|
|
Line 37: |
Line 37: |
| The enclosed inspection plan lists the inspections scheduled through December 31, 2015. | | The enclosed inspection plan lists the inspections scheduled through December 31, 2015. |
|
| |
|
| Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review | | Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. In addition to baseline inspections, the NRC will perform IP 71003, "Post-Approval Site Inspection for License Renewal," and IP 60855, "Operation of an Independent Spent Fuel Storage Installation (ISFSI)." The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possi ble to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security- |
| . In addition to baseline inspections, the NRC will perform IP 71003, "Post-Approval Site Inspection for License Renewal," and IP 60855, "Operation of an Independent Spent Fuel Storage Installation (ISFSI)." The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possi ble to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security- | |
| related inspections, which will be sent via separate, non-publicly available correspondence. | | related inspections, which will be sent via separate, non-publicly available correspondence. |
|
| |
|
Line 62: |
Line 61: |
| ML14241A040 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME TSetzer/TCS ABurritt/ALB HNieh/HKN DATE 08/20/14 08/25/14 08/28/14 | | ML14241A040 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME TSetzer/TCS ABurritt/ALB HNieh/HKN DATE 08/20/14 08/25/14 08/28/14 |
|
| |
|
| Page 1 of 2 08/19/2014 10:32:08Report 22 UnitNumberPlanned Dates Start EndInspection ActivityTitleNo. of Staff on SiteFitzPatrickInspection / Activity Plan 07/01/2014 | | Page 1 of 2 08/19/2014 10:32:08 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on Site FitzPatrickInspection / Activity Plan 07/01/2014 |
| -12/31/20159/22EXAM-INITIAL OL EXAM (2) | | -12/31/20159/22EXAM-INITIAL OL EXAM (2) |
| 41 FY14-FITZPATRICK INITIAL OPERATOR LICENSING EXAM (2ND)
| | 4 1 FY14-FITZPATRICK INITIAL OPERATOR LICENSING EXAM (2ND) |
| U0188808/18/2014 08/22/2014 1 FY14-FITZPATRICK INITIAL OPERATOR LICENSING EXAM (2ND)
| | U01888 08/18/2014 08/22/2014 1 FY14-FITZPATRICK INITIAL OPERATOR LICENSING EXAM (2ND) |
| U0188809/22/2014 10/02/2014EP PROG-EP PROGRAM INSPECTION 11 IPAlert and Notification System Testing711140207/07/201407/11/2014 1 IPEmergency Preparedness Organization Staffing and Augmentation System711140307/07/201407/11/2014 1 IPCorrection of Emergency Preparedness Weaknesses and Deficiencies711140507/07/201407/11/201471124-RADIATION SAFETY INSPECTION 11 IPRadiation Monitoring Instrumentation71124.0507/14/2014 07/18/2014 71003-LR COMMITMENTS INSP PHASE 2 31 IPPost-Approval Site Inspection for License Renewal 7100308/11/2014 08/15/2014 1 IPPost-Approval Site Inspection for License Renewal 7100308/25/2014 08/29/20147111108G-INSERVICE INSPECTION 11 IPInservice Inspection Activities - BWR7111108G09/03/2014 09/10/201471124-RADIATION SAFETY 11 IPRadiological Hazard Assessment and Exposure Controls71124.0109/01/2014 09/05/2014 1 IPOccupational ALARA Planning and Controls71124.0209/01/2014 09/05/2014 1 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0309/01/2014 09/05/2014 1 IPOccupational Dose Assessment71124.0409/01/2014 09/05/2014 1 IPPerformance Indicator Verification7115109/01/2014 09/05/201471124-RAD SAFETY INSP 11 IPRadiological Hazard Assessment and Exposure Controls71124.0111/17/201411/21/2014 1 IPOccupational ALARA Planning and Controls71124.0211/17/201411/21/2014 1 IPRadiation Monitoring Instrumentation71124.0511/17/201411/21/2014 TRI FI-TRIENNIAL FIRE PROTECTION 51 IPFire Protection [Triennial]7111105T12/01/2014 12/05/2014 1 IPFire Protection [Triennial]7111105T12/15/2014 12/19/2014 ISFSI-ISFSI OPERATIONAL INSPECTION 11 IPOperation Of An ISFSI 6085503/01/2015 04/30/2015 1 IPOperation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.103/01/2015 04/30/20158/3EXAM-INITIAL OL EXAM 41 FY15-FITZ INITIAL OPERATOR LICENSING EXAM U0190707/06/2015 08/10/2015 1 FY15-FITZ INITIAL OPERATOR LICENSING EXAM U0190708/03/2015 08/07/2015 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
| | U01888 09/22/2014 10/02/2014EP PROG-EP PROGRAM INSPECTION 1 1 IP A lert and Notification System Testing7111402 07/07/201407/11/2014 1 IP Emergency Preparedness Organization Staffing and Augmentation System7111403 07/07/201407/11/2014 1 IP Correction of Emergency Preparedness Weaknesses and Deficiencies7111405 07/07/201407/11/201471124-RADIATION SAFETY INSPECTION 1 1 IP Radiation Monitoring Instrumentation71124.05 07/14/2014 07/18/2014 71003-LR COMMITMENTS INSP PHASE 2 3 1 IP Post-Approval Site Inspection for License Renewal 7100308/11/2014 08/15/2014 1 IP Post-Approval Site Inspection for License Renewal 71003 08/25/2014 08/29/20147111108G-INSERVICE INSPECTION 1 1 IP Inservice Inspection Activities - BWR7111108G 09/03/2014 09/10/201471124-RADIATION SAFETY 1 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 09/01/2014 09/05/2014 1 IP Occupational ALARA Planning and Controls71124.02 09/01/2014 09/05/2014 1 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 09/01/2014 09/05/2014 1 IP Occupational Dose Assessment71124.04 09/01/2014 09/05/2014 1 IP Performance Indicator Verification71151 09/01/2014 09/05/201471124-RAD SAFETY INSP 1 1 IP Radiological Hazard Assessment and Exposure Controls71124.0111/17/201411/21/2014 1 IP Occupational ALARA Planning and Controls71124.0211/17/201411/21/2014 1 IP Radiation Monitoring Instrumentation71124.0511/17/201411/21/2014 TRI FI-TRIENNIAL FIRE PROTECTION 5 1 IP Fire Protection [Triennial]7111105T 12/01/2014 12/05/2014 1 IP Fire Protection [Triennial]7111105T 12/15/2014 12/19/2014 ISFSI-ISFSI OPERATIONAL INSPECTION 1 1 IP Operation Of An ISFSI 60855 03/01/2015 04/30/2015 1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 03/01/2015 04/30/20158/3EXAM-INITIAL OL EXAM 4 1 FY15-FITZ INITIAL OPERATOR LICENSING EXAM U01907 07/06/2015 08/10/2015 1 FY15-FITZ INITIAL OPERATOR LICENSING EXAM U01907 08/03/2015 08/07/2015 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures. |
|
| |
|
| Page 2 of 2 08/19/2014 10:32:08Report 22 UnitNumberPlanned Dates Start EndInspection ActivityTitleNo. of Staff on SiteFitzPatrickInspection / Activity Plan 07/01/2014 | | Page 2 of 2 08/19/2014 10:32:08 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on Site FitzPatrickInspection / Activity Plan 07/01/2014 |
| -12/31/201571124-RAD SAFETY INSPECTION 11 IPRadiological Hazard Assessment and Exposure Controls71124.0104/06/2015 04/10/2015 1 IPOccupational ALARA Planning and Controls71124.0204/06/2015 04/10/2015 1 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0304/06/2015 04/10/2015 1 IPOccupational Dose Assessment71124.0404/06/2015 04/10/2015 1 IPPerformance Indicator Verification7115104/06/2015 04/10/2015 MODS-PERMANENT PLANT MODIFICATIONS 31 IPEvaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T06/01/2015 06/05/20157111107T-TRIENNIAL HEAT SINK 11 IPHeat Sink Performance7111107T06/08/2015 06/12/2015 MODS-PERMANENT PLANT MODIFICATIONS 31 IPEvaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T06/15/2015 06/19/201571124.07-RAD SAFETY INSPECTION 11 IPRadiological Environmental Monitoring Program71124.0707/20/2015 07/24/2015 1 IPPerformance Indicator Verification7115107/20/2015 07/24/201571124-RAD SAFETY INSPECTION 11 IPRadiological Hazard Assessment and Exposure Controls71124.0109/14/2015 09/18/2015 1 IPOccupational ALARA Planning and Controls71124.0209/14/2015 09/18/2015 1 IPIn-Plant Airborne Radioactivity Control and Mitigation71124.0309/14/2015 09/18/2015 1 IPOccupational Dose Assessment71124.0409/14/2015 09/18/2015 EP-EP EXERCISE 51 IPExercise Evaluation - Hostile Action (HA) Event711140710/19/2015 10/23/2015 1 IPExercise Evaluation - Scenario Review711140810/19/2015 10/23/201571124-RAD SAFETY INSP 11 IPRadiological Hazard Assessment and Exposure Controls71124.0111/16/201511/20/2015 1 IPOccupational ALARA Planning and Controls71124.0211/16/201511/20/2015 1 IPRadiation Monitoring Instrumentation71124.0511/16/201511/20/2015 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures. | | -12/31/201571124-RAD SAFETY INSPECTION 1 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 04/06/2015 04/10/2015 1 IP Occupational ALARA Planning and Controls71124.02 04/06/2015 04/10/2015 1 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 04/06/2015 04/10/2015 1 IP Occupational Dose Assessment71124.04 04/06/2015 04/10/2015 1 IP Performance Indicator Verification71151 04/06/2015 04/10/2015 MODS-PERMANENT PLANT MODIFICATIONS 3 1 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 06/01/2015 06/05/20157111107T-TRIENNIAL HEAT SINK 1 1 IP Heat Sink Performance7111107T 06/08/2015 06/12/2015 MODS-PERMANENT PLANT MODIFICATIONS 3 1 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 06/15/2015 06/19/201571124.07-RAD SAFETY INSPECTION 1 1 IP Radiological Environmental Monitoring Program71124.07 07/20/2015 07/24/2015 1 IP Performance Indicator Verification71151 07/20/2015 07/24/201571124-RAD SAFETY INSPECTION 1 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 09/14/2015 09/18/2015 1 IP Occupational ALARA Planning and Controls71124.02 09/14/2015 09/18/2015 1 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 09/14/2015 09/18/2015 1 IP Occupational Dose Assessment71124.04 09/14/2015 09/18/2015 EP-EP EXERCISE 5 1 IP Exercise Evaluation - Hostile Action (HA) Event7111407 10/19/2015 10/23/2015 1 IP Exercise Evaluation - Scenario Review7111408 10/19/2015 10/23/201571124-RAD SAFETY INSP 1 1 IP Radiological Hazard Assessment and Exposure Controls71124.0111/16/201511/20/2015 1 IP Occupational ALARA Planning and Controls71124.0211/16/201511/20/2015 1 IP Radiation Monitoring Instrumentation71124.0511/16/201511/20/2015 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures. |
| }} | | }} |
|
---|
Category:Inspection Plan
MONTHYEARIR 05000333/20240052024-08-29029 August 2024 Updated Inspection Plan for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2024005) ML24018A0012024-01-18018 January 2024 Notification of Commercial Grade Dedication Inspection (05000333/2024010) and Request for Information IR 05000333/20230052023-08-31031 August 2023 Updated Inspection Plan for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2023005) ML23164A0322023-06-13013 June 2023 Request for Information for a Biennial Problem Identification and Resolution Inspection; Inspection Report 05000333/2023010 ML23152A0042023-06-0101 June 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000333/2023401 IR 05000333/20220062023-03-0101 March 2023 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2022006) ML22321A0102022-11-17017 November 2022 Notification of Conduct of a Fire Protection Team Inspection IR 05000333/20220052022-08-31031 August 2022 Updated Inspection Plan for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2022005) IR 05000333/20210062022-03-0202 March 2022 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2021006) IR 05000333/20220102022-01-0505 January 2022 Information Request for a Triennial Baseline Design Bases Assurance Inspection (Team); Inspection Report 05000333/2022010 IR 05000333/20210052021-09-0101 September 2021 Updated Inspection Plan for the James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2021005) IR 05000333/20200062021-03-0303 March 2021 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2020006) ML21041A1932021-02-10010 February 2021 Request for Information for a Triennial Baseline Design-Basis Capability of Power-Operated Valves Under 10 CFR 50.55a Requirements Inspection; Inspection Report (05000333/2021011) IR 05000333/20200052020-08-31031 August 2020 Updated Inspection Plan for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2020005) IR 05000333/20190062020-03-0303 March 2020 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2019006) ML19326A9262019-11-22022 November 2019 Notification of Conduct of a Fire Protection Team Inspection IR 05000333/20190052019-08-28028 August 2019 Updated Inspection Plan (Inspection Report 05000333/2019005) IR 05000333/20180062019-03-0404 March 2019 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2018006) IR 05000333/20180052018-08-28028 August 2018 Updated Inspection Plan (Inspection Report 05000333/2018005) IR 05000333/20170062018-02-28028 February 2018 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Reports 05000333/2017006, 05000333/2017402, and 05000333/2017501) IR 05000333/20170052017-08-28028 August 2017 Updated Inspection Plan for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2017005) IR 05000333/20160062017-03-0101 March 2017 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2016006) IR 05000333/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2016005) IR 05000333/20150062016-03-0202 March 2016 2015 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2015006) IR 05000333/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2015005) IR 05000333/20140012015-03-0404 March 2015 2014 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2014001)(w/Inspection Plan) ML14247A4532014-09-0404 September 2014 Fitzp Notification of Conduct of a Triennial Fire Protection Baseline Inspection - 90 Day Letter Rev 1 IR 05000333/20140062014-09-0202 September 2014 Mid-Cycle Assessment Letter and Inspection Plan 2014 (ROP-15) - James A. FitzPatrick Nuclear Power Plant (Report 05000333/2014006) ML14177A7752014-06-24024 June 2014 Notification of Conduct of a Triennial Fire Protection Baseline Inspection IR 05000333/20130012014-03-0404 March 2014 2013 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2013001)(w/Inspection Plan) IR 05000333/20130062013-09-0303 September 2013 Mid-Cycle Performance Review and Inspection Plan 2013 (ROP-14) - James A. FitzPatrick Nuclear Power Plant (Report 05000333/2013006) IR 05000333/20120012013-03-0404 March 2013 Annual Assessment Letter for James A. Fitzpatrick Nuclear Power Plant (Report 05000333-12-001) ML12244A3412012-09-0404 September 2012 Mid-Cycle Performance Review and Inspection Plan - 2013 James A. FitzPatrick Nuclear Power Plant IR 05000333/20110012012-03-0505 March 2012 Annual Assessment Letter (Report 05000333/2011001) ML1124208192011-09-0101 September 2011 Mid-Cycle Performance Review and Inspection Plan 2011 - James A. Fitzpatrick Nuclear Power Plant IR 05000333/20100012011-03-0404 March 2011 Annual Assessment Letter for James A. FitzPatrick Nuclear Power Plant (Report 05000333/2010001) ML1024402772010-09-0101 September 2010 Mid-Cycle Performance Review and Inspection Plan 2010 - James A. Fitzpatrick Nuclear Power Plant ML1006214222010-03-0303 March 2010 Annual Assessment Letter - James A. Fitzpatrick, (IR 05000333-10-001) ML0924401472009-09-0101 September 2009 Mid-Cycle Performance Review and Inspection Plan - James A. FitzPatrick Nuclear Power Plant IR 05000333/20090012009-03-0404 March 2009 Annual Assessment Letter, James A. FitzPatrick Nuclear Power Plant (Report 05000333/2009001) ML0824703132008-09-0202 September 2008 Mid-Cycle Performance Review and Inspection Plan, James A. Fitzpatrick IR 05000333/20080012008-03-0303 March 2008 Annual Assessment Letter - James A. FitzPatrick Nuclear Power Plant (Report 05000333/2008001) ML0734709442007-12-13013 December 2007 ROP 8 - Fitzpatrick - Change to Inspection Plan, 12/13/07 ML0724309402007-08-31031 August 2007 Mid-Cycle Performance Review and Inspection Plan - James A. FitzPatrick Nuclear Power Plant IR 05000333/20070012007-03-0202 March 2007 Annual Assessment Letter - James A. Fitzpatrick Nuclear Power Plant (Report 05000333-07-001) ML0606202432006-03-0202 March 2006 Annual Assessment Letter - James A. FitzPatrick Nuclear Power Station (Report 05-333/2006001) ML0506105112005-03-0202 March 2005 Annual Assessment Letter 2005001-Fitzpatrick ML0424402522004-08-30030 August 2004 FitzPatrick Station ROP5 Mid-Cycle Performance Review and Inspection Plan ML0323902312003-08-27027 August 2003 2003 - Mid-Cycle Performance Review and Inspection Plan for FitzPatrick Nuclear Power Plant ML0305807282003-03-0303 March 2003 2003 - Annual Assessment Letter - Fitzpatrick Nuclear Power Plant (50-333/2003-001) 2024-08-29
[Table view] Category:Letter
MONTHYEARIR 05000333/20240902024-10-29029 October 2024 Final Significance Determination of a White Finding with Assessment Follow-Up and Notice of Violation; Inspection Report 05000333/2024090 JAFP-24-0055, Response to Request for Additional Information for License Amendment Request to Add Temporary Change to TS 3.3.2.1, Condition C, Control Rod Block Instrumentation2024-10-29029 October 2024 Response to Request for Additional Information for License Amendment Request to Add Temporary Change to TS 3.3.2.1, Condition C, Control Rod Block Instrumentation IR 05000333/20244022024-10-28028 October 2024 Material Control and Accounting Program Inspection Report 05000333/2024402 (Cover Letter Only) ML24276A1332024-10-17017 October 2024 Issuance of Amendment No. 357 Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision-4, and Administrative Changes ML24282B0302024-10-11011 October 2024 Project Manager Assignment RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24207A0192024-10-0909 October 2024 SE Addendum Related to the License Amendment No. 338 for Implementation of the Alternative Source Term (DPO-2021-001) JAFP-24-0051, Reply to Preliminary White Finding and Apparent Violation in NRC Inspection Report 05000333/2024011; EA-24-0882024-10-0303 October 2024 Reply to Preliminary White Finding and Apparent Violation in NRC Inspection Report 05000333/2024011; EA-24-088 ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24270A0742024-09-30030 September 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, & Opportunity for a Hearing (EPID L-2024-LLA-0134) - LTR ML24270A1452024-09-26026 September 2024 Notice of Enforcement Discretion for James A. Fitzpatrick Nuclear Power Plant JAFP-24-0046, Request for Enforcement Discretion for Technical Specification (TS) 3.3.2.1 Control Rod Block Instrumentation2024-09-25025 September 2024 Request for Enforcement Discretion for Technical Specification (TS) 3.3.2.1 Control Rod Block Instrumentation JAFP-24-0047, License Amendment Request – Temporary Addition to TS 3.3.2.1 Condition C, Control Rod Block Instrumentation to Support Upgrade to Rod Worth Minimizer Software2024-09-25025 September 2024 License Amendment Request – Temporary Addition to TS 3.3.2.1 Condition C, Control Rod Block Instrumentation to Support Upgrade to Rod Worth Minimizer Software JAFP-24-0045, Supplemental Information for License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications2024-09-20020 September 2024 Supplemental Information for License Amendment Request to Revise Technical Specifications to Adopt TSTF-529, Clarify Use and Application Rules, Revision 4, and Administrative Changes to the Technical Specifications IR 05000333/20240112024-09-19019 September 2024 Follow-up to Inspection Procedure 71153 Report 05000333/2024011 and Preliminary White Finding and Apparent Violation JAFP-24-0044, Core Operating Limits Report Cycle 272024-09-16016 September 2024 Core Operating Limits Report Cycle 27 JAFP-24-0043, Revision to Commitment Relating to Resolution of Anchor Darling Double Disc Gate Valve Part 21 Issues2024-09-12012 September 2024 Revision to Commitment Relating to Resolution of Anchor Darling Double Disc Gate Valve Part 21 Issues 05000333/LER-2024-002, Reactor Protection System Electric Power Monitoring System Trip Caused Primary Containment Isolation2024-09-0404 September 2024 Reactor Protection System Electric Power Monitoring System Trip Caused Primary Containment Isolation ML24165A0382024-09-0404 September 2024 Issuance of Amendment No. 356 Update Fuel Handling Accident Analysis IR 05000333/20240052024-08-29029 August 2024 Updated Inspection Plan for James A. Fitzpatrick Nuclear Power Plant (Report 05000333/2024005) 05000333/LER-2024-001-01, EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket2024-08-21021 August 2024 EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000333/20240022024-08-0707 August 2024 Integrated Inspection Report 05000333/2024002 JAFP-24-0034, 10 CFR 50.46 Annual Report2024-07-31031 July 2024 10 CFR 50.46 Annual Report ML24208A0492024-07-30030 July 2024 Notice of Consideration of Issuance of Amendments to Facility Operating Licenses and Proposed No Significant Hazards Consideration Determination (Letter) JAFP-24-0036, Supplement to License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis2024-07-29029 July 2024 Supplement to License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling Accident Analysis JAFP-24-0033, Response to Request for Information Pertaining to a Licensed Operator Positive Fitness-For-Duty Test2024-07-23023 July 2024 Response to Request for Information Pertaining to a Licensed Operator Positive Fitness-For-Duty Test IR 05000333/20244032024-07-18018 July 2024 Biennial Problem Identification and Resolution Inspection Report 05000333/2024403 (Cover Letter Only) IR 05000333/20244012024-07-15015 July 2024 Security Baseline Inspection 05000333/2024401 RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions ML24190A1932024-07-0909 July 2024 Correction Letter of Amendment No. 355 Revise Technical Specifications Section 3.4.3.1, Safety Relief Valves Setpoint Lower Tolerance IR 05000333/20240102024-07-0808 July 2024 Commercial Grade Dedication Inspection Report 05000333/2024010 ML24184A1662024-07-0303 July 2024 Senior Reactor and Reactor Operator Initial License Examinations ML24136A1162024-06-26026 June 2024 Issuance of Amendment No. 355 Revise Technical Specifications Section 3.4.3.1, Safety Relief Valves Setpoint Lower Tolerance 05000333/LER-2024-001, EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket2024-06-24024 June 2024 EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket ML24176A2412024-06-24024 June 2024 Licensed Operator Positive Fitness-for-Duty Test JAFP-24-0027, EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket2024-06-24024 June 2024 EDG Lube Oil Check Valve Bonnet Cap Leak Due to Failed Gasket RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations JAFP-24-0026, Supplement to License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (Srvs) Setpoint Lower Tolerance2024-06-12012 June 2024 Supplement to License Amendment Request to Modify Technical Specification Surveillance Requirement (SR) 3.4.3.1 Safety Relief Valves (Srvs) Setpoint Lower Tolerance ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 JAFP-24-0023, 2023 Annual Radiological Environmental Operating Report2024-05-0909 May 2024 2023 Annual Radiological Environmental Operating Report IR 05000333/20240012024-05-0909 May 2024 Integrated Inspection Report 05000333/2024001 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests JAFP-24-0020, 2023 Annual Radioactive Effluent Release Report2024-04-25025 April 2024 2023 Annual Radioactive Effluent Release Report JAFP-24-0019, 2023 REIRS Transmittal of NRC Form 52024-04-18018 April 2024 2023 REIRS Transmittal of NRC Form 5 ML24106A0152024-04-15015 April 2024 Request for Withholding Information from Public Disclosure Response to Request for Additional Information for License Amendment Request to Update the Technical Specification Bases to Change the Fuel Handling ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24107A6972024-04-12012 April 2024 Engine Systems, Inc Part 21 Report Re EMD Cylinder Liner Water Leak RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24068A0532024-03-28028 March 2024 Issuance of Amendment No. 354 Revise Technical Specifications Section 3.3.1.2, Source Range Monitors Instrumentation 2024-09-04
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BLVD., SUITE 100 KING OF PRUSSIA, PA 19406-2713 September 2, 2014
Mr. Lawrence Coyle Site Vice President Entergy Nuclear Northeast James A. FitzPatrick Nuclear Power Plant P. O. Box 110
Lycoming, NY 13093
SUBJECT: MID-CYCLE ASSESSMENT LETTER FOR JAMES A. FITZPATRICK NUCLEAR POWER PLANT (REPORT 05000333/2014006)
Dear Mr. Coyle:
On August 13, 2014, the U.S. Nuclear Regulatory Commission (NRC) completed its mid-cycle performance review of James A. FitzPatrick Nuclear Power Plant (FitzPatrick). The NRC reviewed the most recent quarterly performance indicators in addition to inspection results and enforcement actions from July 1, 2013 through June 30, 2014. This letter informs you of the
NRC's assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined that overall, FitzPatrick was operated in a manner that preserved public health and safety and met all cornerstone objectives. The NRC determined the performance at FitzPatrick during the most recent quarter was within the Regulatory Response Column of the NRC's Reactor Oversight Process (ROP) Action Matrix, because all inspec tion findings had very low safety significance (Green) and one performance indicator was of low to moderate safety significance (White) in the Initiating Events cornerstone. Specifically, the "Unplanned Power Changes per 7,000 Critical Hours" performance indicator exceeded the Green/White threshold value in the fourth quarter of 2012. From January 20 through 24, 2014, NRC inspectors conducted the onsite portion of a supplemental inspection for the White performance indicator in accordance with Inspection Procedure (IP) 95001, "Supplemental Inspection for One or Two White Inputs in a Strategic Performance Area." The NRC inspectors concluded that the corrective actions taken by FitzPatrick to preclude repetition of the unplanned power changes were not sufficient to meet the inspection objectives. As a result, the inspection was not closed and remains open until additional corrective actions, including the replacement of the condenser tubes during the current refueling outage, have been completed. The NRC will review Entergy's implementation of these additional corrective actions during a future inspection. The performance indicator will continue to be a White ROP Action Matrix input until the performance indicator results allow it to transition below the Green/White threshold. The NRC will notify you via separate correspondence when the plant will transition to the Licensee Response Column.
As a result of the Safety Culture Common Language Initiative, the terminology and coding of cross-cutting aspects were revised. All cross-cutting aspects identified during inspections conducted in calendar year 2014 reflect this revision to Inspection Manual Chapter (IMC) 0310. Cross-cutting aspects identified in 2013 using the 2013 terminology were converted to the latest revision in accordance with the cross-reference in IMC 0310 during the mid-cycle assessment review and evaluated for cross-cutting themes and potential substantive cross-cutting issues in accordance with IMC 0305.
The enclosed inspection plan lists the inspections scheduled through December 31, 2015.
Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the end-of-cycle performance review. In addition to baseline inspections, the NRC will perform IP 71003, "Post-Approval Site Inspection for License Renewal," and IP 60855, "Operation of an Independent Spent Fuel Storage Installation (ISFSI)." The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possi ble to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-
related inspections, which will be sent via separate, non-publicly available correspondence.
In response to the accident at Fukushima, the Commission issued Order EA-12-049, "Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events," which requires licensees to develop, implement, and maintain guidance and strategies to maintain or restore core cooling, containment, and spent fuel pool cooling capabilities following a beyond-design-basis external event. Additionally, the Commission issued Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," which requires licensees to have a reliable means of remotely monitoring wide-range Spent Fuel Pool levels to support effective prioritization of event mitigation and recovery actions in the event of a beyond-des ign-basis external event. The NRC is conducting audits of licensee efforts towards compliance with these Orders. This audit includes an onsite component in order for the NRC to evaluate licensee plans for complying with the Orders, as described in site-specific submittals, and to receive and review information relative to associated open items. This onsite activity will occur in the months prior to a declaration of compliance for the first unit at each site, and will aid staff in development of an ultimate Safety Evaluation for the site. The date for the onsite component at your site is being coordinated with your staff.
A site-specific audit plan for the visit will be provided in advance to allow sufficient time for
preparations.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) Part 2.390 of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records component of the NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact Arthur Burritt at (610)337-5069 with any questions you have regarding this letter.
Sincerely,/RA/ Ho K. Nieh Director Division of Reactor Projects
Docket No. 50-333 License No. DPR-59
Enclosure:
Inspection Plan
cc w/encl: Distribution via ListServ
ML14241A040 SUNSI Review Non-Sensitive Sensitive Publicly Available Non-Publicly Available OFFICE RI/DRP RI/DRP RI/DRP NAME TSetzer/TCS ABurritt/ALB HNieh/HKN DATE 08/20/14 08/25/14 08/28/14
Page 1 of 2 08/19/2014 10:32:08 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on Site FitzPatrickInspection / Activity Plan 07/01/2014
-12/31/20159/22EXAM-INITIAL OL EXAM (2)
4 1 FY14-FITZPATRICK INITIAL OPERATOR LICENSING EXAM (2ND)
U01888 08/18/2014 08/22/2014 1 FY14-FITZPATRICK INITIAL OPERATOR LICENSING EXAM (2ND)
U01888 09/22/2014 10/02/2014EP PROG-EP PROGRAM INSPECTION 1 1 IP A lert and Notification System Testing7111402 07/07/201407/11/2014 1 IP Emergency Preparedness Organization Staffing and Augmentation System7111403 07/07/201407/11/2014 1 IP Correction of Emergency Preparedness Weaknesses and Deficiencies7111405 07/07/201407/11/201471124-RADIATION SAFETY INSPECTION 1 1 IP Radiation Monitoring Instrumentation71124.05 07/14/2014 07/18/2014 71003-LR COMMITMENTS INSP PHASE 2 3 1 IP Post-Approval Site Inspection for License Renewal 7100308/11/2014 08/15/2014 1 IP Post-Approval Site Inspection for License Renewal 71003 08/25/2014 08/29/20147111108G-INSERVICE INSPECTION 1 1 IP Inservice Inspection Activities - BWR7111108G 09/03/2014 09/10/201471124-RADIATION SAFETY 1 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 09/01/2014 09/05/2014 1 IP Occupational ALARA Planning and Controls71124.02 09/01/2014 09/05/2014 1 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 09/01/2014 09/05/2014 1 IP Occupational Dose Assessment71124.04 09/01/2014 09/05/2014 1 IP Performance Indicator Verification71151 09/01/2014 09/05/201471124-RAD SAFETY INSP 1 1 IP Radiological Hazard Assessment and Exposure Controls71124.0111/17/201411/21/2014 1 IP Occupational ALARA Planning and Controls71124.0211/17/201411/21/2014 1 IP Radiation Monitoring Instrumentation71124.0511/17/201411/21/2014 TRI FI-TRIENNIAL FIRE PROTECTION 5 1 IP Fire Protection [Triennial]7111105T 12/01/2014 12/05/2014 1 IP Fire Protection [Triennial]7111105T 12/15/2014 12/19/2014 ISFSI-ISFSI OPERATIONAL INSPECTION 1 1 IP Operation Of An ISFSI 60855 03/01/2015 04/30/2015 1 IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 03/01/2015 04/30/20158/3EXAM-INITIAL OL EXAM 4 1 FY15-FITZ INITIAL OPERATOR LICENSING EXAM U01907 07/06/2015 08/10/2015 1 FY15-FITZ INITIAL OPERATOR LICENSING EXAM U01907 08/03/2015 08/07/2015 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
Page 2 of 2 08/19/2014 10:32:08 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on Site FitzPatrickInspection / Activity Plan 07/01/2014
-12/31/201571124-RAD SAFETY INSPECTION 1 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 04/06/2015 04/10/2015 1 IP Occupational ALARA Planning and Controls71124.02 04/06/2015 04/10/2015 1 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 04/06/2015 04/10/2015 1 IP Occupational Dose Assessment71124.04 04/06/2015 04/10/2015 1 IP Performance Indicator Verification71151 04/06/2015 04/10/2015 MODS-PERMANENT PLANT MODIFICATIONS 3 1 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 06/01/2015 06/05/20157111107T-TRIENNIAL HEAT SINK 1 1 IP Heat Sink Performance7111107T 06/08/2015 06/12/2015 MODS-PERMANENT PLANT MODIFICATIONS 3 1 IP Evaluations of Changes, Tests, and Experiments and Permanent Plant Modifications7111117T 06/15/2015 06/19/201571124.07-RAD SAFETY INSPECTION 1 1 IP Radiological Environmental Monitoring Program71124.07 07/20/2015 07/24/2015 1 IP Performance Indicator Verification71151 07/20/2015 07/24/201571124-RAD SAFETY INSPECTION 1 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 09/14/2015 09/18/2015 1 IP Occupational ALARA Planning and Controls71124.02 09/14/2015 09/18/2015 1 IP In-Plant Airborne Radioactivity Control and Mitigation71124.03 09/14/2015 09/18/2015 1 IP Occupational Dose Assessment71124.04 09/14/2015 09/18/2015 EP-EP EXERCISE 5 1 IP Exercise Evaluation - Hostile Action (HA) Event7111407 10/19/2015 10/23/2015 1 IP Exercise Evaluation - Scenario Review7111408 10/19/2015 10/23/201571124-RAD SAFETY INSP 1 1 IP Radiological Hazard Assessment and Exposure Controls71124.0111/16/201511/20/2015 1 IP Occupational ALARA Planning and Controls71124.0211/16/201511/20/2015 1 IP Radiation Monitoring Instrumentation71124.0511/16/201511/20/2015 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.