Provides Formal Notification That Closing Date for Sale & Transfer of Pilgrim Station Scheduled to Occur on 990713. a Wang Will Be Verbally Notified of Time of Sale Closing
ML20209B943
Person / Time
Site: Pilgrim
Issue date: 06/30/1999
From: Alexander J
BOSTON EDISON CO.
To: Collins S
NRC (Affiliation Not Assigned)
References
BECO-2.99.068, ENGC-99-11, NUDOCS 9907080336
Download: ML20209B943 (2)


Text

-

'~

Q 10 CFR 50.90 moseon adroon Pilgrim Nuclear Power Station Rocky Hill Road Plymouth, Massachusetts 02360-5599 June 30,1999 BECo Ltr. 2.99.068 Entergy Ltr. ENGC 99-11 1

Mr. Samuel J. Collins Pilgrim Nuclear Power Station Director, Office of Nuclear Reactor Regulation Docket Number 50-293 U.S. Nuclear Regulatory Commission License Number DPR 35

{

Washington, DC 20555-0001

Subject:

Boston Edison Company and Enterav Nuclear Generation Comoany Transfer of Facility Operating License and Materials License I

and Conforming License Amendments

References:

1. BECo Ltr 2.98.163 (Entergy Ltr. ENGC 98-01),

dated December 21,1998. TAC NO. MA4447.

t

2. NRC Ltr. 1.99.048 (Order) dated April 29,1999.

This letter constitutes formal notification that the closing date for the sale and transfer of Pilgrim Station is scheduled to occur on July 13,1999. Mr. Alan Wang of your staff will be verbally notified of the time of sale closing.

By Reference 1, Boston Edison Company (Boston Edison) and Entergy Nuclear Generation Company (Entergy Nuclear) requested transfer of the Pilgrim Nuclear Power Station Facility Operating License DPR-35 and NRC Materials License 20-07626-04 from Boston Edison to Entergy Nuclear. Boston Edison and Entergy Nuclear also requested conforming license amendments be issued to become effective upon the sale closing.

By Order dated April 29,1999 (Reference 2), the NRC approved the transfer of the facility operating license and the materials license, and license amendments conforming to the transfer.

I Condition 7 of the Order specified that after the receipt of all required regulatory approvals, the Director, Office of Nuclear Reactor Regulation, shall be notified in writing of the date of the sale and transfer of Pilgrim. All required regulatory approvals have been received since the Order was issued Therefore, this letter is submitted in accordance with Condition 7 of the Order.

D Condition 6 of the Order specified that prior to the sale and transfer of Pilgrim Station, Entergy Nuclear shall provide satisfactory evidence that Entergy Nuclear has obtained the appropriate amount of insurance required by 10 CFR Part 140. Satisfactory evidence that Entergy Nuclear has obtained the appropriate amount of insurance will be submitted in a separate letter prior to the sale closing.

9907000336 990630 PDR ADOCK 0

e Bostdn Edison Company Docket 50-293 Entergy Nuclear Generation Company License No. DPR-35 Conditions 1 through 5 of the Order are contained in the amended Facility Operating License as (new)

Condition K (Conditions Related to the Sale and Transfer).

Please feel free to contact me at Pilgrim Station, (508) 830-8269, if you have any questions or require any additionalinformation regarding the sale closing.

Sinc ander clear Assess ent Group Manager DWE/sc l

Enclosure f

cc:

I Mr. Alan B. Wang, Project Manager Mr. Hubert J. Miller Project Directorate 1-3 Region l Administrator Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop: OWFN 14B20 Region i 1 White Flint North 475 Allendale Road 11555 Rockville Pike King of Prussia, PA 19406 Rockville, MD 20852 Senior Resident inspector U.S. Nuclear Regulatory Commission Pilgrim Nuclear Power Station Attention: Document Control Desk Washington, DC 2.0555-0001 Mr. Robert Hallisey Mr. Peter LaPorte, Director Radiation Control Program Mass. Energy Management Agency Center for Communicable Diseases 400 Worcester Road i

Mass. Dept. of Public Health P.O. Box 1496 305 South Street Framingham, MA 01701-0313 Jamaica Plain, MA 02130 Page 2 299068 1