Summary of Telecommunication with Omaha Public Power District (OPPD) to Discuss Open Item 3.6.2.4.3.2-1 on Electrical Bus Bars - Renewal of the Operating License for Fort Calhoun Station, Unit 1 (FCS)
ML031640609
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 06/13/2003
From: Subbaratnam R
NRC/NRR/DRIP/RLEP
To:
Subbaratnam R NRR/DRIP/RLEP, 415-1478
References
Download: ML031640609 (6)


Text

June 13, 2003 Applicant: Omaha Public Power District FACILITY: Fort Calhoun Station, Unit 1

SUBJECT:

SUMMARY

OF TELECOMMUNICATION WITH OMAHA PUBLIC POWER DISTRICT (OPPD) TO DISCUSS OPEN ITEM 3.6.2.4.3.2-1 ON ELECTRICAL BUS BARS - RENEWAL OF THE OPERATING LICENSE FOR FORT CALHOUN STATION, UNIT 1 (FCS)

On June 6, 2003, the NRC staff (the staff) and representative from OPPD held a telecommunication (telecon) to discuss the Open Item 3.6.2.4.3.2-1 in the draft safety evaluation report for renewal of the operating license for FCS. A list of telecon participants are enclosed (see Enclosure 1). The following is a summary of the discussion.

Staff Question (1) :

The staff had a point of clarification concerning the applicants previous response to a staff dialogue on May 8, 2003 on the subject. The response to the open item were as follows :

"When scoping and screening was performed for bus bars at FCS, as a conservative measure, all bus bars were included in the scope of license renewal with the exception of those associated with SBO. SBO beyond the plant boundary was added later in response to a staff RAI and the NRC Interim Staff Guidance on SBO. All of the in-plant bus bars are inside the enclosure of an active component, such as switchgear, power supplies, etc., and are considered to be piece parts of the larger assembly. Per 10 CFR 54.21, OPPD considers them outside the scope for license renewal. However, in the final response, the last three lines concerning the SBO beyond the plant boundary were omitted. The staff wanted to know why the applicant dropped the discussion.

Resolution:

The applicant did not have any objection to restoring the discussion concerning the SBO path beyond the plant boundary in the discussion as above.

Staff Question (2) :

The staff also had a question regarding the bolted iso-phase bus connection (not welded) if it will be managed as part of the periodic surveillance and preventive maintenance program.

Resolution:

The applicant stated that the bus bars credited in the SBO restoration path are all connected to the primary side of the auxiliary transformers by bolted connections. The aging of the bolted connections is managed through implementation of the OPPD Periodic Surveillance and Preventive Maintenance Program.

The applicant agreed to incorporate these two clarifications in its final response to OI 3.6.2.4.3.2-1.

OPPD has reviewed and provided no comments on this telecon summary.

/RA/

Ram Subbaratnam, Project Manager License Renewal Section License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No.: 50-285

Enclosures:

As stated cc w/encl: See next page

The applicant agreed to incorporate these two clarifications in its final response to OI 3.6.2.4.3.2-1.

OPPD has reviewed and provided no comments on this telecon summary.

/RA/

Ram Subbaratnam, Project Manager License Renewal Section License Renewal and Environmental Impacts Program Division of Regulatory Improvement Programs Office of Nuclear Reactor Regulation Docket No.: 50-285

Enclosures:

As stated cc w/encl: See next page DISTRIBUTION: See next page Accession no.: ML031640609

  • See previous concurrence C:\ORPCheckout\FileNET\ML031640609.wpd OFFICE PM:RLEP:DRIP PM:RLEP:DRIP LA:RLEP:DRIP SC:RLEP:DRIP NAME RSubbaratnam* WBurton* YEdmonds* SLee*

Date 06/12/2003 06/13/2003 06/12/2003 06/13/2003 OFFICIAL RECORD COPY

DISTRIBUTION: Summary of Telecon with OPPD Re: FCS RAIs, Dated: June 13, 2003 ML031640609 HARD COPY RLEP RF WBurton E-MAIL:

PUBLIC J. Johnson W. Borchardt D. Matthews F. Gillespie RidsNrrDe R. Barrett E. Imbro G. Bagchi K. Manoly W. Bateman J. Calvo C. Holden P. Shemanski H. Nieh G. Holahan H. Walker S. Black B. Boger D. Thatcher G. Galletti C. Li J. Moore R. Weisman M. Mayfield A. Murphy W. McDowell S. Smith (srs3)

T. Kobetz R. Assa S. Duraiswamy C. Munson RLEP Staff O. Chopra, EEIB, DE

LIST OF ATTENDEES OMAHA PUBLIC POWER DISTRICT(OPPD)

FORT CALHOUN STATION, UNIT 1 JUNE 6, 2003 Telecon Participants Attendees Affiliation Tom Matthews OPPD Ram Subbaratnam U.S. Nuclear Regulatory Commission (NRC)

Om Chopra NRC Enclosure 1

Ft. Calhoun Station, Unit 1 cc:

Winston & Strawn Mr. S. K. Gambhir ATTN: James R. Curtiss, Esq. Division Manager - Nuclear Operations 1400 L Street, N.W. Omaha Public Power District Washington, DC 20005-3502 Fort Calhoun Station FC-2-4 Adm.

Post Office Box 399 Mr. Kent Wilcox, Chairman Hwy. 75 - North of Fort Calhoun Washington County Board Fort Calhoun, NE 68023-0399 of Supervisors P.O. Box 466 Mr. Mark T. Frans Blair, NE 68008 Manager - Nuclear Licensing Omaha Public Power District Mr. Wayne Walker, Resident Inspector Fort Calhoun Station FC-2-4 Adm.

U.S. Nuclear Regulatory Commission Post Office Box 399 Post Office Box 309 Hwy. 75 - North of Fort Calhoun Fort Calhoun, NE 68023 Fort Calhoun, NE 68023-0399 Regional Administrator, Region IV Mr. Alan P. Nelson U.S. Nuclear Regulatory Commission Nuclear Energy Institute 611 Ryan Plaza Drive, Suite 1000 1776 I Street, N.W., Suite 400 Arlington, TX 76011 Washington, DC 20006-3708 Mr. John Fassell, LLRW Program W. Dale Clark Library Manager Attn: Margaret Blackstone Health and Human Services 215 South 15th Street Regulation and Licensure Omaha, NE 68102 Consumer Health Services 301 Cententiall Mall, South Blair Public Library P. O. Box 95007 Attn: Ruth Peterson Lincoln, Nebraska 68509-5007 210 South 17th Street Blair, NE 68008-2055 Mr. Richard P. Clemens Manager - Fort Calhoun Station Omaha Public Power District Fort Calhoun Station FC-1-1 Plant Post Office Box 399 Hwy. 75 - North of Fort Calhoun Fort Calhoun, NE 68023 Mr. Joseph Gasper Manager - Nuclear Licensing Omaha Public Power District Fort Calhoun Station FC-2-4 Adm.

Post Office Box 399 Hwy. 75 - North of Fort Calhoun Fort Calhoun, NE 68023-0399