Responds to 830111 Generic Ltr 83-01, Operator Licensing Exam Site Visit, Identifying Requests for Site Visits to Conduct Licensing Exams to Be Submitted Jan 1983 - Dec 1985
ML20079N796
Person / Time
Site: Pilgrim
Issue date: 02/28/1983
From: Harrington W
BOSTON EDISON CO.
To: Eisenhut D
Office of Nuclear Reactor Regulation
References
83-57, GL-83-01, GL-83-1, NUDOCS 8303040432
Download: ML20079N796 (2)


Text

. ~ . . , ,

B O STO N EDISON CO M PANY 800 BOYLSTON STREET BOSTON. MAsSACHUBETTs 02199 WILLIAM D. HARRINGTON a ................, February 28, 1983 an==

BECo Letter No. 83- 57 Mr. Darrell G. Eisenhut, Director

-Division of Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission ]

Washington, D.C. 20555 License No. DPR-35 Docket No. 50-293

Subject:

Operator Licensing Examination Site Visit (Generic Letter No. 83-01)

Dear Sir:

This responds to the request for information contained in the NRC letter dated January 11, 1983. .

i In that letter, you requested that we identify all requests for site visits to l conduct licensing examinations or instructor certification which Boston Edison  ;

planned to submit between January,1983 and December,1985. l We believe the following addresses that request:

Request No. 1 Initial (cold) license examinations for units applying for operating licenses.

Response

This does not apply to Pilgrim.

Request No. 2 Initial license examinations to extend licenses to a second, identical unit af ter initial licensing.

Response

This does not apply to Pilgrim.

Request No. 3 Examinations to support certification of utility employees as instructors.

Response

(a) Boston Edison will need SR0 Certification exams for five (5) people in Sep-tember, 1983.

M003 8303040432 830228 PDR ADOCK 05000293

'CD; TON ErlON COMPANY Mr. Darrell G. Eisenhut, Director February 28, 1983 Page 2 (b) We will need an SR0 Certification exam for two (2) people in October,1984.

(c) We will need an SR0 Certification exam for two (2) people in October,1985.

Request No. 4 Examinations to support certification of individuals who are not utility employees but who are under contract to instruct licensed operators.

Response

This does not apply to Pilgrim.-

Request No. 5 Examinations for initial licensing of personnel at operating facilities or for upgrading a license from the Reactor Operator to the Senior Operator level.

Response

(a) An exam is scheduled for March 8,1983. This exam includes four (4) initial R0 and one (1) SR0 licenses.

(b) We will need an exam for five (5) upgrades to SR0 in September, 1983.

(c) We will need an exam for ten (10) initial R0 licenses and five (5) upgrades to SR0 in October, 1984.

(d) We will need an exam for ten (10) initial R0 licenses and five (5) upgrades to SR0 in October, 1985.  !

This response is our best estimate based on the information we have at this time.

With the exception of Response 5(a) above, all dates are tentative.

In addition, this information does not address retesting in cases where exams are failed. We would appreciate any information concerning the scheduling for such retesting should it become necessary.

Although this information is tentative, we hope that you will find it helpful in planning the allocation of your resources. Should you wish further information on this issue, please contact us.

Very truly yours,

<