Category:INSPECTION REPORT
MONTHYEARIR 05000382/19990201999-10-21021 October 1999 Insp Rept 50-382/99-20 on 990815-0925.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support Activities IR 05000382/19990141999-10-19019 October 1999 Insp Rept 50-382/99-14 on 990913-17 & 1004-08.No Violations Noted.Major Areas Inspected:Operator Requalification Training Program IR 05000382/19990181999-09-29029 September 1999 Insp Rept 50-382/99-18 on 990830-0902.Violations Noted.Major Areas Inspected:Implementation of NRC-approved Fire Protection Program IR 05000382/19990191999-09-27027 September 1999 Insp Rept 50-382/99-19 on 990830-0903.No Violations Noted. Major Areas Inspected:Plant Support IR 05000382/19990151999-09-14014 September 1999 Insp Rept 50-382/99-15 on 990719-23 with in Ofc Insp Until 0819.No Violations Noted.Major Areas Inspected:Assessment of 10CFR50.59 Safety Evaluation Program & Review of Previous Insp Findings Involving Tornado Missile Protection IR 05000382/19990071999-09-0808 September 1999 Insp Rept 50-382/99-07 on 990601-11.Noncited Violations Identified.Major Areas Inspected:Operations IR 05000382/19990161999-09-0101 September 1999 Insp Rept 50-382/99-16 on 990704-0814.Noncited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support IR 05000382/19990101999-08-11011 August 1999 Insp Rept 50-382/99-10 on 990719-23.Violations Noted.Major Areas Inspected:Solid Radioactive Waste Mgt & Radioactive Matl Transportation Programs IR 05000382/19990131999-07-15015 July 1999 Insp Rept 50-382/99-13 on 990523-0703.Noncited Violations Noted.Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities IR 05000382/19990121999-06-21021 June 1999 Insp Rept 50-382/99-12 on 990524-27.No Violations Noted. Major Areas Inspected:Operational Status of Licensee Emergency Preparedness Program IR 05000382/19990111999-06-18018 June 1999 Insp Rept 50-382/99-11 on 990524-28.No Violations Noted. Major Areas Inspected:Implementation of Liquid & Gaseous Radwaste Effluent Mgt Program,Status of Effluent Radiation Monitors & Counting Room Instruments IR 05000382/19990091999-06-0303 June 1999 Insp Rept 50-382/99-09 on 990411-0522.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19990061999-05-18018 May 1999 Insp Rept 50-382/99-06 on 990405-09.Non-cited Violations Identified.Major Areas Inspected:Issue Previously Identified During Architect Engineering Insp Which Documented NRC Insp Rept 50-382/98-201 IR 05000382/19990051999-05-10010 May 1999 Insp Rept 50-382/99-05 on 990228-0410.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support ML20206F4801999-05-0303 May 1999 Insp Rept 50-382/99-08 on 990405-07.One Apparent Violation Noted & Being Considered for Escalated Eas.Major Areas Inspected:Plant Support Including Licensee Access Authorization Program IR 05000382/19990041999-04-0909 April 1999 Insp Rept 50-382/99-04 on 990301-19.One Violation Occurred & Being Treated as Noncited Violation.Major Areas Inspected: Review of Licensee Implementation of Facility ISI Program & Followup Review of Reactor Trip Breaker Performance IR 05000382/19990021999-04-0505 April 1999 Insp Rept 50-382/99-02 on 990117-0227.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support Activities IR 05000382/19990031999-03-26026 March 1999 Insp Rept 50-382/99-03 on 990308-12.Violations Noted.Major Areas Inspected:Radiation Protection Program Focusing on RF09 Refueling Outage Activities IR 05000382/19990011999-03-0303 March 1999 Partially Deleted Insp Rept 50-382/99-01 on 990125-29 & 0208-12 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Plant Support IR 05000382/19980181998-12-21021 December 1998 Insp Rept 50-382/98-18 on 981018-1128.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19980151998-11-24024 November 1998 Insp Rept 50-382/98-15 on 980906-1017.No Violations Noted. Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities IR 05000382/19980131998-11-17017 November 1998 Insp Rept 50-382/98-13 on 980831-0901 & 981005-08.No Violations Noted.Major Areas Inspected:Maint Using Guidance of Temp Instruction 2515/137, Insp of Medium-Voltage & Low-Voltage Power Circuit Breakers ML20155D0561998-10-29029 October 1998 Insp Rept 50-382/98-17 on 981005-08.Violations Noted. Major Areas Inspected:Routine Review of Radiation Protection Program Activities ML20155D5111998-10-27027 October 1998 Partially Withheld Insp Rept 50-382/98-16 on 980914-18. Violations Noted.Major Areas Inspected:Licensee Physical Security Program.Portions Withheld (Ref 10CFR2.790) ML20154L1281998-10-0909 October 1998 Insp Rept 50-382/98-14 on 980726-0905.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19980121998-08-21021 August 1998 Insp Rept 50-382/98-12 on 980614-0725.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19992011998-07-27027 July 1998 Insp Rept 50-382/99-201 on 990511-0619.No Violations Noted Major Areas Inspected:Engineering IR 05000382/19980101998-07-20020 July 1998 Insp Rept 50-382/98-10 on 980622-26.No Violations Noted. Major Areas Inspected:Licensee Physical Security Program Including Access Authorization,Alarm Stations,Protected Area Access Control of Personnel & Packages & Vehicles IR 05000382/19980091998-07-10010 July 1998 Insp Rept 50-382/98-09 on 980503-0613.Violations Noted.Major Areas Inspected:Aspects of Operations,Maint,Engineering & Plant Support Activities.Fire Door in Reactor Auxiliary Bldg Was Observed to Be Open W/No Controls in Place IR 05000382/19980081998-05-29029 May 1998 Insp Rept 50-382/98-08 on 980322-0502.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20217B6981998-04-21021 April 1998 Insp Rept 50-382/98-06 on 980201-0321.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000382/19980021998-03-20020 March 1998 Insp Rept 50-382/98-02 on 980202-20.No Violations Noted. Major Areas Inspected:Current Performance & Effectiveness of Corrective Action Program Including Audits & Assessments, Operations & Engineering ML20216E1461998-03-12012 March 1998 Insp Rept 50-382/98-07 on 980302-06.Violations Noted.Major Areas Inspected:Plant Support ML20216E5991998-03-12012 March 1998 Insp Rept 50-382/98-05 on 980202-12.Violations Noted.Major Areas Inspected:Licensee Physical Security Program ML20216E7621998-03-12012 March 1998 Insp Rept 50-382/97-25 on 971201-980205.Violations Noted. Major Areas Inspected:Maint & Engineering IR 05000382/19980031998-03-10010 March 1998 Insp Rept 50-382/98-03 on 980216-20.No Violations Noted. Major Areas Inspected:Operational Status of Emergency Preparedness Program ML20203L2171998-03-0303 March 1998 Insp Rept 50-382/98-04 on 980202-06.Violations Noted.Major Areas Inspected:Radiation Protection Program Including External Exposure Controls,Training Qualifications, Facilities & Equipment & Procedures & Documentation IR 05000382/19970281998-02-11011 February 1998 Insp Rept 50-382/97-28 on 971214-980131.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support Activities IR 05000382/19980011998-01-29029 January 1998 Insp Rept 50-382/98-01 on 980112-15.No Violations Noted. Major Areas Inspected:Implementation of Solid Radwaste Mgt & Radwaste/Matls Transportation Program.Quality Assurance Oversight,Training & Procedural Guidance Were Also Reviewed ML20198M2801998-01-12012 January 1998 Insp Rept 50-382/97-24 on 971102-1213.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20198C8871998-01-0505 January 1998 Insp Rept 50-382/97-26 on 971117-1205.No Violations Noted. Major Areas Inspected:Operator Activities Re Failure to Return Valve ACC-126A,auxiliary Component CWS Flow Control Valve,To Automatic Operation When Restoring CWS ML20198C4561998-01-0202 January 1998 Insp Rept 50-382/97-27 on 971117-1205.Violations Noted. Major Areas Inspected:Review of Licensee Identification That Plant Ventilation Sys Could Adversely Affect Level Indication for Refueling Water Storage Pool IR 05000382/19970181997-12-0505 December 1997 Insp Rept 50-382/97-18 on 971104-07.Violations Noted.Major Areas Inspected:Licensee Performance & Capabilities During full-scale,biennial Exercise of Emergency Plan & Implementing Procedures Performed IR 05000382/19970211997-12-0202 December 1997 Insp Rept 50-382/97-21 on 970922-26 & 1006-10.Violation Noted.Major Areas Inspected:Engineering,Maintenance & Mgt Meetings IR 05000382/19970221997-11-19019 November 1997 Insp Rept 50-382/97-22 on 970921-0001.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19970231997-11-0404 November 1997 Insp Rept 50-382/97-23 on 971006-10.No Violations Noted. Major Areas Inspected:Liquid & Gaseous Radioactive Effluent Waste Mgt Program Including Organization & Mgt Controls & Radioactive Effluent Monitoring IR 05000382/19970191997-10-24024 October 1997 Partially Withheld Insp Rept 50-382/97-19 on 970922-26 (Ref 10CFR73.21).No Violations Identified.Major Areas Inspected: Plant Support Re Land Vehicle Control Measures & Security Program IR 05000382/19970171997-10-23023 October 1997 Insp Rept 50-382/97-17 on 970929-1003.Violations Noted. Major Areas Inspected:Licensed Operator Requalification Program Following Guidelines in Insp Procedure 71001, Licensed Operator Requalification Program Evaluation IR 05000382/19970161997-10-17017 October 1997 Insp Rept 50-382/97-16 on 970810-0920.Violations Noted: Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19970201997-10-0909 October 1997 Insp Rept 50-382/97-20 on 970922-26.Violations Noted.Major Areas Inspected:External & Internal Exposure Control Programs,Surveys,Monitoring & Control of Radioactive Matl & Quality Assurance 1999-09-08
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000382/19990201999-10-21021 October 1999 Insp Rept 50-382/99-20 on 990815-0925.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support Activities IR 05000382/19990141999-10-19019 October 1999 Insp Rept 50-382/99-14 on 990913-17 & 1004-08.No Violations Noted.Major Areas Inspected:Operator Requalification Training Program IR 05000382/19990181999-09-29029 September 1999 Insp Rept 50-382/99-18 on 990830-0902.Violations Noted.Major Areas Inspected:Implementation of NRC-approved Fire Protection Program IR 05000382/19990191999-09-27027 September 1999 Insp Rept 50-382/99-19 on 990830-0903.No Violations Noted. Major Areas Inspected:Plant Support IR 05000382/19990151999-09-14014 September 1999 Insp Rept 50-382/99-15 on 990719-23 with in Ofc Insp Until 0819.No Violations Noted.Major Areas Inspected:Assessment of 10CFR50.59 Safety Evaluation Program & Review of Previous Insp Findings Involving Tornado Missile Protection IR 05000382/19990071999-09-0808 September 1999 Insp Rept 50-382/99-07 on 990601-11.Noncited Violations Identified.Major Areas Inspected:Operations IR 05000382/19990161999-09-0101 September 1999 Insp Rept 50-382/99-16 on 990704-0814.Noncited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support IR 05000382/19990101999-08-11011 August 1999 Insp Rept 50-382/99-10 on 990719-23.Violations Noted.Major Areas Inspected:Solid Radioactive Waste Mgt & Radioactive Matl Transportation Programs IR 05000382/19990131999-07-15015 July 1999 Insp Rept 50-382/99-13 on 990523-0703.Noncited Violations Noted.Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities IR 05000382/19990121999-06-21021 June 1999 Insp Rept 50-382/99-12 on 990524-27.No Violations Noted. Major Areas Inspected:Operational Status of Licensee Emergency Preparedness Program IR 05000382/19990111999-06-18018 June 1999 Insp Rept 50-382/99-11 on 990524-28.No Violations Noted. Major Areas Inspected:Implementation of Liquid & Gaseous Radwaste Effluent Mgt Program,Status of Effluent Radiation Monitors & Counting Room Instruments IR 05000382/19990091999-06-0303 June 1999 Insp Rept 50-382/99-09 on 990411-0522.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19990061999-05-18018 May 1999 Insp Rept 50-382/99-06 on 990405-09.Non-cited Violations Identified.Major Areas Inspected:Issue Previously Identified During Architect Engineering Insp Which Documented NRC Insp Rept 50-382/98-201 IR 05000382/19990051999-05-10010 May 1999 Insp Rept 50-382/99-05 on 990228-0410.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support ML20206F4801999-05-0303 May 1999 Insp Rept 50-382/99-08 on 990405-07.One Apparent Violation Noted & Being Considered for Escalated Eas.Major Areas Inspected:Plant Support Including Licensee Access Authorization Program IR 05000382/19990041999-04-0909 April 1999 Insp Rept 50-382/99-04 on 990301-19.One Violation Occurred & Being Treated as Noncited Violation.Major Areas Inspected: Review of Licensee Implementation of Facility ISI Program & Followup Review of Reactor Trip Breaker Performance IR 05000382/19990021999-04-0505 April 1999 Insp Rept 50-382/99-02 on 990117-0227.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support Activities IR 05000382/19990031999-03-26026 March 1999 Insp Rept 50-382/99-03 on 990308-12.Violations Noted.Major Areas Inspected:Radiation Protection Program Focusing on RF09 Refueling Outage Activities IR 05000382/19990011999-03-0303 March 1999 Partially Deleted Insp Rept 50-382/99-01 on 990125-29 & 0208-12 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Plant Support IR 05000382/19980181998-12-21021 December 1998 Insp Rept 50-382/98-18 on 981018-1128.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19980151998-11-24024 November 1998 Insp Rept 50-382/98-15 on 980906-1017.No Violations Noted. Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities IR 05000382/19980131998-11-17017 November 1998 Insp Rept 50-382/98-13 on 980831-0901 & 981005-08.No Violations Noted.Major Areas Inspected:Maint Using Guidance of Temp Instruction 2515/137, Insp of Medium-Voltage & Low-Voltage Power Circuit Breakers ML20155D0561998-10-29029 October 1998 Insp Rept 50-382/98-17 on 981005-08.Violations Noted. Major Areas Inspected:Routine Review of Radiation Protection Program Activities ML20155D5111998-10-27027 October 1998 Partially Withheld Insp Rept 50-382/98-16 on 980914-18. Violations Noted.Major Areas Inspected:Licensee Physical Security Program.Portions Withheld (Ref 10CFR2.790) ML20154L1281998-10-0909 October 1998 Insp Rept 50-382/98-14 on 980726-0905.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19980121998-08-21021 August 1998 Insp Rept 50-382/98-12 on 980614-0725.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19992011998-07-27027 July 1998 Insp Rept 50-382/99-201 on 990511-0619.No Violations Noted Major Areas Inspected:Engineering IR 05000382/19980101998-07-20020 July 1998 Insp Rept 50-382/98-10 on 980622-26.No Violations Noted. Major Areas Inspected:Licensee Physical Security Program Including Access Authorization,Alarm Stations,Protected Area Access Control of Personnel & Packages & Vehicles IR 05000382/19980091998-07-10010 July 1998 Insp Rept 50-382/98-09 on 980503-0613.Violations Noted.Major Areas Inspected:Aspects of Operations,Maint,Engineering & Plant Support Activities.Fire Door in Reactor Auxiliary Bldg Was Observed to Be Open W/No Controls in Place IR 05000382/19980081998-05-29029 May 1998 Insp Rept 50-382/98-08 on 980322-0502.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20217B6981998-04-21021 April 1998 Insp Rept 50-382/98-06 on 980201-0321.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering IR 05000382/19980021998-03-20020 March 1998 Insp Rept 50-382/98-02 on 980202-20.No Violations Noted. Major Areas Inspected:Current Performance & Effectiveness of Corrective Action Program Including Audits & Assessments, Operations & Engineering ML20216E1461998-03-12012 March 1998 Insp Rept 50-382/98-07 on 980302-06.Violations Noted.Major Areas Inspected:Plant Support ML20216E5991998-03-12012 March 1998 Insp Rept 50-382/98-05 on 980202-12.Violations Noted.Major Areas Inspected:Licensee Physical Security Program ML20216E7621998-03-12012 March 1998 Insp Rept 50-382/97-25 on 971201-980205.Violations Noted. Major Areas Inspected:Maint & Engineering IR 05000382/19980031998-03-10010 March 1998 Insp Rept 50-382/98-03 on 980216-20.No Violations Noted. Major Areas Inspected:Operational Status of Emergency Preparedness Program ML20203L2171998-03-0303 March 1998 Insp Rept 50-382/98-04 on 980202-06.Violations Noted.Major Areas Inspected:Radiation Protection Program Including External Exposure Controls,Training Qualifications, Facilities & Equipment & Procedures & Documentation IR 05000382/19970281998-02-11011 February 1998 Insp Rept 50-382/97-28 on 971214-980131.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support Activities IR 05000382/19980011998-01-29029 January 1998 Insp Rept 50-382/98-01 on 980112-15.No Violations Noted. Major Areas Inspected:Implementation of Solid Radwaste Mgt & Radwaste/Matls Transportation Program.Quality Assurance Oversight,Training & Procedural Guidance Were Also Reviewed ML20198M2801998-01-12012 January 1998 Insp Rept 50-382/97-24 on 971102-1213.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20198C8871998-01-0505 January 1998 Insp Rept 50-382/97-26 on 971117-1205.No Violations Noted. Major Areas Inspected:Operator Activities Re Failure to Return Valve ACC-126A,auxiliary Component CWS Flow Control Valve,To Automatic Operation When Restoring CWS ML20198C4561998-01-0202 January 1998 Insp Rept 50-382/97-27 on 971117-1205.Violations Noted. Major Areas Inspected:Review of Licensee Identification That Plant Ventilation Sys Could Adversely Affect Level Indication for Refueling Water Storage Pool IR 05000382/19970181997-12-0505 December 1997 Insp Rept 50-382/97-18 on 971104-07.Violations Noted.Major Areas Inspected:Licensee Performance & Capabilities During full-scale,biennial Exercise of Emergency Plan & Implementing Procedures Performed IR 05000382/19970211997-12-0202 December 1997 Insp Rept 50-382/97-21 on 970922-26 & 1006-10.Violation Noted.Major Areas Inspected:Engineering,Maintenance & Mgt Meetings IR 05000382/19970221997-11-19019 November 1997 Insp Rept 50-382/97-22 on 970921-0001.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19970231997-11-0404 November 1997 Insp Rept 50-382/97-23 on 971006-10.No Violations Noted. Major Areas Inspected:Liquid & Gaseous Radioactive Effluent Waste Mgt Program Including Organization & Mgt Controls & Radioactive Effluent Monitoring IR 05000382/19970191997-10-24024 October 1997 Partially Withheld Insp Rept 50-382/97-19 on 970922-26 (Ref 10CFR73.21).No Violations Identified.Major Areas Inspected: Plant Support Re Land Vehicle Control Measures & Security Program IR 05000382/19970171997-10-23023 October 1997 Insp Rept 50-382/97-17 on 970929-1003.Violations Noted. Major Areas Inspected:Licensed Operator Requalification Program Following Guidelines in Insp Procedure 71001, Licensed Operator Requalification Program Evaluation IR 05000382/19970161997-10-17017 October 1997 Insp Rept 50-382/97-16 on 970810-0920.Violations Noted: Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19970201997-10-0909 October 1997 Insp Rept 50-382/97-20 on 970922-26.Violations Noted.Major Areas Inspected:External & Internal Exposure Control Programs,Surveys,Monitoring & Control of Radioactive Matl & Quality Assurance 1999-09-08
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000382/19990201999-10-21021 October 1999 Insp Rept 50-382/99-20 on 990815-0925.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support Activities IR 05000382/19990141999-10-19019 October 1999 Insp Rept 50-382/99-14 on 990913-17 & 1004-08.No Violations Noted.Major Areas Inspected:Operator Requalification Training Program PNO-IV-99-038A, on 990929,restart of Waterford 3 Occurred. Cause Identified as Failed Seal Water Heat Exchanger Baffle. New Battle & Seal Assembled Were Installed & Reactor Coolant Pump 2B Was Returned to Svc Satisfactorily1999-10-0101 October 1999 PNO-IV-99-038A:on 990929,restart of Waterford 3 Occurred. Cause Identified as Failed Seal Water Heat Exchanger Baffle. New Battle & Seal Assembled Were Installed & Reactor Coolant Pump 2B Was Returned to Svc Satisfactorily IR 05000382/19990181999-09-29029 September 1999 Insp Rept 50-382/99-18 on 990830-0902.Violations Noted.Major Areas Inspected:Implementation of NRC-approved Fire Protection Program IR 05000382/19990191999-09-27027 September 1999 Insp Rept 50-382/99-19 on 990830-0903.No Violations Noted. Major Areas Inspected:Plant Support PNO-IV-99-038, on 990910,operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.New Baffle & Seal Assembly Were Installed & Plant Was Returned to Power Operations on 9908101999-09-15015 September 1999 PNO-IV-99-038:on 990910,operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.New Baffle & Seal Assembly Were Installed & Plant Was Returned to Power Operations on 990810 IR 05000382/19990151999-09-14014 September 1999 Insp Rept 50-382/99-15 on 990719-23 with in Ofc Insp Until 0819.No Violations Noted.Major Areas Inspected:Assessment of 10CFR50.59 Safety Evaluation Program & Review of Previous Insp Findings Involving Tornado Missile Protection IR 05000382/19990071999-09-0808 September 1999 Insp Rept 50-382/99-07 on 990601-11.Noncited Violations Identified.Major Areas Inspected:Operations IR 05000382/19990161999-09-0101 September 1999 Insp Rept 50-382/99-16 on 990704-0814.Noncited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support PNO-IV-99-032A, on 990801,Waterford 3 Operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.Pump Was Secured Immediately Following Plant Sd.New Baffle & Seal Assembly Was Installed1999-08-12012 August 1999 PNO-IV-99-032A:on 990801,Waterford 3 Operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.Pump Was Secured Immediately Following Plant Sd.New Baffle & Seal Assembly Was Installed IR 05000382/19990101999-08-11011 August 1999 Insp Rept 50-382/99-10 on 990719-23.Violations Noted.Major Areas Inspected:Solid Radioactive Waste Mgt & Radioactive Matl Transportation Programs PNO-IV-99-032, on 990801,Waterford 3 Operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.Pump Was Secured Immediately Following Plan Shutdown.Resident Inspectors Will Monitor1999-08-0303 August 1999 PNO-IV-99-032:on 990801,Waterford 3 Operators Manually Tripped Reactor from 100% Power in Response to Indications of Failure of RCP 2B Seal.Pump Was Secured Immediately Following Plan Shutdown.Resident Inspectors Will Monitor IR 05000382/19990131999-07-15015 July 1999 Insp Rept 50-382/99-13 on 990523-0703.Noncited Violations Noted.Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities IR 05000382/19990121999-06-21021 June 1999 Insp Rept 50-382/99-12 on 990524-27.No Violations Noted. Major Areas Inspected:Operational Status of Licensee Emergency Preparedness Program IR 05000382/19990111999-06-18018 June 1999 Insp Rept 50-382/99-11 on 990524-28.No Violations Noted. Major Areas Inspected:Implementation of Liquid & Gaseous Radwaste Effluent Mgt Program,Status of Effluent Radiation Monitors & Counting Room Instruments ML20196C9461999-06-15015 June 1999 Notice of Violation from Insp Completed on 990422.Violation Noted:Licensee Failed to Consider Info Contained During Background Investigation Before Granting Temporary Unescorted Access to Contractor Employee IR 05000382/19990091999-06-0303 June 1999 Insp Rept 50-382/99-09 on 990411-0522.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support ML20209B8581999-05-25025 May 1999 EN-98-046A:on 990524,staff Withdrew Proposed Civil Penalty in Amount of $110,000 Issued to Licensee.Action Based on Severity Level III Problems Associated with ECCS & Afws IR 05000382/19990061999-05-18018 May 1999 Insp Rept 50-382/99-06 on 990405-09.Non-cited Violations Identified.Major Areas Inspected:Issue Previously Identified During Architect Engineering Insp Which Documented NRC Insp Rept 50-382/98-201 IR 05000382/19990051999-05-10010 May 1999 Insp Rept 50-382/99-05 on 990228-0410.Non-cited Violations Noted.Major Areas Inspected:Operations,Maintenance, Engineering & Plant Support ML20206F4801999-05-0303 May 1999 Insp Rept 50-382/99-08 on 990405-07.One Apparent Violation Noted & Being Considered for Escalated Eas.Major Areas Inspected:Plant Support Including Licensee Access Authorization Program IR 05000382/19990041999-04-0909 April 1999 Insp Rept 50-382/99-04 on 990301-19.One Violation Occurred & Being Treated as Noncited Violation.Major Areas Inspected: Review of Licensee Implementation of Facility ISI Program & Followup Review of Reactor Trip Breaker Performance IR 05000382/19990021999-04-0505 April 1999 Insp Rept 50-382/99-02 on 990117-0227.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support Activities IR 05000382/19990031999-03-26026 March 1999 Insp Rept 50-382/99-03 on 990308-12.Violations Noted.Major Areas Inspected:Radiation Protection Program Focusing on RF09 Refueling Outage Activities IR 05000382/19990011999-03-0303 March 1999 Partially Deleted Insp Rept 50-382/99-01 on 990125-29 & 0208-12 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected:Plant Support ML20207F1581999-03-0303 March 1999 Notice of Violation from Insp on 990125-29 & 0208-12. Violation Noted:Inspector Determined That Waterford Audits SA-98-025.1 & SA-98-036.1,dtd 980916,were Conducted by Individuals Not Independent of Program Mgt Being Audited IR 05000382/19980181998-12-21021 December 1998 Insp Rept 50-382/98-18 on 981018-1128.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19980151998-11-24024 November 1998 Insp Rept 50-382/98-15 on 980906-1017.No Violations Noted. Major Areas Inspected:Aspects of Operations,Maint, Engineering & Plant Support Activities PNO-IV-98-054, on 981117,plant Shutdown Greater than 72 H Due to Unidentified Leak.Investigations by Licensee Verified That Leakage Occurred from RCP 2b Seal Area1998-11-19019 November 1998 PNO-IV-98-054:on 981117,plant Shutdown Greater than 72 H Due to Unidentified Leak.Investigations by Licensee Verified That Leakage Occurred from RCP 2b Seal Area IR 05000382/19980131998-11-17017 November 1998 Insp Rept 50-382/98-13 on 980831-0901 & 981005-08.No Violations Noted.Major Areas Inspected:Maint Using Guidance of Temp Instruction 2515/137, Insp of Medium-Voltage & Low-Voltage Power Circuit Breakers ML20155D0561998-10-29029 October 1998 Insp Rept 50-382/98-17 on 981005-08.Violations Noted. Major Areas Inspected:Routine Review of Radiation Protection Program Activities ML20155D0411998-10-29029 October 1998 Notice of Violation from Insp on 981005-08.Violation Noted: Inspectors Identified That Radiation Surveys to Evaluate Extent of Radiation Levels Had Not Been Performed Prior to Operations Personnel Entering Area ML20155D5111998-10-27027 October 1998 Partially Withheld Insp Rept 50-382/98-16 on 980914-18. Violations Noted.Major Areas Inspected:Licensee Physical Security Program.Portions Withheld (Ref 10CFR2.790) ML20155D5021998-10-27027 October 1998 Notice of Violation from Insp on 980914-18.Violation Noted: Performance Tests of Protected Area Detection Sys Identified That Two Detection Zones Did Not Meet Design Criteria to Detect Test Individuals ML20154L0831998-10-0909 October 1998 Notice of Violation from Insp on 980726-0905.Violation Noted:On 980721,NRC Inspectors Found Door 206,vital Area Portal,Unlocked & Not in Alarm at Central Alarm Station ML20154L1281998-10-0909 October 1998 Insp Rept 50-382/98-14 on 980726-0905.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support PNO-IV-98-045, on 980926,Unit 3 Declared Unusual Event of Hurricane Warning in St Charles Parish.River Bend Station Continued to Operate at Full Power Since Hurricane Force Winds Were Not Predicted in Vicinity of Site1998-09-28028 September 1998 PNO-IV-98-045:on 980926,Unit 3 Declared Unusual Event of Hurricane Warning in St Charles Parish.River Bend Station Continued to Operate at Full Power Since Hurricane Force Winds Were Not Predicted in Vicinity of Site PNO-IV-98-040, on 980917,licensee Commenced Shutdown of Reactor in Order to Replace Pressurizer Code Safety Valve That Had Been Experiencing Increased Leakage.Licensee Plans to Restart Facility on 9809231998-09-18018 September 1998 PNO-IV-98-040:on 980917,licensee Commenced Shutdown of Reactor in Order to Replace Pressurizer Code Safety Valve That Had Been Experiencing Increased Leakage.Licensee Plans to Restart Facility on 980923 IR 05000382/19980121998-08-21021 August 1998 Insp Rept 50-382/98-12 on 980614-0725.No Violations Noted. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000382/19992011998-07-27027 July 1998 Insp Rept 50-382/99-201 on 990511-0619.No Violations Noted Major Areas Inspected:Engineering IR 05000382/19980101998-07-20020 July 1998 Insp Rept 50-382/98-10 on 980622-26.No Violations Noted. Major Areas Inspected:Licensee Physical Security Program Including Access Authorization,Alarm Stations,Protected Area Access Control of Personnel & Packages & Vehicles ML20236P2431998-07-10010 July 1998 Notice of Violation from Insp on 980503-0613.Violation Noted:On 980521,AP UNT-005-013 Was Not Implemented in That Impairment to Fire Door D150 Was Not Controlled IR 05000382/19980091998-07-10010 July 1998 Insp Rept 50-382/98-09 on 980503-0613.Violations Noted.Major Areas Inspected:Aspects of Operations,Maint,Engineering & Plant Support Activities.Fire Door in Reactor Auxiliary Bldg Was Observed to Be Open W/No Controls in Place ML20249A9611998-06-16016 June 1998 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $100,000.Violation Noted:Licensee Identified That Calculated Peak Fuel Cladding Temp Would Have Exceeded 2200 F Using Licensing Basis Analysis & HPSI Flow ML20151R9131998-06-0909 June 1998 EN-98-046:on 980616,notice of Proposed Imposition of Civil Penalty in Amount of $110,000 Issued to Licensee.Action Based on Level III Problem Involving HPSI Flow Issues at Waterford-3 Facility IR 05000382/19980081998-05-29029 May 1998 Insp Rept 50-382/98-08 on 980322-0502.Violations Noted. Major Areas Inspected:Operations,Maintenance,Engineering & Plant Support ML20248F6801998-05-29029 May 1998 Notice of Violation from Insp on 980322-0502.Violation Noted:Licensee Failed to Establish Adequate Procedures for Operation of EDG When in No or Low Electrical Loading Condition in That No Specific Guidance Provided IR 05000382/19980991998-04-24024 April 1998 SALP Rept 50-382/98-99 for 961201-980321 ML20217B6731998-04-21021 April 1998 Notice of Violation from Insp on 980201-0321.Violation Noted:On Past Occasions,Engineer Operated Governor Valve on Emergency Feedwater Turbine W/O Direction or Concurrence of Shift Superintendent or Control Room Supervisor ML20217B6981998-04-21021 April 1998 Insp Rept 50-382/98-06 on 980201-0321.Violations Noted.Major Areas Inspected:Operations,Maint & Engineering 1999-09-08
[Table view] |
Text
_
.
.
'
l ENCLOSURE l
,
U.S. NUCLEAR REGULATORY COMMISSION l
REGION IV
l Docket No.: 50-382 1 l
License No.: NPF-38 l Report No.: 50-382/96-21 Licensee: Entergy Operations, In j Facility: Waterford Steam Electric Station, Unit 3 Location: Hwy.18 l Killona, Louisiana Dates: August 26 to September 12,1996 Inspector: G. A. Pick, Senior Project Engineer Approved By: P. H. Harrell, Chief, Project Branch D ATTACHMENTS:
Attachment 1: Partial List of Persons Contacted List of Inspection Procedures Used List of items Opened, Closed, and Discussed
,
List of Acronyms I
i i
!
i I
!
i
~
9609300182 960923 PDP ADOCK 05000382 G PDR
_
.- . - - = - - __
.
i.
I EXECUTIVE SUMMARY l
Waterford Steam Electric Station, Unit 3 NRC Inspection Report 50-382/96 21 l
l Ooerations !
- Operators properly entered and exited the Technical Specification action statements during the period that the system engineer performed troubleshooting and i
-!
mechanics repaired the normal intake dampers (Section 01.3).
l
- Operators appropriately implemented the corrective action program by initiating condition reports related to operational concerns with control room air conditioning (CRAC) Train B and the inability of a newly developed test procedure to be performed as written (Sections 01.4 and 03.1).
'
Maintenance l
- Mechanics performed work activities in accordance with plant procedures and work instructions (Section M1.1).
Enaineerina i * Overall, the system engineers performed well during the troubleshooting and resolution of the identified leakage through the normalintake dampers. The system engineer who noted the change in control room makeup air flow demonstrated good awareness of system conditions and had a questioning attitude. Also, the system engineer performed a thorough, logical evaluation that identified the reason for the
' failure of CRAC B to meet the pressurization test acceptance criteria (Sections 0 and 01.4).
- System engineers provided good support to the operating organization. A system engineer established a proper postmaintenance test for the normalintake dampers, and engineers performed an appropriate safety evaluation that supported placing a blank flange across the normal intake duct. Further, engineers developed a modification to install access panels in the intake duct to ensure easy access for inspection and developed a special test to ensure leak tightness of the dampers after installation (Section M1.1).
- A system engineer recommended a proper action by requesting an administrative !
limit be established for leakage past the normal intake dampers (Section E1.1). l l
!
- The licensee performed a detailed, thorough root cause analysis of the leakage past the control room normal intake dampers. Further, the recommended corrective J actions should correct the deficiency (Sectior' E1.2).
. _ _ _ _ _ _
.,
.
.
'
2-
- A noncited violation was identified because the licensee identified that lack o preventive maintenance resulted in low leakage dampers that failed to operate properly and an improper test methodology failed to identify the proble (Section E1.2).
!
Reoort Details Summarv of Plant Status The facility operated at 100 percent power during the period covered by this special, announced inspectio l. Operations 01 Conduct of Operations 01.1 Introduction On August 20,1996, the licensee made a 4-hour nonemergency report because of i a deficiency identified with the CRAC system on July 28,1996. Excessive leakage i through the normal intake dampers, assuming a single failure, could result in a single individual exceeding the 30 Rem thyroid exposure limit in 10 CFR Part 50, Appendix A, Criterion 19 and Standard Review Plan 6.4, Section 11.6. Specifically, design engineers calculated that the exposure to a control room operator using 45 scfm maximum unfiltered inteakage following a design basis accident would be
"
35.32 Rem to the thyroid. The inspector performed this specialinspection to verify the facts and assoss the safety and/or regulatory significance of the identified deficienc .2 System Descriotion and Operation The CRAC system includes two full-capacity redundant air-handling units, two full-capacity toilet exhaust fans, a kitchen and conference room exhaust fan, two full-capacity redundant control room emergency filtration units, and redundant isolation dampers for the emergency intakes, normal intake, and exhausts. The control room envelope isolates automatically upon receipt of a safety injection, high :
radiation, or toxic gas actuation signal. On a high radiation or safety injection signal, the normal intake dampers isolate and outside air passes through the emergency filters to provide a clean, fresh air source (pressurization mode) to the control room. On a toxic gas signal, allintakes are isolated and air is recirculated in
the control room (isolate mode).
The CRAC system is designed to maintain grecter than or equal to 0.125 iwg positive pressure within the control room envelope during normal operations to prevent outside air from bypassing the safety-related toxic and chlorine gas monitoring instruments. Specifically, during routine operations, 2200 scfm enters the riormal intake and 2000 scfm is exhausted through the toilet, kitchen, and conference room exhaust fans. The north and south emergency intake provide two sources of control room fresh air for pressurization of the envelope during radiological accident conditions. The north emergency intake is co-located with the
'
normal intake and is provided with safety-related toxic and chlorine gas de:ectio The south emergency intake is located approximately 260 feet to the west of the normalintake and has no toxic and chlorine gas detector ,
l.
.
.
-2-01.3 Discoverv of Unmonitored, Unfiltered Suction Path into The Control Room Enveloce Insoection Scope (93702. 717071 The inspector reviewed condition reports and control room logs and interviewed the l system engineer to verify the circumstances related to the determination of this unmonitored, unfiltered leak path into the control roo Observations and Findinos On July 25,1996, operators initiated a control room pressurization test in accordance with Procedure OP-903-123, " Control Room Envelope Pressure Test,"
Revision 0, to verify integrity of the control room envelope following door maintenance. The operators secured from performing the test because the acceptance criteria could not be verified and initiated Condition Report 96-1145 (refer to Section 03.1).
On July 26, operators performed the control room pressurization test in accordance with Procedure PE-005-004, " Control Room Air Conditioning System Surveillance,"
Revision 6, using CRAC B; however, the operators could not maintain 0.125 iwg positive pressure with 200 scfm makeup flow. The operators initiated Condition Report 96-1147 to identify and correct the root cause of the failure of CRAC B to meet acceptance criteria (refer to Section 01.4). Subsequently, operators successfully performed the test using CRAC A with an adjusted flow rate of 157.5 scfm at 0.125 iwg. The licensee considered the control room envelope operable, as specified in Technical Specification 3.7.6.5, since CRAC A passed the tes Subsequently, after additional troubleshooting, the system engineer confirmed that CRAC B could not maintain the control room at 0.125 iwg positive pressure with 200 scfm makeup flow. In an attempt to diagnose the root cause, the system engineer had operators swap the main air handling units from Train B to A, which in turn opened Train A Damper HVC-102, normal outside air intake outboard isolatio After the damper opened, control room pressure increased. After discussions with the operators, the system engineer concluded that Train B Damper HVC-101, normal outside air intake inboard isolation, must have leaked past the seat. The system engineer became concerned because this path provided an unmonitored, unfiltered source of air into the control room during a design basis acciden On July 27, while troubleshooting using Work Authorization 01149688, the system engineer identified 22 scfm leakage through Damper HVC-101. Mechanical maintenance attempted to adjust the damper travel under troubleshooting guidelines but the seat leakage did not sto On July 28, operators performed Procedure PE-005-004 to determine the leak tightness of the control room. Specifically, operators monitored changes in the
.
_
.
.
3-makeup flow rate with Damper HVC-101 open and Damper HVC-102 closed, with Dampers HVC-101 and -102 closed, and with the normal intake duct blocked by a temporary plate. The system engineer performed the test in this manner to quantify the amount of inleakage. The identified inleakage with both normalintake dampers closed was 9.2 scfm and with Damper HVC-101 open and Damper HVC-102 closed was 45 scf On July 29, the licensee blocked flow through the normal intake with a 3/8-inch steel plate in accordance with Temporary Alteration Request 96-009, " Installation of Blankoff Plate on Control Room Normal Outside Air intake Duct." After installation of the blankoff plate, operators declared the system operable, as specified in Technical Specification 3.7. !
On September 5, as part of a system walkdown, the system engineer conducted a nonintrusive smoke test of the south emergency intake inboard dampers. The control room was in the pressurization mode with suction through the north emergency intake. The system engineer confirmed that the dampers were,in fact, leak tight and documented the test in his system log boo The inspector reviewed the control room logs and found that the operators had properly logged the entry and exit into Technical Specification 3.7.6 limiting conditions for operation action statement Conclusions The inspector concluded that the system engineer wha noted the change in control ,
l room makeup air flow demonstrated good awareness of system conditions and had a questioning attitude. The engineers performed thorough troubleshooting that characterized the quantity of unmonitored, unfiltered leakage into the control roo Operators properly entered and exited Technical Specification action statements and appropriately identified deficiencies with condition report .4 Inability of CRAC B to Meet Pressurization Desian Reauirements Insoection Scoce (71707)
The inspector assessed the system engineer's evaluation of the capability of CRAC B to function as designed by review of condi* ion reports, the system description, and the Updated Final Safety Analysis Report (UFSAR), and interviews with the system engineer. As described in Section 01.3, CRAC B could not maintain the 0.125 iwg positive pressure at 200 s:fm during postmaintenance testin . - _ - _ _ _ _ - _ - - _ - _ _ _
.
.
-4- Observa@_ tend Findinas The system engineer determined from review of plant computer data obtained on July 26, that the reactor auxiliary building (RAB) pressure measured -1.1 iwg instead of the normal-0.7 iwg during the CRAC B pressurization test and measured 0 iwg during the CRAC A pressurization test. The system engineer concluded that Shield Building Ventilation A discharged into the RAB ventilation exhaust, which caused increased negative RAB pressure. Also, the system engineer concluded that RAB doors might have been opened during the CRAC A test, which eliminated the negative pressure because of excessive inleakage. The inspector determined that the licensee had no technical requirement to have the RAB ventilation in servic The licensee initiated the shield building ventilation because the normal containment purge was out of service so that special testing of containment penetrations could be performed. The inspector determined during accidents that the shield building ventilation initially exhausts to the RAB normal ventilation then begins recirculation when the shield building annulus reaches -8 iwg. The lack of communication between the shield building ventilation and the CRAC systems after the RAB ventilation trips would prevent adverse impact on the ability of the CRAC systems I to maintain a positive pressur Conclusions The system engineer performed a thorough, logical evaluation that identified the probable cause for the failure of CRAC B to meet the Technical Specification limit Operations Procedures and Documentation i
03.1 Evaluation of Adeauacy of Procedure OP-903-123 Insoection Scoce (71707)
The inspector reviewed condition reports and Procedure OP-903-123 to evaluate the ability of the recently developed procedure to ensure that all flows into the control room were incorporated into the acceptance criteri Observations and Findinas Condition Report 96-1145 documented that Procedure OP-903-123 failed to properly instruct personnel to normalize flow and differential pressure when the measured pressure was between 0.125-0.130 iwg and failed to specify the required actions when the measured differential pressures exceeded the acceptable rang Further, the procedure acceptance criteria failed to explicitly specify that the flow should be less than or equal to 200 scfm at 0.125 iwg positive pressure. The immediate corrective actions included using Procedure PE-005-00 l
.
.
5-
The inspector confirmed that Procedure OP-903-123 instructed operators to initiate a condition identification whenever they identified flow through the south !
emergency intake during testing. Operators perform the control room pressurization test using the north emergency intake flow path since this path has toxic and chorine gas monitors; hence, flow is not expected from the south intake path. The !
inspector found that these procedure requirements resulted from corrective actions l identified in Condition Report 96-0374. The inspector identified that the procedure !
could be enhanced if guidance specified that operators add any flow measured !
through the south emergency intake to the flow measured from the north l emergency intake. The system engineer initiated actions as specified in Condition j Report 96-1156 to review Procedure OP-903-123 for any enhancements that could I include monitoring for leakage through the standby pat J Conclusions Operators followed their administrative procedures and the corrective action program after identifying that a test procedure could not be implemented as written, ll. Maintenance M1 Conduct of Maintenance M1.1 Maintenance Activities Imolemented on the Normal Intake Damoers Insoection Scoce (62703)
The inspector interviewed the system engineer and reviewed work authorizations, completed test procedures, Temporary Alteration Request 96-009 and supporting safety evaluation, and condition reports to assess the maintenance performed on Dampers HVC-101 and -10 Observations and Findinas On July 27, after datermining that Damper HVC-101 leaked by, the licensee initiated Work Authorization 01149688 to troubleshoot the extent and cause of the deficiency and to repair the dampers. During discussions with the inspector, the system engineer indicated that the dampers have always indicated closed during past testing and indicated that he identified 22 scfm leakage through Damper HVC-10 On July 29,1996, the licensee implemented Temporary Alteration Request 96-00 The temporary modification isolated the normal intake duct to allow mechanics to inspect and repair Dampers HVC-101 and -102. Specifically, mechanics removed the dampers and their actuators from the system, cleaned the damper internals, replaced the T-rings, and adjusted the damper seating action. The system engineer
.
.
-6-l specified a bubble test for a postmaintenance test to verify proper seating of the damper blade in the body. From review of ANSI N509-1990, " Nuclear Power Plant Air Cleaning Units and Components," the inspector determined that the bubble test was the appropriate test for this application. Also, mechanics disassembled, cleaned and inspected internal parts, and reassembled the damper operators using new o rings and seals.
,
The inspector reviewed the safety analysis that supported the installation of the 3/8-inch thick steel plate over the normal intake duct. The engineers calculated that the maximum plate deflection at 5 iwg (design pressure is 4 iwg) would be i
'
0.025 inches compared to a limit of 0.0625 inches. The engineers calculated that negligible stress was exerted on the hold down bolts for the steel plate. The inspector concluded that the licensee accurately assessed that blocking flow into l the normalintake duct did not change the operation of the facility as described in !
the UFSAR. In fact, by blocking the flow through the degraded normal intake duct, l
'
the licensee complied with the system operability requirements of Technical Specification 3.7.6. After completing the maintenance on Dampers HVC-101 and -102, the licensee performed Special Test Procedure 01149688, "HVC-101 and HVC-102 Leak Test,"
Revision 0, to determine, by a smoke test, any further leakage through the damper The system engineer identified that Damper HVC-101 still had 5.5 scfm leakage and indicated that the T-rings may need adjustmen l Because of the difficult access to the normal intake duct, the licensee initiated Work Authorization 01150338 to add access panels. The inspector reviewed the modification package, in part, and found the package well planned and the safety evaluation satisfactory. The licensee will maintain Temporary Alteration Request 90-009 in effect until personnel install the access panels and rework i Damper HVC-10 Conclusions Maintenance personnel performed the work activities in accordance with plant procedures and instructions. Administrative controls ensured that safe, generally effective repair of the normal intake dampers. Engineers performed an appropriate 10 CFR 50.59 analysis related to the temporary modification that implemented the blankoff plate at the inlet to the normal intake duct. A system engineer established a proper postmaintenance test for the normal intake dampers prior to installation I
into the system. Further, engineers developed a modification to install access panels in the intake duct to ensure easy access for inspection and developed a special test to ensure leak tightness of the dampers after installatio .
l
.
- l-7-i l
111. Enaineerina i
E1 Conduct of Engineering
'
E1.1 Potential Overexoosure to Personnel Upon Failure a Ventilation Damper Inspection Scoce (37551) !
The inspector assessed engineering's evaluation of the safety significance of a failure of a single control room normal intake damper by interviewing design
,
engineers, reviewing design calculations, and reviewing licensing and design basis
'
informatio Observations and Findinos The system engineer concluded that Dampers HVC-101 and -102 were allowed no leakage. Consequently, the system engineer requested that design engineering calculate the potential exposure to an operator assuming 10 scfm unmonitored, unfiltered inteakage through the normal intake dampers. Design engineering documented the evaluation in Calculation EC-S96-011, "LOCA Offsite and Control Room Radiological Dose Consequences," Revision A. The calculation demonstrated that the operators would not exceed thyroid dose limits. The system engineer planned to use this information to set an 8 scfm administrative limit in a leak test procedure, as part of the corrective actions for this event (refer to Section E1.2).
The inspector determined that the design engineers performed no formal calculation of the potential increased operator exposure resulting from the excessive inleakag However, the design engineers used the methodology as specified in Calculation EC-S96-011 with 45 scfm substituted for 10 scfm inleakage. The calculation resulted in 35.32 Rem tnyroid exposure to an operator following the analysis guidelines in UFSAR Chapter 15. In addition, the design engineers calculated potential exposure to an individual but used realistic estimates for occupation of the control room other than the time periods assumed in UFSAR Table 15.6-18, " Parameters Used in Evaluating The Radiological Consequences of a Loss of Coolant Accident." The estimate used 13-hour shifts and a rotation of 4 days onshift,3 days offshift,3 days onshift, and 5 days offshift for the first 15 days. For the last 15 days, the engineer assumed 50 percent occupancy. The thyroid exposure to an operator under these conditions would be 27.22 Re Conclusions The inspector considered the system engineer's request for an allowable leakage limit through the CRAC normal intake duct without resulting in an overexposure to the control room opeiatoc to be proper. The inspector concluded that the licensee used an appropriate evaluation methodology, with and without realistic estimates,
. - - - . _
- _ _ _ _ _ _ _ _ _ _
.
-8-
to identify the operator exposure that could have resulted in the event of unfiltered infeakage into the control roo E1.2 Corrective Actions to Resolve Leakaoe Throuoh The Normal Intake Damoers Insoection Scoce (93702,37551)
From discussions with the system engineer and review of the root cause analysis for Condition Report 96-1156, the inspector evaluated the thoroughness of the root cause evaluation and relevance of the proposed corrective act;ons related to the leakage identified through the normal intake dampers. In addition, the inspector reviewed the system design documents, system descriptions, the UFSAR, and plant procedures and interviewed the system engineer to evaluate the appropriateness of the pressurization tes j l
I Observations and Findinos The root cause analysis for Condition Report 96-1156 documented the event sequence, the root cause assessment, similarity to previous occurrences, and recommended short-term and long-term corrective actions. Also, the root cauco analysis described in detail the consequences that might result from other potential leak paths, the root cause of the inability of CRAC B to maintain a positive pressure, and the f ailure of Dampers HVC-101 and -102 to close. The licensee identified no impact from other leakage paths; however, the system engineer indicated that the j test methodology would be reviewed to ensure that it confirms the integrity of the various paths. The licensee established the root cause as dirt and debris found under the valve seat that prevented full closure of the dis The short-term corrective actions included: (1) establishing access panels in the normal intake duct for inspecting Dampers HVC-101 and -102, (2) initiating repetitive tasks to inspect the 10 of 14 control room dampers that did not have tasks to inspect, clean, and replace the soft seats, and (3) calculating the personnel exposure resulting from a 10 scfm leak rate through the normal intak The long-term corrective actions included: (1) establishing an 18-month frequency l for leak rate checking the isolation dampers (Note: initially the licensee will perform quarterly testing to establish a trend), (2) developing a procedure with an administrative limit of 8 scfm to leak rate test Dampers HVC-101 and -102, and (3) reviewing by December 31,1996, the testing configuration for the control room pressure test to ensure compliance with alllicensing documents. Also, the licensee determined that the inaccuracies for the flow measuring loop in the emergency intake lines could be as high as 36 scfm at the lower portion of the indicating rang The inspector expressed concern and the licensee recognized the potential for undetected leakage through the idle emergency intake loop. The test performed by l the system engineer on September 5, eliminated any immediate concerns since the inboard dampers were found to be leak tight and :esting is performed from the north
-9- 1 l
emergency intakes. The system engineer indicated that the review would identify I methods to eliminate air inteakage that could mask test result The licensee had no flow indication for the normal intake path and had no reiuirement to leak test the tightness of the low leakage dampers. The inspector verified from review of design specifications and the valve manufacturer's vendor manual that the normal intake dampers were low leakage dampers. The inspector concluded that the test procedure under development for the normat intake dampers addresses the test concerns. Further, the system engineer selected an appropriate 18-month test frequency since that is the Technical Specification required frequency for performing the control room pressurization tes Technical Specification 6.8.1.c specifies that procedures shall be implemented for surveillance and test activities of safety-related equipment. Procedure PE-005-004, Revision 5, provided instructions to test the integrity of the control room envelop The licensee reviewed Procedure PE-005-004 and determined that the procedure failed to test the normal intake leak path into the control room. The inspector concluded that the failure to perform appropriate testing to ensure that low leakage ventilation dampers remained in good operating condition was a violation identified by the licensee. The licensee implemented immediate actions to correct the deficiency and established a root cause evaluation to propose long-term corrective actions. Further, previous actions related to the control room envelope would not have prevented this deficiency and the deficiency did not result from any willful ac Consequently, this licensee-identified and corrected violation is being treated as a noncited violation consistent with Section Vll.B.1 of the NRC Enforcement Policy
(382/9621-01). Conclusions ,
l The system engineer performed a detailed thorough evaluation to identify the root j cause for the normal intake control room dampers' failure to fully seat. The system l engineer recommended appropriate corrective actions. The inspector determined !
that the licensee identified and corrected deficiency of the control room normal )
intake dampers to remain leak tight was a noncited violatio E2 Engineering Support of Facilities and Equipment J E Review of Facility and Eauipment Conformance to UFSAR Descriotien
!
A recent discovery of a licensee operating a facility in a manner contrary to the UFSAR description highlighted the need for a special focused review that compares plant practices, procedures and/or parameters to the UFSAR descriptions. While performing the inspections discussed in this report, the inspector reviewed the applicable portions of the UFSAR that related to the areas inspected. The following inconsistency was noted between the wording of the UFSAR and the plant practices, procedures and/or procedures observed by the inspecto (....
.,
i k
'
i- !
i .
! -10-t i t
i i
.
'
UFSAR Section 6.4.2.2, " Control Room Air Conditioning System Design," specifies, j in part, makeup air for pressurization is filtered before entering the control room )
- envelope. The inspector concluded from inforrnation obtained during this inspectic'i- l i that the statement is not totally accurate. The licensee discovered that an {
' unfilter'ed auction path can occur if the low leakage dampers leak by because of l poor testing or inadequate maintenance. The corrective actions described in E1.2b, *
l j of this report address this conditio !
l i )
< l V. Manaaement Meetinas l
X1 Exit Meeting Summary The inspector telephonically presented the inspection results to members of licensee management at the conclusion of the inspection on September 12,1996. The licensee acknowledged the findings presente The inspector asked the licensee whether any materials examined during the
.
inspection should be considered proprietary. No proprietary information was identifie _
i l
l
. . . - . - - - - - _ - - - -- -.
.
. i I
. 1 ATTACHMENT 1 i PARTIAL LIST OF, PERSONS CONTACTED Licensee C. M. Dugger, General Manager, Plant Operations J. J. Fisicaro, Director, Nuclear Safety C. Fugate, Assistant Operations Superintendent T. J. Gaudet, Manager, Licensing !
R. T. Kullman, Licensing Engineer !
N. Pazooki, Senior Engineer, Safety and Engineering Analysis - l I
C. P. Talazac, Senior Engineer, System Engineering D. W. Vinci, Superintendent, System Engineering A. J. Wrape, Director, Design Engineering NRC L. A. Keller, Senior Resident inspector T. W. Pruett, Resident inspector INSPECTION PROCEDURES USED 37551 Onsite Engineering 62703 Maintenance Observation j 71707 Plant Operations i i
93702 Prompt Onsite Response to Events at Operating Power Reactors l ITEMS OPENED. CLOSED AND DISCUSSED Opened 50-382/9621-01 NCV Failure to establish repetitive tasks to inspect and refurbish safety-related control room ventilation dampers (Section E1.2).
Closed 50-382/9621-01 NCV Failure to establish repetitive tasks to inspect and refurbish safety-related control room ventilation dampers (Section E1.2).
Discussed None
__ . _ . ..
.
,.
i, -
i
.
-2-
i i
!
! LIST OF ACRONYMS USED l
! CRAC control room air conditioning
- iwg inches water gauge
'
RAB reactor auxiliary building j scfm standard cubic feet per minute
.
UFSAR Updated Final Safety Analysis Report
!
.