- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, ... further results|Request]]
- Acceptance...
- Supplement, Supplement, Supplement
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval
Other: ML20246G698, ML20258A284, ML20269A465, ML20274A111, ML20274A198, ML20307A177, ML20322A052, ML20337A022, ML20351A388, ML21025A340, ML21181A186, ML21217A187, ML23062A466, ML24206A043
|
MONTHYEARML20246G6972020-08-24024 August 2020 Application for Subsequent Renewed Operating Licenses Project stage: Request ML20246G6982020-08-24024 August 2020 Appendix E: Applicants Environmental Report Subsequent Operating License Renewal Stage North Anna Power Station Units 1 and 2 Project stage: Other ML20269A4652020-10-0606 October 2020 SLRA - Portal Letter Project stage: Other ML20258A2842020-10-13013 October 2020 SLRA - Acceptance and Opportunity for Hearing Letter Project stage: Other ML20274A1112020-10-19019 October 2020 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process (EPID No. L-2020-SLE-0000) - Letter to Applicant Project stage: Other ML20274A1982020-10-19019 October 2020 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process (EPID No. L-2020-SLE-0000) - Federal Register Notice Project stage: Other PMNS20201188, Environmental Scoping Meeting Related to the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application2020-10-28028 October 2020 Environmental Scoping Meeting Related to the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application Project stage: Meeting ML20307A1772020-11-0404 November 2020 NRC Presentation North Anna Power Station, Units 1 and 2 Subsequent License Renewal Review Project stage: Other ML20317A2062020-11-12012 November 2020 Environmental Scoping Meeting Related to the North Anna Power Station, Units 1 and 2, Subsequent License Renewal Application Project stage: Meeting ML20324A6792020-11-13013 November 2020 Comment (1) of Kevin Quigley on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20324A6812020-11-13013 November 2020 Comment (3) from Frederick Gerloff on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20324A6832020-11-13013 November 2020 Comment (5) from Joseph Sucha on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20324A6822020-11-13013 November 2020 Comment (4) from Keith Scott on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20324A6802020-11-13013 November 2020 Comment (2) from Luther Jones on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20324A6852020-11-14014 November 2020 Comment (6) from Thomas Owens on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0512020-11-14014 November 2020 Comment (8) of Lisa Hicks-Thomas on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Units 1 and 2 Project stage: Request ML20324A6862020-11-14014 November 2020 Comment (7) from Nancy Ashberry on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0532020-11-15015 November 2020 Comment (9) of Martin Blough on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0542020-11-16016 November 2020 Comment (10) of Michael Hamby on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0582020-11-16016 November 2020 Comment (12) from Melissa Haley on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0572020-11-16016 November 2020 Comment (11) of Lauren Lopez on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Units 1 and 2 Project stage: Request ML20329A4392020-11-17017 November 2020 Pamunkey Consultation Request_North Anna Power Station_17NOV20 Project stage: Request ML20325A0602020-11-17017 November 2020 Comment (13) of Terry Clouthier on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0632020-11-18018 November 2020 Comment (16) of Tracy Gill on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1092020-11-18018 November 2020 Comment (33) of Adam Perry on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Units 1 and 2 Project stage: Request ML20325A1102020-11-18018 November 2020 Comment (34) of Terrance Perrone on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1132020-11-18018 November 2020 Comment (37) of Shawn Williams on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Units 1 and 2 Project stage: Request ML20325A1152020-11-18018 November 2020 Comment (38) of Eric Hendrixson on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1242020-11-18018 November 2020 Comment (42) of Edmond Longest on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1052020-11-18018 November 2020 Comment (31) from Carl Eng on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1012020-11-18018 November 2020 Comment (28) from Ralph Joyce on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0942020-11-18018 November 2020 Comment (26) from J. Crouch on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0752020-11-18018 November 2020 Comment (24) of Richard Zuercher on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Units 1 and 2 Project stage: Request ML20325A0722020-11-18018 November 2020 Comment (21) of Mel Holley on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0652020-11-18018 November 2020 Comment (17) of Tommy Flynn on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1122020-11-18018 November 2020 Comment (36) from Robert George on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0622020-11-18018 November 2020 Comment (15) from Jason Evans on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1032020-11-18018 November 2020 Comment (29) of Steven Eisenrauch on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0612020-11-18018 November 2020 Comment (14) of Kevin Cordray on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0662020-11-18018 November 2020 Comment (18) from Jim Norvelle on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0712020-11-18018 November 2020 Comment (20) of Harold Vaughan on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1172020-11-18018 November 2020 Comment (39) from Carl Aimee Newcomb of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1182020-11-18018 November 2020 Comment (40) of Donald Sharp on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1202020-11-18018 November 2020 Comment (41) of Robert Fleshman on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1112020-11-18018 November 2020 Comment (35) of Greg Boutchyard on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1072020-11-18018 November 2020 Comment (32) of Angela Baker on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A1042020-11-18018 November 2020 Comment (30) of David Strole on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0922020-11-18018 November 2020 Comment (25) of J. Crouch on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0682020-11-18018 November 2020 Comment (19) of Ronald Buchanan on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement; Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request ML20325A0732020-11-18018 November 2020 Comment (22) of Sarah Marshall on Notice of Intent to Conduct Scoping Process and Prepare Environmental Impact Statement Virginia Electric and Power Company; North Anna Power Station, Unit Nos. 1 and 2 Project stage: Request 2020-11-14
[Table View] |
Text
MEMORANDUM TO:
Robert B. Elliott, Chief Environmental Review License Renewal Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards FROM:
Robert Hoffman, Environmental Scientist Environmental Review License Renewal Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards
SUBJECT:
SUMMARY
OF THE HISTORIC AND CULTURAL RESOURCES ENVIRONMENTAL AUDIT MEETING RELATED TO THE REVIEW OF THE SUBSEQUENT LICENSE RENEWAL APPLICATION FOR THE NORTH ANNA POWER STATION, UNITS 1 AND 2 (EPID NUMBER: L-2020-SLE-0000)
On December 1, 2020, staff from the U.S. Nuclear Regulatory Commission (NRC) and the Pamunkey Indian Tribe participated in an environmental audit meeting with Dominion Energy Virginia (Dominion) addressing historic and cultural resources in the vicinity of the North Anna Power Station, Units 1 and 2 (North Anna) in Louisa and Spotsylvania counties, VA. The meeting, conducted virtually using the Microsoft Teams platform, was in regard to the environmental review of the North Anna subsequent license renewal application and the associated National Historic Preservation Act Section 106 consultation. The enclosure is a list of representatives from NRC, the Pamunkey Indian Tribe, and Dominion.
The NRC invited the Pamunkey Indian Tribe to join the meeting in response to the Tribes request to be a consulting party on this proposed undertaking (Agencywide Documents Access and Management System Accession Number ML20329A439). Staff from the NRC, Dominion, and the Tribe participated in the discussion. The Pamunkey Indian Tribe Cultural Resource Director indicated that the Tribe has concerns regarding the timing of the license renewal application and how potential cumulative impacts would be assessed, particularly with regard CONTACT:
Robert Hoffman, REFS/ELRB 301-415-1107 December 17, 2020 Signed by Hoffman, R on 12/17/20
R. Elliott 2
to water quality. The majority of the discussion focused on communications that the applicant has had with Indian Tribes and the Virginia Department of Historic Resources related to this action, specifically the status of architectural surveys of facility structures being conducted to determine National Register of Historic Places eligibility.
Enclosure:
List of Participants
Enclosure HISTORIC AND CULTURAL RESOURCES ENVIRONMENTAL AUDIT MEETING REGARDING THE NORTH ANNA POWER STATION, UNITS 1 AND 2 SUBSEQUENT LICENSE RENEWAL APPLICATION DECEMBER 1, 2020 LIST OF PARTICIPANTS U.S. NUCLEAR REGULATORY COMMISSION Robert Hoffman Nancy Martinez Tam Tran PAMUNKEY INDIAN TRIBE Terry Clouthier DOMINION GENERATION VIRGINIA Paul Aitken Keith Miller Helen Robertson Oula Shehab-Dandan Kim Stapleton Rachel Turney
Memo ML20350B456 OFFICE NMSS/REFS/ERLRB NMSS/REFS/ERMB NMSS/REFS
/ERLRB NMSS/REFS
/ERLRB NAME RHoffman AWalker-Smith TTran RElliott DATE Dec 16, 2020 Dec 16, 2020 Dec 16, 2020 Dec 17, 2020 OFFICE NMSS/REFS/ERLRB NAME RHoffman DATE Dec 17, 2020