IR 05000397/2023004

From kanterella
Jump to navigation Jump to search
Integrated Inspection and Independent Spent Fuel Storage Installation Report 05000397/2023004 and 07200035/2023001
ML24017A169
Person / Time
Site: Columbia  
Issue date: 01/29/2024
From: Patricia Vossmar
NRC/RGN-IV/DORS/PBA
To: Schuetz R
Energy Northwest
References
IR 2023001, IR 2023004
Download: ML24017A169 (29)


Text

January 29, 2024

SUBJECT:

COLUMBIA GENERATING STATION - INTEGRATED INSPECTION AND INDEPENDENT SPENT FUEL STORAGE INSTALLATION REPORT 05000397/2023004 and 07200035/2023001

Dear Robert Schuetz:

On December 31, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Columbia Generating Station. On January 11, 2024, the NRC inspectors discussed the results of this inspection with Dave Brown, Site Vice President, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Patricia J. Vossmar, Chief Reactor Projects Branch A Division of Operating Reactor Safety Docket Nos. 05000397,07200035 License No. NPF-21

Enclosure:

As stated

Inspection Report

Docket Number:

05000397 and 07200035

License Number:

NPF-21

Report Number:

05000397/2023004 and 07200035/2023001

Enterprise Identifier:

I-2023-004-0005 and I-2023-001-0017

Licensee:

Energy Northwest

Facility:

Columbia Generating Station

Location:

Richland, Washington

Inspection Dates:

October 01, 2023, to December 31, 2023

Inspectors:

C. Kline, Senior Resident Inspector

J. Brodlowicz, Resident Inspector

L. Brookhart, Senior Spent Fuel Storage Inspector

K. Clayton, Senior Operations Engineer

J. Copeland, Reactor Inspector

A. Donley, Senior Resident Inspector

J. Freeman, Spent Fuel Storage Inspector

N. Greene, Senior Health Physicist

N. Hernandez, Operations Engineer

J. Melfi, Project Engineer

J. O'Donnell, Senior Health Physicist

D. You, Operations Engineer

Approved By:

Patricia J. Vossmar, Chief

Reactor Projects Branch A

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Columbia Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Columbia Generating Station (CGS) began the inspection period at rated thermal power (RTP).

On October 9, 2023, the unit was reduced to 65 percent RTP for planned adjustable speed drive (ASD) maintenance and returned to 100 percent RTP on October 10, 2023. At approximately 0400 on October 24, 2023, the plant experienced a transient resulting in the trip of multiple feedwater heaters and the unit was reduced to 76 percent RTP. Restoration activities reduced power to 65 percent RTP that night and continued until October 26, 2023, when the unit was returned to 100 percent RTP. On November 25, 2023, the unit was reduced to 86 percent RTP in response to ASD faults. On November 27, 2023, the unit reduced power to 78 percent RTP to recover one ASD drive and returned to 100 percent RTP on November 28, 2023. On December 9, 2023, the unit was reduced to 63 percent RTP for planned ASD and reactor feedwater pump maintenance and returned to 100 percent RTP on December 14, 2023. The unit remained at or near RTP for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures for the following systems: reactor building ventilation, turbine building ventilation, diesel generator ventilation, and radwaste building ventilation on December 28, 2023.

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk -significant systems from impending severe cold weather on October 29, 2023.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)emergency diesel generator 2 when emergency diesel generator 1 was in an extended maintenance window, on October 6, 2023 (2)service water train B while control room chilled water train A was inoperable following a failed surveillance, on November 15, 2023 (3)reactor core isolation cooling (RCIC) following surveillance testing on December 8, 2023 (4)residual heat removal (RHR) train C following surveillance testing on December 21, 2023

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1)fire area SW-2, standby service water pumphouse 1B, on October 2, 2023 (2)fire area 5010, zone 4, building 30, fire pumps in circulating water pump house and water filtrating building, on October 17, 2023 (3)fire area RC-9/2, remote shutdown room, on November 14, 2023 (4)fire area DG-1/1, high-pressure core spray diesel generator room, on November 21, 2023 (5)fire area RC-7, division 2 electrical equipment and reactor protection system rooms, on December 12, 2023 (6)fire area R-6, RCIC pump room, on December 15, 2023

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered October 30, 2023 - December 7, 2023, and the biennial written examinations completed on December 7, 2023.

71111.11B - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Requalification Program (IP Section 03.04) (1 Sample)

(1) Biennial Requalification Written Examinations The inspectors evaluated the quality of the licensed operator biennial requalification written examination administered on October 30, 2023 - December 7, 2023.

Annual Requalification Operating Tests The inspectors evaluated the adequacy of the facility licensees annual requalification operating test.

Administration of an Annual Requalification Operating Test The inspectors evaluated the effectiveness of the facility licensee in administering requalification operating tests required by 10 CFR 55.59(a)(2) and that the facility licensee is effectively evaluating their licensed operators for mastery of training objectives.

Requalification Examination Security The inspectors evaluated the ability of the facility licensee to safeguard examination material, such that the examination is not compromised.

Remedial Training and Re-examinations The inspectors evaluated the effectiveness of remedial training conducted by the licensee, and reviewed the adequacy of re-examinations for licensed operators who did not pass a required requalification examination.

Operator License Conditions The inspectors evaluated the licensees program for ensuring that licensed operators meet the conditions of their licenses.

Control Room Simulator The inspectors evaluated the adequacy of the facility licensees control room simulator in modeling the actual plant, and for meeting the requirements contained in 10 CFR 55.46.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during feedwater heater restoration following an unplanned transient to 75 percent rated thermal power on October 25, 2023.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated simulator-based testing of loss of bus SM-4 followed by an electric anticipated transient without a scram and a small break loss of coolant accident on November 9, 2023.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1)radwaste mixed air fan 53B, division 2 HVAC for critical switchgear, electrical, and battery rooms (2)digital electrohydraulic quadvoter valves

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1)oil filter replacement on RCIC-DT-1 on November 21, 2023

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (6 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Yellow risk, due to extended maintenance outage of emergency diesel generator system A, on October 4, 2023
(2) Yellow risk, due to troubleshooting and repair to emergency diesel generator system A in response to unsatisfactory voltage regulator response, on October 18, 2023 (3)implementation of risk informed completion time for maintenance on division 2 of critical switchgear and battery room HVAC, on October 26, 2023
(4) Yellow risk, due to planned maintenance on the backup transformer, on November 13, 2023
(5) Green risk, due to planned maintenance on control room emergency filtration, on November 29, 2023
(6) Green risk, due to planned maintenance on reactor turbine driven feedwater pump A, on December 12, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1)condition report 452528, control room HVAC chill water valve CCH-V-14A failed to seat during surveillance testing, on November 14, 2023 (2)condition report 451422, diesel generator 1 cooling water leak, on October 9, 2023 (3)condition report 452302, diesel generator 3 air handling unit motor not operating, on December 13, 2023

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02) (2 Samples)

The inspectors evaluated the following temporary or permanent modifications:

(1)turbine service water pinhole leak on October 23, 2023 (2)permanent and long-term scaffolding modifications on November 9, 2023

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (12 Samples)

(1) WO 02203841, following maintenance on standby gas treatment system B, on October 3, 2023
(2) WO 02113947, primary containment integrated leak rate testing, on October 5, 2023
(3) WO 02213807, diesel generator 1 voltage regulator relay replacement, on October 11, 2023
(4) WO 02178456, diesel generator 1 load testing following diesel cooling water leak repair, on October 11, 2023
(5) WO 02077516, diesel generator 1 voltage regulator replacement, on October 13, 2023
(6) WO 02188835, following maintenance on residual heat removal system B, on October 17, 2023
(7) WO 02191021, following reactor feedwater valve 65A replacement, on November 3, 2023
(8) WO 02205063, following control room emergency chiller flushes, on November 15, 2023
(9) WO 02205491, diesel generator 2 monthly operability test following diesel fuel oil leak repair, on November 23, 2023
(10) WO 02202832, standby gas treatment operability test following filter change, on December 6, 2023
(11) WO 02215165, adjustable speed drive 1B/1 borescope testing/troubleshooting, on December 14, 2023
(12) WO 02211310, reactor feedwater turbine oil leak, on December 13, 2023

Surveillance Testing (IP Section 03.01) (4 Samples)

(1) TSP-APRM-C302, LPRM Gain Calibration Test, on November 14, 2023
(2) ESP-RHR-Q901, RHR Pump "A" Time Delay (LPCI) - CFT/CC, on November 6, 2023
(3) ICP-HPCS-M901, HPCS - Keepfill Pump Monitor - CFT/CC, on November 30, 2023
(4) TSP-RCIC-B801, RCIC Leakage Surveillance, on December 5,

RADIATION SAFETY

71124.05 - Radiation Monitoring Instrumentation

Walkdowns and Observations (IP Section 03.01) (10 Samples)

The inspectors evaluated the following radiation detection instrumentation during plant walkdowns:

(1)portable survey instruments "ready for use" at the exit to the radiologically controlled area (RCA)

(2)portable survey instruments in storage, but "available for use" in the instrument lab on radwaste (RW) 467' elevation (3)area radiation monitors in reactor, RW, and turbine buildings (4)process radiation monitors in the reactor, RW, and turbine buildings (5)effluent radiation monitors in the RW building (6)chemistry count room instruments (gamma spectroscopy and liquid scintillation)

(7)personnel contamination monitors, portal monitors, and friskers at the exit to the RCA (8)portal monitors at the exit to the protected area (9)continuous air sampling instruments in the RW building (10)tool and equipment monitors in the RW building

Calibration and Testing Program (IP Section 03.02) (13 Samples)

The inspectors evaluated the calibration and testing of the following radiation detection instruments:

(1) Automess Model 6112M teletector, T070
(2) Canberra ARGOS-5 A/B whole body contamination monitor, HP-EQ-42782
(3) Canberra FastScan, WBC#2
(4) Canberra GEM-5 gamma exit monitor, HP-EQ-68907
(5) Eberline AMS-4 continuous air sampler, HP-EQ-42867
(6) Eberline RO-2 ion chamber, RO170
(7) Fluke/Victoreen 451B ion chamber, RV24
(8) General Atomics RM2300, turbine building vent high range, TEA-RE-13A
(9) General Atomics RM2300, radwaste building vent high range, WEA-RE-14A
(10) General Electric mechanical vacuum pump radiation monitor, AR-RE-21
(11) General Electric area radiation monitor, ARM-RIS-1
(12) Ludlum Model 19 Micro-R meter, L036
(13) Ludlum Model 177 frisker, F124 Effluent Monitoring Calibration and Testing Program Sample (IP Section 03.03) (3 Samples)

The inspectors evaluated the calibration and maintenance of the following radioactive effluent monitoring and measurement instrumentation:

(1)liquid radioactive waste radiation monitor, FDR-RIS-606 (2)reactor building elevated stack monitor, PRM-RE-11, -12, and -13 (3)turbine building vent monitor, TEA-RE-13A

71124.08 - Radioactive Solid Waste Processing & Radioactive Material Handling, Storage, &

Transportation

Radioactive Material Storage (IP Section 03.01)

The inspectors evaluated the licensees performance in controlling, labeling, and securing the following radioactive materials:

(1)sealed sources in the radwaste building (2)boxes in the low specific activity storage pad

(3) Intermodal shipping containers in the spraypond storage area

Radioactive Waste System Walkdown (IP Section 03.02) (3 Samples)

The inspectors walked down the following accessible portions of the solid radioactive waste systems and evaluated system configuration and functionality:

(1)radwaste equipment and floor drain processing systems (2)reactor water clean up (RWCU) filter system (3)self engaging rapid dewatering system (SERDS)

Waste Characterization and Classification (IP Section 03.03) (2 Samples)

The inspectors evaluated the following characterization and classification of radioactive waste:

(1)2020 Columbia Generating Station Part 61 Waste Stream Data, dated April 28, 2022 (2)2022 Columbia Generating Station Part 61 Waste Stream Data, dated September 7, 2023

Shipment Preparation (IP Section 03.04) (1 Sample)

(1) The inspectors observed the preparation and release of radioactive shipment # 23-114 of spent resin on November 15, 2023.

Shipping Records (IP Section 03.05) (5 Samples)

The inspectors evaluated the following non-excepted radioactive material shipments through a record review:

(1)

  1. 21-039, UN2916, radioactive material, type B(U) package, fissile-excepted, 7, RQ

- radionuclides, dated June 15, 2021 (2)

  1. 22-034, UN3321, radioactive material, low specific activity (LSA-II), 7, RQ

- radionuclides, dated October 6, 2022 (3)

  1. 22-045, UN2916, radioactive material, type B(U) package, 7, RQ - radionuclides, dated December 14, 2022 (4)
  1. 23-023, UN3321, radioactive material, low specific activity (LSA-II), 7, RQ

- radionuclides, dated April 27, 2023 (5)

  1. 23-033, UN3321, radioactive material, low specific activity (LSA-II), 7, RQ

- radionuclides, dated April 13,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10)===

(1) October 1, 2022, through September 30, 2023

BI02: RCS Leak Rate Sample (IP Section 02.11) (1 Sample)

(1) October 1, 2022, through September 30, 2023

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensee's corrective action program for trends associated with licensee personnel and contractors adherence to clearance procedures during a six-month period ending December 31, 2023. Condition report (CR) 446560 documented a trend in clearance order errors. In response to the trend, the licensee conducted a gaps, drivers, actions, and results (GDAR) analysis of clearance order practices. CR 446560 identified four clearance order events during a 10-day period of outage activity and the subsequent GDAR analyzed nine clearance order events which spanned the 45-day outage period. The licensee implemented corrective actions, including reviewing training guidance material, implementing additional supervisory oversight, taking personnel accountability actions, clarifying clearance procedures, reviewing operating experience communications practices, and benchmarking outage clearance order practices. Corrective actions specific to benchmarking developing guidance to supervision remain in progress and are not due to be completed until the first quarter of 2024. In the subsequent period following return to rated thermal power on June 23, 2023, the licensee documented 10 clearance order events, including 1 clearance order event which resulted in losing technical specification action statement control for approximately 23 hours2.662037e-4 days <br />0.00639 hours <br />3.80291e-5 weeks <br />8.7515e-6 months <br /> (CR 452865). The licensee conducted a prompt investigation in response to CR 452865 and completed corrective actions including employee coaching, training on operating experience, and modification to clearance order instructions. All prompt investigation corrective actions are complete.

OTHER ACTIVITIES

- TEMPORARY INSTRUCTIONS, INFREQUENT AND ABNORMAL

===60855 - Operation Of An ISFSI The inspectors performed a review of the licensees independent spent fuel storage installation (ISFSI) activities to verify compliance with requirements of the Holtec HI-STORM systems Certificate of Compliance 72-1014, License Amendment 9, Revision 1, and the Final Safety Analysis Report (FSAR), Revision 13.1. The inspectors reviewed selected procedures, corrective action reports, and records to verify ISFSI operations were compliant with the certificate's technical specifications, requirements in the FSAR, and NRC regulations.

Operation Of An ISFSI===

(1) The inspectors evaluated the licensees dry cask storage program from October 23-25, 2023, during an on-site inspection. The Columbia Generating Station's original ISFSI pad was designed to store 54 Holtec International HI-STORM 100 spent fuel storage casks using the MPC-68 or MPC-68M multi-purpose canister (containing 68 boiling-water reactor spent fuel assemblies). At the time of the on-site inspection, the licensee had filled the original ISFSI pads with 54 casks and was performing aging management inspections in accordance with license requirements. Inspectors also performed a walkdown of the ISFSI. No loading activities were observed due to none being scheduled during the FY 2023-2025 triennial inspection cycle.

The inspectors observed and/or reviewed the following activities during the inspection:

  • fuel selection evaluations for the canisters loaded since the last NRC ISFSI inspection (canisters 48 - 54)
  • radiation surveys for radiological dose at the owner-controlled area boundary to verify compliance with the requirements of 10 CFR 72.104 for 2022 and 2023
  • selected ISFSI-related condition reports issued since the last NRC ISFSI inspection
  • quality assurance program implementation, including recent audits, surveillances, receipt inspection, and quality control activities related to ISFSI operations
  • compliance to technical specifications for operational surveillance activities and FSAR required maintenance activities
  • documentation of annual maintenance activities for the cask handling crane
  • selected licensee design changes and program changes for the ISFSI performed under the 10 CFR 72.48 program
  • changes made in the 10 CFR Part 72.212 Evaluation report from revision 13 to revision

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On October 25, 2023, the inspectors presented the triennial ISFSI inspection results to Gregory Higgs, Nuclear Projects General Manager, and other members of the licensee staff.
  • On November 16, 2023, the inspectors presented the radiation safety inspection results to Grover Hettel, Executive Vice President/Chief Nuclear Officer, and other members of the licensee staff.
  • On December 18, 2023, the inspectors presented the licensed operator requalification program inspection results to Grover Hettel, Executive Vice President/Chief Nuclear Officer, and other members of the licensee staff.
  • On January 11, 2024, the inspectors presented the integrated inspection results to Dave Brown, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

22-U03 CLP

Cask Loading Plan

000

AU-DC-22

QUALITY SERVICES AUDIT REPORT

lndependent Spent Fuel Storage lnstallation (lSFSl) Program

04/21/2022

Certificate of

Compliance 72-

1014 Amendment

CERTIFICATE OF COMPLIANCE FOR SPENT FUEL

STORAGE CASKS

001

ENERGY

NORTHWEST

INDEPENDENT

SPENT FUEL

STORAGE

INSTALLATION

CFR 72.212

EVALUATION

Docket number 72-35

016

Miscellaneous

Final Safety

Analysis Report

HI-STORM 100 FINAL SAFETY ANALYSIS REPORT

013.1

OSP-SFS-D101

SPENT FUEL STORAGE CASK HEAT REMOVAL SYSTEM

DAILY CHECKS

05/23/2022

SWP-CAP-01

Corrective Action Program

047

Procedures

SWP-LIC-02

Licensing Basis Impact Determinations

017.1

Radiation

Surveys

Area DLR 2023-1

ISFSI and site perimeter DLR readings.

000

60855

Work Orders

WO Package

2166926 01

MT-CRA-2 Inspection, maintain, and test RX Building Main

Crane (125TON/15TON)

01/17/2023

Corrective Action

Documents

Action Requests

2302, 452769, 452905, 427427

Procedures

SOP-

COLDWEATHER-

OPS

Cold Weather Operations

044

71111.01

Work Orders

Work request 29163408

71111.04

Corrective Action

Action Requests

450785, 444597, 451324, 451325

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

Corrective Action

Documents

Resulting from

Inspection

Action Requests

451232

ISP-RHR-X304

ECCS-LPCI (B and C) Pump discharge low (minimum

flow)-CC

009

OSP-RHR-M106

Residual heat removal system C valve position verification

003

OSP-SW-M102

Standby Service Water Loop B Valve Position Verification

056

SOP-DG2-LU

Emergency Diesel Generator (DIV 2) Valve and Power

Supply Lineup

010

SOP-DG2-STBY

Emergency Diesel Generator (DIV 2) Standby Lineup

26

Procedures

SOP-RCIC-LU

RCIC Valve and Breaker Lineup

004

Work Orders

Work Requests

29170885

Calculations

FP-02-85-03

Combustible Loading Calculation

009

FM892-5

Fire Area Boundary Plan - Miscellaneous Floors and

Buildings

008

GM892-11

Fire Suppression System Plan - Miscellaneous Floors and

Buildings

004

Drawings

M932-1

Fire Main Ring Header

001

NPFP-01

Non-power Block Pre-Fire Plan

008

PFP-DG-

BUILDING

Diesel Generator Building

006

PFP-MN-XFMR-

YD-MISC

Main Transformer Yard Miscellaneous Buildings

009

PFP-RB-422

RCIC Pump Room

009

PFP-RW-467

Radwaste 467

004

Fire Plans

PFP-RW-467

Radwaste 467

008

Miscellaneous

FPSI 23-0345

Fire Protection System Impairment Door C240

000

71111.05

Work Orders

2185720

71111.11A

Miscellaneous

23 Operating Test Results

006

71111.11B

Corrective Action

Documents

Action Requests

433204, 434875, 438584, 438848, 440282, 438897,

448038, 448156, 451465

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Miscellaneous

High Power Results

07/13/2023

Lower Power Results

07/05/2023

Mid Power Results

07/06/2023

C27 Core Testing EOC

07/11/2023

Simulator Review Board Minutes

2/13/2021

Simulator Review Board Minutes

06/12/2022

Simulator Review Board Minutes

2/15/2023

Simulator Review Board Minutes

10/26/2023

LORQ Week 1 Written Examination

000

23 Written Exam Sample Plan and Overlap Tracker

004

23 Written Exam Results

006

LORQ Week 2 Operating Test

001

23 Operating Test Sample Plan and Overlap Tracker

001

Operations Training: Performance Deficiency Analysis and

Remediation

003

Total Simulator Differences Report

11/04/2023

License Reactivation Record Sheet

135

TT03

Simultaneous Closure of all MSIVs

06/15/2023

TT04

Loss of All RRC

06/15/2023

TT06

Turbine Trip from Low Power

06/27/2023

TT09

Maximum Unisolable Steam Leak

06/15/2023

Miscellaneous

TT10

Simultaneous MSIV Closure with Stuck Open SRV

06/15/2023

1.3.1

Operating Policies, Programs, and Practices

140

1.8.10

Administration of Medical Qualifications

2

1.8.11

Medical Examination Program for Licensed Operators

2

GBP-TQS-01

Training Attendance

2

SWP-TQS-01

Training, Qualification and Simulators

21

TDI-02

Systematic Approach to Training

051

TDI-06

Simulator Management

2

TDI-08

Licensed Operator Requalification Program

2

TDI-08

Licensed Operator Requalification Program

2

TDI-23

LORQ Annual Exam Development and Administration

018

TDI-24

Exam Security

21

71111.11B

Procedures

TRG-TQS-02

Application for and Maintenance of Reactor Operator and

Senior Reactor Operator License

009

Corrective Action

Documents

Action Requests

2045, 451927, 451858

Miscellaneous

LORQ LE000033

LORQ Annual NRC Operating Test Week 2

000

ABN-FWH-

HILEVEL/TRIP

Feedwater Heater High Level Trip

013

71111.11Q

Procedures

TDI-23

LORQ Annual Exam Development and Administration

016

Corrective Action

Documents

Action Requests

2835, 416308, 448855, 445408, 451605, 443986,

2438, 442648, 443480, 448426, 443986, 443480,

2648, 442438, 432784, 425907

Expert Panel Meeting Minutes

10/04/2023

Performance Criteria Form DEH-Quadvoter

10/04/2023

58400622

CID

CVI 28-00,103

Operator and Maintenance Instructions and Parts Catalog

for Centrifugal Fans

2

ME-02-17-03

WMA-AH-53B Air Flow Requirements During February Re-

Balance

2

Miscellaneous

ME-02-92-43

Calculation for Room Temperature for DG Building, Reactor

Building, Radwaste Building, and Service Water

014

1.5.11

Maintenance Rule Program

016

Procedures

1.5.15

Equipment Reliability Process Description

007

2144078, 02112870, 02179291, 02207885, 02213989,

205241, 02205059, 02196382

71111.12

Work Orders

Work Requests

29129758, 29171522, 29174206

Corrective Action

Documents

Action Requests

451711, 451747

Fire Tour Log

10/26/2023

P-DG-SYS-A-

EXT-001

Protected Equipment List

10/02/2023

P-E-TR-B-01

eSOMS protection scheme

001

Miscellaneous

P-RFW-P-1A

eSOMS Protection Scheme

001

1.3.76

Integrated Risk Management

066

1.3.83

Protected Equipment Program

038

1.3.83

Protected Equipment Program

038

71111.13

Procedures

1.5.14

Risk Assessment and Management for

Maintenance/Surveillance Activities

044

1.5.24

Risk Informed Completion Time Program

000

Procedures

SOP-HVAC/CR-

SHUTDOWN

Control, Cable and Critical Switchgear Rooms, HVAC

Shutdown

007

71111.13

Work Orders

213989, 02213807, 02213032, 02175691

Calculations

ME-02-14-01

Main Control Room Cooling Analysis

001

Corrective Action

Documents

Action Requests

2528, 451422, 452905

1.3.66

Operability Determination

038

Procedures

OI-41

Work Control Expectations

077

71111.15

Work Orders

20178549

CE-02-87-29

Evaluate ALARA Shielding Frames Constructed from Tube

Lock Scaffolding Members per Procedure GEN-RPP-14

001

Calculations

CE-02-87-29

Excel Scaffolding Evaluation

07/23/2004

Corrective Action

Documents

Action Requests

449860, 425377

Miscellaneous

212420- 02

NDE Results per Work Order Package 02212420- 02

10.2.53

Scaffolding

054

Procedures

SWP-LIC-02

Licensing Basis Impact Determinations

017

212420

71111.18

Work Orders

Work Request 29173558

Corrective Action

Documents

Action Requests

450861, 450887, 447231, 447381, 451364, 451347,

2532, 452528, 452870

Corrective Action

Documents

Resulting from

Inspection

Action Requests

451422

23-28

Integrated Leakage Rate Test Report, Columbia Generating

Station Energy Northwest

08/14/2023

Clearance

D-RHR-CB-P.2B-001

E543-3VA-1

DG1 Exciter Cubicle 1E Control Panel DG/RE

Miscellaneous

TM-2096

Design Valve Factor Criteria used in GL 89-10 Motor

Operated Valve Calculations

004

10.20.1

Diesel Engine Refuel Cycle (2 Year) Preventative

Maintenance Division 1 and Division 2

033

71111.24

Procedures

DG-RLY-DG1/LR

Functionality Test Relay

000

ESP-RHR-Q901

RHR Pump "A" Time Delay (LPCI Mode) - CFT/CC

016

ICP-HPCS-M901

HPCS - Keepfill Pump Monitor - CFT/CC

001

MES-10

Motor Operated Valve Sizing and Switch Setting

011

OSP-CCH/IST-

M701

Control Room Emergency Chiller System A Operability

065

OSP-ELEC-M702

Diesel Generator 2-Monthly Operability Test

071

OSP-ELEC-S701

Diesel Generator 1 Semi-annual Operability Test

063

OSP-RHR/IST-

073

RHR Loop B Operability Test

064

OSP-SGT-M701

Standby Gas Treatment System A Operability

019

SOP-DG1-

START

Emergency Diesel Generator (DIV 1) Start

039

SOP-RFT-START

Reactor Feedwater Turbine System Start

23

SOP-TIP-OPS

TIP System Operations

013

TSP-APRM-C302

LPRM Gain Calibration Test

010

TSP-CONT-C801

Primary Containment Integrated Leak Rate Test

006

TSP-DG1-B502

Standby Diesel Generator DG1 Load Testing

29

Procedures

TSP-RCIC-B801

RCIC Leakage Surveillance

004

71111.24

Work Orders

202859, 02187697, 02179754, 02188195, 02178456,

2187941, 02187942, 02187944, 02187258, 02185133,

213807, 02178456, 02179357, 02205394, 02205063,

205095, 02205491, 02205700, 02202832, 02215165,

211310

100 cc Gas Vial

Efficiency Verification

2/22/2023

mm Filter

Efficiency Verification

2/22/2023

Charcoal

Cartridge

Efficiency Verification

2/21/2023

F124

Instrument Calibration Data Sheet: Ludlum Model 177

2/07/2023

HP-EQ-42782

Instrument Calibration Data Sheet: Canberra ARGOS-5 A/B

07/27/2023

71124.05

Calibration

Records

HP-EQ-68907

Instrument Calibration Data Sheet: Canberra GEM-5

03/02/2023

L036

Instrument Calibration Data Sheet: Ludlum Model 19 Micro-

R Meter

06/21/2023

Report # 1-0105-

03735

Calibration Report: Hopewell BX3 Box Calibrator, SN# 0707-

238

09/11/2023

Report #s:

233989, 234060-

234064

Condenser R Chamber Calibration Report - Victoreen Model

570, SN# 3891

Test # 231961

09/21/2023

RO170

Instrument Calibration Data Sheet: Eberline RO-2

03/31/2023

RV24

Instrument Calibration Data Sheet: Fluke/Victoreen 451B Ion

Chamber

04/07/2023

T070

Instrument Calibration Data Sheet: Automess Model 6112M

Teletector

03/02/2023

W/O 02143592

PPM 16.4.12, Mechanical Vacuum Pump Discharge

Radiation Monitor - CC/RC (AR-RIS-21)

06/05/2021

W/O 02143622

ISP-CMS/PRM-B303 Accident Monitor Primary Containment

Gross Radiation Monitor, CMS-RIS-27E - CC

05/22/2021

W/O 02169379

16.1.11 Reactor Building Elevated Discharge Radiation

Activity Monitor - CC/RC

01/19/2023

W/O 02177091

Calibrate / Repair Outage HP Portable Air Samplers (17)

04/07/2023

W/O 02180813

PPM 16.4.12, Mechanical Vacuum Pump Discharge

Radiation Monitor - CC/RC (AR-RIS-21)

06/05/2023

W/O 02183701

Quench Curve Calibration for Hidex

08/02/2023

W/O 02186644

Calibrate / Repair AMS-4 Continuous Air Monitors (3)

10/07/2023

W/O 02189302

Radiation Calibration of ARM-RIS-1 (ARM-E/S-603A)

(11.2.10.19)

07/06/2022

W/O 02190564

16.7.1 Liquid Radwaste Effluent Radiation Monitor - CC

2/14/2022

W/O 02199439

Perform Efficiency Calibration on iSolo Alpha Counting

System

04/12/2023

Calibration

Records

WBC#2

Canberra FastScan Calibration

09/07/2023

71124.05

Corrective Action

Documents

Action Requests

418254, 422662, 422664, 423619, 426115, 427551, 428303,

29691, 430896, 432362, 432702, 435488, 435798, 437742,

439135, 439162, 440870, 441352, 441676, 449399, 449789

Corrective Action

Documents

Resulting from

Inspection

Action Requests

2642, 452689

Miscellaneous

LDCN-20-020 /

AR 408804408804Remove 18-month calibration frequency requirement from

FSAR Section 12.3.4.3

2/29/2020

1.5.13

Preventive Maintenance Optimization Living Program

048

10.24.18

Area Radiation Monitor Maintenance

014

11.2.24.1

Radiation Protection Work Routines

041

11.2.24.2

Surveillance and Response for Changing Plant Conditions

015

2.1.1

Laboratory Quality Assurance

23

16.1.11

Rx Bldg. Elevated Discharge Radiation Activity Monitoring &

Sampling System - CC/RC

005

16.7.2

FDR-RIS-606, Liquid Radwaste Effluent Radiation Monitor -

RC

008

CSP-INST-M201

Chemistry Monthly Source and Channel Checks

030

GEN-RPP-17

Health Physics Instrument Program Description

004

HPI-0.16

Radiation Protection Portable Instrumentation Use and

Calibration Guidelines

008

HPI-7.33

Eberline Model RO-7 Calibration

008

HPI-7.60

Operation and Calibration of Hopewell BX3 Box Calibrator

001

ISP-TEA/PRM-

X301

TEA High Range Noble Gas Monitor Channel 2 - CC/RC

016

Procedures

ODCM

Offsite Dose Calculation Manual, Amendment 61

05/30/2022

AR-SA: 439162

Snapshot Self-Assessment Report:

NRC IP 71124.05 Radiation Monitoring Instrumentation

08/17/2023

AU-CH-22

Quality Services Audit Report:

Chemistry and Environmental Monitoring Programs

08/10/2022

Self-Assessments

AU-RP/RW -22

Quality Services Audit Report:

Radiation Protection and Process Control Programs

2/14/2022

Corrective Action

Documents

Action Requests

2720, 428208, 439251, 439457, 439458, 439461, 439463,

439465, 439706, 439737, 446956, 447212, 447719

71124.08

Corrective Action

Documents

Resulting from

Inspection

Action Requests

2638, 452639, 452641, 452680, 452687, 452697, 452698,

2753

Radioactive Source Inventory

2/15/2022

Miscellaneous

Columbia Generating Station 2022 Part 61 Waste Stream

Data

09/07/2023

DIC 1554.5

Columbia Generating Station Scaling Factors 2020 -

Revision 1

04/28/2021

Miscellaneous

RW000169

Packaging Radioactive Material for Shipment Training

10/18/2023

PPM 11.2.14.4

Procurement, Receipt, Control, and Leak Test of Radioactive

Sources and Devices

27

PPM 11.2.23.1

Shipping Radioactive Materials and Waste

23

PPM 11.2.23.14

Sampling of Radioactive Waste Streams

014

PPM 11.2.23.2

Computerized Radioactive Waste and Material

Characterization

24

PPM 11.2.23.29

Radioactive Material, Low-Specific Activity Contaminated

Laundry

2

PPM 11.2.23.4

Packaging Radioactive Material and Waste

28

PPM 11.2.23.44

Operation of the Self Engaging Rapid Dewatering System

(SERDS)

011

PPM 11.2.23.46

Shipment of Category 1 and 2 Material

000

SWP-RMP-01

Radioactive Waste Management Program

006

SWP-RMP-02

Radioactive Waste Process Control Program

008

SWP-RMP-03

Hazardous Materials Transportation Security Plan

2

Procedures

SWP-RMP-04

Radioactive Shipping Program

001

M-20221213-3

Source Leak Testing Survey

2/02/2022

M-20230614-8

Source Leak Testing Survey

06/14/2023

M-20230719-3

Outside ISFSI Pad and Building 105 Quarterly

07/19/2023

M-20230822-3

Building 167 and Storage Area Quarterly

08/22/2023

M-20231003-3

Warehouse 5 Quarterly

10/03/2023

M-20231006-1

Outside Storage Area LSA/Spray Pond

10/06/2023

M-20231008-4

GSB Yakima Building Monthly

10/08/2023

M-20231010-5

PSF Standards Lab and NDE Monthly Survey

10/10/2023

Radiation

Surveys

M-20231101-3

Radwaste 437-foot NUPAC Survey 23-015-HP

11/02/2023

AR 448021-01

Annual Radioactive Material Shipping Security Plan Review

(49 CFR 172.800 Review)

08/14/2023

71124.08

Self-Assessments

AR-SA 435882

Annual Review of CGS Implementation of 10 CFR 37,

Physical Protection of Category 1 and Category 2 Quantities

of Radioactive Material (RAM) as required by 10 CFR 37.55

2/01/2022

AR-SA 439233

Assess Columbia's Radiation Protection Organization

readiness for NRC Inspection 71124.08, "Radioactive Solid

Waste Processing and Radioactive Material Handling,

Storage, and Transportation"

08/10/2023

Self-Assessments

AU-RP/RW-22

Quality Services Audit Report: Radiation Protection and

Process Control Programs

2/14/2022

21-039

UN2916, Radioactive Material, Type B(U) package, fissile-

excepted, 7, RQ - Radionuclides

06/15/2021

21-102

UN2916, Radioactive Material, Type B(U) package, 7, RQ -

Radionuclides

11/11/2021

2-034

UN3321, Radioactive Material, Low Specific Activity (LSA-II),

7, RQ - Radionuclides

10/06/2022

2-045

UN2916, Radioactive Material, Type B(U) package, 7, RQ -

Radionuclides

2/14/2022

23-023

UN3321, Radioactive Material, Low Specific Activity (LSA-II),

7, RQ - Radionuclides

04/27/2023

23-033

UN3321, Radioactive Material, Low Specific Activity (LSA-II),

7, RQ - Radionuclides

04/13/2023

Shipping Records23-114

UN3321, Radioactive Material, Low Specific Activity (LSA-II),

7, RQ - Radionuclides

11/15/2023

71124.08

Work Orders

209044-01

HSP-SSC-O801 Sealed Source Check

06/24/2023

CI-10.17

Iodine

015

CSP-I131-W101

Reactor Coolant Isotopic Analysis for I-131 Dose Equivalent

009

71151

Procedures

NEI 99-02

Regulatory Assessment Performance Indicator Guideline

007

71152S

Corrective Action

Documents

Action Requests

446560, 452865, 446127, 448665, 445051, 445813, 446065,

446131, 446169, 447693, 448001, 448918, 449669, 449921,

449942, 449948, 449958, 450029, 450253, 451680, 451754,

2086