MONTHYEARML22333B0922022-12-21021 December 2022 FY22 Nmss/Duwp Operating Experience Report ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML21271A5992021-08-0303 August 2021 License Amendment Request (LAR) 21-01, Chapter 8, 12, Omaha Public Power District, FCS-SAF-103, FCS Deconstruction Health and Safety Plan CAC2 ML21202A3632021-07-20020 July 2021 Memorandum Disposition of Documents Discovered at Jensen Hughes ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary ML21055A4022021-05-14014 May 2021 Memorandum: Final Environmental Assessment and Finding of No Significant Impact of Initial and Updated Decommissioning Funding Plans for the Cooper, Fort Calhoun and Virgil C. Summer Independent Spent Fuel Storage Installations ML21271A1492021-04-13013 April 2021 License Amendment Request (LAR) 21-01, Chapter 1 9 Haley & Aldrich, Inc. Memorandum to Energysolutions, File No. 0127960-006, Fort Calhoun Nuclear Power Statio~1 ML20056E4872020-02-26026 February 2020 Staff Review of Fort Calhoun Independent Spent Fuel Storage Installation Physical Security Plan, Security Training and Qualification Plan, and Safeguard Contingency Plan, Revision 0 and the Verification of Additional Security Measures (ASM) ML18173A0082018-06-20020 June 2018 Cancelling Numerous Inspection Report Numbers ML18108A1212018-04-11011 April 2018 American Nuclear Insurers - Notification of Change in the Number of Power Reactors in the Secondary Financial Protection (SFP) Program ML17275A2642017-11-21021 November 2017 Safety Evaluation Input on Fort Calhoun Station Request for Approval of Permanently Defueled Emergency Plan and Emergency Action Level Scheme, Docket No. 50-285 ML16253A3212016-09-13013 September 2016 Notice of Webinar Meeting with Nebraska Public Power District to Discuss Dam Failure Analysis Developed for the Integrated Assessment for Cooper Nuclear Station ML16088A2042016-03-28028 March 2016 Memo T Bowers from s Ruffin, Technical Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations W/ Encl 2 (Template) ML16088A2052016-03-28028 March 2016 Enclosure 1 - (72.30 DFP Reviews to Be Completed 2015) - Memo T Bowers from s Ruffin, Technial Assistance Requests - Review 2015 Tri-Annual Decommissioning Funding Plans for Multiple Independent Spent Fuel Storage Installations ML16068A3882016-03-0909 March 2016 Memo Ico Staff Review of V.C. Summer Nuclear Station Physical Security Plan Rev. 15 (NS113625) for Verification of ASM Order (EA-13-228) Implementation (CAC L25088) ML16061A5252016-02-26026 February 2016 Memo T Mossman, NSIR, Technical Assistance Request - Review of Physical Security Plan for the Virgil C. Summer Nuclear Station ISFSI (72-1038, 50-395) (L25088) ML16057A1232016-02-26026 February 2016 Cy 2015 Baseline Completion ML16007A4942016-01-11011 January 2016 Review of the Updated Final Safety Analysis Report for the Period June 14, 2014 Through December 4, 2015 ML14163A0022014-06-16016 June 2014 Summary of Audit Conducted March 5-9, 2012, Request to Adopt National Fire Protection Association (NFPA) 805, Performance-Based Standard for Fire Protection for LWR Electric Generating Plants ML14129A4452014-05-12012 May 2014 5/13/2014 Notice of Forthcoming Closed Meeting to Discuss Dam Failure Analysis for Cooper Nuclear Station and Fort Calhoun Station, Unit 1 ML14114A7012014-04-24024 April 2014 Task Interface Agreement - Concurrence on Fort Calhoun Tornado Missile Protection Licensing Basis (TIA 2013-07) ML14085A1842014-03-28028 March 2014 Final Fort Calhoun Gothic TIA Response ML14016A2602014-01-28028 January 2014 Fc Final Containment Structural TIA ML13351A4762013-12-16016 December 2013 Recommendation for NRC to Close Confirmatory Action Letter EA-13-020 Supporting the Restart of Fort Calhoun Station and Recommendation to Issue Post-Restart Confirmatory Action Letter ML13346A0822013-12-12012 December 2013 Notice of Forthcoming Closed Meeting to Discuss Dam Failure Analysis for Cooper Nuclear Station and Fort Calhoun Station, Unit 1 ML13309A0802013-12-11011 December 2013 Memorandum to File: Transcript for 10 CFR 2.206 Petition from Beyond Nuclear (Et Al) Regarding General Electric Mark I and Mark II Boiling-Water Reactors ML13312A8522013-11-0808 November 2013 Meeting Notice with Public to Discuss Fort Calhoun Station ML13253A3542013-09-27027 September 2013 Letter to R. Morris Information Exchange Pertaining to Health Issues Related to Crow Butte Resources Uranium Mine and Ft. Calhoun Nuclear Generating Station ML13165A1972013-06-13013 June 2013 06/26//2013 Notice of Public Meeting with Nebraska Public Power District to Discuss Progress and Status Plans for Addressing Substantive Cross-Culting Issues in the Areas of Human Performance and Problem Identification and Resolution ML13102A1892013-04-15015 April 2013 4/22/12 Notice of Closed Meeting with Omaha Public Power District to Discuss Flooding Issues Associated with Fort Calhoun, Unit 1 ML13101A2232013-04-11011 April 2013 Meeting Notice with Omaha Public Power District - Potential License Amendment Requests for Fort Calhoun, Unit 1 Related to Flood Protection for Raw Water System, Tornado Missile Protection, Piping/Code Use, and Alternate Seismic Criteria ML13066A8772013-03-0707 March 2013 Issuance of Revised U.S. Nuclear Regulatory Commission Manual Chapter 0350 Panel Fort Calhoun Station Restart Checklist Basis Document ML13046A3212013-02-19019 February 2013 Notice of Closed Meeting with Fort Calhoun to Discuss Safeguards Information, Proprietary, or Other Sensitive Information ML12335A1652012-11-30030 November 2012 Forthcoming Meeting with Omaha Public Power District to Discuss Containment Internal Structures Issues to Support Restart of Fort Calhoun Station, Unit 1 ML12345A2702012-11-30030 November 2012 Revised 12/12/2012 Notice of Forthcoming Meeting with Omaha Public Power District to Discuss Containment Internal Structures Issues to Support Restart of Fort Calhoun Station, Unit 1 ML12340A2682012-11-27027 November 2012 CNS Memo DED12-0003 Response to 10 CFR 50.54(f) Section 2.3 Seismic, Enclosing Engineering Evaluation 12-E18, Revision 0 ML12318A3192012-11-13013 November 2012 Issuance of U.S. Nuclear Regulatory Commission Manual Chapter 0350 Panel Fort Calhoun Station Restart Checklist Basis Document ML12251A3172012-09-0707 September 2012 Manual Chapter 0350 Oversight Panel Charter - Revision ML12066A0302012-03-29029 March 2012 Closure Memorandum: Issue for Resolution 2011-001 Fort Calhoun - Failure to Maintain External Flooding Procedures. ML12229A1842012-03-0606 March 2012 Backfit Panel Regarding Fort Calhoun Flooding ML1134707162011-12-13013 December 2011 Memo to M.S.Virgilio Notification of Change to Regulatory Oversight of Fort Calhoun Station ML11293A1982011-10-19019 October 2011 Charter for Backfit Panel on Postulated Failure of Upstream Dams Affecting Fort Calhoun Station ML11250A1712011-09-14014 September 2011 Notice of Forthcoming Meeting with Petitioner Requesting Action Under 10 CFR 2.206 Regarding Immediate Suspension of the Operating Licenses of General Electric (GE) Mark 1 Boiling Water Reactors (Bwrs) ML1120707482011-07-26026 July 2011 July 20, 2011, Meeting Summary Pre-Application Meeting with South Carolina Electric and Gas Regarding General License Independent Spent Fuel Storage Installation Plans (TAC No. L24544) ML1118811312011-07-0707 July 2011 Docketing of Nonproprietary Information Provided by Omaha Public Power District (OPPD) Personnel Following the June 2, 2011, Regulatory Conference ML13106A1702011-07-0101 July 2011 Proposed Adequate Protection Backfit Exception ML1118100852011-06-30030 June 2011 Notice of Meeting with Nebraska Public Power District to Discuss Cooper'S Request to Revise TS 3.4.3, Safety/Relief Valves (Srvs) and Safety Valves (Svs), to Reduce Number of Required SRVs for Overpressure Protection ML11174A2322011-06-21021 June 2011 for the Record-06-21-2011: NRC Ensures Public Safety Through Rigorous Oversight of Nuclear Power Plant Safety Standards ML1113807322011-05-18018 May 2011 Regulatory Conference with Omaha Public Power ML1113306432011-05-16016 May 2011 Notice of Forthcoming Prelicensing Teleconference on 5/26/11 with Omaha Public Power District Related to Fort Calhoun Station, Unit 1's License Amendment Submittal Related to Transition to Risk-Informed NFPA-805 2022-06-06
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 14, 2021 MEMORANDUM TO: File FROM: Chris Allen, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards
SUBJECT:
FINAL ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT FOR THE INITIAL AND UPDATED DECOMMISSIONING FUNDING PLANS SUBMITTED IN ACCORDANCE WITH 10 CFR 72.30 FOR THE COOPER AND FORT CALHOUN INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS AND THE INITIAL DECOMMISSIONING FUNDING PLAN SUBMITTED IN ACCORDANCE WITH 10 CFR 72.30 FOR THE VIRGIL C. SUMMER INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS The subject documents related to the Cooper Nuclear Station, Fort Calhoun Station, Unit 1, and Virgil C. Summer Nuclear Station, Unit No. 1 Independent Spent Fuel Storage Installation decommissioning funding plan submissions for 2012, 2013, 2015, and 2016 were approved this date and are attached for record purposes.
Docket Nos.: 72-66, 72-54 and 72-1038 License No.: SFGL-42, SFL-28 and SFGL-61
Enclosures:
- 1. EA/FONSI FRN
- 2. EA/FONSI for Cooper DFP
- 3. EA/FONSI for Fort Calhoun DFP
- 4. EA/FONSI for Virgil C. Summer DFPs
SUBJECT:
FINAL ENVIRONMENTAL ASSESSMENT AND FINDING OF NO SIGNIFICANT IMPACT FOR THE INITIAL AND UPDATED DECOMMISSIONING FUNDING PLANS SUBMITTED IN ACCORDANCE WITH 10 CFR 72.30 FOR THE COOPER AND FORT CALHOUN INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS AND THE INITIAL DECOMMISSIONING FUNDING PLAN SUBMITTED IN ACCORDANCE WITH 10 CFR 72.30 FOR THE VIRGIL C. SUMMER INDEPENDENT SPENT FUEL STORAGE INSTALLATIONS Document Dated: May 14, 2021 DISTRIBUTION:
PUBLIC DFM r/f RidsNmssRefsFab KLois, NMSS SHarwell, NMSS FMiller, NMSS MHenderson, NMSS RGladney, NMSS BWhite, NMSS JMcKirgan, NMSS JMaltese, OGC PJehle, OGC NMertz, OGC TWengert, NRR VThomas, NRR JParrott, NMSS RidsNMSSResource RidsNrrPMCooper Resource RidsNrrPMSummer Resource ADAMS Package Accession No.: ML21055A396
- via email OFFICE NMSS/DFM: PM NMSS/DFM: LA OGC (NLO) NMSS/STLB: BC NAME CAllen WWheatley* NMertz JMcKirgan*
DATE 2/26/2021 3/1/2021 5/13/2021 5/13/2021 OFFICIAL RECORD COPY