Letter Sequence Acceptance Review |
---|
|
|
MONTHYEARML21252A5142021-09-0909 September 2021 Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections, Rev 1, Using the Consolidated Line Item Improvement Process Project stage: Request ML21274A0022021-09-30030 September 2021 NRR E-mail Capture - Acceptance Review for TSTF-577 LAR (L-2021-LLA-0158) Project stage: Acceptance Review ML21350A4082021-12-16016 December 2021 Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Genera Tor Tube Inspections, Rev 1, Using the Consolidated Line-Item Improvement Process Response to RAI Project stage: Response to RAI ML22068A0712022-03-22022 March 2022 Issuance of Amendment Nos. 292 and 275 to Revise Technical Specifications to Adopt TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube Inspections Project stage: Approval 2021-09-30
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24107A9112024-04-15015 April 2024 NRC to Fws, Follow-up on Request for Concurrence for North Anna SLR ML24107A9122024-04-11011 April 2024 Fws to NRC, Follow-up on Request for Concurrence for North Anna SLR ML24087A0102024-03-26026 March 2024 NRR E-mail Capture - Verbal Relief for North Anna Unit 1 - (ASME Code), Section XI, Subsection IWB-2430 ML24087A0112024-03-23023 March 2024 NRR E-mail Capture - Draft RAIs for Reactor Coolant Pump (RCP) Relief Request (L-2024-LLR-0022) ML24107B1562024-02-20020 February 2024 Cherokee Nation E.Toombs Na Removal Request ML24044A2462024-02-0606 February 2024 001 Radiation Safety Baseline Inspection Information Request ML23320A1122024-01-18018 January 2024 NRC to Fws, Concurrence with Endangered Species Act Determinations for North Anna Power Station, Units 1 and 2, Subsequent License Renewal, Issuance of Draft Supplemental Environmental Impact Statement, and Opportunity for Public Comment ML23355A2722023-12-21021 December 2023 NRR E-mail Capture - Schedule Revision for Emergency Preparedness Staff Augmentation Times License Amendment Request ML23318A1172023-11-13013 November 2023 NRR E-mail Capture - Formal Issuance of RAIs for North Anna Technical Support Center (TSC) License Amendment Request (LAR) (L-2023-LLA-0006) ML23257A2092023-09-14014 September 2023 NRR E-mail Capture - Formal Issuance of 2nd Round RAIs for Surry Units 1&2 and North Anna Units 1&2 Emergency Plans LAR ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23219A1602023-08-0707 August 2023 003 Radiation Safety Baseline Inspection Information Request ML23171B0522023-06-20020 June 2023 NRR E-mail Capture - RAI for Review of Appendix F to DOM-NAF-2-P (Redacted) ML23075A0232023-03-15015 March 2023 NRR E-mail Capture - RAI - License Amend Req (LAR) to Revise Tech Spec (Ts) 3.6.8 Limiting Condition for Operation to Remove Refueling Water Chemical Addition Tank and Replace the Containment Sump Buffer North Anna, 1 and 2 (L-2022-LLA-0162 ML23067A2162023-03-0707 March 2023 NRR E-mail Capture - RAI for North Anna, 1 & 2, Surry 1 & 2, Millstone, 2 & 3, Request for Approval of App. F Fleet Report DOM-NAF-2-P, Qual of the Framatome ORFEO-GAIA and ORFEO-NMGRID CHF Correlations in the Dominion VIPRE-D Computer Code ML23060A0932023-03-0101 March 2023 NRR E-mail Capture - Formal Issuance of RAIs for Surry/North Anna Emergency Plans LAR ML23059A2282023-02-28028 February 2023 NRR E-mail Capture - Draft RAIs for Containment Buffer Change to Natb (L-2022-LLA-0162) ML23039A1712023-02-0808 February 2023 NRR E-mail Capture - Acceptance Review for Technical Support Center (TSC) Relocation (L-2023-LLA-0006) ML23018A0352023-01-17017 January 2023 NRR E-mail Capture - Acceptance Review for Fleet Report Re Appendix F of DOM-NAF-2-P (L-2022-LLT-0003) ML22342B1472022-12-0808 December 2022 NRR E-mail Capture - Acceptance Review for LAR Re NAPS Post LOCA Buffer Change (L-2022-LLA-0162) ML22335A4842022-12-0101 December 2022 NRR E-mail Capture - Acceptance Review for LAR North Anna Power Station - Units 1 and 2 and Surry Power Station - Units 1 and 2 Emergency Plan Staff Augmentation Times (L-2022-LLA-0166) ML22242A0452022-08-23023 August 2022 NRR E-mail Capture - Dominion GL 04-02 Response Draft RAIs (L-2017-LRC-0000) ML22174A3552022-06-23023 June 2022 NRR E-mail Capture - Acceptance Review for Dominion Fleet LAR to Implement TSTF-554 (L-2022-LLA-0078) ML22104A0252022-04-14014 April 2022 NRR E-mail Capture - Dominion Presentation Slides for April 21, 2022 Public Meeting on Emergency Preparedness Submittal for the North Anna Power Station and the Surry Power Station ML22083A2102022-03-24024 March 2022 NRR E-mail Capture - Draft RAI - Relief Request N2-14-LMT-003 Fourth Ten Year Inservice Inspection Interval ML22032A0962022-02-0101 February 2022 002 Radiation Safety Baseline Inspection Information Request ML22018A0272022-01-18018 January 2022 2022 All RFI Responses - Exercise and Program Inspections - Revl ML22007A2672022-01-0707 January 2022 NRR E-mail Capture - North Anna, Unit 2, ASME Section XI Inservice Inspection Program Relief Request N2-14-LMT-003 Fourth Interval Third Period Limited Examinations (L-2021-LLR-0088) ML21335A0812021-12-0101 December 2021 NRR E-mail Capture - Acceptance Review for OMN-28 Request Alternative to ISTC-3700, Position Verification Testing (L-2021-LLR-0086) ML21334A1922021-11-30030 November 2021 NRR E-mail Capture - Audit Plan for Reactor Core Thermal-Hydraulics Using the VIPRE-D Appendix E Review ML21327A3652021-11-23023 November 2021 NRR E-mail Capture - Draft RAI for TSTF-577 LAR ML21326A1502021-11-22022 November 2021 NRR E-mail Capture - Acceptance Review for Relocation of Unit Staff Requirements to the QAPD LAR (L-2021-LLA-0195) ML21322A0962021-11-18018 November 2021 Final Request for Additional Information Set 5 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21312A0082021-11-0404 November 2021 Enclosure 2 - NAPS Draft SER Table A.1-1 Markup ML21312A0012021-11-0404 November 2021 Comments on North Anna Draft SER ML21312A0112021-11-0404 November 2021 Enclosure 3 - NAPS Draft SER Section 3 Comments ML21306A3302021-11-0202 November 2021 NRR E-mail Capture - Acceptance Review for TSTF-569 LAR ML21286A7372021-10-13013 October 2021 Additional Element Included in the Implementation Plan for the Surry Fuel Melt Safety Limit (SL) LAR ML21274A0022021-09-30030 September 2021 NRR E-mail Capture - Acceptance Review for TSTF-577 LAR (L-2021-LLA-0158) ML21312A0072021-09-21021 September 2021 Enclosure 1 - E-mail - Enclosure B - NAPS SER App a - Dominion Comments 9-21-2021 ML21312A0032021-09-21021 September 2021 Enclosure 1 - E-mail - Enclosure a - Dominion Table A4.4-1 Clean Version ML21312A0022021-09-21021 September 2021 Enclosure 1 - E-mail - NAPS SLR SER Appendix a for Dominion Review ML21256A0672021-09-13013 September 2021 Final Request for Confirmation of Information Set 2 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21152A1722021-09-0707 September 2021 NRC to Fws, NRC Issuance of Draft Environmental Impact Statement for North Anna Subsequent License Renewal, Opportunity for Public Comment, and Endangered Species Act Determinations ML21238A0942021-08-25025 August 2021 Draft Request for Additional Information Set Z - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21225A5512021-08-13013 August 2021 Discussion Point for Public Meeting Regarding Fire Protection Piping Cyclic Loading - Transmittal E-mail ML21195A2442021-07-13013 July 2021 NRR E-mail Capture - Draft RAI Appendix E to Topical Report DOM-NAF-2 Qualification of the Framatome BWU-I CHF Correlation in the Dominion Energy VIPRE-D Computer Code ML21188A1632021-07-0707 July 2021 Final Request for Additional Information Set 4 - North Anna SLRA Safety Review (EPID No. L-2020-SLR-0000) - Email ML21154A0152021-06-0101 June 2021 NRR E-mail Capture - Acceptance Review for Primary Grade Water LAR (L-2021-LLA-0082) ML21140A3682021-05-20020 May 2021 Response to North Anna Hardship (Temporary Staff Guidance Additional Guidance for FOF Inspections During the PHE) 2024-04-15
[Table view] |
Text
From: Miller, Ed Sent: Thursday, September 30, 2021 1:34 PM To: Erica.N.Combs@dominionenergy.com
Subject:
Acceptance review for TSTF-577 LAR (L-2021-LLA-0158)
- Erica,
By letter dated September 9, 2021 (Agencywide Documents Access and Management System Package Accession No. ML21252A514), Virginia Electric Power Company, submitted a license amendment request for North Anna Power Station Units 1 and 2. The proposed amendment would implement TSTF-577, Revision 1, and revise Technical Specification 5.6.7, Steam Generator (SG) Program, and TS 5.5.8, Steam Generator Tube Inspection Report. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance revi ew was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to begin its detailed technical review. The acceptance review is also intended to identify whether the request has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an application for an amendment to a license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design feature, and principal safety considerations.
The NRC staff has reviewed your request and concluded that it does provide technical information in sufficient detail to enable the NRC staff to begin its detailed technical review and make an independent assessment regarding the acceptability of the proposed request in terms of regulatory requirements and the protection of public health and safety and the environment.
Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified in requests for additional information despite completion of an adequate acceptance review. You will be advised of any further information needed to support the NRC staffs detailed technical review by separate correspondence.
Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 125 hours0.00145 days <br />0.0347 hours <br />2.066799e-4 weeks <br />4.75625e-5 months <br /> to complete. The NRC staff expects to complete this review by September, 2022. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
These estimates are based on the NRC staffs initial review of the application and they can change due to several factors including requests for additional information, unanticipated addition of scope to the review, review by NRC advisory committees, or h earing-related activities.
If you have any questions, please contact me at (301) 415 2481 or ed.miller@nrc.gov.
Ed Miller (301) 415-2481 Hearing Identifier: NRR_DRMA Email Number: 1369
Mail Envelope Properties (SA1PR09MB748759A51BC0174253A865DEE9AA9)
Subject:
Acceptance review for TSTF-577 LAR (L-2021-LLA-0158)
Sent Date: 9/30/2021 1:34:03 PM Received Date: 9/30/2021 1:34:00 PM From: Miller, Ed
Created By: Ed.Miller@nrc.gov
Recipients:
"Erica.N.Combs@dominionenergy.com" <Erica.N.Combs@dominionenergy.com>
Tracking Status: None
Post Office: SA1PR09MB7487.namprd09.prod.outlook.com
Files Size Date & Time MESSAGE 3355 9/30/2021 1:34:00 PM
Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: