| title = Email from G. Thomas, NRR to D. Hoang, NRR Et Al. FW: North Anna Seismic Report - Summary Report of August 23/2011 Earthquake Response and Restart Readiness Determination Plan North Anna Power Station Units 1 and 2 and ISFSI
| title = Email from G. Thomas, NRR to D. Hoang, NRR Et Al. FW: North Anna Seismic Report - Summary Report of August 23/2011 Earthquake Response and Restart Readiness Determination Plan North Anna Power Station Units 1 and 2 and ISFSI
| author name = Thomas G A
| author name = Thomas G
| author affiliation = NRC/NRR/DE/EMCB
| author affiliation = NRC/NRR/DE/EMCB
| addressee name = Hoang D V, William J, Uribe J F
| addressee name = Hoang D, William J, Uribe J
| addressee affiliation = NRC/NRR/DE/EMCB
| addressee affiliation = NRC/NRR/DE/EMCB
| docket = 05000338, 05000339
| docket = 05000338, 05000339
Line 14: Line 14:
| page count = 9
| page count = 9
}}
}}
=Text=
{{#Wiki_filter:From:            Thomas. Georoe To:                Hoan. Dan; Jessuo William: i      Jua; Basavaraiu. Chakraoani
==Subject:==
FW: NORTH ANNA SEISMIC REPORT - Summary Report of August 23/ 2011 Earthquake Response and Restart Readiness Determination Plan North Anna Power Station Units 1 and 2 and ISFSI Date:              Monday, September 19, 2011 7:31:20 AM Attachments:      11-520 Earthouake Summary Reoort and Restart Plan Final.odf FYI or use.
From: Martin, Robert Sent: Sunday, September 18, 2011 9:18 AM To: Li, Yong; Farzam, Farhad; Tsirigotis, Alexander; Thomas, George; Ulses, Anthony; Casto, Greg; Bailey, Stewart; Dennig, Robert; Evans, Michele; Lubinski, John; Taylor, Robert; Murphy, Emmett; McGinty, Tim; Pham, Bo; Murphy, Martin; Lupold, Timothy; Mitchell, Matthew; McMurtray, Anthony; Wilson, George; Mathew, Roy; Cheok, Michael; Tate, Travis; Harrison, Donnie; Circle, Jeff; Klein, Alex; Holian, Brian; Galloway, Melanie; Auluck, Rajender; Pelton, David; Rosenberg, Stacey; McGinty, Tim; Thompson, Jon; Boger, Bruce; Leeds, Eric; Khanna, Meena; Kulesa, Gloria; Howe, Allen; Boyle, Patrick Cc: Bahadur, Sher; Weerakkody, Sunil
==Subject:==
NORTH ANNA SEISMIC REPORT - Summary Report of August 23/ 2011 Earthquake Response and Restart Readiness Determination Plan North Anna Power Station Units 1 and 2 and ISFSI From: Ginger L Rutherford [mailto:ginger.l.rutherford@dom.com]
Sent: Saturday, September 17, 2011 1:50 PM To: Cotton, Karen; Davis (NMSS), Jennifer; Hiland, Patrick; Khanna, Meena; Manoly, Kamal; acmilankm@aol.com; Mendiola, Anthony; Howe, Allen; Martin, Robert; McCoy, Gerald; Boyle, Patrick; Karwoski, Kenneth; Giitter, Joseph
==Subject:==
11-520 - Summary Report of August 23/ 2011 Earthquake Response and Restart Readiness Determination Plan North Anna Power Station Units 1 and 2 and ISFSI CONFIDENTI            ITY NOTICE:              is electronic messagec6fitains informatio                    ich may.
be legally co idential and/or pr eged and does notjy any case represent                                irmENERGY COMMOD.Y bid or offer r ating thereto which blfnds the sender wit ut an additional express/ ritten confirmati n to that effect. The* formation is inte                            solely for the individual or entity naij~ above and acces y anyone else is authorized. If y are not the)*itended recipie . any disclosure, co ing, distribution r use of the co nts of this information is prgibited and may be lawful. If you h e received this                                ctronic
  ,transmission i frror, please reply
* mediately to the ender that you                            e received the
/  message in      or, and delete it. ank you.
MEMORANDUM TO:                  Eric J. Leeds, Director Office of Nuclear Reactor Regulation FROM:                            Patrick L. Hiland, Director Division of Engineering
==SUBJECT:==
ACTION PLAN TO ADDRESS NORTH ANNA POWER STATION RESTART AS A RESULT OF AUGUST 23, 2011, EARTHQUAKE On August 23, 2011, the North Anna Power Station (NAPS) declared an Alert due to significant seismic activity onsite resulting from an earthquake which had a measured magnitude of 5.8.
On August 26, 2011, initial reviews of the data determined that the seismic activity potentially exceeded the NAPS Design Basis Earthquake magnitude value. Subsequently on August 26, 2011, the licensee declared all safety-related structures, systems and components inoperable and issued a 10 CFR 50.72 Notification.
In response to the recent seismic event, the staff is undertaking various initiatives to address plant restart activities at the NAPS, which includes an Augmented Inspection Team that was dispatched on August 31, 2011. In addition, the staff is in the process of identifying issues and questions for the licensee to consider in order to obtain NRC authorization for plant restart, in accordance with 10 CFR Part 100, Appendix A. The attached action plan describes and tracks the agency's ongoing initiatives related to the NAPS restart activities as a result of the recent seismic event.
==Enclosure:==
As stated CONTACT: Meena Khanna, NRR/DE/EMCB (301) 415-2150
MEMORANDUM TO:                      Eric J. Leeds, Director Office of Nuclear Reactor Regulation FROM:                                Patrick L. Hiland, Director Division of Engineering
==SUBJECT:==
ACTION PLAN TO ADDRESS NORTH ANNA POWER STATION RESTART AS A RESULT OF AUGUST 23, 2011, EARTHQUAKE On August 23, 2011, the North Anna Power Station (NAPS) declared an Alert due to significant seismic activity onsite resulting from an earthquake which had a measured magnitude of 5.8.
On August 26, 2011, initial reviews of the data determined that the seismic activity potentially exceeded the NAPS Design Basis Earthquake magnitude value. Subsequently on August 26, 2011, the licensee declared all safety-related structures, systems and components inoperable and issued a 10 CFR 50.72 Notification.
In response to the recent seismic event, the staff is undertaking various initiatives to address plant restart activities at the NAPS, which includes an Augmented Inspection Team that was dispatched on August 31, 2011. In addition, the staff is in the process of identifying issues and questions for the licensee to consider in order to obtain NRC authorization for plant restart in accordance with 10 CFR Part 100, Appendix A. The attached action plan describes and tracks the agency's ongoing initiatives related to the NAPS restart activities as a result of the recent seismic event.
==Enclosure:==
As stated CONTACT: Meena Khanna, NRR/DE/EMCB (301) 415-2150 INDICATE IN BOX: C*=COPY W/O ATTACHMENTIENCLOSURE, "E"=COPY W/ATTIENCL, *N'=NO COPY OFFICE      EMCB:DE            EMCB:DE          DORL:NRR          DSS:NRR            DCI:NRR    DLR:NRR NAME        MKhanna            KManoly          RMartin          WRuland            MEvans      BHolian 19/    /2011          9/  /2011        9/    /2011      9/  /2011          9/  /2011  9/  /2011 DATEj________________
OFFICEOFIELIZIZEIIIJIRIRIP DIRS:NRR            Region 11          DE:NRR    L    NRR NRRNR K  _
NAME        MCheok              LWert              PHiland          BBoger              JGrobe      ELeeds DATEI            2011          9/  /2011
_9/        9/    /2011      9/  /2011          9/  /2011
_      /Z011  -
NORTH ANNA POWER STATION RESTART ACTION PLAN Last Update: 9/13/2011 Lead Division: DE Supporting Divisions: DSS, DCI, DLR, DRA Supporting Offices: Region II, NMSS, NRO, RES TAC Nos. ME7050 and ME7051 Goal:
The goal of this action plan is to track the agency's ongoing initiatives related to the North Anna Power Station (NAPS) restart decision as a result of the recent seismic event on August 23, 2011.
==Background:==
On August 23, 2011, NAPS experienced a seismic event (5.8 magnitude earthquake reported by the U.S. Geological Survey) which resulted in a loss of offsite power and automatic reactor trip of both units. The licensee declared an Alert due to significant seismic activity at the site.
Subsequent to the earthquake, the licensee stabilized both units, restored offsite power, and retrieved the recorded ground motions at the site resulting from the seismic event, which were sent to the vendor for analysis. On August 26, 2011, initial reviews of the data determined that the seismic activity potentially exceeded the Design Basis Earthquake (DBE) spectrum at frequencies above 5 Hz. Therefore, this event was reportable per 10 CFR 50.72(b)(3)(ii)(B) for the nuclear power plant being in an unanalyzed condition that may have significantly'degraded plant safety.
The NAPS has two DBE, otherwise known as the Safe Shutdown Earthquake (SSE), ground motions, one for structures, systems, and components (SSCs) located on top of rock, which is anchored at 0.12 g, with the second DBE ground motion related to SSCs located on top of soil, which is anchored *:t        ',E Th9- N    ' *? *o          cr~7ing Operating Basis Earthquake (OBE) ground motion spectra, anchored at 0.09 g for soil and 0.06 g for rock. The Vendor has processed the initial seismic data. Preliminary results indicate certain measurements exceeded the SSE, at various frequencies above the limits reported in the final safety analysis report.
The current best estimate of the Peak Ground Acceleration (PGA) for the NAPS site, resulting from the recent seismic event, is 0.26 g, which contains uncertainty. This estimate indicates that the ground motion likely exceeded the DBE response spectra for NAPS Units 1 and 2 (0.12 g) over a considerable frequency range. The estimated ground motion from the earthquake was not surprising, based on the combined operating license application ground motion response spectrum for NAPS Unit 3. This preliminary estimate appears to validate the NRC's current seismic hazard assessment approaches and the basis for Generic Issue (GI)-199 reviews.
It was reported that NAPS potentially exceeded the DBE spectrum at frequencies above 5 H4z.
The vibratory ground motions from the 5.8 magnitude earthquake were recorded in all three orientations (North-South, East-West, and Vertical) at several locations in the plant using two types of instruments: the Engdahl scratch plates that record 12 discrete spectral accelerations between 2 and 25.4 Hz, and the Kinemetrics analog recorders that recorded time histories of the accelerations.
ENCLOSURE
The licensee has retrieved its seismic instrumentation recordings located at different elevation levels from within the plant and has processed some of the information from these recordings.
Preliminary results from the seismic instrumentation indicate exceedance above the final safety analysis report (FSAR) DBE spectra at various frequencies, depending on the building, measurement direction, and elevation.
Both units are in Cold Shutdown (Mode 5) with the residual heat removal system providing core cooling. No significant equipment damage to safety-related systems (including Class 1 structures) has been identified through site walk-downs nor has equipment degradation been detected through plant performance and surveillance testing following the earthquake. The licensee indicated that the spent fuel pit cooling system also remains fully functional and the temperature of the spent fuel pit remained unchanged during the event. The licensee also indicated that the vendor will complete the analysis of the seismic data and this information will be utilized to address the long term actions following the earthquake.
It is also noted that the NAPS independent spent fuel storage installation (ISFSI) suffered minor damage from the earthquake. Twenty five of the twenty seven TN-32 casks slid up to 4.5 inches (4.5") on the concrete pad during the quake. Six cask sets (12 casks) were closer than the 16 foot separation distance specified in the FSAR. There was no damage to the pressure monitors in each cask and no pressure monitoring system alarms during or after the earthquake. There were no crack indications observed in the concrete pad or casks. For the TN-NUHOMS modules, some slight damage was identified around the outlet vents and some surface cracking indications were noted. Additionally, some modules showed gaps between them of approximately 1.5" versus the required 1.0" maximum gap.
The NRC initially dispatched a seismic and structural expert to assist the agency's resident inspectors on site. The NRC then dispatched an Augmented Inspection Team on August 29, 2011, to gather important information for the NRC's continuing evaluation of earthquake risk at US nuclear power plants.
Regulatory Outcome:          ..
In accordance with Appendix A to Part 100, Paragraph V(a)(2), a nuclear power plant is required to be shutdown when the vibratory ground motion exceeds that of the Operating Basis Earthquake. In addition, the regulations state that, "Prior to resuming operations, the licensee will be required to demonstrate to the Commission that no functional damage has occurred to those features necessary for continued operation without undue risk to the health and safety of the public."
Licensee actions are underway to inspect, evaluate, test and repair, if necessary, systems and components to ensure they are capable of performing their required functions. The licensee is performing plant walk downs in accordance with Regulatory Guide (RG) 1.167, "Restart of a Nuclear Power Plant Shutdown by a Seismic Event," which endorses the Electric Power Research Institute (EPRI) ReportTNo. i'2Crires                  for Nuclear Plant Response to an Earthquake," with conditions.
The staff's assessment will utilize the guidance provided in NRC's Regulatory Guide (RG) 1.167, which endorses the EPRI's guidelines. In addition, the staff will utilize the IAEA Safety Report Series No. 66, "Earthquake Preparedness and Response for Nuclear Power Plants," to determine the adequacy of the licensee's restart determinations. It should be noted that the
IAEA Safety Report acknowledges the prospect that hidden damage (especially after an SSE) is a real possibility and its effects should be evaluated with analytical evaluations. Specific actions are identified in the table below, entitled, "North Anna Nuclear Power Plant Restart Action Plan Milestones."
The acceptance criteria that will be utilized by the staff for approval of plant restart include satisfactorily addressing the following:
(1) Confirmatory inspections by the region, (2) Visual walkdowns by the licensee in accordance with the EPRI guidelines, (3) Identification of short term evaluations by licensee (pre-restart), and (4) Identification of long term evaluations by licensee (post-restart).
Project Management Structure:
This project is being performed as a matrix organizational structure. Team members will support project activities directly but will report administratively through their normal management chain. Approvals will be achieved through the standard concurrence process.
Responsible Division Director (DD): Patrick Hiland, DE Responsible Individuals: Meena Khanna and Kamal Manoly, DE Other stakeholders and roles:
DD DORL: Joe Guitter DD DSS: Bill Ruland DD DCI: Michele Evans DD DRA: Michael Cheok DD DLR: Brian Holian DD NMSS/SFST: Vonna Ordaz DDD NRO/DSER: Nilesh Chokshi DD, NRO/DE: T. Bergman OPA: S. Burnell, Manage External Communications OCA: E. Dacus, Congressional Liaison 24Regions: R. Conte, RI; M. Franke andCr,.i,'--,.-                                -.          .
DPR: A. Russell, Action Plan Structure, Action Plan website updates Project Attributes:
The project will consist of five broad phases. The first phase involves continued collection of issues that the staff expects the licensee to address in the short term and long term. Objectives during this phase include assembling a catalogue of questions to request of the licensee to address in either inspection or licensing space. The first phase involves inspection and.
assessment of the licensee's walkdowns and activities, via the Augmented Inspection Team.
The second phase involves identifying short term issues that the licensee must demonstrate prior to restart. The third phase involves identifying long term issues that the licensee must address following plant restart. These items may involve a serieF rýf '" r m.-*+ ings, development of a temporary inspection instruction and, potentially, audits. The fourth phase addresses the development of a regulatory vehicle to ensure that the licensee adequately addresses the new design basis earthquake in its Updated Final Safety Analysis Report, as appropriate. The fifth phase includes the development of regulatory products, which includes potentially issuing an Order, generic communications, and developing communications tools, such as briefing sheets, as appropriate.
Project Success Criteria Include:
Licensee adequately implements the guidance stipulated in RG 1.167 (i.e., EPRI NP-6695 guidelines) and the initiatives within IAEA Safety Report No. 66, to effectively address short and long-term plant restart issues. Stakeholders are informed of and-educated about the safety significance of this issue.
The milestones in the action plan and documents or products that result from completed milestones should be publicly available. Planning information, personnel assignments and draft documents will not, in general, be made public.
Current Status: As noted in table Potential Problems: N/A Closeout Criteria: N/A Proposed Resources and Re-prioritization: Approximately 1.0 FTE is expected to be expended to address this issue. Re-prioritization may be required to support plant restart activities.
DE:            G. Wilson, R. Matthew, M. Khanna DCI:          T. McMurtray, T. Lupold, M. Mitchell, and M. Murphy DSS:          G.Casto, R. Dennig, A. Ulses, A. Mendiola DLR:          B. Pham, R. Auluck, D. Pelton DIRS:          T. Tate, D. Harrison NRO:          C. Munson, R. Karas NMSS:          E. Love and E. Benner RES:          A. Kammerer OPA:          S. Burnell OCA:          E. Dicus Region Ih      R. COnte Region III:    M. Franke Region IV:    A. Shaihk G. Werner
==References:==
: 1. 10 CFR Part 100, Appendix A, Seismic and Geologic Siting for Nuclear Power Plants
: 2. RG 1.167, "Restart of a Nuclear Power Plant Shut Down By a Seismic Event"
: 3. EPRI NP-6695 Guideline, "Guidelines for Nuclear Power Plant Response to an Earthquake" A.A. SJafety Report No. 66, "Earthquake Preparedness and Response for Nuc!,        .
Power Plants"
: 5. Augmented Inspection Charter to Evaluate Total Loss of Offsite Power, Dual Unit Reactor Trips and Plant Equipment Issues Following a Seismic Event at North Anna
: 6. Dominion Presentation Slides, September 8, 2011 (ADAMS Accession No. ML11252A006)
NORTH ANNA NUCLEAR POWER PLANT RESTART ACTION PLAN MILESTONES Item#                              Milestone                      Completion      Lead Date 1        Applicable technical branches within DE, DSS, DCI,      9/16/2011    DE and DLR to identify questions and issues that the licensee should address for restart. This includes short term (prior to restart) and long term initiatives (post restart).
2        As issues are identified and finalized, weekly            Ongoing    DORL conference calls/meetings will be held with licensee to address short and long term actions.
3        Short term and long term actions and issues shall be                  DE identified and documented for issuance to the licensee via DORL.
4        Questions and issues will be categorized in one of the                DORL/DE following: (a) confirmatory inspections by the region, (b) items to be confirmed via licensee's visual inspection/walkdowns, (c) short term evaluations by licensee (pre-restart), and (d) long term evaluations by licensee (post-restart).
Address any safety related concerns associated with                  NMSS 5        the movement of the ISFSIs as a result of the earthquake, via questions and inspections.
6        Upon Augmented Team Inspection exit, any follow-up                    REGION II issues/actions will be communicated and addressed by staff as appropriate. Region to seek assistance via
-*.    .*,        ,,
* fMK "daoress    outstanding issues.        -.    .
Develop a team to address path forward in reviewing                  DE licensee's submittal for plans to restart.
8        Develop the language for an Order, which could later                  DORL/DE be converted to a Confirmatory Action Letter, if needed.
9        Upon receipt of licensee's formal request for restart                DE submittal, team to assess results of their inspections and readiness reviews, with support from technical branches, as appropriate. This will include developing questions and final input to NRC restart document.
10        Assess root cause for diesel generator failure and                    REGION II
          -.      .    - *'    aff's document for restart. Any other issues shall be addressed similarly.
Milestone                          Completion      Lead Date Conduct inspections at site to verify any outstanding                  REGION II issues.
Develop template for NRC Restart Document and                          DORL incorporate input from OGC, etc., as appropriate.
Conduct Public Meeting prior to issuance of NRC                        DORL Restart Document.
Issue NRC Restart Document.                                            DORL As necessary, determine the need for appropriate                      DORLIOGC/OE regulatory vehicle for long term issues, i.e., revisions to FSAR to address new DBE.
Address any potential generic issues, e.g., seismic                    Region II instrumentation power supplies, seismic monitor                        NMSS/DE/DPR locations on structures as well as in the "free field," and seismic monitors on ISFSI pads.
Continue to respond to routine communications                Ongoing  DE between the resident inspectors and local officials based on public interest. See DE Communication Plan (ADAMS ML #).
Address Issues for Resolution, as applicable                          DE/DIRS}}

Latest revision as of 18:55, 6 February 2020

Email from G. Thomas, NRR to D. Hoang, NRR Et Al. FW: North Anna Seismic Report - Summary Report of August 23/2011 Earthquake Response and Restart Readiness Determination Plan North Anna Power Station Units 1 and 2 and ISFSI
ML12054A145
Person / Time
Site: North Anna  Dominion icon.png
Issue date: 09/19/2011
From: George Thomas
NRC/NRR/DE/EMCB
To: Dan Hoang, William J, Juan Uribe
NRC/NRR/DE/EMCB
References
FOIA/PA-2011-0357
Download: ML12054A145 (9)


Text

From: Thomas. Georoe To: Hoan. Dan; Jessuo William: i Jua; Basavaraiu. Chakraoani

Subject:

FW: NORTH ANNA SEISMIC REPORT - Summary Report of August 23/ 2011 Earthquake Response and Restart Readiness Determination Plan North Anna Power Station Units 1 and 2 and ISFSI Date: Monday, September 19, 2011 7:31:20 AM Attachments: 11-520 Earthouake Summary Reoort and Restart Plan Final.odf FYI or use.

From: Martin, Robert Sent: Sunday, September 18, 2011 9:18 AM To: Li, Yong; Farzam, Farhad; Tsirigotis, Alexander; Thomas, George; Ulses, Anthony; Casto, Greg; Bailey, Stewart; Dennig, Robert; Evans, Michele; Lubinski, John; Taylor, Robert; Murphy, Emmett; McGinty, Tim; Pham, Bo; Murphy, Martin; Lupold, Timothy; Mitchell, Matthew; McMurtray, Anthony; Wilson, George; Mathew, Roy; Cheok, Michael; Tate, Travis; Harrison, Donnie; Circle, Jeff; Klein, Alex; Holian, Brian; Galloway, Melanie; Auluck, Rajender; Pelton, David; Rosenberg, Stacey; McGinty, Tim; Thompson, Jon; Boger, Bruce; Leeds, Eric; Khanna, Meena; Kulesa, Gloria; Howe, Allen; Boyle, Patrick Cc: Bahadur, Sher; Weerakkody, Sunil

Subject:

NORTH ANNA SEISMIC REPORT - Summary Report of August 23/ 2011 Earthquake Response and Restart Readiness Determination Plan North Anna Power Station Units 1 and 2 and ISFSI From: Ginger L Rutherford [1]

Sent: Saturday, September 17, 2011 1:50 PM To: Cotton, Karen; Davis (NMSS), Jennifer; Hiland, Patrick; Khanna, Meena; Manoly, Kamal; acmilankm@aol.com; Mendiola, Anthony; Howe, Allen; Martin, Robert; McCoy, Gerald; Boyle, Patrick; Karwoski, Kenneth; Giitter, Joseph

Subject:

11-520 - Summary Report of August 23/ 2011 Earthquake Response and Restart Readiness Determination Plan North Anna Power Station Units 1 and 2 and ISFSI CONFIDENTI ITY NOTICE: is electronic messagec6fitains informatio ich may.

be legally co idential and/or pr eged and does notjy any case represent irmENERGY COMMOD.Y bid or offer r ating thereto which blfnds the sender wit ut an additional express/ ritten confirmati n to that effect. The* formation is inte solely for the individual or entity naij~ above and acces y anyone else is authorized. If y are not the)*itended recipie . any disclosure, co ing, distribution r use of the co nts of this information is prgibited and may be lawful. If you h e received this ctronic

,transmission i frror, please reply

  • mediately to the ender that you e received the

/ message in or, and delete it. ank you.

MEMORANDUM TO: Eric J. Leeds, Director Office of Nuclear Reactor Regulation FROM: Patrick L. Hiland, Director Division of Engineering

SUBJECT:

ACTION PLAN TO ADDRESS NORTH ANNA POWER STATION RESTART AS A RESULT OF AUGUST 23, 2011, EARTHQUAKE On August 23, 2011, the North Anna Power Station (NAPS) declared an Alert due to significant seismic activity onsite resulting from an earthquake which had a measured magnitude of 5.8.

On August 26, 2011, initial reviews of the data determined that the seismic activity potentially exceeded the NAPS Design Basis Earthquake magnitude value. Subsequently on August 26, 2011, the licensee declared all safety-related structures, systems and components inoperable and issued a 10 CFR 50.72 Notification.

In response to the recent seismic event, the staff is undertaking various initiatives to address plant restart activities at the NAPS, which includes an Augmented Inspection Team that was dispatched on August 31, 2011. In addition, the staff is in the process of identifying issues and questions for the licensee to consider in order to obtain NRC authorization for plant restart, in accordance with 10 CFR Part 100, Appendix A. The attached action plan describes and tracks the agency's ongoing initiatives related to the NAPS restart activities as a result of the recent seismic event.

Enclosure:

As stated CONTACT: Meena Khanna, NRR/DE/EMCB (301) 415-2150

MEMORANDUM TO: Eric J. Leeds, Director Office of Nuclear Reactor Regulation FROM: Patrick L. Hiland, Director Division of Engineering

SUBJECT:

ACTION PLAN TO ADDRESS NORTH ANNA POWER STATION RESTART AS A RESULT OF AUGUST 23, 2011, EARTHQUAKE On August 23, 2011, the North Anna Power Station (NAPS) declared an Alert due to significant seismic activity onsite resulting from an earthquake which had a measured magnitude of 5.8.

On August 26, 2011, initial reviews of the data determined that the seismic activity potentially exceeded the NAPS Design Basis Earthquake magnitude value. Subsequently on August 26, 2011, the licensee declared all safety-related structures, systems and components inoperable and issued a 10 CFR 50.72 Notification.

In response to the recent seismic event, the staff is undertaking various initiatives to address plant restart activities at the NAPS, which includes an Augmented Inspection Team that was dispatched on August 31, 2011. In addition, the staff is in the process of identifying issues and questions for the licensee to consider in order to obtain NRC authorization for plant restart in accordance with 10 CFR Part 100, Appendix A. The attached action plan describes and tracks the agency's ongoing initiatives related to the NAPS restart activities as a result of the recent seismic event.

Enclosure:

As stated CONTACT: Meena Khanna, NRR/DE/EMCB (301) 415-2150 INDICATE IN BOX: C*=COPY W/O ATTACHMENTIENCLOSURE, "E"=COPY W/ATTIENCL, *N'=NO COPY OFFICE EMCB:DE EMCB:DE DORL:NRR DSS:NRR DCI:NRR DLR:NRR NAME MKhanna KManoly RMartin WRuland MEvans BHolian 19/ /2011 9/ /2011 9/ /2011 9/ /2011 9/ /2011 9/ /2011 DATEj________________

OFFICEOFIELIZIZEIIIJIRIRIP DIRS:NRR Region 11 DE:NRR L NRR NRRNR K _

NAME MCheok LWert PHiland BBoger JGrobe ELeeds DATEI 2011 9/ /2011

_9/ 9/ /2011 9/ /2011 9/ /2011

_ /Z011 -

NORTH ANNA POWER STATION RESTART ACTION PLAN Last Update: 9/13/2011 Lead Division: DE Supporting Divisions: DSS, DCI, DLR, DRA Supporting Offices: Region II, NMSS, NRO, RES TAC Nos. ME7050 and ME7051 Goal:

The goal of this action plan is to track the agency's ongoing initiatives related to the North Anna Power Station (NAPS) restart decision as a result of the recent seismic event on August 23, 2011.

Background:

On August 23, 2011, NAPS experienced a seismic event (5.8 magnitude earthquake reported by the U.S. Geological Survey) which resulted in a loss of offsite power and automatic reactor trip of both units. The licensee declared an Alert due to significant seismic activity at the site.

Subsequent to the earthquake, the licensee stabilized both units, restored offsite power, and retrieved the recorded ground motions at the site resulting from the seismic event, which were sent to the vendor for analysis. On August 26, 2011, initial reviews of the data determined that the seismic activity potentially exceeded the Design Basis Earthquake (DBE) spectrum at frequencies above 5 Hz. Therefore, this event was reportable per 10 CFR 50.72(b)(3)(ii)(B) for the nuclear power plant being in an unanalyzed condition that may have significantly'degraded plant safety.

The NAPS has two DBE, otherwise known as the Safe Shutdown Earthquake (SSE), ground motions, one for structures, systems, and components (SSCs) located on top of rock, which is anchored at 0.12 g, with the second DBE ground motion related to SSCs located on top of soil, which is anchored *:t ',E Th9- N ' *? *o cr~7ing Operating Basis Earthquake (OBE) ground motion spectra, anchored at 0.09 g for soil and 0.06 g for rock. The Vendor has processed the initial seismic data. Preliminary results indicate certain measurements exceeded the SSE, at various frequencies above the limits reported in the final safety analysis report.

The current best estimate of the Peak Ground Acceleration (PGA) for the NAPS site, resulting from the recent seismic event, is 0.26 g, which contains uncertainty. This estimate indicates that the ground motion likely exceeded the DBE response spectra for NAPS Units 1 and 2 (0.12 g) over a considerable frequency range. The estimated ground motion from the earthquake was not surprising, based on the combined operating license application ground motion response spectrum for NAPS Unit 3. This preliminary estimate appears to validate the NRC's current seismic hazard assessment approaches and the basis for Generic Issue (GI)-199 reviews.

It was reported that NAPS potentially exceeded the DBE spectrum at frequencies above 5 H4z.

The vibratory ground motions from the 5.8 magnitude earthquake were recorded in all three orientations (North-South, East-West, and Vertical) at several locations in the plant using two types of instruments: the Engdahl scratch plates that record 12 discrete spectral accelerations between 2 and 25.4 Hz, and the Kinemetrics analog recorders that recorded time histories of the accelerations.

ENCLOSURE

The licensee has retrieved its seismic instrumentation recordings located at different elevation levels from within the plant and has processed some of the information from these recordings.

Preliminary results from the seismic instrumentation indicate exceedance above the final safety analysis report (FSAR) DBE spectra at various frequencies, depending on the building, measurement direction, and elevation.

Both units are in Cold Shutdown (Mode 5) with the residual heat removal system providing core cooling. No significant equipment damage to safety-related systems (including Class 1 structures) has been identified through site walk-downs nor has equipment degradation been detected through plant performance and surveillance testing following the earthquake. The licensee indicated that the spent fuel pit cooling system also remains fully functional and the temperature of the spent fuel pit remained unchanged during the event. The licensee also indicated that the vendor will complete the analysis of the seismic data and this information will be utilized to address the long term actions following the earthquake.

It is also noted that the NAPS independent spent fuel storage installation (ISFSI) suffered minor damage from the earthquake. Twenty five of the twenty seven TN-32 casks slid up to 4.5 inches (4.5") on the concrete pad during the quake. Six cask sets (12 casks) were closer than the 16 foot separation distance specified in the FSAR. There was no damage to the pressure monitors in each cask and no pressure monitoring system alarms during or after the earthquake. There were no crack indications observed in the concrete pad or casks. For the TN-NUHOMS modules, some slight damage was identified around the outlet vents and some surface cracking indications were noted. Additionally, some modules showed gaps between them of approximately 1.5" versus the required 1.0" maximum gap.

The NRC initially dispatched a seismic and structural expert to assist the agency's resident inspectors on site. The NRC then dispatched an Augmented Inspection Team on August 29, 2011, to gather important information for the NRC's continuing evaluation of earthquake risk at US nuclear power plants.

Regulatory Outcome: ..

In accordance with Appendix A to Part 100, Paragraph V(a)(2), a nuclear power plant is required to be shutdown when the vibratory ground motion exceeds that of the Operating Basis Earthquake. In addition, the regulations state that, "Prior to resuming operations, the licensee will be required to demonstrate to the Commission that no functional damage has occurred to those features necessary for continued operation without undue risk to the health and safety of the public."

Licensee actions are underway to inspect, evaluate, test and repair, if necessary, systems and components to ensure they are capable of performing their required functions. The licensee is performing plant walk downs in accordance with Regulatory Guide (RG) 1.167, "Restart of a Nuclear Power Plant Shutdown by a Seismic Event," which endorses the Electric Power Research Institute (EPRI) ReportTNo. i'2Crires for Nuclear Plant Response to an Earthquake," with conditions.

The staff's assessment will utilize the guidance provided in NRC's Regulatory Guide (RG) 1.167, which endorses the EPRI's guidelines. In addition, the staff will utilize the IAEA Safety Report Series No. 66, "Earthquake Preparedness and Response for Nuclear Power Plants," to determine the adequacy of the licensee's restart determinations. It should be noted that the

IAEA Safety Report acknowledges the prospect that hidden damage (especially after an SSE) is a real possibility and its effects should be evaluated with analytical evaluations. Specific actions are identified in the table below, entitled, "North Anna Nuclear Power Plant Restart Action Plan Milestones."

The acceptance criteria that will be utilized by the staff for approval of plant restart include satisfactorily addressing the following:

(1) Confirmatory inspections by the region, (2) Visual walkdowns by the licensee in accordance with the EPRI guidelines, (3) Identification of short term evaluations by licensee (pre-restart), and (4) Identification of long term evaluations by licensee (post-restart).

Project Management Structure:

This project is being performed as a matrix organizational structure. Team members will support project activities directly but will report administratively through their normal management chain. Approvals will be achieved through the standard concurrence process.

Responsible Division Director (DD): Patrick Hiland, DE Responsible Individuals: Meena Khanna and Kamal Manoly, DE Other stakeholders and roles:

DD DORL: Joe Guitter DD DSS: Bill Ruland DD DCI: Michele Evans DD DRA: Michael Cheok DD DLR: Brian Holian DD NMSS/SFST: Vonna Ordaz DDD NRO/DSER: Nilesh Chokshi DD, NRO/DE: T. Bergman OPA: S. Burnell, Manage External Communications OCA: E. Dacus, Congressional Liaison 24Regions: R. Conte, RI; M. Franke andCr,.i,'--,.- -. .

DPR: A. Russell, Action Plan Structure, Action Plan website updates Project Attributes:

The project will consist of five broad phases. The first phase involves continued collection of issues that the staff expects the licensee to address in the short term and long term. Objectives during this phase include assembling a catalogue of questions to request of the licensee to address in either inspection or licensing space. The first phase involves inspection and.

assessment of the licensee's walkdowns and activities, via the Augmented Inspection Team.

The second phase involves identifying short term issues that the licensee must demonstrate prior to restart. The third phase involves identifying long term issues that the licensee must address following plant restart. These items may involve a serieF rýf '" r m.-*+ ings, development of a temporary inspection instruction and, potentially, audits. The fourth phase addresses the development of a regulatory vehicle to ensure that the licensee adequately addresses the new design basis earthquake in its Updated Final Safety Analysis Report, as appropriate. The fifth phase includes the development of regulatory products, which includes potentially issuing an Order, generic communications, and developing communications tools, such as briefing sheets, as appropriate.

Project Success Criteria Include:

Licensee adequately implements the guidance stipulated in RG 1.167 (i.e., EPRI NP-6695 guidelines) and the initiatives within IAEA Safety Report No. 66, to effectively address short and long-term plant restart issues. Stakeholders are informed of and-educated about the safety significance of this issue.

The milestones in the action plan and documents or products that result from completed milestones should be publicly available. Planning information, personnel assignments and draft documents will not, in general, be made public.

Current Status: As noted in table Potential Problems: N/A Closeout Criteria: N/A Proposed Resources and Re-prioritization: Approximately 1.0 FTE is expected to be expended to address this issue. Re-prioritization may be required to support plant restart activities.

DE: G. Wilson, R. Matthew, M. Khanna DCI: T. McMurtray, T. Lupold, M. Mitchell, and M. Murphy DSS: G.Casto, R. Dennig, A. Ulses, A. Mendiola DLR: B. Pham, R. Auluck, D. Pelton DIRS: T. Tate, D. Harrison NRO: C. Munson, R. Karas NMSS: E. Love and E. Benner RES: A. Kammerer OPA: S. Burnell OCA: E. Dicus Region Ih R. COnte Region III: M. Franke Region IV: A. Shaihk G. Werner

References:

1. 10 CFR Part 100, Appendix A, Seismic and Geologic Siting for Nuclear Power Plants
2. RG 1.167, "Restart of a Nuclear Power Plant Shut Down By a Seismic Event"
3. EPRI NP-6695 Guideline, "Guidelines for Nuclear Power Plant Response to an Earthquake" A.A. SJafety Report No. 66, "Earthquake Preparedness and Response for Nuc!, .

Power Plants"

5. Augmented Inspection Charter to Evaluate Total Loss of Offsite Power, Dual Unit Reactor Trips and Plant Equipment Issues Following a Seismic Event at North Anna
6. Dominion Presentation Slides, September 8, 2011 (ADAMS Accession No. ML11252A006)

NORTH ANNA NUCLEAR POWER PLANT RESTART ACTION PLAN MILESTONES Item# Milestone Completion Lead Date 1 Applicable technical branches within DE, DSS, DCI, 9/16/2011 DE and DLR to identify questions and issues that the licensee should address for restart. This includes short term (prior to restart) and long term initiatives (post restart).

2 As issues are identified and finalized, weekly Ongoing DORL conference calls/meetings will be held with licensee to address short and long term actions.

3 Short term and long term actions and issues shall be DE identified and documented for issuance to the licensee via DORL.

4 Questions and issues will be categorized in one of the DORL/DE following: (a) confirmatory inspections by the region, (b) items to be confirmed via licensee's visual inspection/walkdowns, (c) short term evaluations by licensee (pre-restart), and (d) long term evaluations by licensee (post-restart).

Address any safety related concerns associated with NMSS 5 the movement of the ISFSIs as a result of the earthquake, via questions and inspections.

6 Upon Augmented Team Inspection exit, any follow-up REGION II issues/actions will be communicated and addressed by staff as appropriate. Region to seek assistance via

-*. .*, ,,

  • fMK "daoress outstanding issues. -. .

Develop a team to address path forward in reviewing DE licensee's submittal for plans to restart.

8 Develop the language for an Order, which could later DORL/DE be converted to a Confirmatory Action Letter, if needed.

9 Upon receipt of licensee's formal request for restart DE submittal, team to assess results of their inspections and readiness reviews, with support from technical branches, as appropriate. This will include developing questions and final input to NRC restart document.

10 Assess root cause for diesel generator failure and REGION II

-. . - *' aff's document for restart. Any other issues shall be addressed similarly.

Milestone Completion Lead Date Conduct inspections at site to verify any outstanding REGION II issues.

Develop template for NRC Restart Document and DORL incorporate input from OGC, etc., as appropriate.

Conduct Public Meeting prior to issuance of NRC DORL Restart Document.

Issue NRC Restart Document. DORL As necessary, determine the need for appropriate DORLIOGC/OE regulatory vehicle for long term issues, i.e., revisions to FSAR to address new DBE.

Address any potential generic issues, e.g., seismic Region II instrumentation power supplies, seismic monitor NMSS/DE/DPR locations on structures as well as in the "free field," and seismic monitors on ISFSI pads.

Continue to respond to routine communications Ongoing DE between the resident inspectors and local officials based on public interest. See DE Communication Plan (ADAMS ML #).

Address Issues for Resolution, as applicable DE/DIRS