IR 05000397/2022010
| ML22175A050 | |
| Person / Time | |
|---|---|
| Site: | Columbia |
| Issue date: | 06/30/2022 |
| From: | Vincent Gaddy NRC Region 4 |
| To: | Scheutz R Energy Northwest |
| References | |
| IR 2022010 | |
| Download: ML22175A050 (15) | |
Text
SUBJECT:
COLUMBIA GENERATING STATION - DESIGN BASIS ASSURANCE INSPECTION (TEAM) INSPECTION REPORT 05000397/2022010
Dear Mr. Scheutz:
On May 26, 2022, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Columbia Generating Station and discussed the results of this inspection with Mr. W.G. Hettel, Chief Nuclear Officer/VP Nuclear Generation and other members of your staff. The results of this inspection are documented in the enclosed report.
One finding of very low safety significance (Green) is documented in this report. This finding involved a violation of NRC requirements. We are treating this violation as a non-cited violation (NCV) consistent with Section 2.3.2 of the Enforcement Policy.
If you contest the violation or the significance or severity of the violation documented in this inspection report, you should provide a response within 30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear Regulatory Commission, ATTN:
Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; the Director, Office of Enforcement; and the NRC Resident Inspector at Columbia Generating Station.
If you disagree with a cross-cutting aspect assignment in this report, you should provide a response within 30 days of the date of this inspection report, with the basis for your disagreement, to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001; with copies to the Regional Administrator, Region IV; and the NRC Resident Inspector at Columbia Generating Station.
June 30, 2022 This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Vincent G. Gaddy, Chief Engineering Branch 1 Division of Operating Reactor Safety Docket No. 05000397 License No. NPF-21
Enclosure:
As stated
Inspection Report
Docket Number:
05000397
License Number:
Report Number:
Enterprise Identifier:
I-2022-010-0011
Licensee:
Energy Northwest
Facility:
Columbia Generating Station
Location:
Richland, WA
Inspection Dates:
May 09, 2022, to May 27, 2022
Inspectors:
J. Braisted, Reactor Inspector
M. Chisolm, Reactor Inspector
R. Deese, Senior Reactor Analyst
G. George, Senior Reactor Inspector
C. Smith, Senior Reactor Inspector
F. Thomas, Reactor Inspector
C. Young, Senior Reactor Analyst
Approved By:
Vincent G. Gaddy, Chief
Engineering Branch 1
Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a design basis assurance inspection (team) inspection at Columbia Generating Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
Failure to Identify and Correct Adverse HVAC Airflows in the Division II Electrical Safety Bus Vital Island Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000397/2022010-01 Open/Closed
[H.6] - Design Margins 71111.21M The inspectors identified a Green non-cited violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, for Energy Northwests failure to promptly identify and correct a condition adverse to quality. Specifically, from June 5, 2019, to May 26, 2022, the licensee failed to assure that degraded Division II critical switchgear area heating, ventilation, and air conditioning (HVAC) system airflows were promptly identified and corrected.
Additional Tracking Items
None.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
===71111.21M - Design Bases Assurance Inspection (Team) The inspectors evaluated the following components and listed applicable attributes, permanent modifications, and operating experience:
Design Review - Risk-Significant/Low Design Margin Components (IP Section 02.02) (6 Samples)
From May 9, 2022, to May 26, 2022, the team inspected the following components and listed applicable attributes.
- (1) High-Pressure Core Spray Minimum Control Valve HPCS-V-12
Thrust and set-point calculation
Weak-link calculation to determine the maximum allowable thrust
Evaluation of pressure-locking and thermal binding
Calculation for setpoint range and allowable value determination for high pressure core spray flow indicating switch instrument loop
Preventive maintenance for inspection and lubrication
Surveillance and Inservice testing procedures and results
Corrective action documents to ensure that degraded or nonconforming conditions are identified and corrected
- (2) Division II Battery Chargers E-C1-2A
Vendor technical documentation
Corrective actions associated with the E-C1-2A charger
Surveillance test results to verify charger supplies the required loads
Preventative maintenance and calibration records to ensure setpoints were within established acceptance criteria
Maintenance work orders to ensure appropriate component replacements and relay settings
- (3) High Pressure Core Spray Emergency Diesel Generator DG-ENG-1C
Vendor documents on the operation and maintenance recommendations
Corrective action documents and system health reports
Calculations for fuel oil consumption rates
Suitability of elastomer materials with ultra-low-sulfur-diesel fuel Preventative maintenance and surveillance test records
- (4) High Pressure Core Spray Room Cooler RRA-FN-4
Engineering calculations associated with replacement coils for cooler
Room cooler fan performance data and calculations to verify adequate room cooling
Preventative maintenance results for the fan and coils
Corrective action documents to ensure degraded or nonconforming conditions are identified and corrected
- (5) Division II Direct Current (DC) Bus S1/2
System health report
Heating, ventilation, and air conditioning system calculations and flow balance test results for electrical rooms
Maintenance, inspection, and testing procedures
Vendor operating and maintenance requirements
Short circuit calculations, coordination studies, voltage drop calculations, and maintenance activities to ensure they were appropriate for the design of the Class 1E S1/2 DC Bus
Operating voltage characteristics to verify the Class 1E S1/2 DC Bus and downstream components can perform their design function through input voltage ranges
Corrective action documents to ensure degraded or nonconforming conditions are identified and corrected
- (6) Circuit Breaker 7-73
System health report
Maintenance, inspection, and testing procedures
Vendor operating and maintenance requirements
Short circuit calculations, coordination studies, voltage drop calculations, and maintenance activities to ensure they were appropriate for the design 7-73 Circuit Breaker Design Review - Large Early Release Frequency (LERFs) (IP Section 02.02)===
From May 9, 2022, to May 26, 2022, the team inspected the following component and listed applicable attributes.
- (1) Wetwell to Drywell Vacuum Breaker Valves
Vendor installation, operation, and maintenance manual to compare vendor recommendations with licensee practices.
Design specification to understand requirements for the engineering, design, fabrication, testing, and delivery of the valves.
Preventive maintenance documentation for a limited disassembly, inspection, and reassembly of the valves.
Calculation of leakage rate test acceptance criterion to compare with test procedure and design values to support the primary containment pressure suppression function.
Testing documentation for demonstration of operability per technical specifications and the inservice testing program.
Corrective action documents to ensure that degraded or nonconforming conditions are identified and corrected.
Modification Review - Permanent Mods (IP Section 02.03) (5 Samples)
From May 9, 2022, to May 26, 2022, the team inspected the following permanent plant modifications.
- (1) EC 08076, Power Range Nuclear Monitor System Replacement
- (2) EC 12954, Move Non-1E Loads from Safety Related Inverter E-PP-7AA (Division 1)
- (3) EC 13629, Change RCIC-MO-8 Motor and Gear Ratio for Margin
- (5) EC 17459, MAG Rotor Replacement - RHR-M-V/24A
Review of Operating Experience Issues (IP Section 02.06) (3 Samples)
From May 9, 2022, to May 26, 2022, the team inspected the following operating experience issues.
- (1) NRC Information Notice 2021-03: Operating Experience Related to the Duane Arnold Energy Center Derecho Event on August 10, 2020
- (2) NRC Inspection Manual Operating Experience Smart Sample (OpESS)2020/01: Flex Equipment Design Control, Maintenance, and Testing
- (3) NRC Information Notice 2006-22: New Ultra-Low-Sulfur Diesel Fuel Oil Could Adversely Impact Diesel Engine Performance
INSPECTION RESULTS
Failure to Identify and Correct Adverse HVAC Airflows in the Division II Electrical Safety Bus Vital Island Cornerstone Significance Cross-Cutting Aspect Report Section Mitigating Systems Green NCV 05000397/2022010-01 Open/Closed
[H.6] - Design Margins 71111.21M The inspectors identified a Green non-cited violation of 10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, for Energy Northwests failure to promptly identify and correct a condition adverse to quality. Specifically, from June 5, 2019, to May 26, 2022, the licensee failed to assure that degraded Division II critical switchgear area heating, ventilation, and air conditioning (HVAC) system airflows were promptly identified and corrected.
Description:
The critical switchgear area HVAC system is designed to maintain temperatures in the electrical rooms between 55 degrees Fahrenheit and 104 degrees Fahrenheit during normal operation and to limit the temperatures below equipment operability limits during all emergency modes of operation. The safety-related WMA-FN-53B ventilation system achieves this function by maintaining temperatures for safety-related Division II battery room, charger room, reactor protection system equipment room, HVAC equipment room, and critical switchgear room. The Division II critical switchgear area HVAC system was designed to supply airflow at 22,800 cubic feet per minute to the switchgear area. Calculation ME-02-92-43, Room Temperature Calculation for DG Building, Reactor Building, Radwaste Building and Service Water, Revision 14, conservatively assumes that the WMA-FN-53B ventilation system supply airflow is 90 percent of design flow or 20,520 cubic feet per minute.
The inspectors reviewed the June 5, 2019, airflow testing and balancing results of the Division II critical switchgear room area ventilation system, WMA-FN-53B. The as-found test results indicated that the total supply airflow from the ventilation system was 17,210 cubic feet per minute, which was below design calculation assumptions. Additionally, the supply airflow to the Division II critical switchgear room and charger room were both below minimum airflows assumed in room temperature design calculation. Following damper adjustments, the ventilation system supply airflow was left at 18,038 cubic feet per minute; leaving supply airflow to the Division II charger room, HVAC room, critical switchgear room, battery room, and reactor protection system room below minimum airflows assumed in the design calculation.
Upon discovery of the degraded airflow results, the inspectors requested the licensees condition report, the associated corrective actions, operability determination, and reportability evaluation that identified and corrected the condition adverse to quality. The licensee informed the inspectors that the condition adverse to quality was not entered into the corrective action program; therefore, no corrective actions, operability determination, or past operability evaluation were initiated.
In accordance with Energy Northwest Procedure SWP-CAP-01, Corrective Action Program, the licensee failed to initiate a condition report to identify the degraded airflows and initiate corrective actions to correct the condition adverse to quality.
Corrective Actions: Following prompting by the inspectors, the licensee initiated a condition report to identify the degraded airflow conditions. The licensee reperformed the room temperature calculations with the as-left airflow results. This calculation determined that the Division II WMA-FN-53B system would maintain its design function although with very little design margin.
Corrective Action References: Action Request Condition Report 00433066
Performance Assessment:
Performance Deficiency: The inspectors determined that the failure to identify and initiate corrective actions for degraded airflows in the corrective action program, in accordance with Energy Northwest Procedure SWP-CAP-01, Corrective Action Program," was a performance deficiency.
Screening: The inspectors determined the performance deficiency was more than minor because it was associated with the Equipment Performance attribute of the Mitigating Systems cornerstone and adversely affected the cornerstone objective to ensure the availability, reliability, and capability of systems that respond to initiating events to prevent undesirable consequences. Specifically, Energy Northwest failed to maintain Division II vital island HVAC airflows within the design assumptions, and in order to justify the as-found condition, Energy Northwest revised assumptions solely to obtain favorable results, similar to Example 3.h in Inspection Manual Chapter 0612, Appendix E, "Examples of Minor Issues."
Significance: The inspectors assessed the significance of the finding using Appendix A, The Significance Determination Process (SDP) for Findings At-Power. Using Exhibit 2, Mitigating Systems Screening Questions, the inspectors determined the finding to be of very low safety significance (Green) because the finding affected the design or qualification of a mitigating SSC and did not affect its operability or PRA functionality.
Cross-Cutting Aspect: H.6 - Design Margins: The organization operates and maintains equipment within design margins. Margins are carefully guarded and changed only through a systematic and rigorous process. Special attention is placed on maintaining fission product barriers, defense-in-depth, and safety related equipment. Specifically, since June 2019, the licensee failed to operate and maintain the Division II WM-FN-53B ventilation system well within their design requirements.
Enforcement:
Violation: Title 10 Code of Federal Regulations Part 50, Appendix B, Criterion XVI, "Corrective Action," states "Measures shall be established to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies, deviations, defective material and equipment, and nonconformances are promptly identified and corrected."
Contrary to the above, from June 5, 2019, to May 26, 2022, the licensee failed to assure that conditions adverse to quality were promptly identify and corrected. Specifically, the licensee failed to assure that degraded Division II critical switchgear area heating, ventilation, and air conditioning (HVAC) system airflows were promptly identified and corrected.
Enforcement Action: This violation is being treated as a non-cited violation, consistent with Section 2.3.2 of the Enforcement Policy.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
On May 26, 2022, the inspectors presented the design basis assurance inspection (team) inspection results to Mr. W.G. Hettel, Chief Nuclear Officer/VP Nuclear Generation and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Calculations
2.12.58
Second Level Undervoltage Relay Settings for Buses SM-4,
& 8.
Calculations
216-92-001
Calculation for Weaklink Analysis for RHR Valve 21, 24A,
248, 48A and 488 - 18 In. Carbon Steel Bolted Globe Valve
Calculations
216-92-007
Calculation for Weak-Link Analysis for HPCS Valve 12 - 4in
Carbon Steel Gate Valve
Calculations
9.32.00
HVAC - Control Room, Cable Spread room and Critical
Switchgear
Calculations
C106-92-03.02
HPCS System MOV Design Basis Review
Calculations
CE-02-80-01
Seismic Evaluation on Air Handling Unit Bolts
Calculations
E/I 02-91-06
Short Circuit Current Calculation for the 250V, 125V, and +/-
24V D.C. Systems
Calculations
E/I-02-90-01
Low Voltage System Loading, Security System Loading and
Voltage Calculation
Calculations
E/I-02-92-09
Calculation for Short Circuit Current for 4.16kV and 6.9kV
Buses
Calculations
E/I-02-92-14
Heat Load Calculation for Electrical Equipment and Cables
09/14/2021
Calculations
E/I-02-92-17
Medium Voltage (4.16 KV & 6.9 KV) Electrical Distribution
System Phase Overcurrent Relay Settings
Calculations
ME-02-02-25
AC Gate Valves - MOV Thrust and Set-Point Calculation
Calculations
ME-02-02-27
AC Rising Stem Globe Valve -- MOV Thrust and Setpoint
Calculation
Calculations
ME-02-17-03
WMA-AH-53B Air Flow Requirements during February Re-
Balance
Calculations
ME-02-92-43
Room Temperature Calculation for DG Building, Reactor
Building, Radwaste Building, and Service Water
Calculations
ME-02-96-21
Calculation for MOV Pressure Locking
Calculations
NE-02-07-02
Vacuum Breaker Surveillance Acceptance Criterion
Development
Calculations
NE-02-83-15
Allowable Seat Leakage of Drywell to Wetwell Vacuum
Breaker Valves
Corrective Action
Action Request
00329746, 00387517, 00335659, 00410872, 00414990,
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Documents
(AR)
00432348, 00305653, 00394491, 00408115, 00409229,
00409308, 00410872, 00421315, 00421613, 00425105
Corrective Action
Documents
Resulting from
Inspection
Action Request
(AR)
00432722, 00432726, 00432727, 00432740, 00432756,
00432764, 00432777, 00432778, 00432783,
00432829,00432836, 00432837, 00432838, 00432839,
00432840, 00432841, 00432844, 00432850, 00432856,
00433050, 00433057, 00433065, 00433066, 00433067,
00433143, 00433168, 00433168, 00433170, 00433173,
00433177, 00433178, 00433214, 00433215, 00433230,
00433231, 00433245, 00433268, 00433281, 00433282
Drawings
E502-2
Main One Line Diagram
Drawings
E505-1
DC One Line Diagram
114
Drawings
E505-2
DC One Line Diagram
Drawings
E506-2
Phasing Diagram
Drawings
EWD-46E-211
AC Electrical Distribution System UPS TDAS/PDIS
Computer Power Panel E-PP-US-PT
Drawings
EWD-46E-236
Electrical Wiring Diagram, AC Electrical Distribution System,
Main Control Room, UPS Power Panel E-PP-7AA
Drawings
EWD-50E-002
DC Electrical Distribution System Distribution Panel E-DP-
S1/1B
Drawings
EWD-50E-008
Electrical Wiring Diagram, DC Electrical Distribution System,
Distribution Panel E-DP-S1/2A
Drawings
EWD-50E-009
DC Electrical Distribution System Distribution Panel E-DP-
S1/2B
Drawings
EWD-50E-014
Electrical Wiring Diagram, DC Electrical Distribution System,
Distribution Panel E-DP-S1/2D
Drawings
EWD-50E-015
Electrical Wiring Diagram, DC Electrical Distribution System,
Distribution Panel E-DP-S1/2E
Drawings
M519
Flow Diagram Reactor Core Isolation System
103
Drawings
M520
Flow Diagram, HPCS and LPCS Systems, Reactor Building
105
Drawings
M543-1
Flow Diagram - Reactor Bldg. Primary Containment Cooling
and Purging System
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Drawings
M545-1
Flow Diagram Heating Ventilation and Air Conditioning
Reactor Building
Drawings
M820-2
HVAC Plan and Sections at Elevation 467'-0", Radwaste and
Control Building
Drawings
M821
HVAC Plan and Sections at Elevation 467'-0", Radwaste and
Control Building
Drawings
MEC M820-1
HVAC Plan and Sections at Elevation 467'-0", Radwaste and
Control Building
Drawings
S513
Spray Pond Plan, Sections and Details
Drawings
S514
Structural Standby Service Water Pump House 1A and 1B
Foundation Plan and Sections
Drawings
S515
Pumphouse Intake Screens
Engineering
Changes
235
Calculation for Short Circuit Current for 250V and 125V and
2/07/2016
Engineering
Changes
Child EC to Master EC 14646
Cable / panel wiring termination instructions
Engineering
Changes
Replacement of WMA-M-FN/53A
Engineering
Changes
Master EC - Replace SR 250V / 125V Motor Control Center
DC Buckets ITE Gould Starters with NLI
003
Engineering
Changes
Relay equivalency evaluation for component substitution
Engineering
Changes
Child EC to Master EC 14646
Cable / Panel Wiring Termination Instructions
Engineering
Evaluations
Power Range Neutron Monitor Replacement
Engineering
Evaluations
TD 1312
Evaluation of Replacement Intervals for Engine Driven Fuel
Oil and Cooling Water Pumps
Engineering
Evaluations
TM-2107
Generic Letter 95-07 Pressure Locking and Thermal Binding
Evaluation
Miscellaneous
Inservice Testing Program Plan, Fourth Ten-Year Inspection
Interval
5.001
Miscellaneous
47A-00,131
Westinghouse Electric - Medium Voltage Metal-Clad
Switchgear, Indoor 4160 Volts and 6900 Volts
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Miscellaneous
51A-00,8
EXIDE/YUASA/ENERSYS - Stationary Batteries & Chargers
Miscellaneous
2-00,16
Ametek Solid State Controls
Miscellaneous
2-00,16
Vendor manual Solidstate Controls INC.
200 AMP Battery Charger
Prototype Charger and Panel
004
Miscellaneous
999-00,12,2
Limitorque Critical Component List and Parts List
Miscellaneous
Containment Vacuum Breaker Valves
Miscellaneous
High Pressure Core Spray System (HPCS)
Miscellaneous
Containment Wetwell-To-Drywell Vacuum Breaker Valves
Miscellaneous
CVI 1017-00
Instruction manual for installation, operation, and
maintenance instructions for Aerofin coils
Miscellaneous
CVI 213-05,7
Vacuum Relief Valve and Auxiliaries
Miscellaneous
MOVPP-01
Motor Operated Valve Program
Miscellaneous
SD000200
System Description, Diesel Generator
Miscellaneous
Section 317-DC
Design Basis Document Division 300 Section 317-DC
DC Electrical Distribution System
Procedures
10.1.13
Foreign Materials Controls for System and Components
030
Procedures
10.2.222
Seismic Storage Requirements for Transient Equipment
2
Procedures
10.2.43
Alignment and Tensioning of V-Belt Drives
007
Procedures
10.25.13A
4.16KV Vacuum Breaker Maintenance with Stored Energy
Mechanism
21
Procedures
10.25.18E
Setting DC Voltage Sensing Boards, SCI Battery Chargers
005
Procedures
10.25.18F
Setting Current Limit for SCI Battery Chargers
003
Procedures
10.25.234
Equalize Charging 24 VDC, 125 VDC, and 250 VDC Station
Batteries
2
Procedures
ABN-ELEC-
25VDC
Plant BOP, DIV 1, 2, & 3 125 VDC Distribution System
Failures
017
Procedures
ABN-WIND
Tornado/High Winds
Procedures
Month Battery Testing of 125 VDC E-B1-2
014
Procedures
ESP-RLY277345-
X301
4.16 KV Emergency Bus Degraded Undervoltage Relays (E-
RLY-27/7/3, E-RLY-27/7/4, and E-RLY-27/7/5) - CC
010
Procedures
MI-1.22
Maintenance Department Instructions
25
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Procedures
OQAPD-01
Operational Quality Assurance Program Description (EN-
QA-004)
Procedures
SOP-TMU-OPS
Tower Makeup Water Operation
Procedures
SWP-CAP-01
Corrective Action Program
Work Orders
Work Order (WO)
218641901, 0212321801, 0216123201, 0210824301,
2066788, 0118435101, 0118435001, 02116068, 02043602,
2103287, 02118450, 02160241, 02160245, 02113481,
2146667, 02151550, 02152718, 02152732, 02153296,
2154353, 01288157, 02088282, 02088283, 01183734,
2042615, 02022742, 02088060, 02088063, 02088276,
2143623, 02145157, 02171950, 02094683