IR 05000397/2013004
ML13304A922 | |
Person / Time | |
---|---|
Site: | Columbia |
Issue date: | 10/31/2013 |
From: | Webb Patricia Walker NRC/RGN-IV/DRP/RPB-A |
To: | Reddemann M Energy Northwest |
Walker W | |
References | |
IR-13-004 | |
Download: ML13304A922 (48) | |
Text
UNITED STATES ber 31, 2013
SUBJECT:
COLUMBIA GENERATING STATION - NRC INTEGRATED INSPECTION REPORT 05000397/2013004
Dear Mr. Reddemann:
On September 21, 2013, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Columbia Generating Station. The enclosed inspection report documents the inspection results which were discussed on September 24, 2013 with you and other members of your staff. Inspectors documented the results of this inspection in the enclosed inspection report.
NRC inspectors documented one finding of very low safety significance (Green) in this report.
This finding involved a violation of NRC requirements. Further, inspectors documented a licensee-identified violation which was determined to be of very low safety significance. The NRC is treating these violations as non-cited violations (NCVs) consistent with Section 2.3.2.a of the Enforcement Policy.
If you contest these non-cited violations, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement, United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at the Columbia Generating Station.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the Regional Administrator, Region IV; and the NRC Resident Inspector at the Columbia Generating Station. In accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter, its enclosure, and your response (if any) will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Wayne C. Walker, Branch Chief Project Branch A Division of Reactor Projects Docket No.: 50-397 License No.: NPF-21 Enclosure: Inspection Report 05000397/2013004 w/ Attachment: Supplemental Information cc w/ encl: Electronic Distribution
SUMMARY OF FINDINGS
IR 05000397/2013004; 06/23/2013 - 09/21/2013; Columbia Generating Station, Integrated
Resident and Regional Report; Problem Identification and Resolution.
The report covered a 3-month period of inspection by resident inspectors and an announced baseline inspection by region-based inspectors. One Green non-cited violation of significance was identified. The significance of most findings is indicated by their color (Green, White,
Yellow, or Red) using Inspection Manual Chapter 0609, Significance Determination Process.
The cross-cutting aspect is determined using Inspection Manual Chapter 0310, Components Within the Cross-Cutting Areas. Findings for which the significance determination process does not apply may be Green or be assigned a severity level after NRC management review.
The NRC's program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.
NRC-Identified Findings and Self-Revealing Findings
Cornerstone: Mitigating Systems
- Green.
The inspectors identified a non-cited violation of Technical Specification 3.3.3.2, Remote Transfer System, involving the licensees failure to remove a jumper in the 480 volt motor control center starter for residual heat removal suppression pool spray valve RHR-V-27B during planned replacement activities.
The failure to remove the jumper rendered the remote transfer switch for valve RHR-V-27B inoperable for a period greater than allowed by the stations technical specifications. This issue was entered into the licensees corrective action program as Action Request AR 286816286816
The performance deficiency was more than minor because it affected the protection from external events attribute of the Mitigating System Cornerstone objective and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. The inspectors performed an initial screening of the finding in accordance with NRC Manual Chapter IMC 0609,
Appendix A, "The Significance Determination Process for (SDP) for Findings At-Power. Since the inoperable remote transfer switch potentially affected post-fire safe shutdown, the finding was evaluated using IMC 0609, Appendix F,
Attachment 1, Part 1: Application of Fire Protection SDP Phase 1 Worksheet.
Using Attachment 1, Task 1.3.1, Qualitative Screening for All Finding Categories, the inspectors determined that the finding was of very low safety significance (Green) because it only affected the ability to reach and maintain cold shutdown conditions and did not affect the ability to achieve hot shutdown conditions. The inspectors determined that this finding had a cross-cutting aspect in the area of human performance associated with the decision making component because operations personnel changed the postmaintenance testing for RHR-V-27B motor control center starter to a test that was incapable of detecting the improperly installed jumper H.1(a).
Licensee-Identified Violations
A violation of very low safety significance that was identified by the licensee has been reviewed by the inspectors. Corrective actions taken or planned by the licensee have been entered into the licensees corrective action program. This violation and associated corrective action tracking numbers are listed in Section 4OA7 of this report.
PLANT STATUS
The plant began the inspection period shutdown in Mode 2 for Refueling Outage R21. On June 25, 2013, operators synchronized the main generator with the grid and began power ascension. On June 30, 2013, the plant reached 100 percent power. On July 26, 2013, the licensee reduced power to 81 percent to repair a tube leak in a feedwater heater and returned to 100 percent power on July 29, 2013. On August 7, 2013, the licensee reduced power to 82 percent for an unplanned single rod scram and returned to 100 percent power later the same day. The plant remained at 100 percent power except for planned power reductions for maintenance and testing for the remainder of the inspection period.
REPORT DETAILS
REACTOR SAFETY
Cornerstones: Initiating Events, Mitigating Systems, and Barrier Integrity
1R01 Adverse Weather Protection
.1 Readiness for Seasonal Extreme Weather Conditions
a. Inspection Scope
The inspectors reviewed the licensees adverse weather procedures for seasonal high temperatures and evaluated the licensees implementation of these procedures. The inspectors verified that prior to the onset of hot weather, the licensee had corrected weather-related equipment deficiencies identified during the previous summer.
The inspectors reviewed plant design features and the procedures used by plant personnel to mitigate or respond to adverse weather conditions. The inspectors verified that operator actions specified in these procedures maintained readiness of essential equipment and systems to preclude weather induced initiating events. The inspectors reviewed the FSAR and the performance requirements for selected systems to ensure that selected system components would reasonably remain functional if challenged by adverse weather. The inspectors reviews focused specifically on the following plant systems:
- Main and normal transformers
- Adjustable speed drive system
- Ultimate heat sink The inspectors also reviewed corrective action program items to verify that the licensee was identifying adverse weather issues at an appropriate threshold and entering them into its corrective action program for resolution. Specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of one sample to evaluate the readiness for seasonal adverse weather, as defined in Inspection Procedure 71111.01-05.
b. Findings
No findings were identified.
1R04 Equipment Alignment
.1 Partial Walkdown
a. Inspection Scope
The inspectors performed partial system walkdowns of the following risk-significant systems:
- June 27, 2013, division 1 critical switchgear room cooling
- July 19, 2013, reactor protection system and post-accident monitoring system including environmental qualification of Rosemount transmitters
- July 22, 2013, high pressure core spray system
- August 5, 2013, control room emergency chiller B The inspectors selected these systems based on their risk significance relative to the reactor safety cornerstones at the time they were inspected, while considering out of service time, inoperable or degraded conditions, recent system outages, and maintenance, modification, and testing. The inspectors attempted to identify any discrepancies that could affect the function of the system, and, therefore, potentially increase risk. The inspectors reviewed applicable operating procedures, system diagrams, FSAR, technical specification requirements, administrative technical specifications, outstanding work orders, condition reports, and the impact of ongoing work activities on redundant trains of equipment in order to identify conditions that could have rendered the systems incapable of performing their intended functions. The inspectors also inspected accessible portions of the systems to verify system components and support equipment were aligned correctly and operable. The inspectors examined the material condition of the components and observed operating parameters of equipment to verify that there were no obvious deficiencies. The inspectors also verified that the licensee had properly identified and resolved equipment alignment problems that could cause initiating events or impact the capability of mitigating systems or barriers and entered them into the corrective action program with the appropriate significance characterization. Specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of four partial system walkdown samples as defined in Inspection Procedure 71111.04-05.
b. Findings
No findings were identified.
1R05 Fire Protection
.1 Quarterly Fire Inspection Tours
a. Inspection Scope
The inspectors conducted fire protection walkdowns that were focused on availability, accessibility, and the condition of firefighting equipment in the following risk-significant plant areas:
- July 16, 2013, fire area R-6, reactor core isolation cooling pump room
- July 18, 2013, fire area N/A, main transformer yard
- August 19, 2013, fire areas M-9, M-21 and M-73, instrument rack rooms
- August 28, 2013, fire area DG-10, deluge valve equipment room The inspectors reviewed areas to assess if licensee personnel had implemented a fire protection program that adequately controlled combustibles and ignition sources within the plant; effectively maintained fire detection and suppression capability; maintained passive fire protection features in good material condition; and had implemented adequate compensatory measures for out of service, degraded or inoperable fire protection equipment, systems, or features, in accordance with the licensees fire plan.
The inspectors selected fire areas based on their overall contribution to internal fire risk as documented in the plants Individual Plant Examination of External Events with later additional insights, their potential to affect equipment that could initiate or mitigate a plant transient, or their impact on the plants ability to respond to a security event. Using the documents listed in the attachment, the inspectors verified that fire hoses and extinguishers were in their designated locations and available for immediate use; that fire detectors and sprinklers were unobstructed; that transient material loading was within the analyzed limits; and fire doors, dampers, and penetration seals appeared to be in satisfactory condition and verified that adequate compensatory measures were put in place by the licensee for out of service, degraded, or inoperable fire protection equipment systems or features. The inspectors also verified that minor issues identified during the inspection were entered into the licensees corrective action program.
Specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of four quarterly fire-protection inspection samples, as defined in Inspection Procedure 71111.05-05.
b. Findings
No findings were identified.
.2 Annual Fire Protection Drill Observation
a. Inspection Scope
On August 1, 2013, the inspectors observed a fire brigade activation following report of a simulated fire in the C residual heat removal pump room. The observation evaluated the readiness of the plant fire brigade to fight fires. The inspectors verified that the licensee staff identified deficiencies; openly discussed them in a self-critical manner at the drill debrief, and took appropriate corrective actions. Specific attributes evaluated were
- (1) proper wearing of turnout gear and self-contained breathing apparatus;
- (2) proper use and layout of fire hoses;
- (3) employment of appropriate fire fighting techniques;
- (4) sufficient firefighting equipment brought to the scene;
- (5) effectiveness of fire brigade leader communications, command, and control;
- (6) search for victims and propagation of the fire into other plant areas;
- (7) smoke removal operations;
- (8) utilization of preplanned strategies;
- (9) adherence to the preplanned drill scenario; and
- (10) drill objectives.
These activities constitute completion of one annual fire-protection inspection sample, as defined in Inspection Procedure 71111.05-05.
b. Findings
No findings were identified.
1R06 Flood Protection Measures
a. Inspection Scope
The inspectors reviewed the FSAR, the flooding analysis, and plant procedures to assess susceptibilities involving internal flooding; reviewed the corrective action program to determine if licensee personnel identified and corrected flooding problems; inspected underground bunkers/manholes to verify the adequacy of sump pumps, level alarm circuits, cable splices subject to submergence, and drainage for bunkers/manholes; and verified that operator actions for coping with flooding can reasonably achieve the desired outcomes. The inspectors also inspected the areas listed below to verify the adequacy of equipment seals located below the flood line, floor and wall penetration seals, watertight door seals, common drain lines and sumps, sump pumps, level alarms, and control circuits, and temporary or removable flood barriers. Specific documents reviewed during this inspection are listed in the attachment.
- July 18, 2013, manholes 8 and 10
- August 15, 2013, motor control center MC-7BB and MC-8BB rooms These activities constitute completion of one flood protection measures inspection sample and one bunker/manhole sample, as defined in Inspection Procedure 71111.06-05.
b. Findings
No findings were identified.
1R11 Licensed Operator Requalification Program and Licensed Operator Performance
.1 Quarterly Review of Licensed Operator Requalification Program
a. Inspection Scope
On July 24, 2013, the inspectors observed a crew of licensed operators in the plants simulator during requalification testing. The inspectors assessed the following areas:
- Licensed operator performance
- The ability of the licensee to administer the evaluations and the quality of the training provided
- The modeling and performance of the control room simulator
- The quality of post-scenario critiques
- Follow-up actions taken by the licensee for identified discrepancies These activities constitute completion of one quarterly licensed operator requalification program sample, as defined in Inspection Procedure 71111.11.
b. Findings
No findings were identified.
.2 Quarterly Observation of Licensed Operator Performance
a. Inspection Scope
On June 24, 2013, the inspectors observed the performance of on-shift licensed operators in the plants main control room. At the time of the observations, the plant was in a period of heightened activity due to raising power following completion of Refueling Outage R21.
In addition, the inspectors assessed the operators adherence to plant procedures, including Operating Instruction OI-09, Operations Standards and Expectation, Revision 58 and other operations department policies.
These activities constitute completion of one quarterly licensed-operator performance sample, as defined in Inspection Procedure 71111.11.
b. Findings
No findings were identified.
1R12 Maintenance Effectiveness
a. Inspection Scope
The inspectors evaluated degraded performance issues involving the following risk significant systems:
- August 6, 2013, circulating water pump CW-P-1A The inspectors reviewed events such as where ineffective equipment maintenance has resulted in valid or invalid automatic actuations of engineered safeguards systems and independently verified the licensee's actions to address system performance or condition problems in terms of the following:
- Implementing appropriate work practices
- Identifying and addressing common cause failures
- Scoping of systems in accordance with 10 CFR 50.65(b)
- Characterizing system reliability issues for performance
- Charging unavailability for performance
- Trending key parameters for condition monitoring
- Ensuring proper classification in accordance with 10 CFR 50.65(a)(1) or -(a)(2)
- Verifying appropriate performance criteria for structures, systems, and components classified as having an adequate demonstration of performance through preventive maintenance, as described in 10 CFR 50.65(a)(2), or as requiring the establishment of appropriate and adequate goals and corrective actions for systems classified as not having adequate performance, as described in 10 CFR 50.65(a)(1)
The inspectors assessed performance issues with respect to the reliability, availability, and condition monitoring of the system. In addition, the inspectors verified maintenance effectiveness issues were appropriately handled by a screening and identification process and that issues were entered into the corrective action program with the appropriate significance characterization. Specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of two maintenance effectiveness samples, as defined in Inspection Procedure 71111.12-05.
b. Findings
No findings were identified.
1R13 Maintenance Risk Assessments and Emergent Work Control
a. Inspection Scope
The inspectors reviewed licensee personnel's evaluation and management of plant risk for the maintenance and emergent work activities affecting risk-significant and safety-related equipment listed below to verify that the appropriate risk assessments were performed prior to removing equipment for work:
- June 25, 2013, heavy lifts of transformers near the diesel generator building while increasing power following completion of Refueling Outage R-21.
- July 11, 2013, unplanned high pressure core spray unavailability during planned thermography testing
- August 19, 2013, yellow risk during standby gas treatment B and standby liquid control B planned maintenance The inspectors selected these activities based on potential risk significance relative to the reactor safety cornerstones. As applicable for each activity, the inspectors verified that licensee personnel performed risk assessments as required by 10 CFR 50.65(a)(4)and that the assessments were accurate and complete. When licensee personnel performed emergent work, the inspectors verified that the licensee personnel promptly assessed and managed plant risk. The inspectors reviewed the scope of maintenance work, discussed the results of the assessment with the licensee's probabilistic risk analyst or shift technical advisor, and verified plant conditions were consistent with the risk assessment. The inspectors also reviewed the technical specification requirements and inspected portions of redundant safety systems, when applicable, to verify risk analysis assumptions were valid and applicable requirements were met. Specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of three maintenance risk assessments and emergent work control inspection samples, as defined in Inspection Procedure 71111.13-05.
b. Findings
No findings were identified.
1R15 Operability Evaluations and Functionality Assessments
a. Inspection Scope
The inspectors reviewed the following assessments:
- June 27, 2013, Action Request AR 288321288321documenting intermediate valve indication on reactor core isolation cooling valve RCIC-V-26
- July 12, 2013, Action Request AR 289636289636documenting a disconnected C phase electrical connection for the high pressure core spray service water pump
- July 31, 2013, Action Request AR 290508290508documenting low service water flow to motor control center room cooler RRA-CC-14
- August 1, 2013, Action Request AR 292176292176and 292271 documenting service water pump SW-P-1B performance in the alert range during inservice testing
- August 3, 2013, Action Request AR 290907290907documenting a lack of a coordination study for inverters IN-2A and IN-2B The inspectors selected these operability and functionality assessments based on the risk significance of the associated components and systems along with other factors, such as engineering analysis and judgment, operating experience, and performance history. The inspectors evaluated the technical adequacy of the evaluations to ensure technical specification operability was properly justified and to verify the subject component or system remained available such that no unrecognized increase in risk occurred. The inspectors compared the operability and design criteria in the appropriate sections of the technical specifications and FSAR to the licensees evaluations to determine whether the components or systems were operable. Where compensatory measures were required to maintain operability, the inspectors determined whether the measures in place would function as intended and were properly controlled. Additionally, the inspectors reviewed a sampling of corrective action documents to verify that the licensee was identifying and correcting any deficiencies associated with operability evaluations. Specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of five operability evaluations inspection samples, as defined in Inspection Procedure 71111.15-05.
b. Findings
No findings were identified.
1R19 Post-Maintenance Testing
a. Inspection Scope
The inspectors reviewed the following post-maintenance activities to verify that procedures and test activities were adequate to ensure system operability and functional capability:
- July 11, 2013, post-maintenance testing of high pressure core spray system following C phase motor starter lead replacement
- July 30, 2013, post-maintenance testing of control room cooling coil WMA-CC-51A1 following anode reinstallation
- August 8, 2013, post-maintenance testing of control room emergency chiller CCH-CR-1A following service water pressure switch SW-PS-11A replacement
- August 20, 2013 post-maintenance testing of reactor core isolation cooling valve RCIC-V-26 following limit switch replacement
- August 26, 2013 post-maintenance testing of process radiation monitor PRM-RE-1C following air conditioner maintenance The inspectors selected these activities based upon the structure, system, or component's ability to affect risk. The inspectors evaluated these activities for the following (as applicable):
- The effect of testing on the plant had been adequately addressed; testing was adequate for the maintenance performed
- Acceptance criteria were clear and demonstrated operational readiness; test instrumentation was appropriate The inspectors evaluated the activities against the technical specifications, the FSAR, 10 CFR Part 50 requirements, licensee procedures, and various NRC generic communications to ensure that the test results adequately ensured that the equipment met the licensing basis and design requirements. In addition, the inspectors reviewed corrective action documents associated with post-maintenance tests to determine whether the licensee was identifying problems and entering them in the corrective action program and that the problems were being corrected commensurate with their importance to safety. Specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of five post-maintenance testing inspection samples, as defined in Inspection Procedure 71111.19-05.
b. Findings
No findings were identified.
1R20 Refueling and Other Outage Activities
a. Inspection Scope
The inspectors reviewed the outage safety plan and contingency plans for the Refueling Outage R-21, conducted May 10 through June 25, 2013, to confirm that licensee personnel had appropriately considered risk, industry experience, and previous site-specific problems in developing and implementing a plan that assured maintenance of defense in depth. During the refueling outage, the inspectors observed portions of the reactor startup and monitored licensee controls over the outage activities listed below.
The inspectors also confirmed that the licensee scheduled covered workers such that the minimum days off for individuals working on outage activities were in compliance with 10 CFR 26.205(d)(4) and (5).
- Configuration management, including maintenance of defense in depth, is commensurate with the outage safety plan for key safety functions and compliance with the applicable technical specifications when taking equipment out of service.
- Clearance activities, including confirmation that tags were properly hung and equipment appropriately configured to safely support the work or testing.
- Installation and configuration of reactor coolant pressure, level, and temperature instruments to provide accurate indication, accounting for instrument error.
- Status and configuration of electrical systems to ensure that technical specifications and outage safety-plan requirements were met, and controls over switchyard activities.
- Reactor water inventory controls, including flow paths, configurations, and alternative means for inventory addition, and controls to prevent inventory loss.
- Controls over activities that could affect reactivity.
- Maintenance of secondary containment as required by the technical specifications.
- Refueling activities, including fuel handling and sipping to detect fuel assembly leakage.
- Startup and ascension to full power operation, tracking of startup prerequisites, walkdown of the drywell (primary containment) to verify that debris had not been left which could block emergency core cooling system suction strainers, and reactor physics testing.
- Management of fatigue
- Licensee identification and resolution of problems related to refueling outage activities.
Specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of one refueling outage and other outage inspection sample, as defined in Inspection Procedure 71111.20-05.
b. Findings
No findings were identified.
1R22 Surveillance Testing
a. Inspection Scope
The inspectors selected risk-significant surveillance activities based on risk information and reviewed the FSAR, procedure requirements, and technical specifications to ensure that the surveillance activities listed below demonstrated that the systems, structures, and/or components tested were capable of performing their intended safety functions.
The inspectors either witnessed or reviewed test data to verify that the significant surveillance test attributes were adequate to address the following:
- Preconditioning
- Evaluation of testing impact on the plant
- Acceptance criteria
- Test equipment
- Procedures
- Jumper/lifted lead controls
- Test data
- Testing frequency and method demonstrated technical specification operability
- Test equipment removal
- Restoration of plant systems
- Fulfillment of ASME Code requirements
- Updating of performance indicator data
- Engineering evaluations, root causes, and bases for returning tested systems, structures, and components not meeting the test acceptance criteria were correct
- Reference setting data
- Annunciators and alarms setpoints The inspectors also verified that licensee personnel identified and implemented any needed corrective actions associated with the surveillance testing.
- July 29, 2013, Procedure OSP-SW/IST-Q701, Standby Service Water Loop A Operability, Revision 25
- July 30, 2013, Procedure OSP-SW-M101, Standby Service Water Loop A Valve Position Verification, Revision 33
- August 7, 2013, Procedure OSP-RPS-W401, Manual Scram Functional Test, Revision 7
- August 22, 2013, Procedure OSP-RCIC/IST-Q701, RCIC Valve Operability Test, Revision 3
- September 9, 2013, Procedure ISP-MS-Q924, RHR B and C/ADS Actuation on Level 1 and RCIC Actuation on Reactor Level 2 - CFT/CC, Revision 6
- September 19, 2013, Procedure OSP-INST-H101, Shift and Daily Instrument Checks (Modes 1, 2, 3), Revision 78 used for reactor coolant system leakage detection Specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of six surveillance testing inspection samples, as defined in Inspection Procedure 71111.22-05.
b. Findings
No findings were identified.
Cornerstone: Emergency Preparedness
1EP2 Alert and Notification System Testing
a. Inspection Scope
The inspector discussed with licensee staff the operability of offsite siren emergency warning systems, tone alert radio systems, and backup alerting methods, to determine the adequacy of licensee methods for testing the alert and notification system in accordance with the requirements of 10 CFR Part 50, Appendix E. The inspector also reviewed licensee programs for identifying emergency planning zone residents requiring tone alert radios, for maintaining and auditing records associated with the tone alert radio program, and for maintaining offsite emergency warning sirens. The licensees alert and notification system testing program was compared with criteria in NUREG-0654, Criteria for Preparation and Evaluation of Radiological Emergency Response Plans and Preparedness in Support of Nuclear Power Plants, Revision 1; FEMA Report REP-10, Guide for the Evaluation of Alert and Notification Systems for Nuclear Power Plants; and the licensees current FEMA-approved alert and notification system design report, Columbia Generating Station, Alert and Notification System Design Report, Revision 0, dated June 20, 2013. The specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of one sample as defined in Inspection Procedure 71114.02-06.
b. Findings
No findings were identified.
1EP3 Emergency Response Organization Staffing and Augmentation System
a. Inspection Scope
The inspector discussed with licensee staff the operability of primary and backup systems for augmenting the on-shift emergency response staff to determine the adequacy of licensee methods for staffing emergency response facilities in accordance with the requirements of 10 CFR Part 50, Appendix E. The inspector reviewed licensee methods for staffing alternate emergency response facilities. The inspector also reviewed periodic surveillances of the augmentation system to determine the licensees ability to staff emergency response facilities within the response times described in the site emergency plan. The specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of one sample as defined in Inspection Procedure 71114.03-06.
b. Findings
No findings were identified.
1EP4 Emergency Action Level and Emergency Plan Changes
a. Inspection Scope
The NSIR headquarters staff performed an in-office review of the latest revisions of various Emergency Plan Implementing Procedures (EPIPs) and the Emergency Plan located under ADAMS accession number ML13199A060 as listed in the Attachment.
The licensee determined that in accordance with 10 CFR 50.54(q), the changes made in the revisions resulted in no reduction in the effectiveness of the Plan, and that the revised Plan continued to meet the requirements of 10 CFR 50.47(b) and Appendix E to 10 CFR Part 50. The NRC review was not documented in a safety evaluation report and did not constitute approval of licensee-generated changes; therefore, this revision is subject to future inspection. The specific documents reviewed during this inspection are listed in the Attachment.
These activities constitute completion of one sample as defined in Inspection Procedure 71114.04-05.
b. Findings
No findings were identified.
1EP5 Maintenance of Emergency Preparedness
a. Inspection Scope
The inspector reviewed:
- The licensees corrective action program requirements as documented in procedures SWP-CAP-01, Corrective Action Process, Revisions 27-1 and 27-2, and EPI-30, Emergency Preparedness Condition Report Processing
- The licensees program for identifying and evaluating changes in the emergency planning zone population as documented in procedure EPI-12, Evacuation Time Estimates Review and Revision, Revisions 2 and 3
- The licensees program for maintaining emergency preparedness program equipment as documented in procedures 13.14.4, Emergency Equipment Maintenance and Testing, Revision 50-2, 13.14.9, Emergency Program Maintenance, Revision 29-1, and 13.14.11, EP Equipment, Revision 6
- The licensees program for identifying the impact of changes to the emergency preparedness program as documented in procedures SWP-LIC-02, Licensing Basis Impact Determinations, Revisions 11 and 12, and SWP-LIC-03, Licensing Document Change Process, Revisions 13 and 14
- The licensees audit requirements for the emergency preparedness program as documented in procedures, QAP-ASU-1 Audit Performance, Revisions 4 and 5, and SWP-ASU-01, Evaluations of Programs, Processes, and Suppliers, Revisions 25 and 25-1 The inspector reviewed summaries of 162 corrective action program entries assigned to the emergency preparedness department and emergency response organization between September 2011 and July 2013, and selected 20 for detailed review against the program requirements. The inspector evaluated corrective action requests to determine the licensees ability to identify, evaluate, and correct problems in accordance with the licensee program requirements, planning standard 10 CFR 50.47(b)(14), and the requirements of 10 CFR Part 50, Appendix E. The inspector reviewed summaries of 75 changes to the site emergency plan and implementing procedures, and selected 10 for detailed review against the program requirements. The inspector evaluated the licensees ability to identify reductions in the effectiveness of the emergency plan in accordance with the requirements of 10 CFR 50.54(q)(3), (q)(4), and (q)(5).
The inspector evaluated the licensees ability to maintain adequate facilities and equipment in accordance with the requirements of 10 CFR 50.47(b)(8) and 10 CFR Part 50, Appendix E. The inspector also reviewed 25 quality assurance audits and surveillances related to the emergency preparedness program, two licensee self-assessments, and, eight licensee evaluations of drill and exercise performance.
The inspector visited the licensees alternate facility at Richland, Washington, to determine the licensees ability to relocate the onsite emergency response organization during events in which the site cannot be immediately accessed, in accordance with the requirements of 10 CFR 50, Appendix E.IV(E)(8)(d).
The specific documents reviewed during this inspection are listed in the attachment.
These activities constitute completion of one sample as defined in Inspection Procedure 71114.05-06.
b. Findings
No findings were identified.
1EP6 Drill Evaluation
Training Observations
a. Inspection Scope
The inspectors observed a simulator training evolution for licensed operators on July 9, 2013, which required emergency plan implementation by a licensee operations crew.
This evolution was planned to be evaluated and included in performance indicator data regarding drill and exercise performance. The inspectors observed event classification and notification activities performed by the crew. The inspectors also attended the post evolution critique for the scenario. The focus of the inspectors activities was to note any weaknesses and deficiencies in the crews performance and ensure that the licensee evaluators noted the same issues and entered them into the corrective action program.
As part of the inspection, the inspectors reviewed the scenario package and other documents listed in the attachment.
These activities constitute completion of one training observation sample, as defined in Inspection Procedure 71114.06-05.
b. Findings
No findings were identified.
OTHER ACTIVITIES
Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity, Emergency Preparedness, Public Radiation Safety, Occupational Radiation Safety, and Physical Protection
4OA1 Performance Indicator Verification
.1 Data Submission Issue
a. Inspection Scope
The inspectors performed a review of the performance indicator data submitted by the licensee for the second Quarter 2013 performance indicators for any obvious inconsistencies prior to its public release in accordance with Inspection Manual Chapter 0608, Performance Indicator Program.
This review was performed as part of the inspectors normal plant status activities and, as such, did not constitute a separate inspection sample.
b. Findings
No findings were identified.
.2 Mitigating Systems Performance Index - Emergency ac Power System (MS06)
a. Inspection Scope
The inspectors sampled licensee submittals for the mitigating systems performance index - emergency ac power system performance indicator period third quarter 2012 through second quarter 2013 to determine the accuracy of the reported performance indicator data. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 6.
The inspectors reviewed the licensees operator narrative logs, mitigating systems performance index derivation reports, issue reports, event reports, and NRC integrated inspection reports for the period of July 2012 through June 2013, to validate the accuracy of the submittals. The inspectors reviewed the mitigating systems performance index component risk coefficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensees issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in the attachment to this report.
These activities constitute completion of one mitigating systems performance index -
emergency ac power system sample, as defined in Inspection Procedure 71151-05.
b. Findings
No findings were identified.
.3 Mitigating Systems Performance Index - High Pressure Injection Systems (MS07)
a. Inspection Scope
The inspectors sampled licensee submittals for the mitigating systems performance index - high pressure injection systems performance indicator period third quarter 2012 through second quarter 2013 to determine the accuracy of the reported performance indicator data. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 6.
The inspectors reviewed the licensees operator narrative logs, issue reports, mitigating systems performance index derivation reports, event reports, and NRC integrated inspection reports for the period of July 2012 through June 2013, to validate the accuracy of the submittals. The inspectors reviewed the mitigating systems performance index component risk coefficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensees issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in the attachment to this report.
These activities constitute completion of one mitigating systems performance index -
high pressure injection system sample, as defined in Inspection Procedure 71151-05.
b. Findings
No findings were identified.
.4 Mitigating Systems Performance Index - Residual Heat Removal System (MS09)
a. Inspection Scope
The inspectors sampled licensee submittals for the mitigating systems performance index - residual heat removal system performance indicator period third quarter 2012 through second quarter 2013 to determine the accuracy of the reported performance indicator data. To determine the accuracy of the performance indicator data reported during those periods, the inspectors used definitions and guidance contained in NEI Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 6.
The inspectors reviewed the licensees operator narrative logs, issue reports, mitigating systems performance index derivation reports, event reports, and NRC integrated inspection reports for the period of July 2012 through June 2013, to validate the accuracy of the submittals. The inspectors reviewed the mitigating systems performance index component risk coefficient to determine if it had changed by more than 25 percent in value since the previous inspection, and if so, that the change was in accordance with applicable NEI guidance. The inspectors also reviewed the licensees issue report database to determine if any problems had been identified with the performance indicator data collected or transmitted for this indicator and none were identified. Specific documents reviewed are described in the attachment to this report.
These activities constitute completion of one mitigating systems performance index -
residual heat removal system sample, as defined in Inspection Procedure 71151-05.
b. Findings
No findings were identified.
.5 Drill/Exercise Performance (EP01)
a. Inspection Scope
The inspector sampled licensee submittals for the Drill and Exercise Performance, performance indicator for the period July 2012 through June 2013 to determine the accuracy of the reported performance indicator data. The inspector compared the licensees records and submitted performance indicator reports with the definitions and guidance in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 6. Specifically, the inspector reviewed licensee records and processes including procedural guidance on assessing opportunities for the performance indicator; assessments of performance indicator opportunities during predesignated control room simulator training sessions, performance during the 2012 biennial exercise, and performance during other drills. The specific documents reviewed are described in the attachment to this report.
These activities constitute completion of the drill/exercise performance sample as defined in Inspection Procedure 71151-05.
b. Findings
No findings were identified.
.6 Emergency Response Organization Drill Participation (EP02)
a. Inspection Scope
The inspector sampled licensee submittals for the Emergency Response Organization Drill Participation performance indicator for the period July 2012 through June 2013 to determine the accuracy of the reported performance indicator data. The inspector compared the licensees records and submitted performance indicator reports with the definitions and guidance in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 6. Specifically, the inspector reviewed licensee records and processes including procedural guidance on assessing opportunities for the performance indicator, rosters of personnel assigned to key emergency response organization positions, and exercise participation records.
The specific documents reviewed are described in the attachment to this report.
These activities constitute completion of the emergency response organization drill participation sample as defined in Inspection Procedure 71151-05.
b. Findings
No findings were identified.
.7 Alert and Notification System (EP03)
a. Inspection Scope
The inspector sampled licensee submittals for the Alert and Notification System performance indicator for the period July 2012 through June 2013 to determine the accuracy of the reported performance indicator data. The inspector compared the licensees records and submitted performance indicator reports with the definitions and guidance in Nuclear Energy Institute Document 99-02, Regulatory Assessment Performance Indicator Guideline, Revision 6. Specifically, the inspector reviewed licensee records and processes including procedural guidance on assessing opportunities for the performance indicator and the results of periodic alert notification system operability tests. The specific documents reviewed are described in the attachment to this report.
These activities constitute completion of the alert and notification system sample as defined in Inspection Procedure 71151-05.
b. Findings
No findings were identified.
4OA2 Problem Identification and Resolution
.1 Routine Review of Identification and Resolution of Problems
a. Inspection Scope
As part of the various baseline inspection procedures discussed in previous sections of this report, the inspectors routinely reviewed issues during baseline inspection activities and plant status reviews to verify that they were being entered into the licensees corrective action program at an appropriate threshold, that adequate attention was being given to timely corrective actions, and that adverse trends were identified and addressed. The inspectors reviewed attributes that included the complete and accurate identification of the problem; the timely correction, commensurate with the safety significance; the evaluation and disposition of performance issues, generic implications, common causes, contributing factors, root causes, extent of condition reviews, and previous occurrences reviews; and the classification, prioritization, focus, and timeliness of corrective actions. Minor issues entered into the licensees corrective action program because of the inspectors observations are included in the attached list of documents reviewed.
These routine reviews for the identification and resolution of problems did not constitute any additional inspection samples. Instead, by procedure, they were considered an integral part of the inspections performed during the quarter and documented in Section 1 of this report.
b. Findings
No findings were identified.
.2 Daily Corrective Action Program Reviews
a. Inspection Scope
In order to assist with the identification of repetitive equipment failures and specific human performance issues for follow-up, the inspectors performed a daily screening of items entered into the licensees corrective action program. The inspectors accomplished this through review of the stations daily corrective action documents.
The inspectors performed these daily reviews as part of their daily plant status monitoring activities and, as such, did not constitute any separate inspection samples.
b. Findings
No findings were identified.
.3 Selected Issue Follow-up Inspection
a. Inspection Scope
During a review of items entered in the licensees corrective action program, the inspectors recognized a corrective action item documenting the following:
- Action Request AR 286816286816documenting an improperly installed jumper in 480V motor control center starter RHR-42-8BA5D
- Action Request AR 291197291197documenting a discrepancy in the necessary time critical operator actions needed to cope with a station blackout These activities constitute completion of two in-depth problem identification and resolution sample, as defined in Inspection Procedure 71152-05.
b. Findings
Introduction.
The inspectors identified a Green non-cited violation of Technical Specification 3.3.3.2, Remote Transfer System, involving the licensees failure to remove a jumper in the 480 volt motor control center starter for residual heat removal suppression pool spray valve RHR-V-27B during planned replacement activities. The failure to remove the jumper rendered the remote transfer switch for valve RHR-V-27B inoperable for a period greater than allowed by the stations technical specifications.
Description.
On May 17, 2011, during a planned refueling outage, the licensee replaced 480 volt motor control center starter RHR-42-8BA5D associated with the Train B residual heat removal suppression pool spray valve RHR-V-27B under Work Order 02004108.
The replacement motor control center starter was supplied to the licensee with a factory-installed jumper across Terminals X1 and 19 which bypassed a set of isolation contacts provided for by remote transfer switch RHR-RMS-RSTS57. The work order did not provide specific instructions on the required configuration of jumpers for the motor control center starter but directed electrical maintenance personnel to Procedure PPM 10.25.208, MCC Bucket Replacement Using Spectrum Technologies Inc.,
Revision 3. This procedure relied on skill of the craft to determine proper jumper configuration. During replacement, the factory installed jumper was left in the motor control center starter. On May 20, 2011, the licensee performed post-maintenance testing of 480 volt disconnect switch RHR-42-8BA5D and declared the component operable. The post-maintenance test only consisted of a valve stroke and not a verification of remote transfer switch operability.
On June 4, 2013, the licensee performed Procedure OSP-INST-B701, Remote Shutdown Panel Operability, Revision 17. Step 7.2.16 of this procedure verifies the isolation capability of remote transfer switch RHR-RMS-RSTS57. During performance of this step, the licensee discovered electrical continuity across Terminals X1 and 19 revealing that the jumper was left in place in May 2011. The licensee initiated Action Request AR 286816286816to address the improperly installed jumper and took action to restore the motor control center to the required design configuration. The licensee performed a past operability evaluation which determined that even with the improperly installed jumper, 480 volt motor control center starter RHR-42-8BA5D remained operable.
The inspectors reviewed the past operability evaluation performed for Action Request AR 286816286816and found that the licensees evaluation failed to consider the impact of this jumper on the ability to satisfy technical specification surveillance requirements for the remote shutdown system. Specifically, the improperly installed jumper resulted in the failure to meet Technical Specification Surveillance Requirement 3.3.3.2.4 which requires the licensee to verify each control circuit and transfer switch is capable of performing the intended functions. Since the failure to meet a surveillance constitutes a failure to meet the limiting condition for operation, the inspectors determined that Technical Specification Limiting Condition for Operation 3.3.3.2 Remote Transfer System, was not met from September 18, 2011 when the licensee entered the mode of applicability until May 11, 2013 when Columbia Generating Station shutdown to Mode 3 for Refueling Outage R21.
Following identification by the NRC that the improperly installed jumper resulted in the failure to meet Technical Specification Surveillance Requirement 3.3.3.2.4, the licensee performed a reportability review and issued Licensee Event Report 2013-004-00, Jumper Makes Suppression Pool Spray Valve Remote Transfer Switch Inoperable, documenting a condition prohibited by technical specifications caused by the improperly installed jumper. Action Request AR 287816287816was initiated to address the inadequate past operability review.
Analysis.
The failure to remove a jumper in the 480V disconnect switch for residual heat removal valve RHR-V-27B during planned replacement activities was a performance deficiency. The performance deficiency was more than minor because it affected the protection from external events attribute of the Mitigating System Cornerstone objective and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. The inspectors performed an initial screening of the finding in accordance with NRC Manual Chapter IMC 0609, Appendix A, "The Significance Determination Process for (SDP) for Findings At-Power. Since the inoperable remote transfer switch potentially affected post-fire safe shutdown, the finding was evaluated using IMC 0609, Appendix F, Attachment 1, Part 1: Application of Fire Protection SDP Phase 1 Worksheet. Using Attachment 1, Task 1.3.1, Qualitative Screening for All Finding Categories, the inspectors determined that the finding was of very low safety significance (Green) because it only affected the ability to reach and maintain cold shutdown conditions and did not affect the ability to achieve hot shutdown conditions.
The inspectors determined that this finding had a cross-cutting aspect in the area of human performance associated with the decision making component because operations personnel changed the postmaintenance testing for RHR-V-27B motor control center starter to a test that was incapable of detecting the improperly installed jumper H.1(a).
Enforcement.
Technical Specification 3.3.3.2, Remote Transfer System, requires, in part, that the remote shutdown system functions shall be operable in Modes 1 and 2.
Technical Specification 3.3.3.2, Condition A, requires that when one or more required functions are inoperable, action is taken to restore the required functions to operable status within 30 days. Failure to meet Technical Specification 3.3.3.2, Condition A, requires entry into Technical Specification 3.3.2.2, Condition B. Required Action B.1 requires the unit to be placed in Mode 3 within an additional 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />. Contrary to the above, from September 18, 2011, until May 11, 2013, remote transfer switch RHR-RMS-RSTS57 was inoperable and action was not taken to place the Columbia Generating Station in Mode 3 as required by Technical Specification 3.3.2.2, Required Action B.1. This issue was discovered while the Columbia Generating Station was in Refueling Outage R21 and the licensee took action to restore the inoperable remote transfer switch to operable status prior to startup. This violation is being treated as an NCV, consistent with Section 2.3.2.a of the Enforcement Policy. The violation was entered into the corrective action program as Action Request AR 286816286816 (NCV 05000397/2013004-01, Improperly Installed Jumper Results in Inoperable Remote Shutdown Switch.)
.4 In-depth Review of Operator Workarounds
a. Inspection Scope
On July 10, 2013, the inspectors reviewed the licensees operations aggregate index to determine if any operator workarounds, individually or collectively, could challenge operators response during an event. The inspectors verified that the licensee was identifying, documenting, and implementing corrective actions for operator workarounds.
b. Findings
No findings were identified.
4OA3 Followup of Events and Notices of Enforcement Discretion
.1 (Closed) Licensee Event Report 2013-005-00, Momentary Loss of 115kV Offsite Power
On June 15, 2013, while shutdown in Mode 4 for a planned refueling outage, the Columbia Generating Station experienced a momentary loss of the 115kV offsite power due to a range fire that caused protective relaying to clear one of the transmission lines supplying the site. As a result of the loss of power, valid engineered safety feature actuation signals were generated including start signals for the Division 1 and 2 emergency diesel generators and standby service water pumps. All engineered safety feature equipment started and operated as designed. The inspectors reviewed the licensee event report associated with this event and determined that the report adequately documented the summary of the event including the cause of the event and potential safety consequences. No performance deficiencies were identified. This licensee event report is closed.
4OA5 Other Activities
.1 (Closed) Unresolved Item (URI)05000397/2013008-06, Inadequate Evaluation of
Nonconforming Condition Resulting in Potential Missed Report.
On August 22, 2013, the NRC during a planned biennial problem identification and resolution inspection identified an unresolved item involving a potential failure to submit a required licensee event report following discovery of a non-seismically qualified temperature switch installed in the diesel generator mixed air system. The details of this unresolved item are documented in NRC Inspection Report 05000397/2013008.
Following identification of this issue, the licensee performed vibration testing of the non-seismically qualified temperature switch. Results of this testing showed that the switch would continue to function when subjected to simulated ground force accelerations exceeding the safe shutdown earthquake accelerations for the Columbia Generating Station. Based on these test results, the inspectors concluded that no licensee event report was necessary. This URI is closed.
4OA6 Meetings, Including Exit
Exit Meeting Summary
On July 26, 2013, the inspector presented the results of the onsite inspection of the licensees emergency preparedness program to Mr. A. Black, Operations General Manager, and other members of the licensees staff. The licensee acknowledged the issues presented. The inspector asked the licensee whether any materials examined during the inspection should be considered proprietary. No proprietary information was identified.
On September 24, 2013, the inspectors presented the inspection results to Mr. M. Reddemann, Chief Executive Officer, and other members of the licensee staff. The licensee acknowledged the issues presented. The inspector verified that all proprietary information materials examined during the inspection were returned to the licensee.
4OA7 Licensee-Identified Violations
The following violation of very low safety significance (Green) was identified by the licensee and is a violation of NRC requirements which meets the criteria of the NRC Enforcement Policy for being dispositioned as a Non-Cited Violation.
.1 Technical Specification 5.4.1.a requires, in part, that written procedures be established,
implemented, and maintained as recommended in Regulatory Guide 1.33, Revision 2, Appendix A, dated February 1978. Paragraph 9.a of Regulatory Guide 1.33, Appendix A, requires that maintenance that can affect the performance of safety-related equipment should be properly preplanned and performed in accordance with written procedures, documented instructions, or drawings appropriate to the circumstances.
Contrary to the above, on February 19, 2013, maintenance was performed on the motor control center for high pressure core spray pump HPCS-P-2 under Work Order 02025234, but was not completed in accordance with written instructions. Specifically, Step 4.2 was not completed which required re-terminating and torqueing of the C phase electrical connection. This issue was entered into the corrective action program as Action Request AR 289636289636 A senior reactor analyst performed a detailed risk evaluation for this finding. The finding was of very low safety significance (Green)because the bounding change to the core damage frequency was less than 1.0 x 10-7/year.
SUPPLEMENTAL INFORMATION
KEY POINTS OF CONTACT
Licensee Personnel
- A. Black, Operations General Manager
- D. Clymer, Supervisor, Quality Services
- C. England, Manager, Organization Effectiveness
- A. Fahnestock, Manager, Emergency Preparedness
- R. Garcia, Licensing Engineer
- E. Gilmour, Chief Information Officer
- D. Gregoire, Manager, Regulatory Affairs
- B. Guldemond, Manager, Recovery
- G. Hettel, Vice President, Operations
- C. King, Assistant Plant General Manager
- B. MacKissock, Plant General Manager
- J. Moon, Manager, Training
- R. Parmelee, Manager, Operations Support
- J. Pierce, Manager, Chemistry
- R. Schultz, Manager, Maintenance
- B. Sawatzke, Chief Nuclear Officer
- C. Smith, Manager, Emergency Preparedness Training
- D. Swank, Assistant Vice President, Engineering
- C. Workman, Manager, Security
Attachment
LIST OF ITEMS OPENED, CLOSED, AND DISCUSSED
Opened and Closed
Improperly Installed Jumper Results in Inoperable Remote
- 05000397/2013004-01 NCV Transfer Switch
Closed
- 05000397/2013-005-00 LER Momentary Loss of 115kV Offsite Power Inadequate Evaluation of Nonconforming Condition Resulting in
- 05000397/2013008-06 URI Potential Missed Report