MONTHYEARML24107B1272024-04-22022 April 2024 Ft. Calhoun Meeting Summary of March 27, 2024 Meeting with Omaha Public Power District on Submittal of Phase 1 Final Status Surveys ML22333B0922022-12-21021 December 2022 FY22 Nmss/Duwp Operating Experience Report ML21271A5992021-08-0303 August 2021 License Amendment Request (LAR) 21-01, Chapter 8, 12, Omaha Public Power District, FCS-SAF-103, FCS Deconstruction Health and Safety Plan CAC2 ML21055A4022021-05-14014 May 2021 Memorandum: Final Environmental Assessment and Finding of No Significant Impact of Initial and Updated Decommissioning Funding Plans for the Cooper, Fort Calhoun and Virgil C. Summer Independent Spent Fuel Storage Installations ML21271A1492021-04-13013 April 2021 License Amendment Request (LAR) 21-01, Chapter 1 9 Haley & Aldrich, Inc. Memorandum to Energysolutions, File No. 0127960-006, Fort Calhoun Nuclear Power Statio~1 ML20056E4872020-02-26026 February 2020 Staff Review of Fort Calhoun Independent Spent Fuel Storage Installation Physical Security Plan, Security Training and Qualification Plan, and Safeguard Contingency Plan, Revision 0 and the Verification of Additional Security Measures (ASM) ML18173A0082018-06-20020 June 2018 Cancelling Numerous Inspection Report Numbers ML18108A1212018-04-11011 April 2018 American Nuclear Insurers - Notification of Change in the Number of Power Reactors in the Secondary Financial Protection (SFP) Program ML17275A2642017-11-21021 November 2017 Safety Evaluation Input on Fort Calhoun Station Request for Approval of Permanently Defueled Emergency Plan and Emergency Action Level Scheme, Docket No. 50-285 ML16057A1232016-02-26026 February 2016 Cy 2015 Baseline Completion ML16007A4942016-01-11011 January 2016 Review of the Updated Final Safety Analysis Report for the Period June 14, 2014 Through December 4, 2015 ML14163A0022014-06-16016 June 2014 Summary of Audit Conducted March 5-9, 2012, Request to Adopt National Fire Protection Association (NFPA) 805, Performance-Based Standard for Fire Protection for LWR Electric Generating Plants ML14129A4452014-05-12012 May 2014 5/13/2014 Notice of Forthcoming Closed Meeting to Discuss Dam Failure Analysis for Cooper Nuclear Station and Fort Calhoun Station, Unit 1 ML14114A7012014-04-24024 April 2014 Task Interface Agreement - Concurrence on Fort Calhoun Tornado Missile Protection Licensing Basis (TIA 2013-07) ML14085A1842014-03-28028 March 2014 Final Fort Calhoun Gothic TIA Response ML14016A2602014-01-28028 January 2014 Fc Final Containment Structural TIA ML13351A4762013-12-16016 December 2013 Recommendation for NRC to Close Confirmatory Action Letter EA-13-020 Supporting the Restart of Fort Calhoun Station and Recommendation to Issue Post-Restart Confirmatory Action Letter ML13346A0822013-12-12012 December 2013 Notice of Forthcoming Closed Meeting to Discuss Dam Failure Analysis for Cooper Nuclear Station and Fort Calhoun Station, Unit 1 ML13312A8522013-11-0808 November 2013 Meeting Notice with Public to Discuss Fort Calhoun Station ML13253A3542013-09-27027 September 2013 Letter to R. Morris Information Exchange Pertaining to Health Issues Related to Crow Butte Resources Uranium Mine and Ft. Calhoun Nuclear Generating Station ML13102A1892013-04-15015 April 2013 4/22/12 Notice of Closed Meeting with Omaha Public Power District to Discuss Flooding Issues Associated with Fort Calhoun, Unit 1 ML13101A2232013-04-11011 April 2013 Meeting Notice with Omaha Public Power District - Potential License Amendment Requests for Fort Calhoun, Unit 1 Related to Flood Protection for Raw Water System, Tornado Missile Protection, Piping/Code Use, and Alternate Seismic Criteria ML13066A8772013-03-0707 March 2013 Issuance of Revised U.S. Nuclear Regulatory Commission Manual Chapter 0350 Panel Fort Calhoun Station Restart Checklist Basis Document ML13046A3212013-02-19019 February 2013 Notice of Closed Meeting with Fort Calhoun to Discuss Safeguards Information, Proprietary, or Other Sensitive Information ML12345A2702012-11-30030 November 2012 Revised 12/12/2012 Notice of Forthcoming Meeting with Omaha Public Power District to Discuss Containment Internal Structures Issues to Support Restart of Fort Calhoun Station, Unit 1 ML12335A1652012-11-30030 November 2012 Forthcoming Meeting with Omaha Public Power District to Discuss Containment Internal Structures Issues to Support Restart of Fort Calhoun Station, Unit 1 ML12318A3192012-11-13013 November 2012 Issuance of U.S. Nuclear Regulatory Commission Manual Chapter 0350 Panel Fort Calhoun Station Restart Checklist Basis Document ML12251A3172012-09-0707 September 2012 Manual Chapter 0350 Oversight Panel Charter - Revision ML12066A0302012-03-29029 March 2012 Closure Memorandum: Issue for Resolution 2011-001 Fort Calhoun - Failure to Maintain External Flooding Procedures. ML12229A1842012-03-0606 March 2012 Backfit Panel Regarding Fort Calhoun Flooding ML1134707162011-12-13013 December 2011 Memo to M.S.Virgilio Notification of Change to Regulatory Oversight of Fort Calhoun Station ML11293A1982011-10-19019 October 2011 Charter for Backfit Panel on Postulated Failure of Upstream Dams Affecting Fort Calhoun Station ML1118811312011-07-0707 July 2011 Docketing of Nonproprietary Information Provided by Omaha Public Power District (OPPD) Personnel Following the June 2, 2011, Regulatory Conference ML13106A1702011-07-0101 July 2011 Proposed Adequate Protection Backfit Exception ML11174A2322011-06-21021 June 2011 for the Record-06-21-2011: NRC Ensures Public Safety Through Rigorous Oversight of Nuclear Power Plant Safety Standards ML1113807322011-05-18018 May 2011 Regulatory Conference with Omaha Public Power ML1113306432011-05-16016 May 2011 Notice of Forthcoming Prelicensing Teleconference on 5/26/11 with Omaha Public Power District Related to Fort Calhoun Station, Unit 1's License Amendment Submittal Related to Transition to Risk-Informed NFPA-805 ML1109103272011-04-0505 April 2011 Verbal Authorization, Request for Relief from Code Case N-722 Visual Examination of the Reactor Vessel Hot-Leg Nozzle-to-Safe-End Dissimilar Metal Welds, 4th 10-Year Inservice Inspection Interval ML1108106952011-03-23023 March 2011 Notice of Forthcoming Pre-Licensing Meeting with Omaha Public Power District to Discuss Its Plans to Submit an Extended Power Uprate for Fort Calhoun Station and Issues Related to Equipment Environmental Qualification ML1104808672011-02-18018 February 2011 03/2/2011 Notice of Forthcoming Closed Pre-Licensing Teleconference with Omaha Public Power District to Discuss Its Plans to Submit an Extended Power Uprate for Fort Calhoun Station and Issues Related to Control Rod Withdrawal at Power ML1035605482010-12-23023 December 2010 Notice of Forthcoming Pre-Licensing Meeting with Omaha Public Power District to Discuss Fort Calhoun Station'S Extended Power Uprate, Spent Fuel Pool Criticality, and Proposed License Amendment Request Modeled After TSTF-493 ML1020701262010-08-30030 August 2010 the Nuclear Regulatory Commission Staff Spot-Check Review of Fort Calhoun Station Unit 1, June 30, 2010 - Finding of No Potential Issues in Bank Statements ML1016205062010-06-14014 June 2010 Notice of Forthcoming Teleconference Meeting with Omaha Public Power District to Discuss NRC Staff Request for Additional Information Dated 2/12/2010 on Generic Letter 2004-02 for Fort Calhoun Station, Unit 1 ML1006010322010-03-0101 March 2010 Cy 2009 Baseline Inspection Completion ML1004302742010-02-12012 February 2010 Notice of Forthcoming Teleconference with Omaha Public Power District to Discuss NRC Staff Request for Additional Information on Generic Letter 2004-02 for Fort Calhoun Station, Unit 1 ML0909607752009-04-0606 April 2009 Notice of End-of-Cycle Meeting with Omaha Public Power District - Fort Calhoun Station to Present and Discuss the Performance Results for the Fort Calhoun Station for the Period of January 1 Though December 31, 2008 ML0901504382009-01-16016 January 2009 Notice of Forthcoming Meeting with Omaha Public Power District, to Discuss Oppd'S Plans to Submit an Extended Power Uprate Request for the Fort Calhoun Station, Unit 1 ML0901603362009-01-16016 January 2009 Notice of Forthcoming Meeting with Omaha Public Power District, to Discuss the Fort Calhoun Station'S Transition to National Fire Protection Association (NFPA) 805 ML0814100052008-06-0303 June 2008 Summary of Conference Call with Omaha Public Power District (OPPD) Regarding OPPD Emergency Relief Request Submitted May 15, 2008 for Fort Calhoun Station (Tac No. MD8722) ML0809404512008-04-18018 April 2008 Summary of 12/6/2006 Meeting with Omaha Public Power District, Regarding Water Management Strategies for Resolution of GSI-191 (Tac No MD5780) 2024-04-22
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I V 1600 EAST LAMAR BLVD ARLINGTON, TEXAS 76011-4511 September 7, 2012 MEMORANDUM FROM: Anton Vegel, Director /RA/
Division of Nuclear Materials Safety, Region IV Fort Calhoun Station Oversight Panel Chairman TO: Fort Calhoun Station Oversight Panel Members
SUBJECT:
FORT CALHOUN STATION MANUAL CHAPTER 0350 OVERSIGHT PANEL CHARTER - REVISION The enclosed revised panel charter establishes the purpose, objectives, and composition of the Fort Calhoun Station (FCS) Inspection Manual Chapter (IMC) 0350, Oversight of Reactor Facilities in a Shutdown Condition Due to Significant Performance and/or Operational Concerns, Oversight Panel; the expected outcomes of the oversight process; and the quorum requirements. The charter has been revised to incorporate the recent changes to the panel membership. Questions involving the charter should be directed to me at (817) 200-1106 or anton.vegel@nrc.gov.
Enclosure:
Fort Calhoun Station Manual Chapter 0350 Oversight Panel Charter
Regional Administrator (Elmo.Collins@nrc.gov)
Deputy Regional Administrator (Art.Howell@nrc.gov)
MC0350 Chairman (Anton.Vegel@nrc.gov)
MC0350 Vice-Chairman (Louise.Lund@nrc.gov)
DRP Director (Kriss.Kennedy@nrc.gov)
Acting DRP Deputy Director (Allen.Howe@nrc.gov)
Acting DRS Director (Tom.Blount@nrc.gov)
Acting DRS Deputy Director (Jeff.Clark@nrc.gov)
Senior Resident Inspector (John.Kirkland@nrc.gov)
Resident Inspector (Jacob.Wingebach@nrc.gov)
Branch Chief, DRP/F (Michael.Hay@nrc.gov)
Senior Project Engineer, DRP/F (Rick.Deese@nrc.gov)
Project Engineer, DRP/F (Chris.Smith@nrc.gov)
Public Affairs Officer (Victor.Dricks@nrc.gov)
Public Affairs Officer (Lara.Uselding@nrc.gov)
Branch Chief, DRS/TSB (Ray.Kellar@nrc.gov)
Project Manager (Lynnea.Wilkins@nrc.gov)
Regional Counsel (Karla.Fuller@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
RIV/ETA: OEDO (Silas.Kennedy@nrc.gov)
MC 0350 Panel Member (Michael.Balazik@nrc.gov)
MC 0350 Panel Member (Michael.Markley@nrc.gov)
RSLO (Bill.Maier@nrc.gov)
Office of Enforcement (Roy.Zimmerman@nrc.gov)
Congressional Affairs Officer (Jenny.Weil@nrc.gov)
Office of Nuclear Security and Incident Response (Jim.Wiggins@nrc.gov)
Office of Nuclear Reactor Regulation (Eric.Leeds@nrc.gov)
Regional Administrator, Region III (Chuck.Casto@nrc.gov)
Regional Administrator, Region II (Victor.McCree@nrc.gov)
Regional Administrator, Region I (BiII.Dean@nrc.gov)
Director, Division of Reactor Operator Licensing (Michele.Evans@nrc.gov)
Director, Division of Inspection and Regional Support (Ho.Nieh@nrc.gov)
Director, Division of Preparedness and Response (Robert.Lewis@nrc.gov)
Deputy Director, Division of Security Oversight (Barry.Westreich@nrc.gov)
Branch Chief, NRR/DIRS/IPAB (Rani.Franovich@nrc.gov)
File located: R: _Reactors\_FCS\2012\Panel Charter 090712.docx SUNSI Rev Compl. Yes No ADAMS Yes No Reviewer Initials RWD Publicly Avail Yes No Sensitive Yes No Sens. Type Initials RWD JKirkland LWilkins MMarkley MCHay
/RA/-E /RA/-E /RA/-E /RA/-E 9/6/12 9/6/12 9/6/12 9/6/12 JAClark LLund TBlount KKennedy AVegel
/RA/ /RA/-E /RA/-E /RA/ /RA/
9/6/12 9/6/12 9/6/12 9/7/12 9/7/12 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax
FORT CALHOUN STATION MANUAL CHAPTER 350 OVERSIGHT PANEL CHARTER Purpose
- 1. Establish criteria for the oversight of Fort Calhoun Station (FCS) performance; ensure the NRC communicates a unified and consistent position in a clear and predictable manner to the licensee, public, and other stakeholders.
- 2. Establish a record of the major regulatory and licensee actions taken and technical issues resolved leading to approval for restart and to the eventual return of the plant to the Reactor Oversight Process (ROP).
- 3. Verify that licensee corrective actions are sufficient prior to restart.
- 4. Provide assurance that following restart the plant will be operated safely.
Objectives The Panels duties and planned accomplishments include the following:
- 1. Review all available information directly related to the reason for the plant shutdown for the past four quarters of plant operation. This activity includes a review of performance indicator (PI) data, inspection findings, and docketed correspondence from the licensee.
- 2. Develop the Panel Process Plan and the Restart Checklist. The Panel Process Plan should include a plan for implementing the checklist and for modifying it as necessary to ensure that all risk significant performance issues directly relating to the plant shutdown, including extent of condition and extent of cause, are resolved or dispositioned before restart.
- 3. Maintain the comprehensive Communication Plan to ensure effective communication with internal and external stakeholders.
- 4. Maintain cognizance over the status of the Confirmatory Action Letter (CAL) items and recommend to the Regional Administrator, in consultation with cognizant program office management, any necessary modifications.
- 5. Develop and maintain the site-specific Inspection Plan for continuous overview of licensee performance throughout the licensees pre- and post-restart activities.
- 6. Utilize the site-specific Inspection Plan to identify the resources necessary to review performance deficiencies and identified risk-significant issues for restart.
- 7. Assess the licensees third party evaluation of their safety culture, including the adequacy of the licensees corrective action and improvement program and the ability of the licensee to identify problems. If necessary, perform an independent assessment of the licensees safety culture using the guidance contained in Inspection Procedure 95003.
Enclosure
- 8. Assess the physical readiness of the plant for restart.
- 9. Periodically provide NRC management and the Commission, if requested, briefings and updates on the status of the licensees progress in resolving issues associated with the reasons for shutdown, corrective actions, and the facilitys performance.
- 10. Conduct public periodic meetings with the licensee to discuss progress toward satisfactory completion of the licensees restart program.
- 11. Upon satisfactory inspection and assessment of the completion of the pre-startup portion of the licensees restart program, provide a written recommendation and the basis for the approval for restart to the Regional Administrator and the Director of Nuclear Reactor Regulation (NRR).
- 12. Provide post-restart enhanced oversight of licensee performance until there is a return to the routine oversight and assessment of the ROP. Utilize the site-specific Inspection Plan to develop and implement the necessary inspection activities.
- 13. Provide a written recommendation to the Regional Administrator and the Director of NRR for the return of FCS to the routine oversight and assessment of the ROP.
- 14. Ensure a comprehensive record is developed and maintained that documents NRC decisions and actions related to MC 0350 activities and lessons learned for future Panels.
Panel Membership and Quorum Requirements
- Chairman: Anton Vegel, Director, Division of Nuclear Materials Safety, Region IV
- Vice-Chairman: Louise Lund, Deputy Director, Division of Operating Reactor Licensing, NRR In addition to the Chairman or Vice-Chairman, three of the following members (with at least one Headquarters member) are required to establish a quorum for the Oversight Panel:
- Jeffrey Clark, Acting Deputy Director, Division of Reactor Safety, Region IV
- Michael Hay, Chief, Division of Reactor Projects Branch F, Region IV
- Michael Markley, Chief, Licensing Branch IV, Division of Operating Reactor Licensing, NRR
- *Lynnea Wilkins, Project Manager, Licensing Branch IV, Division of Operating Reactor Licensing, NRR Enclosure
The Panel may add non-voting members as necessary to advise the panel on matters involving facility performance and resolution of technical concerns.
Non-voting member(s):
Michael Balazik, Reactor Operations Engineer, Performance Assessment Branch, Division of Inspection and Regional Support, NRR
- The Project Manager for FCS is responsible for documenting and distributing the Panel meeting minutes.
Enclosure