IR 05000482/2017005: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 3: | Line 3: | ||
| issue date = 08/28/2017 | | issue date = 08/28/2017 | ||
| title = Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2017005) | | title = Updated Inspection Plan for Wolf Creek Generating Station (Report 05000482/2017005) | ||
| author name = Taylor N | | author name = Taylor N | ||
| author affiliation = NRC/RGN-IV/DRP/RPB-B | | author affiliation = NRC/RGN-IV/DRP/RPB-B | ||
| addressee name = Heflin A | | addressee name = Heflin A | ||
| addressee affiliation = Wolf Creek Nuclear Operating Corp | | addressee affiliation = Wolf Creek Nuclear Operating Corp | ||
| docket = 05000482 | | docket = 05000482 | ||
Line 18: | Line 18: | ||
=Text= | =Text= | ||
{{#Wiki_filter:August 28, 2017 | {{#Wiki_filter:August 28, 2017 | ||
==SUBJECT:== | |||
UPDATED INSPECTION PLAN FOR WOLF CREEK GENERATING STATION (REPORT 05000482/2017005) | |||
==Dear Mr. Heflin:== | ==Dear Mr. Heflin:== | ||
Line 27: | Line 28: | ||
The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. | The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. | ||
This inspection plan does not include the plan for security | This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence. | ||
-related inspections, which will be sent via separate, non | |||
-publicly available correspondence. | |||
Additionally, as reflected in the enclosure, during this period the NRC staff will complete Temporary Instruction 2515/191, "Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi | Additionally, as reflected in the enclosure, during this period the NRC staff will complete Temporary Instruction 2515/191, "Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans." This inspection will be conducted at Wolf Creek Generating Station to confirm the station's full implementation of Commission Orders EA-12-049 and EA-12-051. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511 A. Helflin 2 public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). | ||
-Unit Dose Assessment Plans." This inspection will be conducted at Wolf Creek Generating Station to confirm the station's full implementation of Commission Orders EA-12-049 and EA | |||
-12-051. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD ARLINGTON, TX 76011 | |||
-4511 A. Helflin 2 public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading | |||
-rm/adams.html (the Public Electronic Reading Room). | |||
Please contact me at (817) 200-1141 with any questions you have regarding this letter. | Please contact me at (817) 200-1141 with any questions you have regarding this letter. | ||
Line 41: | Line 36: | ||
Sincerely, | Sincerely, | ||
/RA D. Proulx for/ | /RA D. Proulx for/ | ||
Nicholas H. Taylor, Branch Chief Project Branch B Division of Reactor Projects Docket No. 0 5000482 License No. NPF | Nicholas H. Taylor, Branch Chief Project Branch B Division of Reactor Projects Docket No. 0 5000482 License No. NPF-42 Enclosure: Wolf Creek Generating Station Inspection Plan | ||
-42 Enclosure: Wolf Creek Generating Station Inspection Plan | |||
SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword-NRC-002 By:NHT/dll Yes No Publicly Available Sensitive OFFICE RIV/DRP:SPE RIV/DRP:C NAME DProulx NTaylor SIGNATURE /RA/ /RA DProulx for/ DATE 8/28/17 8/28/17 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteWolf CreekInspection / Activity Plan 07/01/2017 | SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword-NRC-002 By:NHT/dll Yes No Publicly Available Sensitive OFFICE RIV/DRP:SPE RIV/DRP:C NAME DProulx NTaylor SIGNATURE /RA/ /RA DProulx for/ DATE 8/28/17 8/28/17 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteWolf CreekInspection / Activity Plan 07/01/2017-06/30/2019 Page 1 of 2 08/25/2017 08:25:55 INIT EXA-INITIAL EXAM 5 1 INITIAL EXAM WOLF CREEK (11/2017) | ||
-06/30/2019 Page 1 of 2 08/25/2017 08:25:55 INIT EXA-INITIAL EXAM 5 1 INITIAL EXAM WOLF CREEK (11/2017) | |||
X02597 10/16/2017 10/20/2017 1 INITIAL EXAM WOLF CREEK (11/2017) | X02597 10/16/2017 10/20/2017 1 INITIAL EXAM WOLF CREEK (11/2017) | ||
X0259711/06/201711/10/2017 EB1-21N-WC DESIGN BASIS INSPECTION PROGRAMS 3 1 IP Design Bases Assurance Inspection (Programs)7111121N 05/08/2017 07/13/2017 PI&R-PI&R FOCUSED SAMPLE - SCWE 2 1 IP In-depth Reviews71152-Reviews 08/29/2017 08/30/2017 EB2-05T-TRIENNIAL FIRE PROTECTION INSPECTION 4 1 IP Fire Protection [Triennial]7111105T 10/02/2017 10/06/2017 1 IP Fire Protection [Triennial]7111105T 10/16/2017 10/20/2017 EP-2-BIENNIAL EP EXERCISE INSPECTION 4 1 IP Exercise Evaluation711140111/13/201711/17/2017 1 IP Emergency Action Level and Emergency Plan Changes711140411/13/201711/17/2017 EP-3-EP PERFORMANCE INDICATOR VERIFICATION 1 1 IP Drill/Exercise Performance71151-EP0111/13/201711/17/2017 1 IP ERO Readiness71151-EP0211/13/201711/17/2017 1 IP A lert & Notification System Reliability71151-EP0311/13/201711/17/2017TI191-MITIGATING STRATEGIES/SFP INST FOR BDBEE 4 1 IP Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 2515/191 01/22/2018 01/26/20187111108-INSERVICE INSPECTION 1 1 IP Inservice Inspection Activities - PWR7111108P 04/02/2018 04/13/2018 RS 12PI-RAD SAFETY 2 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 04/09/2018 04/13/2018 1 IP Occupational ALARA Planning and Controls71124.02 04/09/2018 04/13/2018 1 IP Occupational Exposure Control Effectiveness71151-OR01 04/09/2018 04/13/2018 1 IP RETS/ODCM Radiological Effluent Occurrences71151-PR01 04/09/2018 04/13/2018 INSP-BRQ INSPECTION 2 1 IP Licensed Operator Requalification Program7111111B 06/04/2018 06/08/2018 PI&R-BIENNIAL PI&R INSPECTION 4 1 IP Problem Identification and Resolution71152B06/11/2018 06/15/2018 1 IP Problem Identification and Resolution71152B 06/25/2018 06/29/2018 EB1-21M-WC DESIGN BASES INSPECTION TEAMS 6 1 IP Design Bases Assurance Inspection (Teams)7111121M 07/16/2018 08/03/2018 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures. | X0259711/06/201711/10/2017 EB1-21N-WC DESIGN BASIS INSPECTION PROGRAMS 3 1 IP Design Bases Assurance Inspection (Programs)7111121N 05/08/2017 07/13/2017 PI&R-PI&R FOCUSED SAMPLE - SCWE 2 1 IP In-depth Reviews71152-Reviews 08/29/2017 08/30/2017 EB2-05T-TRIENNIAL FIRE PROTECTION INSPECTION 4 1 IP Fire Protection [Triennial]7111105T 10/02/2017 10/06/2017 1 IP Fire Protection [Triennial]7111105T 10/16/2017 10/20/2017 EP-2-BIENNIAL EP EXERCISE INSPECTION 4 1 IP Exercise Evaluation711140111/13/201711/17/2017 1 IP Emergency Action Level and Emergency Plan Changes711140411/13/201711/17/2017 EP-3-EP PERFORMANCE INDICATOR VERIFICATION 1 1 IP Drill/Exercise Performance71151-EP0111/13/201711/17/2017 1 IP ERO Readiness71151-EP0211/13/201711/17/2017 1 IP A lert & Notification System Reliability71151-EP0311/13/201711/17/2017TI191-MITIGATING STRATEGIES/SFP INST FOR BDBEE 4 1 IP Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 2515/191 01/22/2018 01/26/20187111108-INSERVICE INSPECTION 1 1 IP Inservice Inspection Activities - PWR7111108P 04/02/2018 04/13/2018 RS 12PI-RAD SAFETY 2 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 04/09/2018 04/13/2018 1 IP Occupational ALARA Planning and Controls71124.02 04/09/2018 04/13/2018 1 IP Occupational Exposure Control Effectiveness71151-OR01 04/09/2018 04/13/2018 1 IP RETS/ODCM Radiological Effluent Occurrences71151-PR01 04/09/2018 04/13/2018 INSP-BRQ INSPECTION 2 1 IP Licensed Operator Requalification Program7111111B 06/04/2018 06/08/2018 PI&R-BIENNIAL PI&R INSPECTION 4 1 IP Problem Identification and Resolution71152B06/11/2018 06/15/2018 1 IP Problem Identification and Resolution71152B 06/25/2018 06/29/2018 EB1-21M-WC DESIGN BASES INSPECTION TEAMS 6 1 IP Design Bases Assurance Inspection (Teams)7111121M 07/16/2018 08/03/2018 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures. | ||
Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteWolf CreekInspection / Activity Plan 07/01/2017 | Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteWolf CreekInspection / Activity Plan 07/01/2017-06/30/2019 Page 2 of 2 08/25/2017 08:25:55 RS 5678-RAD SAFETY 4 1 IP Radiation Monitoring Instrumentation71124.05 08/20/2018 08/24/2018 1 IP Radioactive Gaseous and Liquid Effluent Treatment71124.06 08/20/2018 08/24/2018 1 IP Radiological Environmental Monitoring Program71124.07 08/20/2018 08/24/2018 1 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.08 08/20/2018 08/24/2018 EP-1-EP PROGRAM INSPECTION 1 1 IP A lert and Notification System Testing7111402 09/17/2018 09/21/2018 1 IP Emergency Preparedness Organization Staffing and Augmentation System7111403 09/17/2018 09/21/2018 1 IP Emergency Action Level and Emergency Plan Changes7111404 09/17/2018 09/21/2018 1 IP Correction of Emergency Preparedness Weaknesses and Deficiencies7111405 09/17/2018 09/21/2018 1 IP Drill/Exercise Performance71151-EP01 09/17/2018 09/21/2018 1 IP ERO Readiness71151-EP02 09/17/2018 09/21/2018 1 IP A lert & Notification System Reliability71151-EP03 09/17/2018 09/21/2018 EB1-17T-WOLF CREEK 10CFR50.59 INSPECTION 3 1 IP Evaluations of Changes, Tests, and Experiments7111117T 04/29/2019 05/03/2019 RS 24-RP INSPECTION 1 1 IP Occupational ALARA Planning and Controls71124.02 05/06/2019 05/10/2019 1 IP Occupational Dose Assessment71124.04 05/06/2019 05/10/2019 EP-2-EP EXERCISE INSPECTION 4 1 IP Exercise Evaluation7111401 06/03/2019 06/07/2019 1 IP Emergency Action Level and Emergency Plan Changes7111404 06/03/2019 06/07/2019 1 IP Drill/Exercise Performance71151-EP01 06/03/2019 06/07/2019 1 IP ERO Readiness71151-EP02 06/03/2019 06/07/2019 1 IP A lert & Notification System Reliability71151-EP03 06/03/2019 06/07/2019 EP2-EP EXERCISE AND PI INSPECTION 4 1 IP Exercise Evaluation7111401 06/03/2019 06/07/2019 1 IP Emergency Action Level and Emergency Plan Changes7111404 06/03/2019 06/07/2019 1 IP Drill/Exercise Performance71151-EP01 06/03/2019 06/07/2019 1 IP ERO Readiness71151-EP02 06/03/2019 06/07/2019 1 IP A lert & Notification System Reliability71151-EP03 06/03/2019 06/07/2019 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures. | ||
-06/30/2019 Page 2 of 2 08/25/2017 08:25:55 RS 5678-RAD SAFETY 4 1 IP Radiation Monitoring Instrumentation71124.05 08/20/2018 08/24/2018 1 IP Radioactive Gaseous and Liquid Effluent Treatment71124.06 08/20/2018 08/24/2018 1 IP Radiological Environmental Monitoring Program71124.07 08/20/2018 08/24/2018 1 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.08 08/20/2018 08/24/2018 EP-1-EP PROGRAM INSPECTION 1 1 IP A lert and Notification System Testing7111402 09/17/2018 09/21/2018 1 IP Emergency Preparedness Organization Staffing and Augmentation System7111403 09/17/2018 09/21/2018 1 IP Emergency Action Level and Emergency Plan Changes7111404 09/17/2018 09/21/2018 1 IP Correction of Emergency Preparedness Weaknesses and Deficiencies7111405 09/17/2018 09/21/2018 1 IP Drill/Exercise Performance71151-EP01 09/17/2018 09/21/2018 1 IP ERO Readiness71151-EP02 09/17/2018 09/21/2018 1 IP A lert & Notification System Reliability71151-EP03 09/17/2018 09/21/2018 EB1-17T-WOLF CREEK 10CFR50.59 INSPECTION 3 1 IP Evaluations of Changes, Tests, and Experiments7111117T 04/29/2019 05/03/2019 RS 24-RP INSPECTION 1 1 IP Occupational ALARA Planning and Controls71124.02 05/06/2019 05/10/2019 1 IP Occupational Dose Assessment71124.04 05/06/2019 05/10/2019 EP-2-EP EXERCISE INSPECTION 4 1 IP Exercise Evaluation7111401 06/03/2019 06/07/2019 1 IP Emergency Action Level and Emergency Plan Changes7111404 06/03/2019 06/07/2019 1 IP Drill/Exercise Performance71151-EP01 06/03/2019 06/07/2019 1 IP ERO Readiness71151-EP02 06/03/2019 06/07/2019 1 IP A lert & Notification System Reliability71151-EP03 06/03/2019 06/07/2019 EP2-EP EXERCISE AND PI INSPECTION 4 1 IP Exercise Evaluation7111401 06/03/2019 06/07/2019 1 IP Emergency Action Level and Emergency Plan Changes7111404 06/03/2019 06/07/2019 1 IP Drill/Exercise Performance71151-EP01 06/03/2019 06/07/2019 1 IP ERO Readiness71151-EP02 06/03/2019 06/07/2019 1 IP A lert & Notification System Reliability71151-EP03 06/03/2019 06/07/2019 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures. | |||
}} | }} |
Revision as of 05:22, 19 June 2019
ML17242A207 | |
Person / Time | |
---|---|
Site: | Wolf Creek |
Issue date: | 08/28/2017 |
From: | Nick Taylor NRC/RGN-IV/DRP/RPB-B |
To: | Heflin A Wolf Creek |
NICK TAYLOR | |
References | |
IR 2017005 | |
Download: ML17242A207 (5) | |
Text
August 28, 2017
SUBJECT:
UPDATED INSPECTION PLAN FOR WOLF CREEK GENERATING STATION (REPORT 05000482/2017005)
Dear Mr. Heflin:
The enclosed inspection plan lists the inspections scheduled through June 30, 2019, for Wolf Creek Generating Station.
The U.S. Nuclear Regulatory Commission (NRC) provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
This inspection plan does not include the plan for security-related inspections, which will be sent via separate, non-publicly available correspondence.
Additionally, as reflected in the enclosure, during this period the NRC staff will complete Temporary Instruction 2515/191, "Inspection of the Implementation of Mitigation Strategies and Spent Fuel Pool Instrumentation Orders and Emergency Preparedness Communication/Staffing/Multi-Unit Dose Assessment Plans." This inspection will be conducted at Wolf Creek Generating Station to confirm the station's full implementation of Commission Orders EA-12-049 and EA-12-051. In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 1600 E. LAMAR BLVD ARLINGTON, TX 76011-4511 A. Helflin 2 public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at (817) 200-1141 with any questions you have regarding this letter.
Sincerely,
/RA D. Proulx for/
Nicholas H. Taylor, Branch Chief Project Branch B Division of Reactor Projects Docket No. 0 5000482 License No. NPF-42 Enclosure: Wolf Creek Generating Station Inspection Plan
SUNSI Review ADAMS: Non-Publicly Available Non-Sensitive Keyword-NRC-002 By:NHT/dll Yes No Publicly Available Sensitive OFFICE RIV/DRP:SPE RIV/DRP:C NAME DProulx NTaylor SIGNATURE /RA/ /RA DProulx for/ DATE 8/28/17 8/28/17 Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteWolf CreekInspection / Activity Plan 07/01/2017-06/30/2019 Page 1 of 2 08/25/2017 08:25:55 INIT EXA-INITIAL EXAM 5 1 INITIAL EXAM WOLF CREEK (11/2017)
X02597 10/16/2017 10/20/2017 1 INITIAL EXAM WOLF CREEK (11/2017)
X0259711/06/201711/10/2017 EB1-21N-WC DESIGN BASIS INSPECTION PROGRAMS 3 1 IP Design Bases Assurance Inspection (Programs)7111121N 05/08/2017 07/13/2017 PI&R-PI&R FOCUSED SAMPLE - SCWE 2 1 IP In-depth Reviews71152-Reviews 08/29/2017 08/30/2017 EB2-05T-TRIENNIAL FIRE PROTECTION INSPECTION 4 1 IP Fire Protection [Triennial]7111105T 10/02/2017 10/06/2017 1 IP Fire Protection [Triennial]7111105T 10/16/2017 10/20/2017 EP-2-BIENNIAL EP EXERCISE INSPECTION 4 1 IP Exercise Evaluation711140111/13/201711/17/2017 1 IP Emergency Action Level and Emergency Plan Changes711140411/13/201711/17/2017 EP-3-EP PERFORMANCE INDICATOR VERIFICATION 1 1 IP Drill/Exercise Performance71151-EP0111/13/201711/17/2017 1 IP ERO Readiness71151-EP0211/13/201711/17/2017 1 IP A lert & Notification System Reliability71151-EP0311/13/201711/17/2017TI191-MITIGATING STRATEGIES/SFP INST FOR BDBEE 4 1 IP Inspection of Licensee's Responses to Order EA-12-049, EA-12-051 & EP Info Request March 12, 2012 2515/191 01/22/2018 01/26/20187111108-INSERVICE INSPECTION 1 1 IP Inservice Inspection Activities - PWR7111108P 04/02/2018 04/13/2018 RS 12PI-RAD SAFETY 2 1 IP Radiological Hazard Assessment and Exposure Controls71124.01 04/09/2018 04/13/2018 1 IP Occupational ALARA Planning and Controls71124.02 04/09/2018 04/13/2018 1 IP Occupational Exposure Control Effectiveness71151-OR01 04/09/2018 04/13/2018 1 IP RETS/ODCM Radiological Effluent Occurrences71151-PR01 04/09/2018 04/13/2018 INSP-BRQ INSPECTION 2 1 IP Licensed Operator Requalification Program7111111B 06/04/2018 06/08/2018 PI&R-BIENNIAL PI&R INSPECTION 4 1 IP Problem Identification and Resolution71152B06/11/2018 06/15/2018 1 IP Problem Identification and Resolution71152B 06/25/2018 06/29/2018 EB1-21M-WC DESIGN BASES INSPECTION TEAMS 6 1 IP Design Bases Assurance Inspection (Teams)7111121M 07/16/2018 08/03/2018 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.
Report 22 Unit NumberPlanned Dates Start EndInspection ActivityTitle No. of Staff on SiteWolf CreekInspection / Activity Plan 07/01/2017-06/30/2019 Page 2 of 2 08/25/2017 08:25:55 RS 5678-RAD SAFETY 4 1 IP Radiation Monitoring Instrumentation71124.05 08/20/2018 08/24/2018 1 IP Radioactive Gaseous and Liquid Effluent Treatment71124.06 08/20/2018 08/24/2018 1 IP Radiological Environmental Monitoring Program71124.07 08/20/2018 08/24/2018 1 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation71124.08 08/20/2018 08/24/2018 EP-1-EP PROGRAM INSPECTION 1 1 IP A lert and Notification System Testing7111402 09/17/2018 09/21/2018 1 IP Emergency Preparedness Organization Staffing and Augmentation System7111403 09/17/2018 09/21/2018 1 IP Emergency Action Level and Emergency Plan Changes7111404 09/17/2018 09/21/2018 1 IP Correction of Emergency Preparedness Weaknesses and Deficiencies7111405 09/17/2018 09/21/2018 1 IP Drill/Exercise Performance71151-EP01 09/17/2018 09/21/2018 1 IP ERO Readiness71151-EP02 09/17/2018 09/21/2018 1 IP A lert & Notification System Reliability71151-EP03 09/17/2018 09/21/2018 EB1-17T-WOLF CREEK 10CFR50.59 INSPECTION 3 1 IP Evaluations of Changes, Tests, and Experiments7111117T 04/29/2019 05/03/2019 RS 24-RP INSPECTION 1 1 IP Occupational ALARA Planning and Controls71124.02 05/06/2019 05/10/2019 1 IP Occupational Dose Assessment71124.04 05/06/2019 05/10/2019 EP-2-EP EXERCISE INSPECTION 4 1 IP Exercise Evaluation7111401 06/03/2019 06/07/2019 1 IP Emergency Action Level and Emergency Plan Changes7111404 06/03/2019 06/07/2019 1 IP Drill/Exercise Performance71151-EP01 06/03/2019 06/07/2019 1 IP ERO Readiness71151-EP02 06/03/2019 06/07/2019 1 IP A lert & Notification System Reliability71151-EP03 06/03/2019 06/07/2019 EP2-EP EXERCISE AND PI INSPECTION 4 1 IP Exercise Evaluation7111401 06/03/2019 06/07/2019 1 IP Emergency Action Level and Emergency Plan Changes7111404 06/03/2019 06/07/2019 1 IP Drill/Exercise Performance71151-EP01 06/03/2019 06/07/2019 1 IP ERO Readiness71151-EP02 06/03/2019 06/07/2019 1 IP A lert & Notification System Reliability71151-EP03 06/03/2019 06/07/2019 This report does not include INPO and OUTAGE activities. This report shows only on-site and announced inspection procedures.