
P. Cataldo, Senior Reactor Inspector
J. Lilliendahl, Senior Emergency Response Coordinator
K. Mangan, Senior Reactor Inspector
D. McHugh, Reactor Inspector
J. Schoppy, Senior Reactor Inspector
A. Turilin, Reactor Inspector
Approved By:
Mel Gray, Chief
Engineering Branch 1
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a comprehensive engineering team inspection at Beaver Valley Power Station, Units 1 and 2, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
===71111.21M - Comprehensive Engineering Team Inspection
The inspectors evaluated the following components and listed applicable attributes, permanent modifications, Title 10 of the Code of Federal Regulations (10 CFR) 50.59 screening and/or evaluations, and operating experience:
Structures, Systems, and Components (SSCs) (IP section 03.01)===
For each component or operator action sample listed below, the team reviewed licensing and design basis documents and a sampling of applicable operator actions, periodic testing results, corrective action program documents, internal and external operating experience, preventive and corrective maintenance work orders, modifications, and aging management programs. Additionally, the team performed walkdowns of the component or procedure and conducted interviews with licensee personnel.
The team used the attributes contained in IP 71111.21M, Appendix A, Component Review Attributes, such as those listed below as guidance. Specifically, the team evaluated these attributes as per 71111.21M, Appendix B, Component Design Review Considerations and
===71111.21M, Appendix C, Component Walkdown Considerations.
- (1) Risk significant operator action - Unit 1 weather-related Loss-of-Offsite Power
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Components installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
- (2) Unit 1 Power-Operated Relief Valve, 1-PCV-1RC-456
- Air and nitrogen will be available and unimpeded during accident/event conditions.
- Air, nitrogen, and electric, including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Heat will be adequately removed from major components.
- Components installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
- Performance capability of selected components have not been degraded through modifications.
- (3) Unit 1 Recirculation Spray Heat Exchanger "1D," River Water Inlet Isolation Valve, MOV-1RW-104D
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Components installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
- Performance capability of selected components have not been degraded through modifications.
- (4) Unit 1 Quench Spray Pump, 1QS-P1A
- Process medium (water) will be available and unimpeded during accident/event conditions.
- Energy sources (electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Heat will be adequately removed from major components.
- Components installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
- Performance capability of selected components have not been degraded through modifications.
- (5) Unit 1 Safety-Related 125 VDC Battery, No. 1-2 (Bus 1-2)
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Components installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
- (6) Unit 2 Emergency Diesel Generator, 2-2
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Heat will be adequately removed from major components.
- Installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Performance capability of selected components have not been degraded through modifications.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
- (7) Unit 2 Low Head Safety Injection Pump, 2SIS-P21A
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Heat will be adequately removed from major components.
- Components installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
- Performance capability of selected components have not been degraded through modifications.
- (8) Unit 2 Charging Pump, 2CHS-P21A
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Energy sources (fuel, air, steam, electricity), including those used for control functions, will be available and adequate during accident/event conditions.
- Components installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
- (9) Unit 2 Turbine-Driven Auxiliary Feedwater Pump, 2FWE-P22
- Water will be available and unimpeded during accident/event conditions.
- Steam supply will be available and adequate during accident/event conditions.
- Component controls will be functional and provide desired control during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Heat will be adequately removed from major components.
- Components installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
- Performance capability of selected components have not been degraded through modifications.
- (10) Unit 2 Recirculation Spray Heat Exchanger, 2RSS-E21B
- Process medium (water, air, electrical signal) will be available and unimpeded during accident/event conditions.
- Operating procedures (normal, abnormal, or emergency) are consistent with operator actions for accident/event conditions.
- Instrumentation and alarms are available to operators for making necessary decisions.
- Heat will be adequately removed from major components.
- Components installed configuration will support its design basis function under accident/event conditions.
- Component operation and alignments are consistent with design and licensing basis assumptions.
- Design bases and design assumptions have been appropriately translated into design calculations and procedures.
- Acceptance criteria for tested parameters are supported by calculations or other engineering documents to ensure that design and licensing bases are met.
- Tests and/or analyses validate component operation under accident/event conditions.
- Potential degradation is monitored or prevented.
- Equipment qualification is suitable for the environment expected under all conditions.
- Equipment is adequately protected from environmental hazards.
- Component inputs and outputs are suitable for application and will be acceptable under accident/event conditions.
- Performance capability of selected components have not been degraded through modifications.
Modifications (IP section 03.02)===
- (1) Unit 1 EC-20-0012-002: Overload Heater Replacement for MCC-1-41-1M
- (2) Unit 1 EC-21-0022-001: Upgrade MCC-1-1-Q Cutler Hammer Components
- (4) Unit 2 EC-22-1072-001: Thermal Shield Support Block Bolt Bore Internal Thread Staking
- (5) Unit 2 EC-22-1046-001: Through-wall Defect Removal, Line BV-WR-20-151-Q3
10 CFR 50.59 Evaluations/Screening (IP section 03.03) (10 Samples)
(1)18-00478: Implementation of License Amendment /Setting Changes for BV1 Degraded Voltage and Loss of Voltage Protection (2)22-0086-001/2/3: Piping Material Change Downstream of Unit 1 AFWP Restricting Orifices (3)22-0073-001/002: U1 Diesel Tank Level Setpoint Change (4)22-1073-001: Tubing Downstream of 1RC-272 Support Relocation (5)22-1076-001: Installation of Permanent Shielding at 1SW-24 (6)22-0049-001/002/003: Pressure Switch Setpoint Changes for U1 FWIV HYV-1FW-100A/B/C (7)20-0117-001: Replace U2 SWS Emergency Diesel Generator Heat Exchanger Inlet Valves (8)21-0077-001: Protect Fire Protection Lines from Future Wear
- (9) Unit 2, PAF-17-00193/Screen 17-00374/16-00913: Associated with CR-2023-05501 (10)50.59 associated with Compensatory Measure to Maintain Operability for U2 RWST 2QSS-TK21, from CR-2023-06404
Operating Experience Samples (IP section 03.04) (3 Samples)
- (1) NRC IN 2020-04: Operating Experience Regarding Failure of Fire Protection Main Yard Piping
- (2) NRC IN 2021-03: Operating Experience Related to DAEC Derecho Event on August 10, 2020
- (3) NRC IN 2023-01: Risk Insights for High Energy Arcing Faults Operating Experience and Analyses
INSPECTION RESULTS
No findings were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On August 1, 2024, the inspectors presented the comprehensive engineering team inspection results to Barry Blair, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
71111.21M Calculations
10080-E-048
Emergency Diesel Generator Loading with Station Blackout
Revision 16
10080-N-862
Auxiliary Feedwater Pump Performance
Revision 0
211-N-423
Determine the Available NPSH for Low Head Safety
Injection (LHSI) Pumps at Design Flow
Revision 0
8700-DMC-3523
Quench Spray System Performance
Revision 2
8700-E-202
DC System Management Battery 1-2 - Battery Charger 1-2
Revision 3
BV-10080-N-824
Recirculation Spray Heat Exchanger Inputs for MAAP
Containment Analysis
Revision 1
DMC-1516
Determination of the Valve Total Required Thrust, Actuator
Capability and Margin Assessment for AOVs PCV-1RC-
455C, D & 456
Revision 2,
Addendum 1
Corrective Action
Documents
CR-
2011-05786
2013-00419
2017-07594
2018-07705
20-04803
20-06052
20-08083
20-09580
21-08267
21-09187
22-00253
22-00542
22-01653
22-05250
22-05564
22-07907
22-08878
23-00246
23-01707
23-02575
23-03005
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
23-03077
23-03128
23-03906
23-04171
23-04462
23-05492
23-05501
23-05660
23-06861
23-09188
24-00897
24-00966
24-02299
24-02955
24-02967
24-02972
24-02973
24-03488
24-03785
24-04511
Corrective Action
Documents
Resulting from
Inspection
CR-2024-
05832
05844
05850
05884
05887
05902
05904
05917
05918
05921
05934
05935
05936
05996
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
06010
06012
06040
06041
06054
06074
06164
06166
06168
06170
06192
06196
06197
201
Drawings
RE-0001V
25DC One Line Diagram, Sheet 1
Revision 37
Engineering
Evaluations
2-04
CFR Part 21 Masoneilan Evaluation
2/04/2012
EER-601419582
U1/U2 RWST Boron/Instrument Mission Time
Revision 0
EER-601448014
Evaluate Out-of-Tolerance PCV-1RC-456
05/02/2024
Miscellaneous
Quench Spray Pump [QS-P-1A] Test
07/07/2022
1OST-13.1
Quench Spray Pump [1QS-P1A] Test
07/29/2024
1OST-47.03G
Containment Isolation and ASME Sections XI Test
07/29/2024
2502.190-230-
001
Operation and Maintenance Manual for Emergency Diesel
Generators
08/07/2019
2OST-11.01
LHSI Pump Full Flow Test
2/26/2023
2OST-36.2
Emergency Diesel Generator [2EGS*EG2-2] Monthly Test
06/26/2024
2OST-36.2
Emergency Diesel Generator [2EGS*EG2-2] Monthly Test
07/24/2024
2OST-36.23
EDG Simultaneous Start Test
10/30/2021
2OST-36.2A
Emergency Diesel Generator [2EGS*EG2-2] 9-Hour Test
05/13/2023
Safety Evaluation Report Related to the License Renewal of
Beaver Valley Power Station
October
2009
RAD/50.59
Screen 23-01338
RWST Level Sensing Lines Cold Weather Protection
Verification
Revision 0
NDE Reports
Eddy Current
Report 55140680
U2 RSS-E21B, 1R22
10/25/2021
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Procedures
BVBP-OPS-0029
Control of Critical Actions
Revision 12
NOP-OP-1013-02 Time Critical Operator Actions for Actuating CREVs
Revision 0
NOP-OP-1013-02 Time Critical Operator Actions for Terminating Uncontrolled
Charging flow to the RCS
Revision 0
Work Orders
200557370
200761059
200943046
200837181
200476965
200800869
200848185
200849618
200849729
200849744
200850565
200853218
200744228
200795833
200797763
200832743
200650530