Reconfirms NRC Approval of Decommissioning Plan Referred to in Trust Agreement,In Response to Recipient . Commitment to Provide Funds for Decommissioning Plan Made Condition of License SNM-7 w/830429 Renewal of License
ML20235E332
Person / Time
Site: 07000008
Issue date: 09/23/1987
From: Rouse L
NRC OFFICE OF NUCLEAR MATERIAL SAFETY & SAFEGUARDS (NMSS)
To: Bahlmann J
Battelle Memorial Institute, COLUMBUS LABORATORIES
References
NUDOCS 8709280068
Download: ML20235E332 (2)


Text

- _ _ _ _ _ _ _ _ _ _ _

,04 - m {

. , nysm g " ,

I SEP 2 31987 y RlA4 Docket No. 70-8 ,

l Pio,t i 4 _ . . . _ . . . -

-~~~~ --

Mr. Jerome R. Bahlmann General Counsel and Vice President pg Battelle Columbus Division 505 King Avenue LPDR __. .

Columbus, Ohio 43201-2693 EfdUf n i' MI{N '

Dear Mr. Bahlmann:

g ggp3 In your letter of August 25, 1987, you stated that the Trustee who holds funds for expenses associated with decontamination and decommissioning Battelle's Columbus Laboratories would like to have a current lotter from the Nuclear Regulatory Commission (NRC) noting approval of the decommissioning plan referred to in the Trust Agreements.

You requested that we reconfirm NRC approval of the decommissioning plan in a letter that you will then forwtrd to the Trustee.

We originally approved your conceptual decommissioning plan with its cost estimate for the Hot Cell Laboratory by letter dated June 29, 1979. Your commitments to provide funds for decommissioning were later made a condition of License No. SNM-7 when the license was renewed on April 29, 1983. We understand that approximately

$1,200,000 has been &ccumulated in the Trust Funds to date. This represents a small fraction of the total cost you have estimated for decontamination and decommissioning the facilities used by Battelle for work with radioactive materials. However, since the Department of Energy (D0E) has accepted responsibility for cleanup of the contamination of the Battelle facilities which resulted from DOE-sponsored work, DOE will provide the majority of the funds for Battelle to decommission the facilities. Although these funds may not begin to become available until at least FY1989, we have no objection to disbursements from Battelle's Trust Funds for expenses associated with decommissioning in accordance with the approved conceptual decommissioning plan prior to DOE making available the bulk of the funds at later times. We hereby reconfirm NRC approval of the conceptual decommissioning plan.

As we have discussed with you previously, final amendments to NRC regulations on decommissioning are being prepared. When the amendments become effective, licensees will be required to submit detailed decommissioning plans to the NRC for review and approval. This will surely occur before or during the time you are decommissioning your facilities. Therefore if there are funds remaining in the Trust Funds at the time detailed decommissioning plans are required, we 8709280068$$$og ADOCK PDR PDR C

SEP 2 31987 ' .

Mr. Jerome R. Bahlmann- 2 )

L would expect that further disbursements from the Funds from that time forward would require NRC approval of a detailed decommissioning plan. We understand that such a plan will be developed in connection with the DOE contract modification for decommissioning, and we do not anticipate that the plan would be inconsistent with NRC requirements.

Please let me know if you have.any questions concerning NRC actions involving the Trust Agreements.

Sincerely.

Original Signed by Leland C. Rouse, Chief Fuel Cycle Safety Branch Division of Industrial and Medical Nuclear Safety  ;

cc: Mr. Harley L. Toy Distribution:

Docket 70-8 NMSS R/F PDR IMSB R/F IMAF R/F LCRouse PLoysen GTerry FBrown GFrance, RIII

' (:IMAF, :IMf/lW

.y.

0FC NAME:PL6ysen :IWfp g....L {d .

b:GA :LCRouse  :  :  :

DATE:7/1/87 : a /(1/87 : //iff87:

( OFFICIAL RECORD COPY

?

_ _ - _ _ _ - _ _ _ _ _