n L hBoston Edison UgijV A 8EC ENERGY CDMPANY J.F. Alexander Nuclear Assessment Group Manager June 7,1999 BECo Ltr. 2.99.058 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Notification of Chanae in Corrective Action Completion Date

References:

4 A

BECo letter 2.98.070, dated May 27,1998, " Reply to Notice of Violation and Proposed imposition of Civil Penalty -165,000, dated April 27,1998, (NRC Inspection Report No. 50-293/97-05,12 and 13)"

j In Reference "A", Boston Edison Company (BECo) committed to complete a modification during refueling outage 12 to replace the residual heat removal spray flow indicators and associated instrumentation with state of the art equipment to lower the instrument uncertainty to be in compliance with R.G.1.105 (Violation No, l.C.4). The proposed indicators failed quality assurance assessments for digital verification, b

validation, and control of software. The proposed modification can be completed on-line. Procurement of quality compliant indicators is proceeding with a different vendor with a planned October 1999 completion date.

The NRC resident inspector has been apprised of these changes as part of the routine interface activity. Should you require further information, please do not hesitate to

/

contact me or Mr. Walter Lobo at 508-830-7940.

)

I and WGUnb 299058 9906160035 990607

~

PPR ADOCK 05000293 G

PDR Pilgrim Nuclear Power Station, Rocky Hill Road, Plymouth, Massachusetts 02360 i

k cc: Region i Administrator Sr. Resident inspector

, U.S. Nuclear Regulatory Commission Pilgrim Nuclear Power Station 475 Allendale Road King of Prussia, PA 19406

' Mr. Alan B. Wang, Project Manager -

Project Directorate 1-3 Office of Nuclear Reactor Regulation Mail Stop: OWFN 8F2 U.S. Nuclear Regulatory Commission 1 White Flint North 11555 Rockville Pike Rockville, MD 20852