IR 05000397/2022010

From kanterella
Jump to navigation Jump to search
Design Basis Assurance Inspection (Team) Inspection Report 05000397/2022010
ML22175A050
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 06/30/2022
From: Vincent Gaddy
NRC Region 4
To: Scheutz R
Energy Northwest
References
IR 2022010
Download: ML22175A050 (15)


Text

SUBJECT:

COLUMBIA GENERATING STATION - DESIGN BASIS ASSURANCE INSPECTION (TEAM) INSPECTION REPORT 05000397/2022010

Dear Mr. Scheutz:

On May 26, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Columbia Generating Station and discussed the results of this inspection with Mr. W.G. Hettel, Chief Nuclear Officer/VP Nuclear Generation and other members of your staff. The results of this inspection are documented in the enclosed report.

One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.

If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Columbia Generating Station.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Columbia Generating Station.

June 30, 2022 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Vincent G. Gaddy, Chief Engineering Branch 1 Division of Operating Reactor Safety Docket No. 05000397 License No. NPF-21

Enclosure:

As stated

Inspection Report

Docket Number:

05000397

License Number:

NPF-21

Report Number:

05000397/2022010

Enterprise Identifier:

I-2022-010-0011

Licensee:

Energy Northwest

Facility:

Columbia Generating Station

Location:

Richland, WA

Inspection Dates:

May 09, 2022, to May 27, 2022

Inspectors:

J. Braisted, Reactor Inspector

M. Chisolm, Reactor Inspector

R. Deese, Senior Reactor Analyst

G. George, Senior Reactor Inspector

C. Smith, Senior Reactor Inspector

F. Thomas, Reactor Inspector

C. Young, Senior Reactor Analyst

Approved By:

Vincent G. Gaddy, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (team) inspection at Columbia Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

Failure to Identify and Correct Adverse HVAC Airflows in the Division II Electrical Safety Bus Vital Island Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000397/2022010-01 Open/Closed

[H.6] - Design Margins 71111.21M The inspectors identified a Green non-cited violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, for Energy Northwests failure to promptly identify and correct a condition adverse to quality. Specifically, from June 5, 2019, to May 26, 2022, the licensee failed to assure that degraded Division II critical switchgear area heating, ventilation, and air conditioning (HVAC) system airflows were promptly identified and corrected.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

===71111.21M - Design Bases Assurance Inspection (Team) The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:

Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (6 Samples)

From May 9, 2022, to May 26, 2022, the team inspected the following components and listed applicable attributes.

(1) High-Pressure Core Spray Minimum Control Valve HPCS-V-12

Thrust and set-point calculation

Weak-link calculation to determine the maximum allowable thrust

Evaluation of pressure-locking and thermal binding

Calculation for setpoint range and allowable value determination for high pressure core spray flow indicating switch instrument loop

Preventive maintenance for inspection and lubrication

Surveillance and Inservice testing procedures and results

Corrective action documents to ensure that degraded or nonconforming conditions are identified and corrected

(2) Division II Battery Chargers E-C1-2A

Vendor technical documentation

Corrective actions associated with the E-C1-2A charger

Surveillance test results to verify charger supplies the required loads

Preventative maintenance and calibration records to ensure setpoints were within established acceptance criteria

Maintenance work orders to ensure appropriate component replacements and relay settings

(3) High Pressure Core Spray Emergency Diesel Generator DG-ENG-1C

Vendor documents on the operation and maintenance recommendations

Corrective action documents and system health reports

Calculations for fuel oil consumption rates

Suitability of elastomer materials with ultra-low-sulfur-diesel fuel Preventative maintenance and surveillance test records

(4) High Pressure Core Spray Room Cooler RRA-FN-4

Engineering calculations associated with replacement coils for cooler

Room cooler fan performance data and calculations to verify adequate room cooling

Preventative maintenance results for the fan and coils

Corrective action documents to ensure degraded or nonconforming conditions are identified and corrected

(5) Division II Direct Current (DC) Bus S1/2

System health report

Heating, ventilation, and air conditioning system calculations and flow balance test results for electrical rooms

Maintenance, inspection, and testing procedures

Vendor operating and maintenance requirements

Short circuit calculations, coordination studies, voltage drop calculations, and maintenance activities to ensure they were appropriate for the design of the Class 1E S1/2 DC Bus

Operating voltage characteristics to verify the Class 1E S1/2 DC Bus and downstream components can perform their design function through input voltage ranges

Corrective action documents to ensure degraded or nonconforming conditions are identified and corrected

(6) Circuit Breaker 7-73

System health report

Maintenance, inspection, and testing procedures

Vendor operating and maintenance requirements

Short circuit calculations, coordination studies, voltage drop calculations, and maintenance activities to ensure they were appropriate for the design 7-73 Circuit Breaker Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===

From May 9, 2022, to May 26, 2022, the team inspected the following component and listed applicable attributes.

(1) Wetwell to Drywell Vacuum Breaker Valves

Vendor installation, operation, and maintenance manual to compare vendor recommendations with licensee practices.

Design specification to understand requirements for the engineering, design, fabrication, testing, and delivery of the valves.

Preventive maintenance documentation for a limited disassembly, inspection, and reassembly of the valves.

Calculation of leakage rate test acceptance criterion to compare with test procedure and design values to support the primary containment pressure suppression function.

Testing documentation for demonstration of operability per technical specifications and the inservice testing program.

Corrective action documents to ensure that degraded or nonconforming conditions are identified and corrected.

Modification Review - Permanent Mods (IP Section 02.03) (5 Samples)

From May 9, 2022, to May 26, 2022, the team inspected the following permanent plant modifications.

(1) EC 08076, Power Range Nuclear Monitor System Replacement
(2) EC 12954, Move Non-1E Loads from Safety Related Inverter E-PP-7AA (Division 1)
(3) EC 13629, Change RCIC-MO-8 Motor and Gear Ratio for Margin
(4) EC 14646, Replace SR 250V / 125V Motor Control Center DC Buckets ITE Gould Starters with NLI
(5) EC 17459, MAG Rotor Replacement - RHR-M-V/24A

Review of Operating Experience Issues (IP Section 02.06) (3 Samples)

From May 9, 2022, to May 26, 2022, the team inspected the following operating experience issues.

(1) NRC Information Notice 2021-03: Operating Experience Related to the Duane Arnold Energy Center Derecho Event on August 10, 2020
(2) NRC Inspection Manual Operating Experience Smart Sample (OpESS)2020/01: Flex Equipment Design Control, Maintenance, and Testing
(3) NRC Information Notice 2006-22: New Ultra-Low-Sulfur Diesel Fuel Oil Could Adversely Impact Diesel Engine Performance

INSPECTION RESULTS

Failure to Identify and Correct Adverse HVAC Airflows in the Division II Electrical Safety Bus Vital Island Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000397/2022010-01 Open/Closed

[H.6] - Design Margins 71111.21M The inspectors identified a Green non-cited violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, for Energy Northwests failure to promptly identify and correct a condition adverse to quality. Specifically, from June 5, 2019, to May 26, 2022, the licensee failed to assure that degraded Division II critical switchgear area heating, ventilation, and air conditioning (HVAC) system airflows were promptly identified and corrected.

Description:

The critical switchgear area HVAC system is designed to maintain temperatures in the electrical rooms between 55 degrees Fahrenheit and 104 degrees Fahrenheit during normal operation and to limit the temperatures below equipment operability limits during all emergency modes of operation. The safety-related WMA-FN-53B ventilation system achieves this function by maintaining temperatures for safety-related Division II battery room, charger room, reactor protection system equipment room, HVAC equipment room, and critical switchgear room. The Division II critical switchgear area HVAC system was designed to supply airflow at 22,800 cubic feet per minute to the switchgear area. Calculation ME-02-92-43, Room Temperature Calculation for DG Building, Reactor Building, Radwaste Building and Service Water, Revision 14, conservatively assumes that the WMA-FN-53B ventilation system supply airflow is 90 percent of design flow or 20,520 cubic feet per minute.

The inspectors reviewed the June 5, 2019, airflow testing and balancing results of the Division II critical switchgear room area ventilation system, WMA-FN-53B. The as-found test results indicated that the total supply airflow from the ventilation system was 17,210 cubic feet per minute, which was below design calculation assumptions. Additionally, the supply airflow to the Division II critical switchgear room and charger room were both below minimum airflows assumed in room temperature design calculation. Following damper adjustments, the ventilation system supply airflow was left at 18,038 cubic feet per minute; leaving supply airflow to the Division II charger room, HVAC room, critical switchgear room, battery room, and reactor protection system room below minimum airflows assumed in the design calculation.

Upon discovery of the degraded airflow results, the inspectors requested the licensees condition report, the associated corrective actions, operability determination, and reportability evaluation that identified and corrected the condition adverse to quality. The licensee informed the inspectors that the condition adverse to quality was not entered into the corrective action program; therefore, no corrective actions, operability determination, or past operability evaluation were initiated.

In accordance with Energy Northwest Procedure SWP-CAP-01, Corrective Action Program, the licensee failed to initiate a condition report to identify the degraded airflows and initiate corrective actions to correct the condition adverse to quality.

Corrective Actions: Following prompting by the inspectors, the licensee initiated a condition report to identify the degraded airflow conditions. The licensee reperformed the room temperature calculations with the as-left airflow results. This calculation determined that the Division II WMA-FN-53B system would maintain its design function although with very little design margin.

Corrective Action References: Action Request Condition Report 00433066

Performance Assessment:

Performance Deficiency: The inspectors determined that the failure to identify and initiate corrective actions for degraded airflows in the corrective action program, in accordance with Energy Northwest Procedure SWP-CAP-01, Corrective Action Program," was a performance deficiency.

Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, Energy Northwest failed to maintain Division II vital island HVAC airflows within the design assumptions, and in order to justify the as-found condition, Energy Northwest revised assumptions solely to obtain favorable results, similar to Example 3.h in Inspection Manual Chapter 0612, Appendix E, "Examples of Minor Issues."

Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 2, Mitigating Systems Screening Questions, the inspectors determined the finding to be of very low safety significance (Green) because the finding affected the design or qualification of a mitigating SSC and did not affect its operability or PRA functionality.

Cross-Cutting Aspect: H.6 - Design Margins: The organization operates and maintains equipment within design margins. Margins are carefully guarded and changed only through a systematic and rigorous process. Special attention is placed on maintaining fission product barriers, defense-in-depth, and safety related equipment. Specifically, since June 2019, the licensee failed to operate and maintain the Division II WM-FN-53B ventilation system well within their design requirements.

Enforcement:

Violation: Title 10 Code of Federal Regulations Part 50, Appendix B, Criterion XVI, "Corrective Action," states "Measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and corrected."

Contrary to the above, from June 5, 2019, to May 26, 2022, the licensee failed to assure that conditions adverse to quality were promptly identify and corrected. Specifically, the licensee failed to assure that degraded Division II critical switchgear area heating, ventilation, and air conditioning (HVAC) system airflows were promptly identified and corrected.

Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

On May 26, 2022, the inspectors presented the design basis assurance inspection (team) inspection results to Mr. W.G. Hettel, Chief Nuclear Officer/VP Nuclear Generation and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Calculations

2.12.58

Second Level Undervoltage Relay Settings for Buses SM-4,

& 8.

71111.21M

Calculations

216-92-001

Calculation for Weaklink Analysis for RHR Valve 21, 24A,

248, 48A and 488 - 18 In. Carbon Steel Bolted Globe Valve

71111.21M

Calculations

216-92-007

Calculation for Weak-Link Analysis for HPCS Valve 12 - 4in

Carbon Steel Gate Valve

71111.21M

Calculations

9.32.00

HVAC - Control Room, Cable Spread room and Critical

Switchgear

71111.21M

Calculations

C106-92-03.02

HPCS System MOV Design Basis Review

71111.21M

Calculations

CE-02-80-01

Seismic Evaluation on Air Handling Unit Bolts

71111.21M

Calculations

E/I 02-91-06

Short Circuit Current Calculation for the 250V, 125V, and +/-

24V D.C. Systems

71111.21M

Calculations

E/I-02-90-01

Low Voltage System Loading, Security System Loading and

Voltage Calculation

71111.21M

Calculations

E/I-02-92-09

Calculation for Short Circuit Current for 4.16kV and 6.9kV

Buses

71111.21M

Calculations

E/I-02-92-14

Heat Load Calculation for Electrical Equipment and Cables

09/14/2021

71111.21M

Calculations

E/I-02-92-17

Medium Voltage (4.16 KV & 6.9 KV) Electrical Distribution

System Phase Overcurrent Relay Settings

71111.21M

Calculations

ME-02-02-25

AC Gate Valves - MOV Thrust and Set-Point Calculation

71111.21M

Calculations

ME-02-02-27

AC Rising Stem Globe Valve -- MOV Thrust and Setpoint

Calculation

71111.21M

Calculations

ME-02-17-03

WMA-AH-53B Air Flow Requirements during February Re-

Balance

71111.21M

Calculations

ME-02-92-43

Room Temperature Calculation for DG Building, Reactor

Building, Radwaste Building, and Service Water

71111.21M

Calculations

ME-02-96-21

Calculation for MOV Pressure Locking

71111.21M

Calculations

NE-02-07-02

Vacuum Breaker Surveillance Acceptance Criterion

Development

71111.21M

Calculations

NE-02-83-15

Allowable Seat Leakage of Drywell to Wetwell Vacuum

Breaker Valves

71111.21M

Corrective Action

Action Request

00329746, 00387517, 00335659, 00410872, 00414990,

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Documents

(AR)

00432348, 00305653, 00394491, 00408115, 00409229,

00409308, 00410872, 00421315, 00421613, 00425105

71111.21M

Corrective Action

Documents

Resulting from

Inspection

Action Request

(AR)

00432722, 00432726, 00432727, 00432740, 00432756,

00432764, 00432777, 00432778, 00432783,

00432829,00432836, 00432837, 00432838, 00432839,

00432840, 00432841, 00432844, 00432850, 00432856,

00433050, 00433057, 00433065, 00433066, 00433067,

00433143, 00433168, 00433168, 00433170, 00433173,

00433177, 00433178, 00433214, 00433215, 00433230,

00433231, 00433245, 00433268, 00433281, 00433282

71111.21M

Drawings

E502-2

Main One Line Diagram

71111.21M

Drawings

E505-1

DC One Line Diagram

114

71111.21M

Drawings

E505-2

DC One Line Diagram

71111.21M

Drawings

E506-2

Phasing Diagram

71111.21M

Drawings

EWD-46E-211

AC Electrical Distribution System UPS TDAS/PDIS

Computer Power Panel E-PP-US-PT

71111.21M

Drawings

EWD-46E-236

Electrical Wiring Diagram, AC Electrical Distribution System,

Main Control Room, UPS Power Panel E-PP-7AA

71111.21M

Drawings

EWD-50E-002

DC Electrical Distribution System Distribution Panel E-DP-

S1/1B

71111.21M

Drawings

EWD-50E-008

Electrical Wiring Diagram, DC Electrical Distribution System,

Distribution Panel E-DP-S1/2A

71111.21M

Drawings

EWD-50E-009

DC Electrical Distribution System Distribution Panel E-DP-

S1/2B

71111.21M

Drawings

EWD-50E-014

Electrical Wiring Diagram, DC Electrical Distribution System,

Distribution Panel E-DP-S1/2D

71111.21M

Drawings

EWD-50E-015

Electrical Wiring Diagram, DC Electrical Distribution System,

Distribution Panel E-DP-S1/2E

71111.21M

Drawings

M519

Flow Diagram Reactor Core Isolation System

103

71111.21M

Drawings

M520

Flow Diagram, HPCS and LPCS Systems, Reactor Building

105

71111.21M

Drawings

M543-1

Flow Diagram - Reactor Bldg. Primary Containment Cooling

and Purging System

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Drawings

M545-1

Flow Diagram Heating Ventilation and Air Conditioning

Reactor Building

71111.21M

Drawings

M820-2

HVAC Plan and Sections at Elevation 467'-0", Radwaste and

Control Building

71111.21M

Drawings

M821

HVAC Plan and Sections at Elevation 467'-0", Radwaste and

Control Building

71111.21M

Drawings

MEC M820-1

HVAC Plan and Sections at Elevation 467'-0", Radwaste and

Control Building

71111.21M

Drawings

S513

Spray Pond Plan, Sections and Details

71111.21M

Drawings

S514

Structural Standby Service Water Pump House 1A and 1B

Foundation Plan and Sections

71111.21M

Drawings

S515

Pumphouse Intake Screens

71111.21M

Engineering

Changes

235

Calculation for Short Circuit Current for 250V and 125V and

+/- 24V DC

2/07/2016

71111.21M

Engineering

Changes

EC 15617

Child EC to Master EC 14646

Cable / panel wiring termination instructions

71111.21M

Engineering

Changes

EC 19100

Replacement of WMA-M-FN/53A

71111.21M

Engineering

Changes

EC14646

Master EC - Replace SR 250V / 125V Motor Control Center

DC Buckets ITE Gould Starters with NLI

003

71111.21M

Engineering

Changes

EC15333

Relay equivalency evaluation for component substitution

71111.21M

Engineering

Changes

EC15692

Child EC to Master EC 14646

Cable / Panel Wiring Termination Instructions

71111.21M

Engineering

Evaluations

EC8076

Power Range Neutron Monitor Replacement

71111.21M

Engineering

Evaluations

TD 1312

Evaluation of Replacement Intervals for Engine Driven Fuel

Oil and Cooling Water Pumps

71111.21M

Engineering

Evaluations

TM-2107

Generic Letter 95-07 Pressure Locking and Thermal Binding

Evaluation

71111.21M

Miscellaneous

Inservice Testing Program Plan, Fourth Ten-Year Inspection

Interval

5.001

71111.21M

Miscellaneous

47A-00,131

Westinghouse Electric - Medium Voltage Metal-Clad

Switchgear, Indoor 4160 Volts and 6900 Volts

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Miscellaneous

51A-00,8

EXIDE/YUASA/ENERSYS - Stationary Batteries & Chargers

71111.21M

Miscellaneous

2-00,16

Ametek Solid State Controls

71111.21M

Miscellaneous

2-00,16

Vendor manual Solidstate Controls INC.

200 AMP Battery Charger

200 AMP DC Distribution Panel

Prototype Charger and Panel

004

71111.21M

Miscellaneous

999-00,12,2

Limitorque Critical Component List and Parts List

71111.21M

Miscellaneous

AED SPC 13F

Containment Vacuum Breaker Valves

71111.21M

Miscellaneous

AED SPC 308

High Pressure Core Spray System (HPCS)

71111.21M

Miscellaneous

AED SPC V1

Containment Wetwell-To-Drywell Vacuum Breaker Valves

71111.21M

Miscellaneous

CVI 1017-00

Instruction manual for installation, operation, and

maintenance instructions for Aerofin coils

71111.21M

Miscellaneous

CVI 213-05,7

Vacuum Relief Valve and Auxiliaries

71111.21M

Miscellaneous

MOVPP-01

Motor Operated Valve Program

71111.21M

Miscellaneous

SD000200

System Description, Diesel Generator

71111.21M

Miscellaneous

Section 317-DC

Design Basis Document Division 300 Section 317-DC

DC Electrical Distribution System

71111.21M

Procedures

10.1.13

Foreign Materials Controls for System and Components

030

71111.21M

Procedures

10.2.222

Seismic Storage Requirements for Transient Equipment

2

71111.21M

Procedures

10.2.43

Alignment and Tensioning of V-Belt Drives

007

71111.21M

Procedures

10.25.13A

4.16KV Vacuum Breaker Maintenance with Stored Energy

Mechanism

21

71111.21M

Procedures

10.25.18E

Setting DC Voltage Sensing Boards, SCI Battery Chargers

005

71111.21M

Procedures

10.25.18F

Setting Current Limit for SCI Battery Chargers

003

71111.21M

Procedures

10.25.234

Equalize Charging 24 VDC, 125 VDC, and 250 VDC Station

Batteries

2

71111.21M

Procedures

ABN-ELEC-

25VDC

Plant BOP, DIV 1, 2, & 3 125 VDC Distribution System

Failures

017

71111.21M

Procedures

ABN-WIND

Tornado/High Winds

71111.21M

Procedures

ESP-B12-F101

Month Battery Testing of 125 VDC E-B1-2

014

71111.21M

Procedures

ESP-RLY277345-

X301

4.16 KV Emergency Bus Degraded Undervoltage Relays (E-

RLY-27/7/3, E-RLY-27/7/4, and E-RLY-27/7/5) - CC

010

71111.21M

Procedures

MI-1.22

Maintenance Department Instructions

25

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

71111.21M

Procedures

OQAPD-01

Operational Quality Assurance Program Description (EN-

QA-004)

71111.21M

Procedures

SOP-TMU-OPS

Tower Makeup Water Operation

71111.21M

Procedures

SWP-CAP-01

Corrective Action Program

71111.21M

Work Orders

Work Order (WO)

218641901, 0212321801, 0216123201, 0210824301,

2066788, 0118435101, 0118435001, 02116068, 02043602,

2103287, 02118450, 02160241, 02160245, 02113481,

2146667, 02151550, 02152718, 02152732, 02153296,

2154353, 01288157, 02088282, 02088283, 01183734,

2042615, 02022742, 02088060, 02088063, 02088276,

2143623, 02145157, 02171950, 02094683