ML112211617

From kanterella
Jump to navigation Jump to search
7/27/2011- Summary of Public Meeting with Omaha Public Power District to Discuss Post-Flooding Recovery Actions for Fort Calhoun Station
ML112211617
Person / Time
Site: Fort Calhoun Omaha Public Power District icon.png
Issue date: 08/05/2011
From: James Drake
NRC/RGN-IV/DRS/PSB-2
To: Bannister D
Omaha Public Power District
References
Download: ML112211617 (17)


Text

August 5, 2011 David J. Bannister, Vice President and Chief Nuclear Officer Omaha Public Power District Fort Calhoun Station FC-2-4 P.O. Box 550 Fort Calhoun, NE 68023-0550

Subject:

MEETING

SUMMARY

FOR PUBLIC MEETING WITH OMAHA PUBLIC POWER DISTRICT

Dear Mr. Bannister:

On July 27, 2011, representatives of the Omaha Public Power District (OPPD) met with NRC personnel at the Doubletree Inn, in Omaha, Nebraska, to discuss post-flooding recovery actions for Fort Calhoun Station. The list of attendees and a copy of the presentation slides are included as Enclosures 1, 2 and 3.

The purpose of the meeting was to discuss OPPDs plans and actions for identifying and assessing impacts of the long-term flooding on plant structures and equipment prior to the future restart of Fort Calhoun Station. During the meeting, OPPD representatives discussed post-flooding recovery actions they plan to take prior to restarting the plant, including plans to conduct an extensive review of plant systems, structures and components, including support systems and site structures. The details of the discussion are provided in the attached slides used by OPPD during their presentation. OPPD officials stated that they would submit a detailed plan to the NRC within two weeks of the date of the meeting.

NRC representatives discussed their intention to incorporate OPPD commitments into a Confirmatory Action Letter to confirm OPPDs commitments to complete certain actions prior to restarting Fort Calhoun Station. Following issuance of the Confirmatory Action Letter, NRC representatives discussed their plans to conduct inspections to verify completion of applicable actions in the Confirmatory Action Letter, and to conduct a public meeting to discuss the results of those inspections, prior to restart of the plant.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter and its enclosures will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRCs Agency wide Documents Access and Management System (ADAMS). ADAMS is accessible from the Public UNITED STATES NUCLEAR REGULATORY COMMISSION REGION IV 612 EAST LAMAR BLVD, SUITE 400 ARLINGTON, TEXAS 76011-4125

Electronic Reading Room page of the NRCs public web site at http://www.nrc.gov/readingrm/adams.html.

Sincerely,

/RA/

James F. Drake, Chief (Temporary)

Project Branch E Division of Reactor Projects

Enclosures:

1. Meeting Attendance List
2. NRC Presentation Slides
3. OPPD Presentation Slides cc: Distribution via ListServ

Electronic distribution by RIV:

Elmo Collins, Regional Administrator, Region IV Kriss Kennedy, Director, Division of Reactor Projects (DRP)

Jeffrey Clark, Acting Deputy Director, DRP James Drake, Branch Chief (Temporary), Project Branch E, DRP John Kirkland, Senior Resident Inspector, Fort Calhoun Station Art Howell, DRA Anton Vegel, D, DRS Robert Caldwell, DD, DRS Sue Bogle (OEWEB Resource)

John McHale (OEDO RIV Coordinator)

OEMAIL, D/OE Jenny Weil, OCA Lynnea Wilkins, Project Manager, NRR Ray Azua, Senior Project Engineer, PB/FC John Kirkland, Senior Resident Inspector Jacob Wingebach, Resident Inspector Victor Dricks, Region IV PAO Lara Uselding, Region IV PAO Bill Maier, Region IV RSLO Karla Fuller, Region IV RC Nick Taylor, Region IV ACES Ray Kellar, Region IV ACES Lisa Quayle, Region IV RA Administrative Assistant Anita Tannenbaum, Region IV DRA Administrative Assistant Dawn Yancey, Region IV DRP Administrative Assistant Dana Lackey, Region IV DRP Administrative Assistant Verlyn Jenkins, Region IV DRP Administrative Assistant Vivian Mehrhoff, Region IV DRS Administrative Assistant Tracy Karl, Region IV DRS Administrative Assistant Deborah Harrison, Region IV DRS Administrative Assistant Berni Madison, FC Resident Administrative Assistant Earnestine Clay, BC, DRMA Harold McKelvey, IRMB Phil Longdo, Receptionist Ann Mattila, Support Services Specialist R:\\_REACTORS\\FCS\\2011\\Public Mtg Summary 07-27-2011.docx ML112170296 SUNSI Rev Compl.

Yes No ADAMS Yes No Reviewer Initials JFM1 Publicly Avail Yes No Sensitive Yes No Sens. Type Initials JFM1 RIV/PE:DRP PAO RSLO D:DRP C:DRP/E JFMelfi VLDricks WAMaier KMKennedy JFDrake

/RA/

/RA/

/RA/

/RA/verbal to JFD

/RA/

08/04/2011 08/04/2011 08/04/2011 08/05/2011 08/05/2011 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax ML112211617

1 Fort Calhoun Station Public Meeting Post-flooding recovery actions 1

Nuclear Regulatory Commission - Region IV July 27, 2011 NRC Personnel

  • Elmo Collins, Regional Administrator, Region IV
  • Kriss Kennedy, Director, Division of Reactor Projects (DRP)
  • Jeffrey Clark, Acting Deputy Director, DRP

Agenda

  • Opening and Introductions
  • Purpose and Objectives
  • NRC Focus & Actions OPPD P i

3

  • Discussion
  • NRC Closing Remarks
  • NRC available to address public questions Meeting Purpose
  • Communicate NRC and OPPD actions in response to flooding at Fort Calhoun Station (FCS)
  • Discuss NRC and OPPD actions prior to restart of FCS
  • Discuss plans to formalize OPPD commitments in a Confirmatory Action Letter 4

2 Meeting Objectives

  • External stakeholder understanding of NRC and OPPD to flooding at FCS
  • Shared understanding of:

- Planned NRC and OPPD actions needed prior to restart of FCS

- Actions OPPD commits to complete prior to restart of FCS

- NRCs intent to document OPPD commitments in a Confirmatory Action Letter 5

NRC Focus & Actions

  • NRC actions during flooding
  • NRC focus and actions for follow up p

to flooding and plant restart

- Focus areas

- Commitments

- Inspections

- Follow up 6

OPPD Presentation David Bannister 7

David Bannister Vice President / Chief Nuclear Officer Omaha Public Power District NRC Closing Remarks

  • Remarks by NRC Representatives 8

3 Open to the Public

  • The NRC places a high priority on keeping the public and stakeholders informed of its activities
  • At www.nrc.gov, you can:

9 g

, y

- Find public meeting dates and transcripts;

- Read NRC testimony, speeches, press releases, and policy decisions;

- Access the agencys Electronic Reading Room to find NRC publications and documents; and

- Subscribe to LISTSERVE to automatically receive correspondence from the NRC.

Contacting the NRC

  • Report an emergency

- (301) 816-5100 (call collect)

  • Report a safety concern 10

- (800) 695-7403

- Allegation@nrc.gov

  • General information or questions

- www.nrc.gov

- Select What We Do for Public Affairs 11 Questions?

7/29/2011 1

Fort Calhoun Station NRC Public Meeting July 27, 2011 Dave Bannister Vice President - Nuclear Agenda

  • Current Conditions
  • Flooding Actions Levels
  • On-Going Flood Response On Going Flood Response
  • Post-Flooding Recovery Actions
  • Commitment to Safety Current Conditions
  • Reactor has been shutdown since April 9, 2011

- All normal electrical power sources are available

- All normal cooling systems are available

- All normal makeup water sources are available

- All emergency backup systems are available

- Contingency backup systems have been added Flooding Action Levels

  • 1014 ft - Design Basis Flood Level (Maximum rainfall + snow melt + dam failure)
  • 1009 ft - Technical Specification Shutdown Level Level
  • 1004 ft - Abnormal Operations Procedure Shutdown Level (Approximate ground level of plant site)

7/29/2011 2

Flooding Action Levels

  • Emergency Response Procedure

- 1004 ft - Entry conditions for NOUE (June 6, 2011)

- 1009 ft - Escalation conditions for ALERT

<1004 ft Exit conditions for NOUE

- <1004 ft - Exit conditions for NOUE

  • 1006 Ft Current River Level
  • Level Predictions depend on weather and dam releases On-Going Flood Response
  1. 1 Priority - Nuclear Safety
  1. 2 Priority - Protect Corporate Assets
  • Incident Command Structure

- Incident Commander and Logistics Coordinator assist th O ti Shift M the Operations Shift Manager

- Primary Responsibility is to monitor flooding conditions, mitigate water intrusion and assist with special staffing and supply needs related to the flooding conditions

- Additional staff added to monitor pumping stations and erect elevated walkways On-Going Flood Response

  • Flood Control Barriers:

- Metal flood gates protect equipment necessary for nuclear safety

- Earthen berm around the switchyard allows full Earthen berm around the switchyard allows full use of off-site electrical power sources

- Aqua-Dams keep water away from buildings and allow continued use of plant facilities

- Hesco barriers allow continued use of normal access points to the plant protected area

7/29/2011 3

Training Center 10089 Elevation Switchyard 1006-1007 Elevation Admin Bldg 1007 Elevation Security Bldg 10044 Elevation Intake Struc 10076 Flo Elevation Turbine Bldg 1032 Elevation On-Going Flood Response

  • Additional Contingency Actions

- Backup portable diesel generator

- Additional diesel fuel oil storage tankers Additional fire truck on site

- Additional fire truck on site

- Additional makeup water storage

- Pumping stations to remove barrier seepage

- Additional parking lot for support staff

- Elevated walkways, bridges and boats Training Center 10089 Elevation Switchyard 1006-1007 Elevation Admin Bldg 1007 Elevation Security Bldg 10044 Elevation Intake Struc 10076 Flo Elevation Turbine Bldg 1032 Elevation

7/29/2011 4

On-Going Flood Response

  • Support from Local and Extended Community

- Fire Departments (Blair, Fort Calhoun, Bennington)

- Blair Public Schools (temporary parking facility)

- Construction and Engineering Companies

- Construction Supply Companies Construction Supply Companies

- Staff augmentation

- Alternate working locations

- Municipal, State and Federal Agencies

- Elected Officials (Board, Senator, Congressmen)

- INPO and Nuclear Utilities

- OPPD Employees Post-Flooding Recovery Actions

  • OPPD is prepared to respond with cleanup and site restoration followed by plant restart
  • The duration of the flooding is unprecedented in the nuclear industry and requires careful in the nuclear industry and requires careful consideration and diligence prior to plant restart Post-Flooding Recovery Actions
  • Extensive review of all plant systems, structures and components, including support systems and site structures, to assess the impact of the flood impact of the flood
  • Lessons learned from flood recovery efforts outside the nuclear industry Post-Flooding Recovery Actions
  • Regardless of river level, the plant will not be restarted until OPPD is certain that it is safe
  • OPPD will make formal commitments to the NRC regarding post-flooding recovery actions to ensure continued safe operation at FCS
  • Commitments will be met prior to changing plant conditions
  • OPPD will not start-up FCS without concurrence from the NRC that all restart commitments have been satisfied

7/29/2011 5

OPPD is developing detailed action plans

  • Site Restoration Plan

- Including removal of flood barriers, site cleanup and flood impact assessments Post-Flooding Recovery Actions

  • Refueling Outage Completion Plan

- Including restart of the reactor and generation of electricity

  • Regulatory Response Plan

- Including coordination of the NRC confirmatory action letter response Site Restoration Plan Key Elements:

1. Assess flooding impact and overall condition of:

Plant systems, structure and components, including the Fire Protection System Support systems, including the switchyard and communication systems Site structures, including used fuel storage Underground cables Underground piping systems Security systems, structures and equipment Emergency response systems, structures and equipment Note: Any discrepancies will be documented in the condition reporting system to ensure timely resolution Site Restoration Plan Key Elements:

2. Remove temporary flood barriers and equipment Aqua-Dam, Hesco barriers, sandbags Scaffold walkways and bridges Portable pumps and fuel containers Portable tanks and generators Miscellaneous equipment and supplies
3. Cleanup debris deposited by flood waters
4. Perform site surveys following site cleanup
5. Restore electrical bus 1B4A Site Restoration Plan Key Elements:
6. Assess Engineering Programs to determine any necessary flood-related changes 7

Assess the impact on warehouse supply inventory

7. Assess the impact on warehouse supply inventory
8. Assess any remaining modifications that may need to be incorporated into the site configuration control program

7/29/2011 6

Refueling Outage Completion Plan Key Elements:

1. Evaluate the need to add additional activities to the RFO scope based on assessments performed under the Site Restoration Plan
2. Complete all planned RFO maintenance
3. Complete all planned RFO STs and PMs
4. Complete a verification of all system lineups
5. Verify completion of Confirmatory Action Letter (CAL) commitments
6. Start-up plant and generate electricity Regulatory Response Plan Key Elements:
1. Submit detailed post-flooding action plans
2. Conduct periodic conference calls with NRC to communicate action plan status
3. Respond to the NRC CAL
4. Coordinate NRC inspection activities
5. Resolve long-term CAL commitments that extend beyond plant startup
6. Provide detailed lessons learned report Commitment to Safety
  • OPPD is committed to ensuring that public health and safety remains the #1 priority
  • OPPD will provide detailed post-flooding action plans to the NRC for their review action plans to the NRC for their review
  • OPPD will aggressively implement the post-flooding action plans as river conditions improve in accordance with CAL commitments Commitment to Safety
  • An independent oversight panel will review flood impact assessments
  • Regardless of river level, the plant will not be restarted until OPPD is certain that it is safe restarted until OPPD is certain that it is safe

7/29/2011 7

Training Center 10089 Elevation Switchyard 1006-1007 Elevation Admin Bldg 1007 Elevation Security Bldg 10044 Elevation Intake Struc 10076 Flo Elevation Turbine Bldg 1032 Elevation