IR 05000397/2023001

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000397/2023001 - April 26, 2023
ML23122A076
Person / Time
Site: Columbia 
Issue date: 05/05/2023
From: Patricia Vossmar
NRC/RGN-IV/DORS/PBA
To: Schuetz R
Energy Northwest
References
IR 2023001
Download: ML23122A076 (19)


Text

May 05, 2023

SUBJECT:

COLUMBIA GENERATING STATION - INTEGRATED INSPECTION REPORT 05000397/2023001

Dear Robert Schuetz:

On March 31, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Columbia Generating Station. On April 13, 2023, the NRC inspectors discussed the results of this inspection with Dave Brown, Vice President of Operations, and other members of your staff.

The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Columbia Generating Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Columbia Generating Station. This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Patricia J. Vossmar, Chief Reactor Projects Branch A Division of Operating Reactor Safety Docket No. 05000397 License No. NPF-21

Enclosure:

As stated

Inspection Report

Docket Number:

05000397

License Number:

NPF-21

Report Number:

05000397/2023001

Enterprise Identifier:

I-2023-001-0002

Licensee:

Energy Northwest

Facility:

Columbia Generating Station

Location:

Richland, WA

Inspection Dates:

January 1, 2023, to March 31, 2023

Inspectors:

P. Niebaum, Senior Resident Inspector

A. Donley, Senior Resident Inspector

S. Lichvar, Resident Inspector

H. Strittmatter, Emergency Preparedness Inspector

Approved By:

Patricia J. Vossmar, Chief

Reactor Projects Branch A

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Columbia Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Implement a Station Procedure Resulted in a Challenge to Primary Containment Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000397/2023001-01 Open/Closed

[H.12] - Avoid Complacency 71152A The inspectors reviewed a self-revealed Green, non-cited violation (NCV) of Technical Specification (TS) 5.4.1.a, Procedures, for the licensees failure to establish, implement, and maintain procedures recommended in Appendix A of Regulatory Guide 1.33, revision 2.

Specifically, the licensee failed to establish and monitor wetwell (WW) pressure as a key parameter while preforming OSP-RHR/IST-Q702, RHR Loop A Operability Test, with suppression pool spray in service, in accordance with licensee procedure OI-09, Operations Standard and Expectations. This resulted in a momentary loss and challenge to primary containment integrity when WW to reactor building vacuum breakers CSP-V-9 and CSP-V-10 opened in response to lowering WW pressure.

Additional Tracking Items

None.

PLANT STATUS

Columbia began the inspection period at rated thermal power (RTP). On January 11 and 12, 2023, the unit was down powered to approximately 46 percent for reactor recirculation pump adjustable speed drive (ASD) glycol coolant leak repairs. Following repairs and restoration of the ASD drive, the unit was returned to full RTP on January 14, 2023. On February 26, 2023, the 1A2 channel of ASD system experienced a failure which resulted in a down power to 93 percent once the recirculation loop flows were matched. On February 28, 2023, Columbia lowered power to 74 percent to recover the 1A2 channel following repairs and achieved 100 percent power later that day. On March 26, the station experienced a loss of the ASD channel 1A2 which ultimately resulted in a power reduction to approximately 90 percent RTP once the recirculation loop flows were matched. On March 27, 2023, following repairs to the 1A2 ASD channel, the station lowered power to approximately 73 percent to recover/repower the 1A2 ASD channel. Power was restored to approximately 100 percent on March 28, 2023. Later on March 28, 2023, the station identified issues with the ASD 1A2 channel and reduced power to approximately 89 percent RTP. On March 29, 2023, the station reduced power to approximately 83 percent RTP to take the 1A2 channel out of service. Once the station determined that the 1A1 channel could support higher flows/power, the station raised power to 89 percent RTP. Power remained at approximately 89 percent RTP for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)control room air conditioning system B while system A was out of service for maintenance on January 11, 2023 (2)control room air conditioning system A while system B was out of service for maintenance on January 24, 2023 (3)reactor core isolation cooling (RCIC) system while the high-pressure core spray diesel generator was out of service for maintenance on February 27-28, 2023 (4)diesel generator (DG) system A while DG system B was out of service for maintenance on March 21-22, 2023

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Area RC-12/1, HVAC equipment room B division 2, on January 11, 2023
(2) Fire Area DG-1/1, HPCS diesel generator room, on January 27, 2023
(3) Fire Area RC-11/1, HVAC equipment room A division 1, on March 9, 2023
(4) Fire Area DG-3/2, DG-2 diesel generator room, on March 12, 2023
(5) Fire Area TG-1/2, turbine generator 471, NW general area, on March 13, 2023

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated internal flooding mitigation protections in the reactor building 471-foot elevation.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during power maneuvering for planned adjustable speed drive maintenance on January 12, 2022.

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated a licensed operator requalification evaluated scenario on March 6, 2023.

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (1 Sample)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) RCIC-P-3, reactor core isolation cooling water leg (keep fill) pump

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (5 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1)elevated risk for planned maintenance associated with a cooling coil replacement in WMA-AH-51A, control room air handling unit, on January 10, 2023 (2)yellow risk during the performance of ICP-CSP-X301, reactor building vacuum breaker actuation instrumentation channel calibration, on January 23 and 24, 2023 (3)yellow risk during replacement of a digital electro-hydraulic control system filter on February 9, 2023 (4)yellow risk during a planned maintenance outage of diesel generator 3 on February 27, 2023 (5)elevated/yellow risk during main turbine quadvoter valve solenoid replacement on March 16, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensee's justifications and actions associated with the following operability determinations and functionality assessments:

(1) CR 440991, CSP-DPT-6 (containment supply purge differential pressure transmitter)found low out of tolerance during surveillance testing on January 24, 2023
(2) CR 441013, locked in low air pressure alarm following emergency diesel generator 3 bar over, on January 26, 2023
(3) CR 441445, LPCS-FIS-4 flexible conduit detached from flow instrument on February 7, 2023
(4) CR 442498, reactor core isolation cooling system leakage beneath RCIC-DT-1 on March 13, 2023

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (3 Samples)

(1) OSP-CCH/IST-M702, Control Room Emergency Chiller System B Operability, on January 6, 2023
(2) OSP-ELEC-M703, HPCS Diesel Generator Monthly Operability Test, on February 28, 2023
(3) OSP-MT-W701, Quad Voter Solenoid Valve Test following replacement of a main turbine quadvoter solenoid pilot valve with work order (WO) 02205059, on March 16, 2023

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) OSP-ELEC-M701, Diesel Generator 1 - Monthly Operability Test, on January 5, 2023
(2) WO 02195089, monthly diesel generator 2 operability surveillance, on January 20, 2023

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) OSP-RHR/IST-Q704, RHR Loop C Operability Test, on January 20, 2023

71114.02 - Alert and Notification System Testing

Inspection Review (IP Section 02.01-02.04) (1 Sample)

(1) The inspectors evaluated the maintenance and testing of the alert and notification system between November 1, 2020, and January 31, 2023.

71114.03 - Emergency Response Organization Staffing and Augmentation System

Inspection Review (IP Section 02.01-02.02) (1 Sample)

(1) The inspectors evaluated the readiness of the Emergency Preparedness Organization between November 1, 2020, and January 31, 2023. Inspectors also evaluated the licensee's ability to staff their emergency response facilities in accordance with emergency plan commitments.

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the 10 CFR 50.54(q) emergency plan change process and practices between November 1, 2020, and January 31, 2023. The evaluation reviewed screenings and evaluations documenting implementation of the process. In addition, the inspectors evaluated:

Emergency Plan, revision 68, effective January 26, 2023 PPM 13.14.4, Emergency Equipment Maintenance and Testing, revision 57, effective June 16, 2022 This evaluation does not constitute NRC approval.

71114.05 - Maintenance of Emergency Preparedness

Inspection Review (IP Section 02.01 - 02.11) (1 Sample)

(1) The inspectors evaluated the maintenance of the emergency preparedness program between November 1, 2020, and January 31, 2023. The evaluation reviewed evidence of completing various emergency plan commitments, the conduct of drills and exercises, licensee audits and assessments, and the maintenance of equipment important to emergency preparedness.

71114.06 - Drill Evaluation

Select Emergency Preparedness Drills and/or Training for Observation (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated an emergency preparedness drill on February 14,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

IE01: Unplanned Scrams per 7000 Critical Hours Sample (IP Section 02.01)===

(1) January 1, 2022, through December 31, 2022 IE03: Unplanned Power Changes per 7000 Critical Hours Sample (IP Section 02.02) (1 Sample)
(1) January 1, 2022, through December 31, 2022

IE04: Unplanned Scrams with Complications (USwC) Sample (IP Section 02.03) (1 Sample)

(1) January 1, 2022, through December 31, 2022

EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)

(1) October 1, 2022, through December 31, 2022 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
(1) October 1, 2022, through December 31, 2022 EP03: Alert and Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
(1) October 1, 2022, through December 31, 2022

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following:

(1) CR 441418, CSP-V-9 and CSP-V-10 opened during OSP-RHR/IST-Q702, on February 6, 2023
(2) CR 442428, required element missed in simulator evaluation, on March 9,

INSPECTION RESULTS

Failure to Implement a Station Procedure Resulted in a Challenge to Primary Containment Cornerstone Significance Cross-Cutting Aspect Report Section Barrier Integrity Green NCV 05000397/2023001-01 Open/Closed

[H.12] - Avoid Complacency 71152A The inspectors reviewed a self-revealed Green, non-cited violation (NCV) of Technical Specification (TS) 5.4.1.a, Procedures, for the licensees failure to establish, implement, and maintain procedures recommended in Appendix A of Regulatory Guide 1.33, revision 2.

Specifically, the licensee failed to establish and monitor wetwell (WW) pressure as a key parameter while preforming OSP-RHR/IST-Q702, RHR Loop A Operability Test, with suppression pool spray in service, in accordance with licensee procedure OI-09, Operations Standard and Expectations. This resulted in a momentary loss and challenge to primary containment integrity when WW to reactor building vacuum breakers CSP-V-9 and CSP-V-10 opened in response to lowering WW pressure.

Description:

On February 6, 2023, during performance of licensee surveillance procedure OSP-RHR/IST-Q702, RHR Loop A Operability Test, WW pressure lowered as expected with suppression pool sprays in service. The associated pressure changes were neither monitored adequately nor established as a key parameter. The unmonitored pressure drop led to cycling of the reactor building (RB) to WW vacuum breakers CSP-V-9 and CSP-V-10, representing a momentary loss and challenge to primary containment integrity.

The inspectors noted that during the performance of procedure OSP-RHR/IST-Q702, RHR Loop A Operability Test, the crew did not closely monitor WW pressure as it trended downward, which contributed to the opening of the WW to RB vacuum breakers. When CSP-V-9 and CSP-V-10 opened, a momentary loss and challenge to primary containment integrity occurred. Following this, one of the vacuum breaker valves (CSP-V-10) did not indicate closed in the control room, so the licensee entered Technical Specification Action Statement 3.6.1.6.A, and sent an equipment operator to the valve to verify it was closed locally.

The inspectors also noted that procedure OSP-RHR/IST-Q702, RHR Loop A Operability Test, contains a caution statement that states operation of the suppression pool sprays may cause WW pressure to drop and cycling of RB and WW vacuum breakers.

Considering all of the above, the inspectors concluded that during the RHR Loop A Operability Test, the control room failed to establish and assign WW pressure as a key parameter and monitor it adequately.

The inspectors confirmed that although CSP-V-9 and CSP-V-10 opened unintentionally, the system performed as designed and cycled the vacuum breakers closed, representing only a momentary loss of primary containment integrity.

Corrective Actions: The licensee entered this issue into their corrective action program as condition report 441418 and performed a critique to evaluate their response and lessons learned.

Corrective Action References: 441418

Performance Assessment:

Performance Deficiency: Failure to implement procedure OI-09, Operations Standard and Expectations, revision 084, in accordance with Regulatory Guide 1.33 and TS 5.4.1.a was a performance deficiency. Specifically, Section 4.2.7 of OI-09 states that key parameters are established to allow precise control of critical parameters and safe operation of plant systems, but during an RHR Loop A Operability Test, the control room failed to establish and assign WW pressure as a key parameter.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Human Performance attribute of the Barrier Integrity cornerstone and adversely affected the cornerstone objective to provide reasonable assurance that physical design barriers protect the public from radionuclide releases caused by accidents or events. Specifically, by not establishing a key parameter and adequately monitoring WW pressure with suppression pool spray in service, the licensee unintentionally caused a WW pressure drop that opened the RB to WW vacuum breakers (containment supply purge valves, CSP-V-9, and CSP-V-10) resulting in an unnecessary challenge to primary containment.

Significance: The inspectors assessed the significance of the finding using IMC 0609 Appendix A, The Significance Determination Process (SDP) for Findings At-Power. The inspectors determined that the finding was of very low safety significance (Green) because although this resulted in a momentary actual open pathway from the WW to the RB, it was controlled by an operable containment supply purge valve control system and the valves were verified to be closed after they actuated. Also, the finding did not involve an actual reduction in the function of hydrogen igniters in containment.

Cross-Cutting Aspect: H.12 - Avoid Complacency: Individuals recognize and plan for the possibility of mistakes, latent issues, and inherent risk, even while expecting successful outcomes. Individuals implement appropriate error reduction tools. Specifically, individual contributors perform a thorough review of the work site and planned activity every time work is performed rather than relying on past successes and assumed conditions.

Enforcement:

Violation: Technical Specification 5.4.1.a, Procedures, requires, in part, that written procedures shall be established, implemented, and maintained in accordance with Regulatory Guide 1.33, revision 2. Section 2.g of Appendix A to Regulatory Guide 1.33 recommends power operation and process monitoring procedures. The licensee established procedure OI-09, Operations Standard and Expectations, as a power operation and process monitoring procedure. Procedure OI-09 requires, in part, that key parameters be established to allow precise control of critical parameters and safe operation of plant systems.

Contrary to the above, on February 6, 2023, the licensee failed to establish key parameters to allow precise control of critical parameters and safe operation of plant systems. Specifically, during performance of procedure OSP-RHR/IST-Q702, RHR Loop A Operability Test, the licensee did not establish WW pressure as a key parameter, which impacted precise control of containment integrity and resulted in a momentary loss and challenge to primary containment integrity when the WW to RB vacuum breakers, CSP-V-9 and CSP-V-10, opened in response to lowering WW pressure.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On February 9, 2023, the inspectors presented the emergency preparedness biennial program inspection results to William G. Hettel, Chief Nuclear Officer/ VP Nuclear Generation, and other members of the licensee staff.

On April 13, 2023, the inspectors presented the integrated inspection results to Dave Brown, Vice President of Operations, and other members of the licensee staff.

THIRD PARTY REVIEWS The inspectors reviewed the World Association of Nuclear Operators (WANO)/Institute on Nuclear Power Operations (INPO) report that was issued during the inspection period.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.04

Corrective Action

Documents

Resulting from

Inspection

Action Requests

2782

71111.04

Drawings

M519

Flow Diagram Reactor Core Isolation Cooling System

103

71111.04

Drawings

M775

Flow Diagram Emergency Chilled Water Piping System

Control Room

031, 032

71111.04

Procedures

SOP-DG1-LU

Emergency Diesel Generator (DIV 1) Valve and Power Supply

Lineup

009

71111.04

Procedures

SOP-DG1-STBY

Emergency Diesel Generator (DIV 1) Standby Lineup

23

71111.04

Procedures

SOP-HVAC/CR-

LU

Control, Cable, and Critical Switchgear Rooms HVAC Lineup

003

71111.04

Procedures

SOP-HVAC/CR-

OPS

Control, Cable, and Critical Switchgear Rooms HVAC

Operations

030

71111.04

Procedures

SOP-HVAC/CR-

STBY

Control, Cable, and Critical Switchgear Rooms HVAC in

Standby Status

2

71111.04

Procedures

SOP-RCIC-LU

RCIC Valve and Breaker Lineup

004

71111.04

Procedures

SOP-SW-LU

Standby Service Water System Valve & Breaker Lineup

016

71111.04

Work Orders

2194139

71111.05

Calculations

FP-02-85-03

Combustible Loading Calculation

011

71111.05

Corrective Action

Documents

Resulting from

Inspection

Action Requests

440618, 440575, 442335

71111.05

Fire Plans

PFP-DG-

BUILDING

Diesel Generator Building Pre-Fire Plan

005

71111.05

Fire Plans

PFP-RW-525

Radwaste 525

008

71111.05

Fire Plans

PFP-TG-471

Turbine Generator 471 Pre-Fire Plan

006

71111.05

Miscellaneous

A554

Door Schedule Sheet 2

033

71111.05

Miscellaneous

FM892-3

Fire Barrier and Fire Boundary Plan Operating Floors at El

501-0, 507-0 and 525-0

007

71111.05

Procedures

1.3.57

Barrier Impairment

046

71111.05

Procedures

15.2.14

Function Check, Sensitivity Check and Cleaning of

Photoelectric Detectors

015

71111.05

Procedures

ABN-FIRE

Fire

045

71111.05

Work Orders

2066677, 02167597, 02195886

71111.06

Corrective Action

Documents

Resulting from

Inspection

Action Requests

441373

71111.06

Engineering

Evaluations

ME-02-02-02

Reactor Building Flooding Analysis

004

71111.06

Engineering

Evaluations

ME-02-02-32

Post Fire Safe Shutdown (PFSS) Flooding Analysis - Reactor

Building

000

71111.11Q

Corrective Action

Documents

Action Requests

2262

71111.11Q

Miscellaneous

LR002579

Cycle 23-1 Evaluated Scenario

000

71111.11Q

Procedures

3.2.6

Power Maneuvering

21

71111.11Q

Procedures

A.603.A8

603.A8 Annunciator Panel Alarms

046

71111.11Q

Procedures

SOP-COND-

SHUTDOWN

Main Condensate System Shutdown

26

71111.11Q

Procedures

SOP-CW-

SHUTDOWN

Circulating Water and Cooling Towers Shutdown

008

71111.11Q

Procedures

SOP-RFT-

SHUTDOWN

Reactor Feedwater Turbine Shutdown

016

71111.11Q

Procedures

TDI-08

Licensed Operator Requalification Program

21

71111.11Q

Procedures

TDI-23

LORQ Annual Exam Development and Administration

018

71111.12

Corrective Action

Documents

Action Requests

439058, 439205, 439395, 439427, 439491, 439967, 440884,

2278

71111.12

Procedures

5.1.1

Emergency Operating Procedure (EOP) Flow Chart for RPV

(reactor pressure vessel) Control

23

71111.12

Procedures

SYS-4-22

Maintenance Rule Program

015

71111.13

Corrective Action

Documents

Resulting from

Inspection

Action Requests

2683

71111.13

Miscellaneous

High risk work plan for WO 02194023

2/29/2022

71111.13

Miscellaneous

High risk work plan for WO 02202434

01/10/2023

71111.13

Procedures

1.3.76

Integrated Risk Management

064

71111.13

Procedures

1.3.83

Protected Equipment Program

037

71111.13

Procedures

1.5.14

Risk Assessment and Management for

Maintenance/Surveillance Activities

044

71111.13

Work Orders

2194023, 02166978, 02205059

71111.15

Calculations

E/I-02-91-1072

Setpoint determination for instrument loop CSP-DPT-6

000

71111.15

Corrective Action

Documents

2498, 442876

71111.15

Drawings

M512-1

Flow Diagram Diesel Oil and Miscellaneous Systems Diesel

Generator Building

048

71111.15

Drawings

M543-3

Flow Diagram Reactor Building Primary Containment Cooling

and Purging System

004

71111.15

Engineering

Evaluations

EC 18082

High Energy Line Break (HELB) evaluation

000

71111.15

Operability

Evaluations

CMR-95-0228

Calculation Modification Record for E/I-02-91-1072

03/08/1995

71111.15

Procedures

1.3.66

Operability Determination

038

71111.15

Procedures

4.DG3

DG3 Annunciator Panel Alarms

21

71111.15

Procedures

ICP-CSP-X301

Vacuum Breaker Actuation Instrumentation - CC

006

71111.15

Procedures

ISP-CSP/IST-

B101

RB-WW Vacuum Breaker Setpoint Verification, Visual

Inspection, Actuation and VPI-CC

003

71111.15

Procedures

OSP-DG3-STBY

High Pressure Core Spray Diesel Generator Standby Lineup

2

71111.15

Procedures

OSP-ELEC-S703

HPCS Diesel Generator Semi-Annual Operability Test

068

71111.15

Procedures

OSP-RCIC/IST-

Q701

RCIC Operability Test

71111.15

Procedures

TSP-RCIC-B801

RCIC Leakage Surveillance

71111.15

Work Orders

2174877, 02197701, 02197704, 02166978

71111.15

Work Orders

Work Requests

29169313

71111.24

Calculations

ME-02-05-01

Determination of acceptable oil leakage rates from pump

motors

001

71111.24

Corrective Action

Documents

Action Requests

440287, 441039, 442648

71111.24

Corrective Action

Documents

Resulting from

Inspection

Action Requests

440823

71111.24

Procedures

OSP-DO-Q702

DO-P-1B Operability

2

71111.24

Procedures

OSP-ELEC-M102

DO-TK-3B Monthly Operability Test

006

71111.24

Procedures

OSP-ELEC-M702

Diesel Generator 2 - Monthly Operability Test

069

71111.24

Work Orders

2194600, 02194139, 02194971, 02193773, 02175153,

2192160, 02196497

71114.02

Miscellaneous

CGS Alert and Notification System (ANS) Design Report

2

71114.02

Miscellaneous

1st Quarter 2022 ERO Call-In Drill Report

03/15/2022

71114.02

Procedures

TSI-6.2.22

EP Annual Emergency Response Siren System Activation

Test

09/27/2021

71114.02

Procedures

TSI-6.2.22

EP Annual Emergency Response Siren System Activation

Test

10/03/2019

71114.02

Procedures

TSI-6.2.32

EP Siren Polling Test

003

71114.03

Miscellaneous

4th Quarter 2021 ERO Call-In Drill Report

2/17/2021

71114.03

Miscellaneous

2nd Quarter 2021 ERO Call-In Drill Report

06/22/2021

71114.03

Miscellaneous

1st Quarter 2021 ERO Call-In Drill Report

03/17/2021

71114.03

Miscellaneous

3rd Quarter 2021 ERO Call-In Drill Report

09/15/2021

71114.03

Miscellaneous

ERO Call-Out Drill Team A

11/17/2021

71114.03

Miscellaneous

ERO Call-Out Drill Team D

09/27/2022

71114.03

Miscellaneous

4th Quarter 2022 ERO Call-In Drill Report

2/06/2022

71114.03

Miscellaneous

EP-02

ERO On-Shift Staffing Analysis Report

003

71114.03

Procedures

PPM 13.4.1

Emergency Notifications

044

71114.04

Miscellaneous

50.54(q) Screening for E-Plan Revision 68 Editorials

11/30/2022

71114.04

Miscellaneous

50.54(q) Screening for E-Plan Revision 68

2/28/2022

71114.04

Miscellaneous

50.54(q) Effectiveness Evaluation for PPM 13.14.4 Revision

04/04/2022

71114.04

Miscellaneous

50.54(q) Screening for PPM 13.14.4 Revision 57

03/29/2022

71114.04

Miscellaneous

50.54(q) Screening for SWP-EPP-01 Revision 24

11/22/2022

71114.04

Miscellaneous

50.54(q) Effectiveness Evaluation for E-Plan Revision 68

2/28/2022

71114.04

Procedures

EPI-16

50.54(q) Change Evaluation

01/11/2022

71114.05

Corrective Action

Documents

Action Requests

2865, 413338, 413822, 414008, 414139, 414414, 414993,

415144, 415590, 415859, 416009, 416084, 416383, 417096,

417389, 418058, 420879, 420927, 423847, 424824, 425263,

28926, 430259, 430989, 432074, 432157, 432295, 433116,

434313, 435460, 436001, 436644, 437044, 437077, 437081,

437119, 437918, 437980, 438355, 438513

71114.05

Corrective Action

Documents

Resulting from

Inspection

Action Requests

441467, 441556, 441557

71114.05

Miscellaneous

Focused Self-Assessment Report, Emergency Preparedness

09/07/2021

71114.05

Miscellaneous

Focused Self-Assessment Report, Emergency Preparedness

08/10/2022

71114.05

Miscellaneous

Quality Services Evaluation Report 2022 EP Program 12-

Month Audit Frequency Evaluation

2/07/2022

71114.05

Miscellaneous

EP Contaminated Injured Man Drill Report

11/04/2021

71114.05

Miscellaneous

EP Contaminated Injured Man Drill Report

11/17/2022

71114.05

Miscellaneous

Reactor Coolant Sampling Drill Report

11/30/2021

71114.05

Miscellaneous

Reactor Coolant Sampling Drill Report

2/06/2022

71114.05

Miscellaneous

AU-EP-21

Emergency Preparedness 24-Month Audit

03/18/2021

71114.05

Procedures

Emergency Plan

067

71114.05

Procedures

Emergency Plan

068

71114.05

Procedures

PPM 13.14.4

Emergency Equipment Maintenance and Testing

057

71114.05

Procedures

PPM 13.14.8

Drill and Exercise Program

018

71114.05

Procedures

PPM 13.14.9

Emergency Program Maintenance

030

71114.05

Procedures

SWP-EPP-01

Emergency Response Organization and Training

23

71114.05

Procedures

TSI-6.2.19

EP Federal Telephone System Functional Phone Testing

2

71114.05

Procedures

TSI-6.2.29

EP Emergency Response Facsimile Machine Functional Test

003

71114.05

Procedures

TSI-6.2.30

EP Emergency Response Dial-up Extension Functional Test

001

71114.05

Procedures

TSI-6.2.31

EP Emergency Response Crash Extension Functional Test

003

71114.05

Procedures

TSI-6.2.6

EP Emergency Response Ringdown System Functional Test

001

71114.05

Work Orders

Work Order Task

2173553-01

71114.05

Work Orders

Work Request 29158281, 29163333, 29167996, 29166716

71114.06

Miscellaneous

Emergency Response Organization (ERO) Drill Scenario,

Section 6 for EP drill on February 14, 2023

2/14/2023

71114.06

Miscellaneous

Team D ERO Drill Summary

2/14/2023

71114.06

Miscellaneous

EP Drill Classification Notification Forms (CNFs) for Alert, Site

Area Emergency and General Emergency

2/14/2023

71114.06

Miscellaneous

Columbia Generating Station ERO Team "D" ERO Drill

February 14, 2023, After Action Report/Improvement Plan

03/13/2023

71114.06

Procedures

13.14.8

Drill and Exercise Program

018

71114.06

Procedures

EPI-21

Drill and Exercise Development and Implementation

019

71151

Miscellaneous

Monthly PI Summary Spreadsheets for 2022

71151

Miscellaneous

December 2022 Station Performance Spreadsheet

71151

Miscellaneous

Operations Logs

01/01/2022 -

2/31/2022

71151

Miscellaneous

ANS Test Results and PI Data 4th Quarter 2022

71151

Miscellaneous

ERO Participation PI Tracking Data 4th Quarter 2022

71151

Miscellaneous

DEP Opportunity PI Data 4th Quarter 2022

71151

Procedures

EPI-18

Emergency Preparedness Performance Indicators

27

71152A

Miscellaneous

Form 26297

CRS/SM/STA/IA Evaluation Summary

003

71152A

Miscellaneous

Form 26299

CRO Evaluation Summary

003

71152A

Miscellaneous

Form 27035

Operator Fundamentals Evaluation, evaluated scenario on

March 9, 2023

006

71152A

Miscellaneous

LR000250

Operations Requalification Training, Cycle 22-2 Evaluated

Scenario

000

71152A

Procedures

SW-CAP-01

Corrective Action Program

045

71152A

Procedures

TDI-08

Licensed Operator Requalification Program

21

71152A

Procedures

TDI-23

LORQ Annual Exam Development and Administration

018