Responds to Re NRC Efforts on Review Activities for Proposed one-time Shipment of Trojan Reactor Vessel,For Disposal.Nrc decision-making Process Acting in Parrallel & in Concert with Other Necessary Approvals
ML20151Y876
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 09/11/1998
From: Shirley Ann Jackson, The Chairman
NRC COMMISSION (OCM)
To: Blumenauer E, Defazio P, Furse E, Hooley D, Galen Smith, Rich Smith, Wyden R
HOUSE OF REP., SENATE
Shared Package
ML20151Y881 List:
References
NUDOCS 9809210065
Download: ML20151Y876 (7)


Text

- _ _. . . _ . _ ._

\

h&

[ 3 4 ,4 UNITED STATES NUCLEAR REGULATORY COMMISSION g# ' ~

a nd,,*,. [ ,

O .

l

! E o WASHINGTON. D.C. 20565-0001 - t 1 tk j

/ September 11, 1998 CHAIRMAN l

The Honorable Ron Wyden United States Senate Washington, D.C. 20510

Dear Senator Wyden:

I am responding to your August 17,1998, letter regarding the U.S. Nuclear Regulatory Commission's (NRC) efforts regarding review activities for the proposed one-time shipment of

' the Trojan reactor vessel, for disposal. As indicated in your letter, you are aware that this review involves technical issues, and the staff is actively engaged in determining the adequacy .

I of this proposal and its impact on public health and safety. Also, you urged the staff to continue its active participation and complete the review by September 30,1998.

Although the review is still in process, the staff is in its final review phase and is planning to submit a paper containing the staff's recommendation for Commission review in early October 1998. This paper will allow the Commission, itself, to review the matter of granting or denying

the exemptions to the applicable transportation regulations that would be necessary to allow the Trojan reactor vessel to be shipped in the manner requested. Contingent upon a favorable determination regarding the request, the staff expects to issue the final decision in November 1998, which would allow Portland General Electric Company (PGE) sufficient time to grout the reactor vessel internals in preparation for an August 1999 shipment.

Besides NRC approval, I hasten to add that PGE must also obtain, before shipment:

(a) approval to dispose of the reactor vessel at the U.S. Ecology site in the State of Washington; (b) an exemption from the U.S. Department of Transportation (DOT) regulations; and, (c) approval of a modification to the Trojan Decommissioning Plan from the State of Oregon. We have coordinated our review schedule with DOT, the U.S. Coast Guard, and the States of Oregon and Washington. The NRC decision-making process is acting in parallel, and in concert with, othm 1ssary approvals.

' I want to assure you that the staff will continue to work diligently toward reaching a final decision on this matter as soon as practical and will maintain its focus on ensuring public health and safety.

Sincerely,

?

l l Shirley Ann Jackson

\

' I 9809210065 980911 Y PDR COMMS NRCC CORRESPONDENCE PDR ,

I

/ 4 UNITED STATES

  • p $ ' NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20666-0001 i
s. i September 11, 1998 k..... CHARMAN i

. The Honorable Robert F. Smith United States House of Representatives Washington, D.C. 20515 .

Dear Congressman Smith:

I am responding to your August 17,1998, letter regarding the U.S. Nuclear Regulatory Commission's (NRC) efforts regarding review activities for the proposed one-time shipment of

. the Trojan reactor vessel, for disposal. As indicated in your letter, you are aware that this review involves technical issues, and the staff is actively engaged in determining the adequacy ,

. of this proposal and its impact on public health and safety. Also, you urged the staff to continue

'its active participation and complete the review by September 30,1998. .

. Although the review is still in process, the staff is in its final review phase and is planning to .,

submit a paper containing the staff's recommendation for Commission review in early October i 1998. This paper will allow th* Commission, itself, to review the matter of granting or denying

. the exemptions to the applicable transportation regulations that would be necessary to allow the Trojan reactor vessel to be shipped in the manner requested. Contingent upon a favorable

' determination regarding the request, the staff expects to issue the final decision in November .

1998, which would allow Portland General Electric Company (PGE) sufficient time to grout the reactor vessel intemals in preparation for an August 1999 shipment.

Besides NRC approval, I hasten to add that PGE must also obtain, before shipment:

(a) approval to dispose of the reactor vessel at the U.S. Ecology site in the State of Washington; (b) an exemption from the U.S. Department of Transportation (DOT) regulations; and, (c) approval of a modification to the Trojan Decommissioning Plan from the State of ,

Oregon. We have coordinated our review schedule with DOT, the U.S. Coast Guard, and the

~ States of Oregon and Washington. The NRC decision-making process is acting in parallel, and i in concert with, other necessary approvals.

I want to assure you that the staff will continue to work diligently toward reaching a final  !

decision on this matter as soon as practical and will maintain its focus on ensuring public health and safety.

Sincerely, b l Shirley Ann Jackson i

I

-- .- , - .. n - - _ , , , , .- -e .-, . . - - . . - , n . , - - .

  1. % UNITED STATES

./

O k' NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 2066H001 I

September 11, 1998 k.....

CHAMMAN The Honorable Gordon Smith United States Senate Washington, D.C. 20510

Dear Senator Smith:

I am responding to your August 17,1998, letter regarding the U.S. Nuclear Regulatory Commission's (NRC) efforts regarding review activities for the proposed one-time shipment of the Trojan reactor vessel, for disposal. As indicated in your letter, you are aware that this review involves technical issues, and the staff is actively engaged in determining the adequacy of this proposal and its impact on public health and safety. Also, you urged the staff to continue its active participation and complete the review by September 30,1998.

. Although the review is still in process, the staff is in its final review phase and is planning to submit a paper containing the staff's recommendation for Commission review in early October

~

L 1998. This paper will allow the Commission, itself, to review the matter of granting _or denying the exemptions to the applicable transportation regulations that would be necessary to allow the Trojan reactor vessel to be shipped in the manner requested. Contingent upon a favorable determination regarding the request, the staff expects to issue the final decision in November 1998, which would allow Portland General Electric Company (PGE) sufficient time to grout the reactor vessel internals in preparation for an August 1999 shipment.

Besides NRC approval, I hasten to add that PGE must also obtain, before shipment:

(a) approval to dispose of the reactor vessel at the U.S. Ecology site in the State of Washington; (b) an exemption from the U.S. Department of Transportation (DOT) regulations; ,

' and, (c) approval of a modification to the Trojan Decommissioning Plan from the Stato of l

' Oregon. We have coordinated our review schedule with DOT, the U.S. Coast Guard, and the  !

States of Oregon and Washington. The NRC decision-making process is acting in parallel, and in concert with, other necessary approvals. j l

l want to assure you that the staff will continue to work diligently toward reaching a final i decision on this matter as soon as practical and will maintain its focus on ensuring public health j and safety. l 1

Sincerely, j Shirley Ann Jackson j i

i

1

% ' UNITED STATES -

.- a k "'

NUCLEAR REGULATORY COMMISSION WASHINGTON,' D.C. 20066-0001

]

5 ju

\...../ CHAMMAN September 11, 1998 The Honorable Peter A. DeFazio

United States House of Representatives Washington, D.C. 20515

Dear Congressman DeFazio:

I am responding to your August 17,1998, letter regarding the U.S. Nuclear Regulatory Commission's (NRC) efforts regarding review activities for the proposed one-time shipment of the Trojan reactor vessel, for disposal. As indicated in your letter, you are aware that this review involves technical issues, and the staff is actively engaged in determining the adequacy of this proposal and its impact on public health and safety. Also, you urged the staff to continue its active participation and complete the review by September 30,1998.

Although the review is still in process, the staff is in its final review phase and is planning to l submit a paper containing the staff's recommendation for Commission review in early October 1998. This paper will allow the Commission, itself, to review the matter of granting or denying the exemptions to the applicable transportation regulations that would be necessary to allow the Trojan reactor vessel to be shipped in the manner requested. Contingent upon a favorable determination regarding the request, the staff expects to issue the final decision in November 1998, which would allow Portland General Electric Company (PGE) sufficient time to grout the

. reactor vessel intemals in preparation for an August 1999 shipment.

Besides NRC approval, I hasten to add that PGE must also obtain, before shipment:

(a) approval to dispose of the reactor vessel at the U.S. Ecology site in the State of Washington; (b) an exemption from the U.S. Department of Transportation (DOT) regulations; and, (c) approval of a modification to the Trojan Decommissioning Plan from the State of l Oregon. We have coordinated our review schedule with DOT, the U.S. Coast Guard, and the l States of Oregon and Washington. The NRC decision making process is acting in parallel, and in concert with, other necessary approvals.

I want to assure you that the staff will continue to work diligently toward reaching a final l decision on this matter as soon as practical and will maintain its focus on ensuring public health and safety.  ;

Sincerely,  !

l M

Shirley Ann Jackson i

l-1 i

. ~ - ._ . m - . .

  1. UNITED STATES

. j }'; NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20655-0001 i 5 l

/ September 11, 1998

.....f CHAIRMAN The Honorable Elizabeth Furse l United States House of Representatives Washington, D.C. 20515

Dear Congresswoman Furse:

I am responding to your August 17,1998, letter regarding the U.S. Nuclear Regulatory Commission's (NRC) efforts regarding review activities for the proposed one-time shipment of the Trojan reactor vessel, for disposal. As indicated in your letter, you are aware that this review involves technical issues, and the staff is actively engaged in determining the adequacy of this proposal and its impact on public health and safety. Also, you urged the staff to continue its active participation and complete the review by September 30,1998.

Although the review is still in process, the staff is in its final review phase and is planning to i submit a paper containing the staff's recommendation for Commission review in early October  !

j 1998. This paper will allow the Commission, itself, to review the matter of granting or denying the exemptions to the applicable transportation regulations that would be necessary to allow the Trojan reactor vessel to be shipped in the manner requested. Contingent upon a favorable determination regarding the request, the staff expects to issue the final decision in November 1998, which would allow Portland General Electric Company (PGE) sufficient time to grout the reactor vessel internals in preparation for an August 1999 shipment.

Besides NRC approval, I hasten to add that PGE must also obtain, before shipment:

(a) approval to dispose of the reactor vessel at the U.S. Ecology site in the State of Washington; (b) an exemption from the U.S. Department of Transportation (DOT) regulations; and, (c) approval of a modification to the Trojan Decommissioning Plan from the State of Oregon. We have coordinated our review schedule with DOT, the U.S. Coast Guard, and the States of Oregon and Washington. The NRC decision-making process is acting in parallel, a1d in concert with, other necessary approvals.

I want to assure you that the staff will continue to work diligently toward reaching a final decision on this matter as soon as practical and will maintain its focus on ensuring public health and safety.

Sincerely,

=

b Shirley Ann Jackson I

p

[ A

'g UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20565-0001 e

September 11, 1998 k...../

CHAIRMAN  !

The Honorable Darlene Hooley United States House of Representatives Washington, D.C. 20515

Dear Congresswoman Hooley:

I am responding to your August 17,1998, letter regarding the U.S. Nuclear Regulatory .

Commission's (NRC) efforts regarding review activities for the proposed one-time shipment of the Trojan reactor vessel, for disposal. As indicated in your letter, you are aware that this review involves technical issues, and the staff is actively engaged in determining the adequacy of this proposal and its impact on public health and safety. Also, you urged the staff to continue its active participation and complete the review by September 30,1998. ,

Although the review is still in process, the staff is in its final review phase and is planning to submit a paper containing the staff's recommendation for Commission review in early October .

.1998. This paper will allow the Commission, itself, to review the matter of granting or denying the exemptions to the applicable transportation regulations that would be necessary to allow the Trojan reactor vessel to be shipped in the manner requested. Contingent upon a favorable determination regarding the request, the staff expects to issle the final decision in November 1998, which would allow Portland General Electric Company (PGE) sufficient time to grout the reactor vessel intemals in preparation for an August 1999 shipment.

Besides NRC approval, I hasten to add that PGE must also obtain, before shipment: ,

(a) approval to dispose of the reactor vessel at the U.S. Ecology site in the State of Washington; (b) an exemption from the U.S. Department of Transportation (DOT) regulations; and, (c) approval of a modification to the Trojan Decommissioning Plan from the State of Oregon. We have coordinated our review schedule with DOT, the U.S. Coast Guard, and the States of Oregon and Washington. The NRC decision-making process is acting in parallel, and in concert with, other necessary approvals.

I want to assure you that the staff will continue to work diligently toward reaching a final decision on this matter as soon as practical and will maintain its focus on ensuring public health and safety.

Sincerely, 1

Shirley Ann Jackson i

l

/ 5 UNITED STATES O' k NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20556-0001 g g

\,,,,,,/ September 11, 1998 CHAIRMAN The Honorable Earl Blumenauer United States House of Representatives Washington, D.C. 20515

Dear Congressman Blumenauer:

i I am responding to your August 17,1998, letter regarding the U.S. Nuclear Regulatory ,

Commission's (NRC) efforts regarding review activities for the proposed one-time shipment of the Trojan reactor vessel, for disposal. As indicated in your letter, you are aware that this review involves technical issues, and the staff is actively engaged in determining the adequacy of this proposal and its impact on public health and safety. Also, you urged the staff to continue its active participation and complete the review by September 30,1998.

Although the review is still in process, the staff is in its final review phase and is planning to j submit a paper containing the staff's recommendation for Commission review in early October i 1998. This paper will allow the Commission, itself, to review the matter of granting or denying the exemptions to the applicable transportation regulations that would be necessary to allow the Trojan reactor vessel to be shipped in the manner requested. Contingent upon a favorable determination regarding the request, the staff expects to issue the final decision in November 1998, which would allow Portland General Electric Company (PGE) sufficient time to grout the reactor vessel internals in preparation for an August 1999 shipment.

Besides NRC approval, I hasten to add that PGE must also obtain, before shipment:

(a) approval to dispose of the reactor vessel at the U.S. Ecology site in the State of Washington; (b) an exemption from the U.S. Department of Transportation (DOT) regulations; and, (c) approval of a modification to the Trojan Decommissioning Plan from the State of Oregon. We have coordinated our review schedule with DOT, the U.S. Coast Guard, and the States of Oregon and Washington. The NRC decision-making process is acting in parallel, and in concert with, other necessary approvals.

I want to assure you that the staff will continue to work diligently toward reaching a final decision on this matter as soon as practical and will maintain its focus on ensuring public health and safety.

Sincerely, Shirley Ann Jackson