ML14139A344

From kanterella
Jump to navigation Jump to search

Summary of Closed Meeting Between Representatives of the Nuclear Regulatory Commission, Omaha Public Power District and Nebraska Public Power District to Discuss Flooding Analysis
ML14139A344
Person / Time
Site: Cooper, Fort Calhoun  Omaha Public Power District icon.png
Issue date: 05/29/2014
From: Robert Kuntz
Containment and Balance of Plant Branch
To:
Nebraska Public Power District (NPPD), Omaha Public Power District
Kuntz R, NRR/JLD, 415-3733
References
TAC MF3035, TAC MF3036
Download: ML14139A344 (3)


Text

LICENSEES:

FACILITIES:

SUBJECT:

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May 29, 2014 Omaha Public Power District Nebraska Public Power District Fort Calhoun Station, Unit 1 Cooper Nuclear Station

SUMMARY

OF MAY 9, 2014, CLOSED MEETING BETWEEN REPRESENTATIVES OF THE NUCLEAR REGULATORY COMMISSION, OMAHA PUBLIC POWER DISTRICT AND NEBRASKA PUBLIC POWER DISTRICT TO DISCUSS THE FLOODING ANALYSIS ASSOCIATED WITH FORT CALHOUN STATION, UNIT 1 AND COOPER NUCLEAR STATION (TAC NOS. MF3035 AND MF3036)

On May 9, 2014, the U.S. Nuclear Regulatory Commission (NRC) staff held a meeting with Omaha Public Power District (OPPD), and Nebraska Public Power District (NPPD) to discuss potential interim actions for the flooding hazard reevaluation (FHR) for Fort Calhoun Station, Unit 1 (FCS) and Cooper Nuclear Station (CNS). The meeting was held at NRC Headquarters in Rockville, MD. The participants in the meeting included the following individuals:

NRC - Christopher Cook, Ken See, Rob Kuntz, Rob Taylor, Andrea Kock, Mike Markley and Joe Sebrosky OPPD - Harry Goodman Joe Gasper, Larry Cieslik, and Bill Hansher NPPD-Matt Nienaber, Rod Penfield, Dan Suman, Roman Estrada, and Bryan Ford The purpose of the meeting was to discuss the licensees' plans for interim actions at FCS and CNS. By letters dated August 26, 2013 (Agencywide Documents Access and Management System (ADAMS) under Accession No. ML13240A128) and August 22, 2013 (Accession No. ML13246A075) OPPD, and NPPD respectively, requested NRC staff assistance in obtaining information from the U.S. Army Corps of Engineers (USACE) to support OPPD's and NPPD's development of a FHR response to the March 12, 2012, request for information (ADAMS Accession No. ML12073A348). By letters dated April4, 2014 (ADAMS Accession Nos.

ML14091A383 and ML14091A345) the NRC transmitted the USACE results to CNS and FCS.

The licensees stated that they are developing interim action plans based on the USACE results found in the Apri14, 2014, letter. The licensees further stated that the plans would likely be a combination of protective and mitigative measures.

CONTACT: Robert F. Kuntz, NRR/JLD 301-415-3733 The staff stated that the plan should be in sufficient detail so that the staff could determine that the measures taken or planned could be implemented as described and would protect or mitigate the potential hazard as described in the plan. The staff further stated that its expectations are that OPPD and NPPD provide their interim actions for FCS and CNS within 60 days of the receipt of the USAGE results. The staff indicated it could be receptive to OPPD and NPPD taking slightly longer than 60 days given the level of detail expected in the interim actions document. However, the staff emphasized that OPPD and NPPD would have to make the case for extending the schedule for providing interim actions beyond 60 days.

Please direct any inquiries to me at 301-415-3733 or at Robert.Kuntz@nrc.gov.

Docket Nos. 50-285 and 50-298 cc: Distribution via ListServ

ML14139A344 OFFICE NRR/JLD/PMB/PM NAME RKuntz DATE 5/29/14 OFFICE NRR/JLD/PMB/PM NAME MMitchell DATE 5/29/14 NRR/JLD/LA*

Slent 5/19/14 NRR/JLD/PMB/PM RKuntz 5/29/14